CN105714770A - Reinforced type cast-in-situ bored pile structure and construction method thereof - Google Patents

Reinforced type cast-in-situ bored pile structure and construction method thereof Download PDF

Info

Publication number
CN105714770A
CN105714770A CN201610081900.2A CN201610081900A CN105714770A CN 105714770 A CN105714770 A CN 105714770A CN 201610081900 A CN201610081900 A CN 201610081900A CN 105714770 A CN105714770 A CN 105714770A
Authority
CN
China
Prior art keywords
pile
construction
reinforcing
bored concrete
preset
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610081900.2A
Other languages
Chinese (zh)
Inventor
曹慧
许利东
王晓曙
涂伟
陈明
徐金鑫
彭小毅
崔洪
潘延连
王项敏
余琨琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YANTAI CONSTRUCTION ENGINEERING FOUNDATION ENGINEERING Co Ltd
Original Assignee
YANTAI CONSTRUCTION ENGINEERING FOUNDATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YANTAI CONSTRUCTION ENGINEERING FOUNDATION ENGINEERING Co Ltd filed Critical YANTAI CONSTRUCTION ENGINEERING FOUNDATION ENGINEERING Co Ltd
Priority to CN201610081900.2A priority Critical patent/CN105714770A/en
Publication of CN105714770A publication Critical patent/CN105714770A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/50Piles comprising both precast concrete portions and concrete portions cast in situ

Abstract

The invention provides a reinforced type cast-in-situ bored pile structure and a construction method thereof. Through holes (3) in which reinforcing piles can be inserted are preformed in a filling pile (1) in the radial direction. In the construction process of the filling pile, vertical steel pipes or PVC pipes are inserted in advance according to the number and the positions of the preformed hole sites, and the preformed through holes are formed in the filling pile after construction is finished; and when the filling pile needs to be reinforced, the prefabricated reinforcing piles are inserted in the preformed through holes, and the bottom ends of the reinforcing piles are inserted in a geological stratum at the bottom of the filling pile. By the adoption of the reinforced type cast-in-situ bored pile structure, if a pile foundation cannot meet the requirement for structural stability in the later construction period, the reinforcing piles can be adopted for conducting reinforcing construction through the preformed hole sites, and construction conditions are reserved for later reinforcing or strengthening construction while the requirements for the pile foundation structural stability and the use function currently are met. For a pile foundation project under a special project geological condition, the project problem that sedimentation of a pile foundation is not even or the bearing capacity of a pile bottom is insufficient is solved.

