CN105604223B - Dried hanging hang structure and its application method for stone curtain wall - Google Patents
Dried hanging hang structure and its application method for stone curtain wall Download PDFInfo
- Publication number
- CN105604223B CN105604223B CN201510961717.7A CN201510961717A CN105604223B CN 105604223 B CN105604223 B CN 105604223B CN 201510961717 A CN201510961717 A CN 201510961717A CN 105604223 B CN105604223 B CN 105604223B
- Authority
- CN
- China
- Prior art keywords
- keel
- pendant
- stone material
- material plate
- groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Finishing Walls (AREA)
Abstract
The present invention relates to a kind of dried hanging hang structures of stone curtain wall, including stone material plate, keel and dry-hanging component, the end face of the stone material plate is provided with the groove being coupled with dry-hanging component, it is characterized by: the dry-hanging component includes pendant and locating part, the pendant is flexibly connected by connector with keel, one end of the pendant is provided with the hook being coupled with the groove, and the locating part is fixed on keel or pendant, vertical with keel after installing stone material plate to limit pendant.The combination of dry-hanging component provided by the present invention is simpler, easy for installation, and fast, a worker can be operated, and solving dry-hanging component in the prior art, structure is complicated, erroneous for installation and there are security risk, and whole installation process is time saving and energy saving.
Description
Technical field
The present invention relates to stone curtain wall, especially a kind of dried hanging hang structure and its application method for stone curtain wall.
Background technique
Notification number is that the patent of CN102720288A discloses a kind of connection method of welding curtain wall dried hanging part, the patent
Disclose it is a kind of including keel, corner code, the flat code composition of stone material corner brace, double hook dried hanging hang structure, in [0035] section of specification,
Dried hanging hang structure also needs fixing stone corner brace, stone material corner brace is fixed on keel after keel are installed on wall by corner code
Two sides, then connect the flat code of double hook ([0036] section of specification) on the stone material corner brace fixed, and double hook put down into code 4
It is fixed in the slot that stone material is opened.From the foregoing, it can be seen that the dried hanging hang structure of the patent disclosure is also set between keel and the flat code of double hook
It is equipped with stone material corner brace, during installation, the flat code of double hook for direct fixing stone will be by installation stone material corner brace
It can be connected and fixed with keel, it is really cumbersome in actual operation in this way;Moreover, all being adopted between keel, stone material corner brace, the flat code of double hook
It is connected with, installs time-consuming and laborious;In addition, the connection structure of multicomponent, easily because a certain component therein does not connect
It is good, and loosen, it causes danger.In addition, can clearly be known in the document by attached drawing, which is being installed
In the process, it is first to fix the flat code of the double hook of fixing stone bottom, then stone material is placed on the flat code of the double hook, will then fixes
The flat code of double hook above the curtain wall corresponds to the groove fixing stone corner brace of stone material upper end, and completion is completely fixed the stone material, it
Afterwards, followed by the flat code of the double hook that stone material is placed in upper layer, so circulation installation upwards.In the installation process, the flat code of double hook is
It cannot all be installed before stone material is installed, i.e., can only replace installation with stone material, and, the flat code of double hook will be bolted, because
And such mounting means at least needs two people, inconvenient for operation and high labor cost.
Summary of the invention
Therefore, in view of the above-mentioned problems, the present invention proposes that a kind of structure is simple, easy for installation, efficiently dry-fasten stone curtain wall
Structure and its application method.
The present invention adopts the following technical scheme:
The dried hanging hang structure of stone curtain wall, including stone material plate, keel and dry-hanging component, the end face setting of the stone material plate
There is the groove being coupled with dry-hanging component, it is characterised in that: the dry-hanging component includes pendant and locating part, and the pendant is logical
It crosses connector to be flexibly connected with keel, one end of the pendant is provided with the hook being coupled with the groove, the locating part
It is fixed on keel or pendant, it is vertical with keel after stone material plate is installed to limit pendant.
Further, the connector is bolt, which, can be centered on bolt after being bolted to keel
Circular-rotation.
Further, the connector is the convex block for being set to pendant two sides, be provided on the keel of the pendant two sides with
The groove that the convex block is cooperatively connected, the pendant is by realizing the connection with keel for convex block clamping and groove.
Further, the cross section of the convex block is round or rectangle, is cooperatively connected on the keel with the convex block recessed
Slot end is also round or rectangle.
Further, the locating part is fixed on keel or pendant, and is located at the rear of connector.
Further, the locating part is fixed on keel or pendant, and is located at the front of connector.
Further, the locating part is fixed on keel;The locating part is the crossbeam for connecting more keel.
Further, the hook is dove-tail form hook or T-shape hook, with fixed two adjacent stone plates simultaneously
Block.
Beneficial effects of the present invention: the combination of dry-hanging component provided by the present invention is simpler, easy for installation, fast,
One worker can be operated, and solving dry-hanging component in the prior art, structure is complicated, erroneous for installation and there are security risks, entirely
Installation process is time saving and energy saving.
Detailed description of the invention
Fig. 1 is first embodiment of the present invention front schematic view;
Fig. 2 is that the locating part in the present invention is fixed on pendant, and is located at the rear schematic diagram of connector;
Fig. 3 is that the locating part in the present invention is fixed on keel, and is located at the front schematic diagram of connector;
Fig. 4 is that the locating part in the present invention is fixed on pendant, and is located at the front schematic diagram of connector;
Fig. 5 is the stereoscopic schematic diagram of the second embodiment of the present invention;
Fig. 6 is the longitudinal profile schematic diagram of the second embodiment of the present invention;
Fig. 7 is that the locating part of the second embodiment in the present invention is fixed on keel, and the front for being located at connector is illustrated
Figure.
Specific embodiment
Now in conjunction with the drawings and specific embodiments, the present invention is further described:
Embodiment 1
Referring to Fig. 1, the present invention is used for the dried hanging hang structure of stone curtain wall, including stone material plate 4, keel 1 and dry-hanging component
2, the groove 41 being coupled with dry-hanging component is provided on the upper and lower end face of the stone material plate 4, and the dry-hanging component 2 includes
Pendant 21 and locating part 22, the pendant 21 are connected to the side 11 of keel 1 by bolt 3, and can be with bolt 3 for center circumference
Rotation, one end of the pendant 21 are provided with " T " hook 211 being coupled with the groove 41, and the locating part 22 is fixed on
On keel 1, and it is located at the rear of bolt 3, it is vertical with keel 1 after stone material plate 4 is installed to limit pendant 21.
In practice of construction, such as Fig. 1, all pendants 21 can be installed on keel by bolt 3 in advance, and make pendant 21 can
It rotates relative to keel 1, before placing stone material plate 4, pendant 21 is rotated to horizontal position, then, by stone plate
Stone material plate 4, is placed on pendant 21 that (i.e. pendant blocks under the stone material plate by the corresponding hook 211 of groove 41 on block 4
End), because locating part 22 limits the tail end of pendant 21, make after stone material plate 4 is installed, pendant 21 will not continue the inverse time because of load-bearing
Needle rotation;Stone material plate is installed and then rotates the pendant 21 on upper layer to horizontal position, so that the pendant 21 on the upper layer blocks
The upper end of the stone material plate, followed by, the stone material plate on upper layer is placed on the pendant 21 on aforementioned upper layer, in this way, recycle to
Upper installation.The dry-hanging component that the invention is related to makes 2 structure of dry-hanging component more by the way that rotation pendant 21 is arranged on keel 1
Simply, easier for installation, solving dry-hanging component in the prior art, structure is complicated, erroneous for installation and asking there are security risk
Topic;In addition, the 21 fixing stone plate of rotation pendant is simple and fast (need to only rotate down), a worker be can be operated,
It is time saving and energy saving, greatly improve operating efficiency.
It is worth explanation, in above-described embodiment, the pendant 21 may also set up (to be not limited to fix with the centre of keel 1
In the side of keel);The hook 211 can also be dove-tail form, as long as two adjacent stone material plates, shape can be fixed simultaneously
It is unlimited.
In addition, the locating part 22 can be directly welded on keel 1, can also be fixed on certainly by connector, such as bolt
On keel 1;And the locating part is also securable on pendant 21, such as Fig. 2 and Fig. 4;The locating part can also be placed in bolt 3 simultaneously
Front or behind, such as Fig. 1-Fig. 4;The shape of the locating part 22 can be bulk, sheet, strip, or the above-mentioned shape with limiting slot
Shape, when locating part 22 is fixed on keel, which can also be the crossbeam of the multiple keel of connection, to be block in locating part 22
When shape, sheet, strip, saves and locating part is installed at the keel matched with each pendant;To sum up, as long as pendant 21 can be limited
Vertical with keel 1 after installing stone material plate 4, the shape of locating part and position are unlimited.
Embodiment 2
Please refer to Fig. 5, Fig. 6, the present invention is used for the dried hanging hang structure of stone curtain wall, including stone material plate 4, keel 1 and cladding
Component 2 is provided with the groove 41 being coupled with dry-hanging component, the dry-hanging component 2 on the upper and lower end face of the stone material plate 4
Including pendant 23 and locating part 22, the two sides of the pendant 23 are provided with rectangular cam 232, set on the side 11 of the keel 1
It is equipped with the rectangular recess 111 being cooperatively connected with convex block 232, the pendant 23 is by realizing the clamping of convex block 232 and groove 111
With the connection of keel 1;For convenience, efficiently by the clamping of convex block 232 with groove 111, the height of the groove 111 is greater than convex block
232 thickness;One end of the pendant 23 is provided with the dove-tail form hook 231 being coupled with the groove 41, the locating part
22 are fixed on keel 1, and are located at the rear of convex block 232, vertical with keel 1 after installing stone material plate 4 to limit pendant 21.
In practice of construction, such as Fig. 5-Fig. 6, the locating part 22 is to be fixed on keel in advance, when installation, by pendant 23
It is entered between two keel 1 with the state of fore-and-aft tilt plus lateral inclination, after pendant 23 enters groove 111, by pendant 23
With it is longitudinal be laterally each perpendicular to the state clampings of keel 1 with groove 111, while being limited part 22 and being limited in its bottom, with
Make with keel still to keep plumbness after stone material plate is installed;Then, by the corresponding hook of groove 41 in stone material plate 4
231 (i.e. pendants block the stone material plate lower end), stone material plate 4 is placed on pendant 23, followed by, in the above described manner,
Then the pendant 23 on installation upper layer, then installs the stone material plate on upper layer in the upper layer pendant with the upper end of fixing stone plate
On, so circulation installation upwards.
In the embodiment, convex block 232 is integrally formed with pendant 23, convex block can also be connected and be hung by connector certainly
On part.The cross section of convex block 232 is rectangle setting in the embodiment, and groove 111 with matching is also rectangle, rectangle setting
Help to limit pendant relative to keel rotation, and more firm with the connection of keel;It is worth noting that the rectangular recess
As long as 111 guarantee with rectangular cam 232 cooperate part (i.e. the bottom of Fig. 5 further groove 111) be rectangle (Fig. 5 further groove 111
Top shape is unlimited) it can reach the purpose of this programme;In addition, the rectangular arrangement is a kind of preferred embodiment, it can also be by convex block 232
The other shapes that cross section is circle etc. are set as, groove 111 with matching also guarantees for respective shapes or only and rectangle
The part that convex block 232 cooperates is respective shapes.
In the embodiment, the hook 231 can also be T-shape, as long as two adjacent stone material plates can be fixed simultaneously,
Shape is unlimited.
Referring to Fig. 7, the locating part 22 may be alternatively located at the front of convex block when locating part 22 is fixed on keel, still,
Vertical with keel after pendant installs stone material plate to guarantee, the convex block 232 need to be limited in the top of groove 111;In addition, scheming
In 5, Fig. 6 scheme, locating part 22 is affixed on keel, in fact, locating part 22 can also not changed to the premise of position
Under, it is directly fixed on pendant 23, can also achieve the object of the present invention.
As described in Example 1, locating part 22 can be directly welded on keel 1, certainly can also by connector, such as bolt,
It is fixed on keel 1;The shape of locating part 22 can also be bulk, sheet, strip in the embodiment, or with the above-mentioned of limiting slot
Shape, when locating part 22 is fixed on keel, which can also be the crossbeam of the multiple keel of connection, to be in locating part 22
When bulk, sheet, strip, saves and locating part is installed at the keel matched with each pendant;To sum up, as long as pendant can be limited
23 is vertical with keel 1 after installing stone material plate 4, and the shape of locating part and position are unlimited.
A method of stone curtain wall being installed using the dried hanging hang structure of embodiment 2, comprising: step 1: by dry hanging article with longitudinal direction
Inclination plus the state of lateral inclination enter between two keel, after pendant 23 enters groove 111, by pendant 23 with it is longitudinal with
It is laterally each perpendicular in the state clamping and groove 111 of keel 1, while being limited part limitation, so as to be hung after installation stone material plate
Part and keel still keep plumbness;
Step 2: by the corresponding hook of groove stone material plate lower end, stone material plate 4 being placed on pendant 23;Step
3: upper layer pendant is connected to keel by the method for repeating step 1, and the upper layer is linked up with to the groove of corresponding stone material plate upper end, complete
At the installation of monolithic stone material plate;
The installation circulation step 2 of the stone material plate on upper layer, step 3 operation;If installing the stone material plate of a new column, circulation step
Rapid 1, step 2, step 3 operation.
Although specifically showing and describing the present invention in conjunction with preferred embodiment, those skilled in the art should be bright
It is white, it is not departing from the spirit and scope of the present invention defined by the appended claims, it in the form and details can be right
The present invention makes a variety of changes, and is protection scope of the present invention.
Claims (9)
1. being used for the dried hanging hang structure of stone curtain wall, including stone material plate, keel and dry-hanging component, the end face of the stone material plate are set
It is equipped with the groove being coupled with dry-hanging component, it is characterised in that: the dry-hanging component includes pendant and locating part, the pendant
It is flexibly connected by connector with keel, one end of the pendant is provided with the hook being coupled with the groove, the limit
Part is fixed on keel or pendant, vertical with keel after installing stone material plate to limit pendant.
2. being used for the dried hanging hang structure of stone curtain wall as described in claim 1, it is characterised in that: the connector is bolt, should
Pendant, can be using bolt as center circular-rotation after being bolted to keel.
3. being used for the dried hanging hang structure of stone curtain wall as described in claim 1, it is characterised in that: the connector is to be set to extension
The convex block of part two sides, is provided with the groove being cooperatively connected with the convex block on the keel of the pendant two sides, and the pendant is by will be convex
Block clamping and groove, realize the connection with keel.
4. being used for the dried hanging hang structure of stone curtain wall as claimed in claim 3, it is characterised in that: the cross section of the convex block is circle
Shape or rectangle, the groove being cooperatively connected on the keel with the convex block are also round or rectangle.
5. being used for the dried hanging hang structure of stone curtain wall as described in claim 1, it is characterised in that: the locating part is fixed on keel
Or on pendant, and it is located at the rear of connector.
6. being used for the dried hanging hang structure of stone curtain wall as claimed in claim 2, it is characterised in that: the locating part is fixed on keel
Or on pendant, and it is located at the front of connector.
7. such as the dried hanging hang structure described in claim 5 or 6 for stone curtain wall, it is characterised in that: the locating part is fixed on
On keel;The locating part is the crossbeam for connecting more keel.
8. being used for the dried hanging hang structure of stone curtain wall as described in claim 1, it is characterised in that: the hook is that dove-tail form is linked up with
Or T-shape hook, with fixed two adjacent stone material plates simultaneously.
9. a kind of method of the dried hanging hang structure installation stone curtain wall using claim 3, comprising:
Step 1: adding the state of lateral inclination to enter between two keel with fore-and-aft tilt dry hanging article, enter groove in pendant
Afterwards, pendant is each perpendicular in the state clamping and groove of keel with longitudinal direction and laterally, while is limited part and limits, so as to install
Pendant and keel still keep plumbness after stone material plate;
Step 2: by the corresponding hook of groove stone material plate lower end, stone material plate being placed on pendant;
Step 3: upper layer pendant is connected to keel by the method for repeating step 1, and corresponding stone material plate upper end is linked up on the upper layer
Groove, complete monolithic stone material plate installation;
The installation circulation step 2 of upper layer stone material plate, step 3 operation;If installing the stone material plate of a new column, circulation step 1, step
Rapid 2, step 3 operation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510961717.7A CN105604223B (en) | 2015-12-20 | 2015-12-20 | Dried hanging hang structure and its application method for stone curtain wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510961717.7A CN105604223B (en) | 2015-12-20 | 2015-12-20 | Dried hanging hang structure and its application method for stone curtain wall |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105604223A CN105604223A (en) | 2016-05-25 |
CN105604223B true CN105604223B (en) | 2018-12-25 |
Family
ID=55984522
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510961717.7A Active CN105604223B (en) | 2015-12-20 | 2015-12-20 | Dried hanging hang structure and its application method for stone curtain wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105604223B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111139991A (en) * | 2020-01-17 | 2020-05-12 | 洪斯衍 | Dry-hanging stone mounting structure and mounting method |
CN111764540A (en) * | 2020-06-19 | 2020-10-13 | 中国五冶集团有限公司 | Light partition wall dry-hanging main keel structure and mounting method thereof |
CN114150803A (en) * | 2021-12-13 | 2022-03-08 | 滁州风禹新材料科技有限公司 | Light curtain wall keel assembly and mounting method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2332766Y (en) * | 1998-08-24 | 1999-08-11 | 王召鹏 | Dry hanging fixer for outer curtain wall decorative stone of building |
CN2541532Y (en) * | 2002-04-15 | 2003-03-26 | 云南旭光节能有限公司 | Curtain wall hook |
CN2641181Y (en) * | 2003-08-08 | 2004-09-15 | 李怀亮 | SE stone curtain wall element |
CN2718124Y (en) * | 2004-04-30 | 2005-08-17 | 林文雄 | Dismountable stone dry hanging fixing structure |
CN201762935U (en) * | 2010-03-09 | 2011-03-16 | 薛益成 | Plate-type wall material dry-hanging device and upright column thereof |
CN102535700A (en) * | 2012-02-17 | 2012-07-04 | 秦皇岛市中贤幕墙装饰工程有限公司 | Independently detachable small unit type stone curtain wall hanging piece system |
CN102720288A (en) * | 2012-05-23 | 2012-10-10 | 天津市韩建科技有限公司 | Method for connecting solderless curtain wall dry pendant |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0293430U (en) * | 1989-01-13 | 1990-07-25 |
-
2015
- 2015-12-20 CN CN201510961717.7A patent/CN105604223B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2332766Y (en) * | 1998-08-24 | 1999-08-11 | 王召鹏 | Dry hanging fixer for outer curtain wall decorative stone of building |
CN2541532Y (en) * | 2002-04-15 | 2003-03-26 | 云南旭光节能有限公司 | Curtain wall hook |
CN2641181Y (en) * | 2003-08-08 | 2004-09-15 | 李怀亮 | SE stone curtain wall element |
CN2718124Y (en) * | 2004-04-30 | 2005-08-17 | 林文雄 | Dismountable stone dry hanging fixing structure |
CN201762935U (en) * | 2010-03-09 | 2011-03-16 | 薛益成 | Plate-type wall material dry-hanging device and upright column thereof |
CN102535700A (en) * | 2012-02-17 | 2012-07-04 | 秦皇岛市中贤幕墙装饰工程有限公司 | Independently detachable small unit type stone curtain wall hanging piece system |
CN102720288A (en) * | 2012-05-23 | 2012-10-10 | 天津市韩建科技有限公司 | Method for connecting solderless curtain wall dry pendant |
Also Published As
Publication number | Publication date |
---|---|
CN105604223A (en) | 2016-05-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105604223B (en) | Dried hanging hang structure and its application method for stone curtain wall | |
CN108708481A (en) | Constructional column exempts from formwork construction method | |
CN108699847A (en) | Side guard plate, the ceiling formwork system at least one this side guard plate and the method for setting up this side guard plate | |
CN205088823U (en) | Hanging piece for stone curtain wall | |
CN105464265A (en) | Pressed-connection unit type curtain wall and sealing part | |
CN106592878B (en) | A kind of photovoltaic board mount applied to steel encaustic tile | |
CN213683000U (en) | Mounting structure of environmental protection decorative board | |
CN108301585A (en) | Armouring keel-free direct pendant | |
CN104453089B (en) | Steel beam device of steel structure house | |
CN111021609B (en) | Inclined plane unit type curtain wall | |
CN210947318U (en) | Dry-hanging stone structure | |
CN203834834U (en) | Guardrail | |
CN103485456A (en) | Non-coplanar inclined unit curtain wall system | |
CN205051594U (en) | Hanging structure and wall -hanging power inverter who has said hanging structure | |
CN210421872U (en) | Laminated slab overhanging scaffold I-steel embedded pipe | |
CN212478354U (en) | Convex structure seamless heat preservation structure decoration integrated system omitting keel welding | |
CN203821848U (en) | Corner connecting clamp device for steel frame template | |
CN202450664U (en) | Installation structure for fiber cement cladding panel | |
CN210659690U (en) | Outer frame combined section structure of aluminum alloy window | |
CN208563846U (en) | Armouring keel-free direct pendant | |
CN107675883B (en) | Convex point box girder for top die | |
CN208152351U (en) | A kind of adapter that can be decoupled | |
CN205224572U (en) | A ledger board for fastener -style steel pipe scaffold | |
CN204715733U (en) | A kind of aluminium-plastic-wood composite shuttering | |
CN210563745U (en) | Assembled fence |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C41 | Transfer of patent application or patent right or utility model | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20160513 Address after: 361021 No. 52 waterfront 301, Jimei District, Fujian, Xiamen Applicant after: Li Yanling Address before: 361021 No. 52 waterfront 301, Jimei District, Fujian, Xiamen Applicant before: Shen Libin |
|
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |