CN105544403B - Adjustable inner formwork for construction of bridge variable-cross-section hollow pier and construction method thereof - Google Patents

Adjustable inner formwork for construction of bridge variable-cross-section hollow pier and construction method thereof Download PDF

Info

Publication number
CN105544403B
CN105544403B CN201610032363.2A CN201610032363A CN105544403B CN 105544403 B CN105544403 B CN 105544403B CN 201610032363 A CN201610032363 A CN 201610032363A CN 105544403 B CN105544403 B CN 105544403B
Authority
CN
China
Prior art keywords
template
section
formwork
piece
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610032363.2A
Other languages
Chinese (zh)
Other versions
CN105544403A (en
Inventor
王杰先
刘文军
周卫华
许开来
韩瑞生
李鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Fourth Highway Engineering Co Ltd
Original Assignee
CCCC Fourth Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Fourth Highway Engineering Co Ltd filed Critical CCCC Fourth Highway Engineering Co Ltd
Priority to CN201610032363.2A priority Critical patent/CN105544403B/en
Publication of CN105544403A publication Critical patent/CN105544403A/en
Application granted granted Critical
Publication of CN105544403B publication Critical patent/CN105544403B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
    • E—FIXED CONSTRUCTIONS
    • E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00—Structural or constructional details of bridges
    • E01D19/02—Piers; Abutments ; Protecting same against drifting ice

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

An adjustable inner formwork for construction of a bridge variable-cross-section hollow pier comprises four side formwork bodies forming four edges of the inner formwork and four chamfer formwork bodies located at four corners of the inner formwork. Each side formwork body comprises an integral formwork body and two combined formwork bodies. Each combined formwork body comprises multiple seam closing and block drawing formwork bodies. A side wing is arranged on each of the two sides of each chamfer formwork body, and the two side wings of each chamfer formwork body are in overlap joint with the adjacent side formwork bodies. During construction, by reducing the number of the seam closing and block drawing formwork bodies of the inner formwork and adjusting the overlap width of the chamfer formwork bodies and the side formwork bodies, constant changing of the cross section size of a pier body is achieved, the difficulty in inner formwork size changing of the variable-cross-section thin-wall hollow high pier is lowered, the precision of control over the boundary dimension of the pile body is improved, repeated use of the formwork is achieved, and investment in and consumption of the formwork are reduced.

Description

Adjustable internal-mold plate and construction method for the construction of bridge variable cross-section hollow pier
Technical field
The present invention relates to a kind of inner template of bridge variable cross-section thin-wall hollow high-pier, and bridge is carried out using this inner template The method of variable cross-section hollow pier construction, belongs to bridge variable cross-section high pier construction field.
Background technology
As Longspan Bridge increasingly adopts Materials with High Strength and thin-wall construction, bridge variable cross-section tall pier and thin wall sets Meter is widely adopted.Bridge variable cross-section thin-wall hollow high-pier body has the advantages that reasonable stress, material-saving, pier shaft design bottom Greatly, top is little, sets certain slope ratio (usually 80 along short transverse:1), its size is gradually tapered up from bottom to top.But variable cross-section The control difficulty of high pier overall dimensions in work progress increases, the segmented pouring construction from bottom to top of high pier, and segment sizes are not Disconnected change, it is necessary to configure the template of various cross dimensions, or hypomere template continuous cutting is poured into use for epimere, To adapt to being continually changing for pier shaft size;The template of various cross dimensions is configured, is caused the input of template and is consumed very big, and cut out Cutting template then needs to expend more artificial, and cuts size and be not easy to control, especially internal model, in the limited sky of a closing In, operation difficulty is bigger.
The content of the invention
It is an object of the invention to provide it is a kind of easy to operate, it is safe and reliable, it is adapted to the construction of variable cross-section thin-wall hollow high-pier Adjustable internal-mold, it is possible to achieve the reuse of Thin-walled Hollow Pier body internal model, reduce template input and consumption, drop Low construction cost simultaneously improves efficiency of construction.
For realizing the purpose of the present invention, present invention firstly provides a kind of for the adjustable of bridge variable cross-section hollow pier construction Inner template, including 4 pieces of side templates on four sides of composition inner template, and positioned at 4 pieces of chamfering formworks at 4 angles of inner template, its feature It is:Every piece of side template includes one piece of integral mold plate and two pieces of gang forms, and every piece of gang form includes that polylith is received seam and takes out block mould Plate, receives the perpendicular rib for being respectively provided on two sides with angle steel making that seam takes out block template per block, and two pieces of adjacent receipts seams are taken out Perpendicular rib is connected with;Receipts seam outermost with a gang form takes out block template by bolt respectively for the both sides of one piece of integral mold plate Connection one piece of side template of composition;Include Angle formwork per chamfering formwork described in block, Angle formwork is respectively provided on two sides with flank, the side 135 ° of angle is formed between the wing and Angle formwork, and the width of flank is received seam and takes out 1/2nd of block template width more than one piece;It is described Two flanks of Angle formwork are Chong Die with the side template for closing on respectively to be overlapped.
For realizing the purpose of the present invention, the present invention also provides one kind and carries out bridge variable cross-section using above-mentioned adjustable internal-mold plate The construction method of hollow pier, pier stud external mold adopt hydraulic climbing slding form operation, internal model to construct using overmolded mode, and its feature exists In:
According to the design size of first segment pier stud, the quantity of block template is taken out by increasing and decreasing the receipts seam of every piece of side template both sides, By the width adjustment of every piece of side template of first segment inner template to appropriate size, then every piece of chamfering of first segment inner template is installed Template and side template, keep the both sides of every piece of side template to overlap a fixed width with the flank of adjacent chamfering formwork respectively during installation Degree, installation after-pouring first segment pier stud concrete;Each section inner template from second section up, first according to pier before installing The slope ratio of post, calculating inner template should be to the size of contract, and can then see by the both sides of every piece of side template of increase and phase The width of the flank lap of adjacent chamfering formwork reaches the contraction size of requirement, if can reach, according to first segment internal model The mounting means of plate is installed, and is adjusted the both sides of every piece of side template with the flank lap of adjacent chamfering formwork when mounted Save proper width;If can not reach, the receipts seam for reducing side template both sides takes out the quantity of block template, then according in first segment The mounting means of template is installed, and pours the section concrete.
The present invention is provided with parting in inner template and takes out block template, takes out block template and regulation chamfering by increasing and decreasing internal model parting Template takes out block template overlapping widths to realize being continually changing for pier shaft sectional dimension with parting, with easy to operate, controllability Strong advantage, reduces the difficulty of variable cross-section thin-wall hollow high-pier internal model change in size, improves pier shaft overall dimensions control essence Degree, realizes the recycling of template, reduces template input and consumes, and improves efficiency of construction.
Description of the drawings
Fig. 1 is the overlooking the structure diagram of inner template of the present invention;
Fig. 2 is the side template overlooking the structure diagram of inner template;
Fig. 3 is the overlooking the structure diagram of gang form;
Fig. 4 is the planar structure schematic diagram of gang form;
Fig. 5 is one piece receives the overlooking the structure diagram that seam takes out block template;
Fig. 6 is the structural representation of chamfering formwork.
Specific embodiment
As shown in figure 1, a kind of adjustable internal-mold plate for the construction of bridge variable cross-section hollow pier provided by the present invention, bag 4 pieces of side templates 1 on four sides of composition inner template are included, and positioned at 4 pieces of chamfering formworks 2 at 4 angles of inner template;
As shown in Fig. 2 every piece of side template 1 includes one piece of integral mold plate 3 and two pieces of gang forms 4;
As shown in Fig. 3, Fig. 4, Fig. 5, every piece of gang form 4 includes that polylith is received seam and takes out block template 5, receives seam for one piece and takes out block template 5 take out block template with another piece of receipts seam is connected by bolt 6, and polylith receipts seam is taken out block template 5 and connects the composition gang form according to this 4;
As shown in Fig. 2 block template 5 is taken out with 4 outermost receipts seam of a gang form respectively in the both sides of one piece of integral mold plate 3 leading to Cross the connection one piece of side template of composition of bolt 6;
As shown in fig. 6, include Angle formwork 7 per chamfering formwork described in block 2, Angle formwork 7 is respectively provided on two sides with flank 8, institute State the angle for forming 135 ° between flank 8 and Angle formwork 7.
During installation, overlap two flanks of the chamfering formwork Chong Die with the side template for closing on respectively, as shown in fig. 1.
As a kind of specific embodiment, as shown in Fig. 3, Fig. 5, that receives per block that seam takes out block template 5 is respectively provided on two sides with angle steel The perpendicular rib 9 for making, two pieces of adjacent receipts seams are taken out.
When the present invention is embodied as, can by the width of flank be set greater than one piece receive seam take out block template width two/ One, it is easy to, by adjusting flank and the overlap lap width of side template, realize inner template dimensional contraction.
Used as a kind of specific embodiment, the present invention can receive per block when in use and stitch the width for taking out block template and be set to 150mm;The flank width of the chamfering formwork is set greater than into 75mm.
When the construction of bridge variable cross-section hollow pier is carried out using above-mentioned adjustable internal-mold plate provided by the present invention, outside pier stud Mould adopts hydraulic climbing slding form operation, internal model to construct using overmolded mode.Inner template construction can adopt following methods:
