CN105649321A - Assembly system and assembly method for shear wall templates - Google Patents

Assembly system and assembly method for shear wall templates Download PDF

Info

Publication number
CN105649321A
CN105649321A CN201610151868.0A CN201610151868A CN105649321A CN 105649321 A CN105649321 A CN 105649321A CN 201610151868 A CN201610151868 A CN 201610151868A CN 105649321 A CN105649321 A CN 105649321A
Authority
CN
China
Prior art keywords
formwork
groups
screw
pressing rods
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610151868.0A
Other languages
Chinese (zh)
Other versions
CN105649321B (en
Inventor
牛志祥
高长玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN201610151868.0A priority Critical patent/CN105649321B/en
Publication of CN105649321A publication Critical patent/CN105649321A/en
Application granted granted Critical
Publication of CN105649321B publication Critical patent/CN105649321B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/08Forms, which are completely dismantled after setting of the concrete and re-built for next pouring
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/065Tying means, the tensional elements of which are threaded to enable their fastening or tensioning
    • E04G17/0655Tying means, the tensional elements of which are threaded to enable their fastening or tensioning the element consisting of several parts
    • E04G17/0657Tying means, the tensional elements of which are threaded to enable their fastening or tensioning the element consisting of several parts fully recoverable

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本发明公开了一种剪力墙模板的拼装系统,模板组均是由若干块模板构成,同一组模板组中相邻的模板之间均设置有压条,压条主要由压条板和附板构成,压条板设置对应的模板之间,压条板的顶端和对应的模板底端接触,压条板的底端与对应的模板顶端接触,附板的同时与对应的模板的侧壁接触,相邻附板之间形成压杆槽,附板上设置有螺杆孔,压杆槽中均设置有纵向压杆,在纵向压杆上设置有若干组横向压杆,纵向压杆设置在横向压杆和压条板之间,在每组横向压杆上设置有若干组拉紧机构,拉紧机构穿过对应的螺杆孔后分别与两组模板组上的横向压杆固定。本系统便于装卸,保护了模板的完整性,能够重复利用,增大了压杆的接触面积,能够保证使用的稳固性。

The invention discloses an assembling system for a shear wall formwork. A formwork group is composed of several formworks. Layering bars are arranged between adjacent formworks in the same group of formwork groups. The layering bars are mainly composed of layering plates and attached plates. The batten is set between the corresponding templates, the top of the batten is in contact with the bottom of the corresponding template, the bottom of the batten is in contact with the top of the corresponding template, and the attached board is in contact with the side wall of the corresponding template at the same time, and the adjacent attached board A pressure rod groove is formed between them, screw holes are set on the attached plate, longitudinal pressure rods are arranged in the pressure rod grooves, several groups of horizontal pressure rods are arranged on the longitudinal pressure rods, and the longitudinal pressure rods are arranged on the horizontal pressure rods and the bead plate In between, several groups of tensioning mechanisms are arranged on each group of transverse pressing rods, and the tensioning mechanisms pass through the corresponding screw holes and are respectively fixed with the transverse pressing rods on the two groups of formwork groups. The system is convenient for loading and unloading, protects the integrity of the template, can be reused, increases the contact area of the pressing bar, and can ensure the stability of use.

Description

一种剪力墙模板的拼装系统及其拼装方法A kind of assembling system and assembling method of shear wall formwork

技术领域 technical field

本发明涉及建筑领域,具体涉及一种剪力墙模板的拼装系统及其拼装方法。 The invention relates to the field of construction, in particular to an assembling system and an assembling method of a shear wall formwork.

背景技术 Background technique

剪力墙又称抗风墙或抗震墙、结构墙。房屋或构筑物中主要承受风荷载或地震作用引起的水平荷载和竖向荷载的墙体。防止结构剪切破坏。它分平面剪力墙和筒体剪力墙。平面剪力墙用于钢筋混凝土框架结构、升板结构、无梁楼盖体系中。为增加结构的刚度、强度及抗倒塌能力,在某些部位可现浇或预制装配钢筋混凝土剪力墙。现浇剪力墙与周边梁、柱同时浇筑,整体性好。筒体剪力墙用于高层建筑、高耸结构和悬吊结构中,由电梯间、楼梯间、设备及辅助用房的间隔墙围成,筒壁均为现浇钢筋混凝土墙体,其刚度和强度较平面剪力墙高可承受较大的水平荷载。墙根据受力特点可以分为承重墙和剪力墙,前者以承受竖向荷载为主,如砌体墙;后者以承受水平荷载为主。在抗震设防区,水平荷载主要由水平地震作用产生,因此剪力墙有时也称为抗震墙。剪力墙按结构材料可以分为钢板剪力墙、钢筋混凝土剪力墙和配筋砌块剪力墙。其中以钢筋混凝土剪力墙最为常用。 Shear walls are also called wind-resistant walls, seismic walls, and structural walls. Walls in houses or structures that mainly bear horizontal loads and vertical loads caused by wind loads or earthquakes. Prevents structural shear damage. It is divided into plane shear wall and cylinder shear wall. Planar shear walls are used in reinforced concrete frame structures, raised slab structures, and beamless floor systems. In order to increase the rigidity, strength and collapse resistance of the structure, reinforced concrete shear walls can be cast-in-place or prefabricated in some parts. The cast-in-place shear wall and the surrounding beams and columns are poured at the same time, and the integrity is good. Cylinder shear walls are used in high-rise buildings, high-rise structures and suspension structures. They are surrounded by partition walls of elevator rooms, stairwells, equipment and auxiliary rooms. The tube walls are all cast-in-place reinforced concrete walls. The strength is higher than that of the plane shear wall and can withstand larger horizontal loads. Walls can be divided into load-bearing walls and shear walls according to their stress characteristics. The former mainly bears vertical loads, such as masonry walls; the latter mainly bears horizontal loads. In the seismic fortification area, the horizontal load is mainly generated by the horizontal earthquake action, so the shear wall is sometimes called the seismic wall. According to the structural materials, shear walls can be divided into steel plate shear walls, reinforced concrete shear walls and reinforced block shear walls. Among them, reinforced concrete shear walls are the most commonly used.