Description

One can reinforcement type drill-pouring pilework and construction method thereof
Technical field
The invention belongs to building pile foundation engineering technical field, be specifically related to a kind of drill-pouring pilework and construction method thereof.
Background technology
Along with the iterative method of China's capital construction, all kinds of architectural engineerings such as base pit engineering, slope project, science of bridge building emerge in large numbers therewith.In above-mentioned engineering, pile foundation engineering is essential.In recent years, the pile foundation engineering under the special engineering geological conditions such as limestone (karst) cumulosol regional, deep area gets more and more.Owing to multiformity and the correlation theory of special geologic condition study the factors such as not enough, cause installing intersection result and Practical Project geological conditions inconsistent, thus causing that design and construction can not good solving practical problems, a lot of pile foundation engineerings all can occur there is also the engineering problems such as solution cavity under differential settlement, stake after construction, so having to carry out reinforcing or again constructing for built pile foundation engineering.Existing reinforcement means mainly has three kinds, and a stake side grouting at the bottom of scheme one is is reinforced, and scheme two is cast-in-situ bored pile consolidated by adding piles, and scheme three is to increase Using Anchor Rod Static.But these three reinforcement means has some limitations and difficulty of construction, as scheme one needs to ask, Grouting Pipe is installed outside pile body steel reinforcement cage in advance, if being fitted without in advance, scheme one is difficult to, simultaneously under Karst Geology, program mud jacking amount is difficult to estimate, effect also needs to pass through verification experimental verification;Scheme two is respectively to set up a pile before and after former stake, former stake is connected by linking beam, and the program requires that original building basis is not affected by staking, and simultaneously the program is affected relatively greatly by construction technology and cost is higher;Scheme three is at former stake Zhou Zengshe anchor jacked pile, is connected by cushion cap, and the program uses limited in Deep Thick Soft Ground Area, it is difficult to reach to improve the reinforcing purpose of bearing capacity.And again construct and not only affect the duration, also create the huge waste of manpower and materials.
Summary of the invention
It is an object of the invention to solve the deficiencies in the prior art, a kind of simple in construction is provided, is prone to reinforce built pile foundation engineering or strengthen and can avoid again to construct, can reinforcement type drill-pouring pilework and construction method thereof with what save engineering material and duration.
The purpose of the present invention is achieved through the following technical solutions:
One can reinforcement type drill-pouring pilework, in bored concrete pile, be radially preset with the through hole that can be inserted into reinforcing pile.
The through hole that the present invention presets in bored concrete pile is three holes that Kong Weicheng equilateral triangle relation is arranged.Adopting steel pipe or pvc pipe in bored concrete pile preset hole position, preset hole position diameter is 160~200mm.The end face of the reinforcing pile in insertion through hole and bored concrete pile either flush.Reinforcing pile bottom extends downward bottom surface beyond bored concrete pile bottom surface.
Can the construction method step of reinforcement type drill-pouring pilework as follows:
A. according to installing intersection report and piling strtucture stability requirement, it is determined that include the construction parameter that cast-in-situ bored pile diameter, stake are long;
B. pile-forming machine perching, is irrigated pile driving construction;Work progress is previously inserted according to preset hole bit quantity and position upright steel pipe or pvc pipe, is formed in the bored concrete pile of construction and preset through hole;
C. when bored concrete pile is reinforced by needs, being inserted the reinforcing pile of well in advance and preset in through hole, the end face of reinforcing pile and bored concrete pile either flush, reinforcing pile bottom is inserted in the geological stratification bottom bored concrete pile.
What adopt the present invention can reinforcement type drill-pouring pilework, if phase pile foundation can not meet structural stability requirement after construction, reinforcing pile can be adopted to carry out strengthening construction while meeting current piling strtucture stability requirement and using functional requirement by preset hole position, reinforce for the later stage or strengthen the reserved execution conditions of construction.For the pile foundation engineering under special engineering geological conditions, the present invention can effectively solve that pile foundation settlement is uneven or the engineering roadblock such as Lack of support at the bottom of stake, has higher Practical Project and is worth.
Accompanying drawing explanation
Fig. 1 is present invention radial section schematic diagram when being not inserted into reinforcing pile;
Fig. 2 is the radial section schematic diagram after the present invention inserts reinforcing pile;
Fig. 3 is the Section A-A figure of Fig. 2.
Detailed description of the invention
As shown in Figure 1, Figure 2, Figure 3 shows, of the present invention can reinforcement type drill-pouring pilework, be the through hole 3 being radially preset with in bored concrete pile 1 and can be inserted into reinforcing pile 2.The through hole 2 preset in bored concrete pile 1 is generally three holes, and its Kong Weicheng equilateral triangle relation is arranged.1 footpath of bored concrete pile is typically no less than 1m.Being generally adopted steel pipe or pvc pipe in bored concrete pile 1 preset hole position, preset hole position diameter is generally 160~200mm.Reinforcing pile 2 can well in advance standby, the stake footpath of reinforcing pile and preset hole position diameter matches, pile shaft material strength grade is consistent with bored concrete pile 1.
Of the present invention can the construction method step of reinforcement type drill-pouring pilework as follows:
A. according to installing intersection report and piling strtucture stability requirement, it is determined that include the construction parameter that cast-in-situ bored pile diameter, stake are long;
B. pile-forming machine perching, is irrigated pile driving construction by prior art construction method;Work progress is previously inserted according to preset hole bit quantity and position upright steel pipe or pvc pipe, is formed in the bored concrete pile of construction and preset through hole;
C. when bored concrete pile is reinforced by needs, being inserted the reinforcing pile of well in advance presets in through hole, the end face of reinforcing pile and bored concrete pile either flush, and reinforcing pile bottom extends downward bottom surface beyond bored concrete pile bottom surface, inserting in the geological stratification bottom bored concrete pile, insertion depth is not less than 1m.The stake of reinforcing pile is long to be determined according to practice of construction environmental condition and stability requirement.

Claims (6)

1. one kind can reinforcement type drill-pouring pilework, it is characterised in that in bored concrete pile (1), be radially preset with the through hole (3) that can be inserted into reinforcing pile (2).
2. one according to claim 1 can reinforcement type drill-pouring pilework, it is characterised in that three holes that the through hole (2) preset in bored concrete pile (1) is arranged for Kong Weicheng equilateral triangle relation.
3. one according to claim 1 and 2 can reinforcement type drill-pouring pilework, it is characterised in that adopting steel pipe or pvc pipe in bored concrete pile (1) preset hole position, preset hole position diameter is 160~200mm.
4. one according to claim 1 and 2 can reinforcement type drill-pouring pilework, it is characterised in that insert end face and bored concrete pile (1) either flush of reinforcing pile (2) in through hole.
5. one according to claim 1 and 2 can reinforcement type drill-pouring pilework, it is characterised in that described reinforcing pile (2) bottom extends downward bottom surface beyond bored concrete pile (1) bottom surface.
6. can the construction method of reinforcement type drill-pouring pilework as described in any one of claim 1-5, it is characterised in that method step is as follows:
A. according to installing intersection report and piling strtucture stability requirement, it is determined that include the construction parameter that cast-in-situ bored pile diameter, stake are long;
B. pile-forming machine perching, is irrigated pile driving construction;Work progress is previously inserted according to preset hole bit quantity and position upright steel pipe or pvc pipe, is formed in the bored concrete pile of construction and preset through hole;
C. when bored concrete pile is reinforced by needs, being inserted the reinforcing pile of well in advance and preset in through hole, the end face of reinforcing pile and bored concrete pile either flush, reinforcing pile bottom is inserted in the geological stratification bottom bored concrete pile.
CN201610081900.2A 2016-02-05 2016-02-05 Reinforced type cast-in-situ bored pile structure and construction method thereof Pending CN105714770A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610081900.2A CN105714770A (en) 2016-02-05 2016-02-05 Reinforced type cast-in-situ bored pile structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610081900.2A CN105714770A (en) 2016-02-05 2016-02-05 Reinforced type cast-in-situ bored pile structure and construction method thereof

Publications (1)

Publication Number Publication Date
CN105714770A true CN105714770A (en) 2016-06-29

Family

ID=56156624

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610081900.2A Pending CN105714770A (en) 2016-02-05 2016-02-05 Reinforced type cast-in-situ bored pile structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN105714770A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104113A (en) * 2017-12-26 2018-06-01 中铁第四勘察设计院集团有限公司 Exceeded ruggedized construction and construction method are deformed for friction pile in work progress
CN110374086A (en) * 2019-05-28 2019-10-25 上海长凯岩土工程有限公司 It is a kind of for improving the spreading construction method of existing pier, pile bearing capacity

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1072981A (en) * 1992-10-22 1993-06-09 张平潮 Deep foundation, stake reserved passageway construction method
CN1298050A (en) * 2000-12-04 2001-06-06 罗明 High-pressure rotating spraying bottom-spreading technology for pre-buried pipe
CN1298990A (en) * 2000-12-20 2001-06-13 罗明 High-pressure rotary spray technique for enlarging base of preburied pipe
JP2009280966A (en) * 2008-05-19 2009-12-03 Nippon Steel Corp Steel pipe pile and construction method therefor
CN205530231U (en) * 2016-02-05 2016-08-31 云南建工基础工程有限责任公司 Can reinforcement type drilling bored concrete pile structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1072981A (en) * 1992-10-22 1993-06-09 张平潮 Deep foundation, stake reserved passageway construction method
CN1298050A (en) * 2000-12-04 2001-06-06 罗明 High-pressure rotating spraying bottom-spreading technology for pre-buried pipe
CN1298990A (en) * 2000-12-20 2001-06-13 罗明 High-pressure rotary spray technique for enlarging base of preburied pipe
JP2009280966A (en) * 2008-05-19 2009-12-03 Nippon Steel Corp Steel pipe pile and construction method therefor
CN205530231U (en) * 2016-02-05 2016-08-31 云南建工基础工程有限责任公司 Can reinforcement type drilling bored concrete pile structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104113A (en) * 2017-12-26 2018-06-01 中铁第四勘察设计院集团有限公司 Exceeded ruggedized construction and construction method are deformed for friction pile in work progress
CN110374086A (en) * 2019-05-28 2019-10-25 上海长凯岩土工程有限公司 It is a kind of for improving the spreading construction method of existing pier, pile bearing capacity

Similar Documents

Publication Publication Date Title
WO2018210019A1 (en) Pile formation method for down-the-hole impact rotary jet composite piles
CN203625893U (en) Rock-embedded cast-in-place pile
CN108343071A (en) A kind of foundation pit supporting construction and construction method of steel sheet pile combined deposited pile
CN1926287B (en) Working method of pile with an extended head
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN102767180A (en) Construction method for strengthening base of static-pressure anchor rod pile
CN113186903A (en) Combined pile structure and construction method for treating insufficient bearing capacity of deep foundation pit construction pile by adopting combined pile structure
CN205530231U (en) Can reinforcement type drilling bored concrete pile structure
CN111749288B (en) Load-reducing heightening structure of existing retaining wall and construction method thereof
CN105649073A (en) Static root drilling type construction method for planting piles
CN111485544A (en) Disposal detection structure and method for karst cave under rock-socketed pile base
CN105625418A (en) Cast-in-place pile structure provided with cored expanded head jet grouting piles and construction method of cast-in-place pile structure
CN109594575A (en) A kind of open caisson periphery grouting and reinforcing soil body construction method
CN206428707U (en) A kind of integrated pile tube dado structure of pattern foundation pit supporting structure precipitation
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN105386610A (en) Protective construction method for natural-foundation ancient architectures at top of asymmetric deep foundation pit
CN105464105A (en) Pile forming structure and method of zero-friction pile
CN105714770A (en) Reinforced type cast-in-situ bored pile structure and construction method thereof
CN205382482U (en) Bored concrete pile structure with it spouts stake soon to add core enlarged footing
CN105735383A (en) Partial underground obstacle removing construction method capable of reserving structural system
CN209941754U (en) High-voltage power pipe culvert in-situ protection structure
CN109681212B (en) Excavation construction method of small-section loess tunnel
CN206368375U (en) A kind of electric power pylon basis
CN102493436A (en) Novel manual tunneling construction method of rectangular anti-slide pile
CN109322315A (en) A kind of retaining structure and its construction method for high Steep Slope Embankment location

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 650501 Yunnan city of Kunming Province Economic and Technological Development Zone Forest Road No. 188

Applicant after: Yunnan construction investment foundation engineering Co., Ltd.

Address before: 650501 Yunnan city of Kunming Province Economic and Technological Development Zone Forest Road No. 188

Applicant before: YANTAI CONSTRUCTION ENGINEERING FOUNDATION ENGINEERING CO., LTD.

COR Change of bibliographic data
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160629