According to the design size of first segment pier stud, the quantity of block template is taken out by increasing and decreasing the receipts seam of every piece of side template both sides, By the width adjustment of every piece of side template of first segment inner template to appropriate size, then every piece of chamfering of first segment inner template is installed Template and side template, keep the both sides of every piece of side template to overlap a fixed width with the flank of adjacent chamfering formwork respectively during installation Degree, installation after-pouring first segment pier stud concrete;Each section inner template from second section up, first according to pier before installing The slope ratio of post, calculating inner template should be to the size of contract, and can then see by the both sides of every piece of side template of increase and phase The width of the flank lap of adjacent chamfering formwork reaches the contraction size of requirement, if can reach, according to first segment internal model The mounting means of plate is installed, and is adjusted the both sides of every piece of side template with the flank lap of adjacent chamfering formwork when mounted Save proper width;If can not reach, the receipts seam for reducing side template both sides takes out the quantity of block template, then according in first segment The mounting means of template is installed, and pours the section concrete.
As a kind of specific embodiment of said method, following steps are specifically may include:
(1) design size according to first segment pier stud, takes out the number of block template by increasing and decreasing the receipts seam of every piece of side template both sides Amount, by the width adjustment of every piece of side template of first segment inner template to appropriate size;4 pieces of chamferings of first segment inner template are first installed Template, then by four pieces of side templates be respectively mounted in place, keep every piece of side template both sides respectively with adjacent chamfering formwork Flank overlaps one fixed width, and every piece of chamfering formwork and side template are fixed, first segment pier stud concrete is then poured;
(2) the slope ratio according to pier stud, calculates size of the second section pier stud to contract;By first segment inner template installation side Formula installs second section inner template, and the width of second section inner template side form is identical with first segment, but when mounted, by increasing per block The both sides of side template and the width of the flank lap of adjacent chamfering formwork, are retracted to the inner template after installation and require chi It is very little, then pour second section concrete;
(3) when the concrete strength of first segment template reaches form removal requirement, remove first segment template;According to the slope of pier stud Than calculating size of Section of three pier stud to contract, then taking out the quantity of block template by reducing side template both sides parting, make The width of every piece of side template reaches the dimensional requirement to contract, then according to the installation method of first segment inner template, is installed to In second section inner template, complete Section of three pier stud inner template and install, and pour Section of three pier stud concrete;
(4) after second section concrete reaches strength of mould stripping, remove second section inner template;By reducing side template both sides point Seam takes out the quantity of block template, is identical with Section three of side template width by the width adjustment of side template;Then according to second section The mounting means of inner template, attaches it in Section of three inner template, during installation, according to the slope ratio of pier stud, calculates Section four Size of the pier stud to contract, then, by increasing the both sides of every piece of side template and the flank overlapping portion of adjacent chamfering formwork The width for dividing, makes Section of after installation four inner template be retracted to desired size, Section of four pier stud concrete of installation after-pouring;
(5) repeat step (3), the mode of (4), are circulated up construction successively, until pier stud is all poured and completed.
Hereinafter the concrete of bridge variable cross-section hollow pier construction is carried out by an adjustable internal-mold plate using the present invention again Embodiment, further illustrates to said method.
In the embodiment, bridge pier body is 60-106 rice, and pier shaft is bilateral nonuniform thin-walled hollow pier, and pier shaft slope ratio is 80:1, pier top end is 4.0*5.5 rice, and base opening is (4+h*0.0125) * (5.5+h*0.0125) rice, and same type pier shaft has 16 Seat.
The bridge external mold adopts 6m hydraulic self-creeping formworks, and the adjustable internal-mold plate of the present invention that internal model is adopted, highly with external mold one Cause.
6150mm designs are highly pressed in the segmented construction of pier shaft, inner template single-unit, actually pour mixed mud 6000mm, bound edge 150mm.According to 80:Than understanding, 6000mm height pier shafts monolateral receipts seam 75mm, i.e. pier shaft often raise 6000mm, the side of inner template on 1 slope Template width should reduce 150mm.
Steel plate of the inner template panel using 6mm, erects rib and adopts 8 angle steel, is welded into integral mold plate with panel, and back cord is adopted [12 channel-section steel adopts the finish rolling deformed bar of φ 25mm to pull bar to Two bors d's oeuveres.Each section form height is 6150mm, is actually poured Concrete 6000mm, remaining is bound edge template, and often saving template includes 4 pieces of side templates and 4 pieces of chamfering formworks, and every piece of side template includes One integral mold plate, every piece of integral mold plate both sides connect two pieces of receipts seams and take out block section template composition.
Seam will be received to take out block template monolithic width and be set to 150mm, the flank width of chamfering formwork is set greater than 75mm.
The both wings of chamfering formwork do not set rib in length and breadth, take out block template 50~150mm of Chong Die overlap joint with seam is received.Seam is received by increasing and decreasing Take out block template number, and adjustment two flank of chamfering formwork and receipts seam taken out the Chong Die lap width of block template to adjust internal model board size, Realize that pier shaft becomes slope.
When template rises one to be saved, two flank of chamfering formwork is taken out into block template lap increase 75mm with seam is received, is met The 75mm that 6000m height pier shafts closing slope reduces is required;Template often rises 2 sections, i.e., often pour two pier stud sections, inner template both sides Seam being received simultaneously and reducing size, concrete mode is to unclamp the connecting bolt for receiving that seam is taken out between the perpendicular rib of block template, and both sides respectively remove one piece 150 wide seams of receiving take out block template.
Concrete mode is as follows:
(1) design size according to first segment pier stud, takes out the number of block template by increasing and decreasing the receipts seam of every piece of side template both sides Amount, by the width adjustment of every piece of side template of first segment inner template to appropriate size;4 pieces of chamferings of first segment inner template are first installed Template, then by four pieces of side templates be respectively mounted in place, keep every piece of side template both sides respectively with adjacent chamfering formwork Flank overlaps one fixed width, and every piece of chamfering formwork and side template are poured first segment respectively with being fixed with external mold to pull bar, then Pier stud concrete;
(2) according to pier stud 80:1 slope ratio, calculates second section pier stud to contract 150mm;Pacify by first segment inner template Dress mode installs second section inner template, and the width of second section inner template side form is identical with first segment, but when mounted, by every piece of side The both sides of template increase 75mm than first segment respectively with the width of the flank lap of adjacent chamfering formwork, after making installation Inner template is retracted to desired size, then pours second section concrete;
(3) when the concrete strength of first segment template reaches form removal requirement, remove first segment template;According to pier stud 80:1 Slope ratio, calculate Section of three pier stud to contract 300mm, side template both sides removed into one piece of wide parting of 150mm respectively and is taken out Block template, makes the width of every piece of side template reduce 300mm, then according to the installation method of first segment inner template, is installed to second In section inner template, complete Section of three pier stud inner template and install, and pour Section of three pier stud concrete;
(4) after second section concrete reaches strength of mould stripping, remove second section inner template;According to the slope ratio of pier stud, calculate Going out Section of four pier stud should be to contract 450mm;The side template both sides pulled down are removed into one piece of wide parting of 150mm respectively and takes out block mould Plate, then according to the mounting means of second section inner template, attaches it in Section of three inner template, during installation, then by every piece of side The both sides of template increase 75mm respectively with the width of the flank lap of adjacent chamfering formwork than Section three, after making installation Section four, inner template is retracted to desired size, Section of four pier stud concrete of installation after-pouring;
(5) repeat step (3), the mode of (4), are circulated up construction successively, until pier stud is all poured and completed.
The inner template of the present invention can be used in turn, and a pier stud construction is finished, and the receipts seam of every piece of side template is taken out block template Again it is bolted together with connecting bolt, returns to prototype structure size, for next pier stud construction usage.

Claims (4)

1. a kind of adjustable internal-mold plate for the construction of bridge variable cross-section hollow pier, including 4 pieces of sides on composition inner template four sides Template, and positioned at 4 pieces of chamfering formworks at 4 angles of inner template, it is characterised in that:Every piece of side template includes one piece of integral mold plate and two Block gang form, every piece of gang form include that polylith is received seam and takes out block template, and that receives per block that seam takes out block template is respectively provided on two sides with angle The perpendicular rib that steel makes, two pieces of adjacent receipts seams are taken out;The both sides of one piece of integral mold plate point Receipts seam not outermost with a gang form is taken out block template and is bolted one piece of side template of composition;Per chamfering formwork described in block Including Angle formwork, the angle for being respectively provided on two sides with flank, forming 135 ° between the flank and Angle formwork of Angle formwork, the width of flank Degree is received seam and takes out 1/2nd of block template width more than one piece;Two flanks of the chamfering formwork respectively with the side template weight for closing on It is stacked with and connects.
2. it is according to claim 1 for bridge variable cross-section hollow pier construction adjustable internal-mold plate, it is characterised in that:Often It is 150mm that block is received and stitches the width for taking out block template;The flank width of the chamfering formwork is more than 75mm.
3. the adjustable internal-mold plate described in a kind of employing claim 1 carries out the construction method of bridge variable cross-section hollow pier, pier stud External mold adopts hydraulic climbing slding form operation, internal model to construct using overmolded mode, it is characterised in that:According to the design of first segment pier stud Size, takes out the quantity of block template, by every piece of side template of first segment inner template by increasing and decreasing the receipts seam of every piece of side template both sides Then width adjustment is installed every piece of chamfering formwork and side template of first segment inner template, is kept per block during installation to appropriate size The both sides of side template overlap one fixed width with the flank of adjacent chamfering formwork respectively, and installation after-pouring first segment pier stud is mixed Solidifying soil;Each section inner template from second section up, the slope ratio before installing first according to pier stud, calculating inner template inwardly should receive The size of contracting, can then see by increasing the both sides of every piece of side template and the width of the flank lap of adjacent chamfering formwork Degree reaches the contraction size of requirement, if can reach, installs according to the mounting means of first segment inner template, and when mounted will be every The both sides of block side template are adjusted to proper width with the flank lap of adjacent chamfering formwork;If can not reach, reduce The receipts seam of side template both sides takes out the quantity of block template, then according to the mounting means of first segment inner template is installed, and pours the section Concrete.
4. the construction method of bridge variable cross-section hollow pier according to claim 3, it is characterised in that comprise the following steps:
(1) design size according to first segment pier stud, takes out the quantity of block template by increasing and decreasing the receipts seam of every piece of side template both sides, will The width adjustment of every piece of side template of first segment inner template is to appropriate size;4 pieces of chamfering formworks of first segment inner template are first installed, Then four pieces of side templates are respectively mounted the both sides flank weight respectively with adjacent chamfering formwork for keeping every piece of side template in place Folded one fixed width, every piece of chamfering formwork and side template are fixed, and then pour first segment pier stud concrete;
(2) the slope ratio according to pier stud, calculates size of the second section pier stud to contract;Pacify by first segment inner template mounting means Dress second section inner template, the width of second section inner template side form are identical with first segment, but when mounted, by increasing every piece of side form The both sides of plate and the width of the flank lap of adjacent chamfering formwork, make the inner template after installation be retracted to desired size, Then pour second section concrete;
(3) when the concrete strength of first segment template reaches form removal requirement, remove first segment template;According to the slope ratio of pier stud, Size of Section of three pier stud to contract is calculated, the quantity of block template is then taken out by reducing side template both sides parting, is made every The width of block side template reaches the dimensional requirement to contract, then according to the installation method of first segment inner template, is installed to In two section inner templates, complete Section of three pier stud inner template and install, and pour Section of three pier stud concrete;
(4) after second section concrete reaches strength of mould stripping, remove second section inner template;Taken out by reducing side template both sides parting The quantity of block template, is identical with Section three of side template width by the width adjustment of side template;Then according to second section internal model The mounting means of plate, attaches it in Section of three inner template, during installation, according to the slope ratio of pier stud, calculates Section of four pier stud To the size of contract, then, by increasing both sides and the flank lap of adjacent chamfering formwork of every piece of side template Width, makes Section of after installation four inner template be retracted to desired size, Section of four pier stud concrete of installation after-pouring;
(5) repeat step (3), the mode of (4), are circulated up construction successively, until pier stud is all poured and completed.
CN201610032363.2A 2016-01-18 2016-01-18 Adjustable inner formwork for construction of bridge variable-cross-section hollow pier and construction method thereof Active CN105544403B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610032363.2A CN105544403B (en) 2016-01-18 2016-01-18 Adjustable inner formwork for construction of bridge variable-cross-section hollow pier and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610032363.2A CN105544403B (en) 2016-01-18 2016-01-18 Adjustable inner formwork for construction of bridge variable-cross-section hollow pier and construction method thereof

Publications (2)

Publication Number Publication Date
CN105544403A CN105544403A (en) 2016-05-04
CN105544403B true CN105544403B (en) 2017-03-22

Family

ID=55823934

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610032363.2A Active CN105544403B (en) 2016-01-18 2016-01-18 Adjustable inner formwork for construction of bridge variable-cross-section hollow pier and construction method thereof

Country Status (1)

Country Link
CN (1) CN105544403B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106012859B (en) * 2016-07-04 2018-07-31 宁夏宁博通模板有限责任公司 A kind of double variable cross-section hollow plate beam internal models and two-way rigid locking support construction
CN106835982A (en) * 2016-12-19 2017-06-13 中铁局集团第二工程有限公司 Continuous beam self-balancing type adjustable inner cavity template
CN106930192B (en) * 2017-04-21 2018-12-18 中交一公局第一工程有限公司 Assembled variable cross-section contracture sliding mode system and its construction method
CN107761548A (en) * 2017-09-14 2018-03-06 中铁十九局集团第二工程有限公司 Slope-changing hollow high pier reverse formwork construction method for passenger special line
CN107700531B (en) * 2017-09-29 2019-10-08 中国十七冶集团有限公司 A kind of erection method of chamfering set shaped steel formwork
CN109306664A (en) * 2018-11-05 2019-02-05 云南建投第三建设有限公司 A sliding plate type inner formwork of variable-section thin-walled hollow piers
CN110670487B (en) * 2019-10-12 2024-07-23 中铁大桥局集团有限公司 Pier column steel bar positioning device and construction method thereof
CN110670491A (en) * 2019-10-29 2020-01-10 中国铁建大桥工程局集团有限公司 Front anchor chamber roof cast-in-place construction device and construction method
CN113186824A (en) * 2021-04-13 2021-07-30 中铁六局集团太原铁路建设有限公司 Rollover construction method for round-end-shaped solid pier
CN115094758A (en) * 2022-05-23 2022-09-23 云南交投集团云岭建设有限公司 Construction method of variable-section thin-wall hollow pier double-layer template system
CN118309265A (en) * 2024-04-01 2024-07-09 中建二局第三建筑工程有限公司 A construction method for moving up a variable-section building template applied to a variable-section building

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB191228873A (en) * 1912-12-16 1913-06-12 Alvin Sidney Miller Adjustable Bracing for Buildings, Bridges and the like.
US7976244B2 (en) * 2007-03-20 2011-07-12 Keating Joseph W Method and system for constructing and installing docks
CN203160135U (en) * 2013-03-29 2013-08-28 中国水电建设集团铁路建设有限公司 Adjustable arc template used in construction of thin-wall hollow pier
CN203200664U (en) * 2013-04-11 2013-09-18 新疆北新路桥集团股份有限公司 Slip-form construction device for variable cross-section hollow high pier
CN103161126A (en) * 2013-04-11 2013-06-19 新疆北新路桥集团股份有限公司 Road bridge variable section hollow high pier slip-form construction method
CN205529916U (en) * 2016-01-18 2016-08-31 中交第四公路工程局有限公司 Inner formword with adjustable be used for construction of hollow mound of bridge variable cross section

Also Published As

Publication number Publication date
CN105544403A (en) 2016-05-04

Similar Documents

Publication Publication Date Title
CN105544403A (en) Adjustable inner formwork for construction of bridge variable-cross-section hollow pier and construction method thereof
CN206106054U (en) Assembly type structure prefabricated component special mould
CN110394884A (en) A kind of prefabricated post adjustable mold and prefabricated column production method
CN105220877B (en) Vertical formwork bottom mortar leakage prevention, level-off integrated apparatus
CN207757819U (en) General utility tool formula laminated floor slab mold
CN112536898A (en) Adjustable general stair mold
CN208441138U (en) Integrated prefabricated pipe gallery based on composite floor
CN207812625U (en) Special-shaped gutter template integrated apparatus
CN105178198A (en) Adjustable formwork for variable cross-section high pier of bridge
CN219505043U (en) Steel template for precast column concrete pouring
CN207296409U (en) Build aluminum alloy pattern plate external corner connecting piece
CN209190965U (en) A kind of adjustable prefabricated board die
CN205529916U (en) Inner formword with adjustable be used for construction of hollow mound of bridge variable cross section
CN214725110U (en) a stair mold
CN207847151U (en) The telescopic support device to cornice for installing exterior wall
CN108004986B (en) Tunnel anti-collision wall template reinforcing system and construction method
CN105350767A (en) Aluminium alloy template protruded-section profile and unit template structure thereof
CN203905326U (en) Construction form for construction of roof exhaust pipe piers
CN210414929U (en) Assembled stair mould
CN217517649U (en) Calandria pouring die
CN217974054U (en) A formwork adjustment device for bridge pier columns with variable slopes on all sides
CN117404112A (en) In-situ precast trolley, in-situ precast tunnel trench construction device and method
CN106914984A (en) A kind of construction method of prefabricated composite construction board
CN115351882B (en) Large-size adjustable UHPC special-shaped component die and application method thereof
CN106089257A (en) A kind of tunnel ditch cable trough construction trolley

Legal Events

Date Code Title Description