剪力墙模板是钢筋混凝土结构中重要的模板形式,在模板上钻孔的剪力墙模板的安装方法在施工现场长期使用,但现有方法存在模板不易拆除,且在拆除模板是容易造成模板破坏,因此模板重复利用率低,模板的固定效果差,容易浇筑时产生位移,导致剪力墙的墙体结构受到破坏,内部应力达不到要求。 Shear wall formwork is an important formwork form in reinforced concrete structures. The installation method of shear wall formwork with holes drilled on the formwork has been used for a long time on the construction site, but the existing method has the disadvantage that the formwork is not easy to remove, and it is easy to cause the formwork to be damaged when the formwork is removed. Therefore, the reuse rate of the formwork is low, the fixing effect of the formwork is poor, and it is easy to cause displacement during pouring, resulting in damage to the wall structure of the shear wall, and the internal stress cannot meet the requirements.

发明内容 Contents of the invention

本发明所要解决的技术问题是现有方法存在模板不易拆除,且在拆除模板是容易造成模板破坏,因此模板重复利用率低,模板的固定效果差,容易浇筑时产生位移,导致剪力墙的墙体结构受到破坏,内部应力达不到要求,目的在于提供一种剪力墙模板的拼装系统及其拼装方法,解决现有方法存在模板不易拆除,且在拆除模板是容易造成模板破坏,因此模板重复利用率低,模板的固定效果差,容易浇筑时产生位移,导致剪力墙的墙体结构受到破坏,内部应力达不到要求的问题。 The technical problem to be solved by the present invention is that the formwork in the existing method is difficult to dismantle, and the formwork is easily damaged when the formwork is removed, so the formwork reuse rate is low, the formwork is poorly fixed, and it is easy to generate displacement during pouring, resulting in failure of the shear wall. The wall structure is damaged, and the internal stress does not meet the requirements. The purpose is to provide an assembly system and an assembly method for the shear wall formwork. The existing methods are not easy to remove the formwork, and the formwork is easily damaged when the formwork is removed. Therefore, The reuse rate of the formwork is low, the fixing effect of the formwork is poor, and it is easy to cause displacement during pouring, which leads to the damage of the wall structure of the shear wall and the problem that the internal stress cannot meet the requirements.

本发明通过下述技术方案实现: The present invention realizes through following technical scheme:

一种剪力墙模板的拼装系统,包括两组相互平行的模板组,所述模板组均是由若干块模板构成,同一组模板组中相邻的模板之间均设置有压条,压条主要由压条板和附板构成,压条板设置对应的模板之间,且压条板的厚度与模板厚度相同,压条板的顶端和对应的模板底端接触,压条板的底端与对应的模板顶端接触,附板与压条板固定为整体结构,附板的同时与对应的模板的侧壁接触,同一块压条板上的相邻附板之间形成压杆槽,附板上设置有螺杆孔,螺杆孔同时穿过附板和压条板,压杆槽中均设置有纵向压杆,在纵向压杆上设置有若干组横向压杆,纵向压杆设置在横向压杆和压条板之间,横向压杆和纵向压杆相互垂直设置,在每组横向压杆上设置有若干组拉紧机构,拉紧机构穿过对应的螺杆孔后分别与两组模板组上的横向压杆固定。传统在进行剪力墙浇筑时,需要预先支模,便于混凝土浇筑后的成型,但是传统的模板在使用后不易拆除,且在拆除模板是容易造成模板破坏,因此模板重复利用率低,模板的固定效果差,容易浇筑时产生位移,导致剪力墙的墙体结构受到破坏,内部应力达不到要求,而利用本系统拼装的模板,通过压条实现对模板的拼装,不用在模板上钻孔,保证了模板本身的完整性,阻隔横向钢管对模板的直接接触,避免钢管在模板上的打滑,并且钢管能够与压条上的压杆槽进行配合,增大其接触面积,能够大大提高稳固性,横竖交叉的结构能够保证模板之间位置被固定,通过拉紧机构拉紧后,在模板之间浇筑混凝土时更加稳固,不会产生位移,使得形成的剪力墙结构达到设定要求,内部应力稳定,而且模板不会受到破坏,能够重复进行利用。 An assembling system for a shear wall formwork, comprising two sets of formwork groups parallel to each other, the formwork sets are composed of several formworks, and beading is arranged between adjacent formworks in the same set of formwork groups, and the beading is mainly composed of The bead board and the attached board are formed, the bead board is arranged between the corresponding formwork, and the thickness of the bead board is the same as the thickness of the formwork, the top of the bead board is in contact with the bottom end of the corresponding formwork, and the bottom end of the bead board is in contact with the top end of the corresponding formwork, The attachment plate and the beading plate are fixed as an integral structure, and the attachment plate is in contact with the side wall of the corresponding formwork at the same time, and the pressure bar groove is formed between the adjacent attachment plates on the same beading plate, and the attachment plate is provided with screw holes, and the screw holes At the same time through the attached plate and the batten board, the longitudinal pressing bar is arranged in the pressing bar groove, and several groups of horizontal pressing bars are arranged on the longitudinal pressing bar. The longitudinal pressing bar is arranged between the horizontal pressing bar and the pressing bar. The vertical pressure rods are arranged perpendicular to each other, and several groups of tensioning mechanisms are arranged on each group of horizontal pressure rods. The tensioning mechanisms pass through the corresponding screw holes and are respectively fixed with the horizontal pressure rods on the two groups of formwork groups. Traditionally, when pouring a shear wall, pre-formwork is required to facilitate the molding after concrete pouring, but the traditional formwork is not easy to dismantle after use, and it is easy to cause formwork damage when the formwork is removed, so the reuse rate of the formwork is low and the cost of the formwork is low. The fixing effect is poor, and it is easy to cause displacement during pouring, resulting in damage to the wall structure of the shear wall, and the internal stress cannot meet the requirements. However, the formwork assembled by this system can be assembled by pressing strips without drilling holes on the formwork , to ensure the integrity of the formwork itself, to block the direct contact of the horizontal steel pipe to the formwork, to avoid the slipping of the steel pipe on the formwork, and the steel pipe can cooperate with the pressure bar groove on the bead to increase its contact area, which can greatly improve the stability , the horizontal and vertical cross structure can ensure that the positions between the formworks are fixed. After being tightened by the tensioning mechanism, the concrete between the formworks will be more stable and will not be displaced, so that the formed shear wall structure meets the set requirements. The stress is stable, and the template will not be damaged, and can be reused repeatedly.

拉紧机构包括压紧罩、螺杆和锁紧螺帽,压紧罩压在横向压杆上,压紧罩的端面内凹形成两组弧面凹槽,弧面凹槽对应与横向压杆的外壁贴合,螺杆穿过压紧罩后从两根钢管之间设置在对应的螺杆孔中,锁紧螺帽套合在螺杆上并与压紧罩远离弧面凹槽的一端接触。横向压杆和纵向压杆均是采用空心钢管构成,每组横向压杆中每组横向压杆均由两根相互平行的空心钢管构成,在每个压杆槽中设置的纵向压杆为一根空心钢管,通过压紧罩上的弧面凹槽与横向压杆的外壁进行卡紧,螺杆穿过压紧罩后进行拉紧,保证了模板位置的固定,混凝土浇筑后不会变形,内部应力稳定,而且模板不会受到破坏,能够重复进行利用。 The tensioning mechanism includes a compression cover, a screw rod and a locking nut. The compression cover is pressed on the transverse pressure rod, and the end face of the compression cover is concaved to form two sets of arc surface grooves. The arc surface grooves correspond to the horizontal pressure rods. The outer wall is bonded, the screw rod passes through the compression cover and is set between the two steel pipes in the corresponding screw hole, and the locking nut fits on the screw rod and contacts with the end of the compression cover away from the groove on the arc surface. Both the horizontal pressing bar and the longitudinal pressing bar are made of hollow steel pipes. Each group of horizontal pressing bars in each group of horizontal pressing bars is composed of two hollow steel pipes parallel to each other. The longitudinal pressing bar set in each pressing bar groove is a A hollow steel pipe is clamped with the outer wall of the horizontal pressure rod through the arc groove on the compression cover, and the screw is tightened after passing through the compression cover to ensure the fixed position of the formwork, and the concrete will not be deformed after pouring. The stress is stable, and the template will not be damaged, and can be reused repeatedly.

