CN105625687A - Mud effect imitating ground paving method - Google Patents

Mud effect imitating ground paving method Download PDF

Info

Publication number
CN105625687A
CN105625687A CN201610074761.0A CN201610074761A CN105625687A CN 105625687 A CN105625687 A CN 105625687A CN 201610074761 A CN201610074761 A CN 201610074761A CN 105625687 A CN105625687 A CN 105625687A
Authority
CN
China
Prior art keywords
mud
imitative
spatula
concrete
effect
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610074761.0A
Other languages
Chinese (zh)
Other versions
CN105625687B (en
Inventor
王理忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Scape Orange Stone Ecological Art Ground Science And Technology Co Ltd In Beijing
Original Assignee
Scape Orange Stone Ecological Art Ground Science And Technology Co Ltd In Beijing
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Scape Orange Stone Ecological Art Ground Science And Technology Co Ltd In Beijing filed Critical Scape Orange Stone Ecological Art Ground Science And Technology Co Ltd In Beijing
Priority to CN201610074761.0A priority Critical patent/CN105625687B/en
Publication of CN105625687A publication Critical patent/CN105625687A/en
Application granted granted Critical
Publication of CN105625687B publication Critical patent/CN105625687B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors

Abstract

The invention discloses a mud effect imitating ground paving method which comprises the following steps of (1) paving light brown concrete; (2) slicking the concrete by using a darby slicker, smoothing and extracting mud by using a magnesium spatula or a fiber spatula; (3) surface finishing by using a steel spatula, and manufacturing a rolloff; (4) scattering an aggregate, and beating properly, wherein the aggregate scattered firstly is big in grain size and the aggregate scattered later is small in grain size; (5) scattering a natural ash releasing agent; (6) coining by using a mud line imitating die; (7) isolating and maintaining. By the mud effect imitating ground paving method disclosed by the invention, a natural and real mud ground effect can be imitated so as to satisfy modern architecture decoration requirements.

Description

A kind of imitative mud effect ground pavement method
Technical field
This patent disclosure relates generally to building decoration field, be specifically related to a kind of imitative mud effect ground pavement method.
Background technology
Requiring more and more higher with the decorative effect of landing ground with the collocation of building and view, the theme decorative effect emulation property on ground is also more and more higher, and the effect on some theme ground adopts traditional paving process cannot realize. In theme park, ground pavement typically requires the effect reaching imitative natural reality, but traditional handicraft cannot meet, by the improvement of technique process so that it is reach to meet the effect of true nature.
Summary of the invention
It is an object of the invention to provide a kind of imitative mud effect ground pavement method, copy out naturally real mud ground effect.
Imitative mud effect ground pavement method according to the present invention, comprises the following steps:
(1) light brown that paves concrete;
(2) darby strikes off, and magnesium spatula or fiber spatula are closed flat and carry slurry;
(3) face is received in steel spatula, makes rolling simultaneously;
(4) spread aggregate, first spread aggregate size big after to spread aggregate size little, suitably pat;
(5) nature ash releasing agent is spread;
(6) imprint with imitative mud texture mould;
(7) isolation maintenance.
In a preferred embodiment of the invention, further comprise the steps of:
After step (2) completes, shed the hardening agent of designated color, then carry out step (3). Hardening agent can Concrete Structure painted. Color can select according to design.
In another preferred embodiment of the invention, further comprise the steps of:
(8) it is rinsed after concrete strength reaches 75%, scrubs with the hydrochloric acid solution of dilution, then rinse with water;
(9) treat that ground is dried, carry out sealing operation with the sealant of oiliness or matt effect.
In one particular embodiment of the present invention, wherein the middle slump laid of step (1) controls at 10 �� 3cm.
According to the imitative ice face effect earth construction of one and method for paving, it is possible to copy out naturally real mud ground effect, to meet the demand of modem architectural ornament.
Detailed description of the invention
(1) prepare before construction
Job site should be surveyed, it is determined that design and arrangement and method for construction before construction.
Concrete foundation surface layer does imitative mud construction before, for the construction joint (subsiding crack, expansion joint) on original surface layer and in dry lay along seam move towards malthoid, to prevent the concrete base layer deformation stress rupture to imitative mud layer.
Before formal construction, it usually needs make imitative mud ground face fade effect model, verify whether the impressing concrete for making match ratio mixing and stirring material meets requirement of strength; And whether checking impressing effect and hardening agent, the releasing agent color effects used meet designing requirement.
(2) material requirements
1, concrete requires:
Concrete entire body color is generally light brown, and slump should ensure that at about 10 �� 3cm.
2, hardening agent and releasing agent require:
Selection: the color of hardening agent and releasing agent is determined according to design, the color of releasing agent generally selects nature ash.
Consumption: hardening agent consumption is every bag and uses 6 square metres, and releasing agent consumption is every bag and sheds 50 square metres; Wherein every bag is 25kg.
3, aggregate requirements:
Aggregate includes color pebble, its particle diameter be divided into 4-6mm, 8-10mm, 20-30mm not etc., arrange in pairs or groups according to certain ratio. Aggregate can also include various shell.
(3) imitative mud effect construction
1, being cleaned up by the work surface that need to construct, protection job site is not contaminated.
2, by impressing effect design requirement, first carrying out color concrete cast, finished surface carries out paving vibrating, and darby strikes off, magnesium spatula or fiber spatula are closed flat and carry slurry, and light is received in steel spatula, makes rolling simultaneously. Time suitable, carry out after shedding hardening agent receiving light. Pour into a mould that concrete receipts light is floating should meet drainage grade designing requirement and whole structure.
When large area continuous concrete placing, in order to prevent, concrete deformation cracking from need to arrange movement joint, rise seam. The common tailor's of setting sequence can affect its overall artistic effect, in the present invention, the setting of construction joint is to do abnormity bending with high-strength steel sheet, imitative mud construction surface arranges requirement by construction joint crack, deformation is ftractureed because volume is relatively big so both to prevent concrete, also makes its whole structure be more nearly the practical situation of imitative mud.
3, shed aggregate, be first sprinkled upon crack place, after spread other ground, first spread aggregate size big after to spread aggregate little, suitably pat.
4, when concrete surface humidity carries out embossing process steps when 20-35%, first raise and spread releasing agent, raise along concrete surface tangential direction and spread, it is ensured that raise sprinkle even, it is ensured that exhaustive. Releasing agent is raised after spreading, and adopts imitative mud texture mould to imprint, and adopts polylith mould closely to splice continuously and imprints, to ensure impressing texture continuity.
5, the work face completing region being made isolating and protecting, the time is generally 7 days.
6, it is rinsed after concrete strength reaches 75% after 7 days.
Rinsing requirement: the releasing agent of surface attachment is rinsed well completely, its degree of adhesion depth looked by the releasing agent being attached to concrete topping, scrubs in right amount with the hydrochloric acid solution of dilution so that it is clear layer, be imbued with stereovision.
7, after upper one procedure terminates, check whether construction quality exists mass defect, and whether various aggregates drop phenomenon, if meet designing requirement, rectification existing problems.
8, generally, to be checked errorless, again rinse, treat that ground is dried, carry out sealing operation with oiliness or matt effect sealant. Cleaning dirt and spot it is prone to by the ground after encapsulation process.
9, ground in the finished can also sprinkle leaves, branch, to simulate true ground.
It will be appreciated by those skilled in the art that the step that is embodied as described above is only for being better understood from the present invention, in being embodied as, it is possible to suitably adjust as required.

Claims (4)

1. an imitative mud effect ground pavement method, comprises the following steps:
(1) light brown that paves concrete;
(2) darby strikes off, and magnesium spatula or fiber spatula are closed flat and carry slurry;
(3) face is received in steel spatula, makes rolling simultaneously;
(4) spread aggregate, first spread aggregate size big after to spread aggregate size little, suitably pat;
(5) nature ash releasing agent is spread;
(6) imprint with imitative mud texture mould;
(7) isolation maintenance.
2. imitative mud effect ground pavement method according to claim 1, further comprises the steps of:
After step (2) completes, shed the hardening agent of designated color, then carry out step (3).
3. imitative mud effect ground pavement method according to claim 1, further comprises the steps of:
(8) it is rinsed after concrete strength reaches 75%, scrubs with the hydrochloric acid solution of dilution, then rinse with water;
(9) treat that ground is dried, carry out sealing operation with the sealant of oiliness or matt effect.
4. imitative mud effect ground pavement method according to claim 1, the slump wherein laid in step (1) controls at 10 �� 3cm.
CN201610074761.0A 2016-02-02 2016-02-02 A kind of imitative mud effect ground pavement method Active CN105625687B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610074761.0A CN105625687B (en) 2016-02-02 2016-02-02 A kind of imitative mud effect ground pavement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610074761.0A CN105625687B (en) 2016-02-02 2016-02-02 A kind of imitative mud effect ground pavement method

Publications (2)

Publication Number Publication Date
CN105625687A true CN105625687A (en) 2016-06-01
CN105625687B CN105625687B (en) 2018-09-11

Family

ID=56040993

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610074761.0A Active CN105625687B (en) 2016-02-02 2016-02-02 A kind of imitative mud effect ground pavement method

Country Status (1)

Country Link
CN (1) CN105625687B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10102729A (en) * 1996-10-03 1998-04-21 San Apro Kk Polyurethane leveling material, and leveling method using it
CN1492105A (en) * 2003-09-04 2004-04-28 俞子平 Concrete colour embossing ground floor technology
JP2007283607A (en) * 2006-04-14 2007-11-01 Hachiya Kenzai Kogyo Kk Molding method of concrete
KR20100039775A (en) * 2008-10-08 2010-04-16 삼중씨엠텍(주) Constructing method of color pattern floors
CN104032930A (en) * 2014-06-27 2014-09-10 中建八局第二建设有限公司 Press molded concrete ground construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10102729A (en) * 1996-10-03 1998-04-21 San Apro Kk Polyurethane leveling material, and leveling method using it
CN1492105A (en) * 2003-09-04 2004-04-28 俞子平 Concrete colour embossing ground floor technology
JP2007283607A (en) * 2006-04-14 2007-11-01 Hachiya Kenzai Kogyo Kk Molding method of concrete
KR20100039775A (en) * 2008-10-08 2010-04-16 삼중씨엠텍(주) Constructing method of color pattern floors
CN104032930A (en) * 2014-06-27 2014-09-10 中建八局第二建设有限公司 Press molded concrete ground construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张苏玲: "《彩色压印地坪在湿陷性黄土地区的应用》", 《山西建筑》 *
戴超: "《复杂分隔多向找坡彩色压印混凝土地坪施工技术》", 《施工技术》 *

Also Published As

Publication number Publication date
CN105625687B (en) 2018-09-11

Similar Documents

Publication Publication Date Title
CN104032930A (en) Press molded concrete ground construction method
CN103866669B (en) The preparation method that a kind of surface different colours or material aggregate realize the cement permeable concrete ground structure of fade effect
CN109025343A (en) A kind of hollowing displacement repairerment engineering method of hollowing outdoor tile
CN104746772B (en) Ash concrete hollow partition board anti-cracking construction method
CN102140836A (en) Construction method of large-size floor tile
CN106499091A (en) A kind of assembling type partition wall construction method based on ALC plates
CN109838065A (en) A kind of ground brick flooring paving construction method
CN103556557A (en) Manufacturing method of color concrete granite flamed-surface terrace
CN101260742A (en) Grouting reinforcement process for harnessing Tibet ancient architecture detached murals
CN107338967A (en) A kind of new technology and new material of aging blocks outdoor tile facing renewal and reform
CN109057385A (en) Engineering method is repaired in the fixed pin part slip casting of inlet of a kind of hollowing inner-outer wall ceramic tile, stone material
CN203977688U (en) The decoration integrated side fascia of a kind of structural thermal insulation
CN107292060A (en) Basement roadway applications method based on BIM technology
CN105625687A (en) Mud effect imitating ground paving method
CN106639135A (en) Novel assembled type H-shaped prefabricated composite wall board and preparation method thereof
CN101973782B (en) Method for repairing white marble cultural relic
CN109266224A (en) A kind of water-repellent paint and its use construction method
CN105735614B (en) A kind of imitative ice face effect ground structure and method for paving
CN108385614A (en) A kind of concrete facing board construction method of anti-floating towing force
CN108863167A (en) Concrete reparation and means of defence and structure based on asphalt material
CN102691423B (en) Construction method for duplicating soft mould and installing building granitic plaster floriation member
CN110344527A (en) A kind of anchoring type is secondary to pour diamond dust abrasion-resistant ground and its construction technology
CN109853888A (en) A kind of historical building plucking wall surface construction technology
CN104532968A (en) Method of preventing connecting part between concrete structure and rear filling wall from being cracked
CN109025167A (en) A kind of construction method of colour die floor

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 100070 Fengtai District, Beijing, South Fourth Ring Road 188, two, 5, 6 floor (Park)

Applicant after: Beijing Zhongjing orange stone Polytron Technologies Inc

Address before: 100000 Fengtai District, Beijing, South Fourth Ring Road 188, two, 5, six floor.

Applicant before: BEIJING ORANGESTONE ECOLOGICAL ART GROUND TECHNOLOGY Co.,Ltd.

GR01 Patent grant
GR01 Patent grant