模板组一般是分为两组平行设置,每组模板组都是由多块模板构成,然后将固定为整体结构的压条板和附板设置在相邻的模板之间,并且压条板保持与模板在同一铅垂平面中,附板与相邻的模板贴住,将纵向压杆卡入压杆槽中,横向压杆设置在纵向压杆表面,并且横向压杆的中心线和纵向压杆的中心线垂直,每组横向压杆和对应的压条板设置在同一高度,将压紧罩压紧在对应的横向压杆上,并且保持横向压杆外壁嵌入弧面凹槽中,然后螺杆穿过压紧罩后从每组横向压杆之间穿过螺杆孔,并且螺杆两端设置在两组模板组外部,在螺杆上旋合上锁紧螺帽完成拼装。 The formwork group is generally divided into two sets of parallel settings, each formwork group is composed of multiple formworks, and then the battens and attached plates fixed as a whole structure are arranged between adjacent formworks, and the battens are kept in contact with the templates. In the same vertical plane, the attached plate is attached to the adjacent formwork, the longitudinal compression bar is snapped into the compression bar groove, the horizontal compression bar is set on the surface of the longitudinal compression bar, and the center line of the horizontal compression bar and the longitudinal compression bar The center line is vertical, and each group of horizontal pressing rods and the corresponding pressing strips are set at the same height, and the pressing cover is pressed on the corresponding horizontal pressing rods, and the outer wall of the horizontal pressing rods is kept embedded in the arc groove, and then the screw passes through After compressing the cover, pass through the screw holes between each group of horizontal pressing rods, and the two ends of the screw rods are arranged outside the two template groups, and the locking nuts are screwed on the screw rods to complete the assembly.

本发明与现有技术相比,具有如下的优点和有益效果:本系统便于装卸,保护了模板的完整性,能够重复利用,增大了压杆的接触面积,能够保证使用的稳固性,对于拉紧后在模板之间浇筑混凝土时更加稳固,不会产生位移,使得形成的剪力墙结构达到设定要求。 Compared with the prior art, the present invention has the following advantages and beneficial effects: the system is convenient for loading and unloading, protects the integrity of the template, can be reused, increases the contact area of the pressing bar, and can ensure the stability of use. After tensioning, it will be more stable when pouring concrete between the templates, and no displacement will occur, so that the formed shear wall structure meets the set requirements.

附图说明 Description of drawings

此处所说明的附图用来提供对本发明实施例的进一步理解,构成本申请的一部分,并不构成对本发明实施例的限定。在附图中: The drawings described here are used to provide a further understanding of the embodiments of the present invention, constitute a part of the application, and do not limit the embodiments of the present invention. In the attached picture:

图1为本发明结构示意图; Fig. 1 is a structural representation of the present invention;

图2为压条的结构示意图; Fig. 2 is the structural representation of layering bar;

图3为本发明的局部侧视图。 Fig. 3 is a partial side view of the present invention.

附图中标记及对应的零部件名称: Marks and corresponding parts names in the attached drawings:

1-压紧罩,2-横向压杆,3-锁紧螺帽,4-纵向压杆,5-螺杆,6-模板,7-压条,8-压条板,9-附板,10-压杆槽,11-螺杆孔。 1-compression cover, 2-horizontal pressure rod, 3-lock nut, 4-longitudinal pressure rod, 5-screw, 6-template, 7-layer, 8-layer board, 9-attached plate, 10-pressure Rod slot, 11-screw hole.

具体实施方式 detailed description

为使本发明的目的、技术方案和优点更加清楚明白,下面结合实施例和附图,对本发明作进一步的详细说明,本发明的示意性实施方式及其说明仅用于解释本发明,并不作为对本发明的限定。 In order to make the purpose, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the examples and accompanying drawings. As a limitation of the present invention.

实施例: Example:

如图1、图2、图3所示,一种剪力墙模板的拼装系统,包括两组相互平行的模板组,所述模板组均是由若干块模板6构成,同一组模板组中相邻的模板6之间均设置有压条7,压条7主要由压条板8和多块附板9构成,压条板8设置对应的模板6之间,且压条板8的厚度与模板6厚度相同,使得压条板8与模板6能够贴合后在铅垂方向在同一平面中,压条板8的顶端和对应的模板6底端接触,压条板8的底端与对应的模板6顶端接触,附板9与压条板8固定为整体结构,附板9的同时与对应的模板6的侧壁接触,同一块压条板8上的相邻附板9之间形成压杆槽10,附板9上设置有螺杆孔11,螺杆孔11同时穿过附板9和压条板8,压杆槽10中均设置有纵向压杆4,在纵向压杆4上设置有若干组横向压杆2,纵向压杆4设置在横向压杆2和压条板8之间,横向压杆2和纵向压杆4相互垂直设置,在每组横向压杆2上设置有若干组拉紧机构,拉紧机构穿过对应的螺杆孔11后分别与两组模板组上的横向压杆2固定;所述横向压杆2中每组横向压杆2均由两根相互平行的空心钢管构成;所述拉紧机构包括压紧罩1、螺杆5和锁紧螺帽3,压紧罩1压在横向压杆2上,压紧罩1的端面内凹形成两组弧面凹槽,弧面凹槽对应与横向压杆2的外壁贴合,螺杆5穿过压紧罩1后从两根钢管之间设置在对应的螺杆孔11中,锁紧螺帽3套合在螺杆5上并与压紧罩1远离弧面凹槽的一端接触。图1所示为系统的其中一侧,另一侧模板按照相同的构造进行拼装,两面模板拼装完成后构成一个整体的剪力墙模板系统。图1所述的模板组为三块模板在铅垂方向拼装而成,每一侧的模板铅垂方向平行设置,模板6采用木板制成,对木模板不裁剪、不开孔,使木模板具有良好的可重复利用性。穿孔压板系提前加工,压条板的厚度与木模板厚度相同,压条板与附板通过木工钉连接成一个整体。附板9之间的间距与纵向压杆的间距一致,使两块相邻附板9之间形成一个纵向压杆槽10,附板9也作为挡板,利用其两端伸出一定的距离与模板产生接触,并且接触位置要在两组模板组相互远离的壁面处,使得模板在拉紧时能够保持稳定,起到阻挡作用,拼装结构不会松散,系统中的部件保持固定。螺杆孔11穿透附板9和压条板8,螺杆孔11之间的间距根据剪力墙高度的不同进行调节。 As shown in Fig. 1, Fig. 2 and Fig. 3, an assembly system of a shear wall formwork includes two sets of formwork groups parallel to each other. Beads 7 are arranged between adjacent formworks 6, and beadings 7 are mainly composed of beading plates 8 and multiple attached plates 9. Beading plates 8 are arranged between corresponding formworks 6, and the thickness of beading plates 8 is the same as that of templates 6. After the beading plate 8 and the formwork 6 can be fitted together in the same plane in the vertical direction, the top of the beading plate 8 is in contact with the bottom end of the corresponding template 6, and the bottom end of the beading plate 8 is in contact with the top of the corresponding template 6, and the attached plate 9 and the beading plate 8 are fixed as an integral structure, and the attached plate 9 is in contact with the side wall of the corresponding formwork 6 at the same time. There are screw holes 11, and the screw holes 11 pass through the attached plate 9 and the batten plate 8 at the same time, the longitudinal pressing bars 4 are arranged in the pressing bar grooves 10, and several groups of transverse pressing bars 2 are arranged on the longitudinal pressing bars 4, and the longitudinal pressing bars 4. It is arranged between the horizontal pressing bar 2 and the batten plate 8. The horizontal pressing bar 2 and the longitudinal pressing bar 4 are arranged perpendicular to each other. Several groups of tensioning mechanisms are arranged on each set of horizontal pressing bars 2, and the tensioning mechanisms pass through the corresponding The screw holes 11 are respectively fixed with the lateral compression rods 2 on the two groups of formwork groups; each group of lateral compression rods 2 in the lateral compression rods 2 is composed of two hollow steel pipes parallel to each other; the tensioning mechanism includes a compression Cover 1, screw rod 5 and lock nut 3, the compression cover 1 is pressed on the transverse pressure rod 2, the end face of the compression cover 1 is concaved to form two sets of arc surface grooves, and the arc surface grooves correspond to the transverse pressure rod 2 The outer wall of the screw rod 5 passes through the compression cover 1 and is set in the corresponding screw hole 11 between the two steel pipes. The locking nut 3 fits on the screw rod 5 and is away from the compression cover 1. one end of the slot. Figure 1 shows one side of the system, and the formwork on the other side is assembled according to the same structure. After the two sides of the formwork are assembled, a whole shear wall formwork system is formed. The template group described in Fig. 1 is formed by assembling three templates in the vertical direction, and the templates on each side are arranged in parallel in the vertical direction. It has good reusability. The perforated pressing board is processed in advance, and the thickness of the pressing board is the same as that of the wood formwork, and the pressing board and the attached board are connected into a whole by carpentry nails. The spacing between the attached plates 9 is consistent with the spacing of the longitudinal pressure bars, so that a longitudinal bar groove 10 is formed between two adjacent attached plates 9, and the attached plates 9 are also used as baffle plates, and the two ends of the attached plates are used to extend a certain distance Make contact with the formwork, and the contact position should be at the wall where the two formwork groups are far away from each other, so that the formwork can remain stable when it is tightened, and play a blocking role, the assembled structure will not be loose, and the components in the system will remain fixed. The screw holes 11 penetrate the attached plate 9 and the batten plate 8, and the distance between the screw holes 11 is adjusted according to the height of the shear wall.

模板组一般是分为两组平行设置,每组模板组都是由多块模板6构成,然后将固定为整体结构的压条板8和附板9设置在相邻的模板6之间,并且压条板8保持与模板6在同一铅垂平面中,压条板8如同是嵌在模板6之间,附板9与相邻的模板6贴住,附板9顶端和底端突出与压条板8的顶端,用于在拉紧时与模板6外表贴紧,起到限位作用,将纵向压杆4卡入压杆槽10中,横向压杆2设置在纵向压杆4表面,并且横向压杆2的中心线和纵向压杆4的中心线垂直,每组横向压杆2和对应的压条板8设置在同一高度,将压紧罩1压紧在对应的横向压杆2上,并且保持横向压杆2外壁嵌入弧面凹槽中,更加稳定,防止打滑,然后螺杆5穿过压紧罩1后从每组横向压杆2之间穿过螺杆孔11,并且螺杆两端设置在两组模板组外部,在螺杆5上旋合上锁紧螺帽3完成拼装,利用这种拼装后形成的结构,能够在浇筑混凝土时更加稳固,不需要在模板上钻孔,保证了模板的完整性,能够多次进行重复利用,模板的结构得到了保护,其内部应力也更加稳定,从而在多次使用时更加安全,浇筑形成的混凝土墙结构稳定。 The formwork group is generally divided into two groups of parallel arrangements, and each group of formwork groups is composed of a plurality of formworks 6, and then the beading plate 8 and the attached plate 9 fixed as an integral structure are arranged between adjacent formworks 6, and the beading The plate 8 is kept in the same vertical plane as the formwork 6, the beading plate 8 is embedded between the formworks 6, the attached plate 9 sticks to the adjacent formwork 6, and the top and bottom ends of the attached plate 9 protrude from the beading plate 8 The top end is used to be tightly attached to the surface of the template 6 when tensioning, and to play a position-limiting role. The longitudinal pressure bar 4 is snapped into the pressure bar groove 10, the horizontal pressure bar 2 is arranged on the surface of the longitudinal pressure bar 4, and the horizontal pressure bar 2 is vertical to the centerline of the longitudinal compression rod 4, each set of horizontal compression rods 2 and the corresponding bead plate 8 are set at the same height, and the compression cover 1 is pressed on the corresponding horizontal compression rod 2, and the horizontal pressure is maintained. The outer wall of the pressure rod 2 is embedded in the arc groove, which is more stable and prevents slipping. Then the screw 5 passes through the compression cover 1 and passes through the screw hole 11 between each group of horizontal pressure rods 2, and the two ends of the screw are arranged in two groups Outside the formwork group, screw the lock nut 3 on the screw rod 5 to complete the assembly. The structure formed after this assembly can be more stable when pouring concrete, and there is no need to drill holes in the formwork to ensure the integrity of the formwork , can be reused many times, the structure of the formwork is protected, and its internal stress is more stable, so it is safer when used multiple times, and the structure of the concrete wall formed by pouring is stable.

以上所述的具体实施方式,对本发明的目的、技术方案和有益效果进行了进一步详细说明,所应理解的是,以上所述仅为本发明的具体实施方式而已,并不用于限定本发明的保护范围,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。 The specific embodiments described above have further described the purpose, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above descriptions are only specific embodiments of the present invention and are not intended to limit the scope of the present invention. Protection scope, within the spirit and principles of the present invention, any modification, equivalent replacement, improvement, etc., shall be included in the protection scope of the present invention.

Claims (5)

1.一种剪力墙模板的拼装系统,其特征在于,包括两组相互平行的模板组,所述模板组均是由若干块模板(6)构成,同一组模板组中相邻的模板(6)之间均设置有压条(7),压条(7)主要由压条板(8)和附板(9)构成,压条板(8)设置对应的模板(6)之间,且压条板(8)的厚度与模板(6)厚度相同,压条板(8)的顶端和对应的模板(6)底端接触,压条板(8)的底端与对应的模板(6)顶端接触,附板(9)与压条板(8)固定为整体结构,附板(9)的同时与对应的模板(6)的侧壁接触,同一块压条板(8)上的相邻附板(9)之间形成压杆槽(10),附板(9)上设置有螺杆孔(11),螺杆孔(11)同时穿过附板(9)和压条板(8),压杆槽(10)中均设置有纵向压杆(4),在纵向压杆(4)上设置有若干组横向压杆(2),纵向压杆(4)设置在横向压杆(2)和压条板(8)之间,横向压杆(2)和纵向压杆(4)相互垂直设置,在每组横向压杆(2)上设置有若干组拉紧机构,拉紧机构穿过对应的螺杆孔(11)后分别与两组模板组上的横向压杆(2)固定。 1. an assembling system of a shear wall formwork, is characterized in that, comprises two groups of formwork groups parallel to each other, and said formwork groups are all made of several formworks (6), adjacent formworks in the same group of formwork groups ( 6) are provided with bead (7), the bead (7) is mainly composed of bead (8) and attached plate (9), the bead (8) is set between the corresponding formwork (6), and the bead ( 8) has the same thickness as the template (6), the top of the batten (8) is in contact with the bottom of the corresponding template (6), and the bottom of the batten (8) is in contact with the top of the corresponding template (6). (9) is fixed with the batten board (8) as an integral structure, and the attached board (9) is in contact with the side wall of the corresponding formwork (6) at the same time, and the adjacent attached board (9) on the same batten board (8) A bar groove (10) is formed between them, and a screw hole (11) is provided on the attachment plate (9). The screw hole (11) passes through the attachment plate (9) and the bead plate (8) at the same time. Both are provided with longitudinal pressing rods (4), on which several groups of horizontal pressing rods (2) are arranged, and the longitudinal pressing rods (4) are arranged between the horizontal pressing rods (2) and the battens (8) Between them, the horizontal pressing rods (2) and the longitudinal pressing rods (4) are arranged perpendicularly to each other, and several sets of tensioning mechanisms are arranged on each set of horizontal pressing rods (2). After the tensioning mechanisms pass through the corresponding screw holes (11), They are respectively fixed with the horizontal pressing rods (2) on the two groups of formwork groups. 2.根据权利要求1所述的一种剪力墙模板的拼装系统,其特征在于,所述横向压杆(2)中每组横向压杆(2)均由两根相互平行的空心钢管构成。 2. The assembling system of a shear wall formwork according to claim 1, characterized in that, each set of transverse compression bars (2) in the transverse compression bars (2) is composed of two parallel hollow steel pipes . 3.根据权利要求2所述的一种剪力墙模板的拼装系统,其特征在于,所述拉紧机构包括压紧罩(1)、螺杆(5)和锁紧螺帽(3),压紧罩(1)压在横向压杆(2)上,压紧罩(1)的端面内凹形成两组弧面凹槽,弧面凹槽对应与横向压杆(2)的外壁贴合,螺杆(5)穿过压紧罩(1)后从横向压杆(2)的两根钢管之间设置在对应的螺杆孔(11)中,锁紧螺帽(3)套合在螺杆(5)上并与压紧罩(1)远离弧面凹槽的一端接触。 3. The assembling system of a shear wall formwork according to claim 2, characterized in that, the tensioning mechanism includes a compression cover (1), a screw (5) and a locking nut (3), the compression The tight cover (1) is pressed on the transverse pressure rod (2), and the end surface of the compression cover (1) is concave to form two sets of arc surface grooves, and the arc surface grooves correspond to the outer wall of the transverse pressure rod (2). After the screw (5) passes through the compression cover (1), it is set between the two steel pipes of the horizontal pressure rod (2) in the corresponding screw hole (11), and the locking nut (3) is sleeved on the screw (5) ) and contact with the end of the compression cover (1) away from the arc groove. 4.根据权利要求1所述的一种剪力墙模板的拼装系统,其特征在于,所述纵向压杆(4)为空心钢管。 4. The assembling system of a shear wall formwork according to claim 1, characterized in that, the longitudinal compression bar (4) is a hollow steel pipe. 5.一种剪力墙模板的拼装方法,其特征在于,将多块模板依次沿着铅垂方向平行设置,然后将固定为整体结构的压条板(8)和附板(9)设置在相邻的模板(6)之间,并且压条板(8)保持与模板(6)在同一铅垂平面中,附板(9)与相邻的模板(6)贴住,将纵向压杆(4)卡入压杆槽(10)中,横向压杆(2)设置在纵向压杆(4)表面,并且横向压杆(2)的中心线和纵向压杆(4)的中心线垂直,每组横向压杆(2)和对应的压条板(8)设置在同一高度,将压紧罩(1)压紧在对应的横向压杆(2)上,并且保持横向压杆(2)外壁嵌入弧面凹槽中,然后螺杆(5)穿过压紧罩(1)后从每组横向压杆(2)之间穿过螺杆孔(11),并且螺杆两端设置在两组模板组外部,在螺杆(5)上旋合上锁紧螺帽(3)完成拼装。 5. A method for assembling a shear wall formwork, characterized in that multiple formworks are arranged in parallel along the vertical direction in turn, and then the beading board (8) and the attached board (9) fixed as the overall structure are arranged on the corresponding Between the adjacent templates (6), and the batten board (8) is kept in the same vertical plane as the template (6), the attached board (9) sticks to the adjacent template (6), and the longitudinal pressing bar (4 ) into the bar groove (10), the transverse bar (2) is set on the surface of the longitudinal bar (4), and the center line of the transverse bar (2) is perpendicular to the center line of the longitudinal bar (4). Set the set of horizontal pressing rods (2) and the corresponding pressing strips (8) at the same height, press the pressing cover (1) on the corresponding horizontal pressing rods (2), and keep the outer wall of the horizontal pressing rods (2) embedded In the groove of the arc surface, the screw (5) passes through the compression cover (1) and passes through the screw hole (11) between each set of horizontal pressing rods (2), and the two ends of the screw are set outside the two template groups , screw the locking nut (3) on the screw rod (5) to complete the assembly.
CN201610151868.0A 2016-03-17 2016-03-17 A kind of assembling system and assembling method of shear wall formwork Active CN105649321B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610151868.0A CN105649321B (en) 2016-03-17 2016-03-17 A kind of assembling system and assembling method of shear wall formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610151868.0A CN105649321B (en) 2016-03-17 2016-03-17 A kind of assembling system and assembling method of shear wall formwork

Publications (2)

Publication Number Publication Date
CN105649321A true CN105649321A (en) 2016-06-08
CN105649321B CN105649321B (en) 2017-08-01

Family

ID=56493929

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610151868.0A Active CN105649321B (en) 2016-03-17 2016-03-17 A kind of assembling system and assembling method of shear wall formwork

Country Status (1)

Country Link
CN (1) CN105649321B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108994971A (en) * 2018-06-30 2018-12-14 吴兴铭锯钢琴厂 Perforating device is used in a kind of production of piano
CN110295738A (en) * 2019-06-21 2019-10-01 中国一冶集团有限公司 Shear wall formwork structure and construction method
CN112443159A (en) * 2020-12-02 2021-03-05 中建三局集团有限公司 Template tapping-free clamp and construction method thereof
CN113550584A (en) * 2021-09-22 2021-10-26 江苏兴宇铝业科技有限公司 A method of using a building aluminum module fastening system
CN114458006A (en) * 2022-01-25 2022-05-10 中国一冶集团有限公司 Cast in situ concrete wallboard steel bar formwork fixed knot constructs

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1999019127A2 (en) * 1997-10-16 1999-04-22 Bruce Liuska Wall forming system and method of forming a wall of hardenable material
US20050035268A1 (en) * 2002-10-23 2005-02-17 Ward Philip T. Concrete forming method employing threaded coupling slots
US20140263942A1 (en) * 2013-03-15 2014-09-18 Romeo Ilarian Ciuperca Hybrid insulated concrete form and method of making and using same
CN203961274U (en) * 2014-06-12 2014-11-26 四川省晟茂建设有限公司 Great wall template support system
CN205387817U (en) * 2016-03-17 2016-07-20 中国五冶集团有限公司 Shear wall template's system of assembling

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1999019127A2 (en) * 1997-10-16 1999-04-22 Bruce Liuska Wall forming system and method of forming a wall of hardenable material
US20050035268A1 (en) * 2002-10-23 2005-02-17 Ward Philip T. Concrete forming method employing threaded coupling slots
US20140263942A1 (en) * 2013-03-15 2014-09-18 Romeo Ilarian Ciuperca Hybrid insulated concrete form and method of making and using same
CN203961274U (en) * 2014-06-12 2014-11-26 四川省晟茂建设有限公司 Great wall template support system
CN205387817U (en) * 2016-03-17 2016-07-20 中国五冶集团有限公司 Shear wall template's system of assembling

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108994971A (en) * 2018-06-30 2018-12-14 吴兴铭锯钢琴厂 Perforating device is used in a kind of production of piano
CN110295738A (en) * 2019-06-21 2019-10-01 中国一冶集团有限公司 Shear wall formwork structure and construction method
CN112443159A (en) * 2020-12-02 2021-03-05 中建三局集团有限公司 Template tapping-free clamp and construction method thereof
CN113550584A (en) * 2021-09-22 2021-10-26 江苏兴宇铝业科技有限公司 A method of using a building aluminum module fastening system
CN113550584B (en) * 2021-09-22 2021-11-26 江苏兴宇铝业科技有限公司 Use method of building aluminum module fastening system
CN114458006A (en) * 2022-01-25 2022-05-10 中国一冶集团有限公司 Cast in situ concrete wallboard steel bar formwork fixed knot constructs

Also Published As

Publication number Publication date
CN105649321B (en) 2017-08-01

Similar Documents

Publication Publication Date Title
CN105649321B (en) A kind of assembling system and assembling method of shear wall formwork
US8434280B2 (en) Modular building units
JP5806676B2 (en) Method and apparatus for reinforcing and reducing the weight of floor and roof frame structures
KR20200008685A (en) Method for reinforcing the Earthquake of a concrete columns
CN107859403B (en) Assembled building structure
JP5856646B2 (en) Wooden truss beam unit and its installation method
KR20140010265A (en) Reusable Waffle Slab Formwork Assembly
CN108035546A (en) A kind of shear wall formwork for placing fixing device for building
CN211897810U (en) A single-column pier girder bridge and its anti-overturning device
KR20180090230A (en) Device for reinforcing the Earthquake of a concrete columns and Methods
KR101991938B1 (en) Device for reinforcing the Earthquake of a concrete columns and Methods
CN205387817U (en) Shear wall template's system of assembling
KR20200141855A (en) Construction structure for wall
CN210289158U (en) Temporary support device for connecting laminated plate with beam or wall
KR20180090231A (en) Device for reinforcing the Earthquake of a concrete columns and Methods
CN110894753B (en) A formwork device for a wall and a method of making the same
KR100930003B1 (en) Slab formwork and slab construction method using the same
KR20230025210A (en) A foundation set for a traditional korean house
CN219343541U (en) Connecting device for steel frame beam and concrete column
CN106223465A (en) Assembly concrete orthogonal-diagonal lattice space lattice boxlike bundled tube structure and manufacture method
CN219100544U (en) Precast concrete assembly stair
CN211817977U (en) Steel bar formwork structure of bearing column
KR102720024B1 (en) Form bar having inclined plate
CN218933506U (en) Wall body anti-seismic mechanism is built in room
KR101320697B1 (en) Concrete mold connector and method for connecting concrete mold using concrete mold connector

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant