CN105449546A - Combined-type power distribution cabinet pedestal and installation operation method thereof - Google Patents

Combined-type power distribution cabinet pedestal and installation operation method thereof Download PDF

Info

Publication number
CN105449546A
CN105449546A CN201510822172.1A CN201510822172A CN105449546A CN 105449546 A CN105449546 A CN 105449546A CN 201510822172 A CN201510822172 A CN 201510822172A CN 105449546 A CN105449546 A CN 105449546A
Authority
CN
China
Prior art keywords
power distribution
distribution cabinet
brace summer
hole
split
Prior art date
Application number
CN201510822172.1A
Other languages
Chinese (zh)
Inventor
甘宇鹏
田晋羽
孙宝武
李辉
吴勇
Original Assignee
国网辽宁省电力有限公司锦州供电公司
国家电网公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 国网辽宁省电力有限公司锦州供电公司, 国家电网公司 filed Critical 国网辽宁省电力有限公司锦州供电公司
Priority to CN201510822172.1A priority Critical patent/CN105449546A/en
Publication of CN105449546A publication Critical patent/CN105449546A/en

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS, OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B1/00Frameworks, boards, panels, desks, casings; Details of substations or switching arrangements
    • H02B1/26Casings; Parts thereof or accessories therefor
    • H02B1/30Cabinet-type casings; Parts thereof or accessories therefor

Abstract

The invention discloses a combined-type power distribution cabinet pedestal, and the pedestal comprises pedestal frames which are made of two steel channels, wherein the openings of the two pedestal frames are opposite to each other. The front side walls of the two pedestal frames are connected with each other through a supporting beam therebetween, and the rear side walls of the two pedestal frames are connected with each other through a supporting beam therebetween. The supporting beams are formed through supporting beam branch bodies made of a plurality of steel channel segments, and connecting plates connected between each two adjacent supporting beam branch bodies. The top surfaces of the pedestal frames and the supporting beam branch bodies are respectively provided with a power distribution cabinet installation hole. The invention also discloses an installation operation method for the combined-type power distribution cabinet pedestal, and the method comprises the steps: enabling the pedestal frames, the supporting beam branch bodies and the connecting plates to be assembled; enabling a power distribution cabinet to be installed on the pedestal frames and the supporting beam branch bodies; enabling the power distribution cabinet pedestal and a power distribution cabinet on the pedestal to be moved to the ground of a cable well; enabling a cable to be connected to power distribution equipment in the power distribution cabinet, covering the bottom of the pedestal with concrete, arranging a circular isolation strip surrounding the concrete, keeping it grow naturally for ten days, and moving away the isolation strip after the concrete is solidified.

Description

Assemblied distribution base and installation exercise method thereof
Technical field
The present invention relates to the base for power supply controller switching equipment breaker in middle cabinet, particularly a kind of assemblied distribution base and installation exercise method thereof.
Background technology
Power distribution cabinet is the controller switching equipment for power distribution, control, metering and connection cable in power supply system, being directly placed on ground and causing the phenomenon such as structural instability, power distribution cabinet corrosion, power distribution cabinet need be seated on power distribution cabinet base for preventing power distribution cabinet.At present, the installation exercise mode of power distribution cabinet base is: first measure power distribution cabinet bed-plate dimension to be installed, and the power distribution cabinet base of " mouth " font is built into according to the size brick of power distribution cabinet bottom surface to be installed and cement, natural Health preservation more than 24 hours again, after power distribution cabinet base dries, being seated in by power distribution cabinet on power distribution cabinet base, and being fixed on power distribution cabinet base by earth anchor by power distribution cabinet, there is following shortcoming in the method:
1, power distribution cabinet base dimensions is not easily grasped, and easily occurs error, makes to start a leak bottom switch cubicle.
2, curing time is long.When carrying out robbing electric power and repairing operation, the size as the new switch cubicle size that need change and former switch cubicle has difference, then need again to make base, the base made needs to carry out concrete curing, extends interruption duration, affects normal power supply.
3, during installation earth anchor, power distribution cabinet base is frangible.When earth anchor being dug into power distribution cabinet base, easily by broken for power distribution cabinet base cutter, need again make power distribution cabinet base.
Summary of the invention
The present invention is to solve the problems of the technologies described above, and provides one can improve installation dimension precision, shorten non-damageable assemblied distribution base and installation exercise method thereof in activity duration, installation process.
Technical solution of the present invention is: a kind of assemblied distribution base, comprise two channel-section steels to make and just right mounting of dehiscing, brace summer is connected between the front side wall of two mountings and between rear wall, described brace summer is the brace summer split of being made up of more piece channel-section steel, the connecting plate be connected between adjacent two joint brace summer splits is formed, and is respectively equipped with power distribution cabinet installing hole at the end face of described mounting and brace summer split.
The front-rear side walls of described mounting is respectively equipped with circular hole, is respectively equipped with strip hole at the sidewall two ends of described brace summer split, in the circular hole and strip hole of correspondence, be installed with bolt.
The sidewall of described brace summer split is positioned at the upper and lower both sides of strip hole and is respectively equipped with connecting hole I, be respectively equipped with connecting hole II at four angles place of described connecting plate, in the connecting hole I and connecting hole II of correspondence, be installed with bolt.
Air vent hole is respectively equipped with on the end face top, left and right of two mountings.
Scribble waterproof coating on described mounting, brace summer split and connecting plate surface, prevent from mounting, brace summer and connecting plate speckle with dew corrosion.
An installation exercise method for assemblied distribution base, its concrete steps are as follows:
1, select the mounting of respective amount, brace summer split and connecting plate according to the quantity of power distribution cabinet, and connected between each parts by bolt;
2, adjust spacing between mounting and corresponding brace summer split, and each power distribution cabinet is arranged in corresponding mounting and brace summer split by bolt;
3, by the ground of cable Jing Chu repair smooth after, by power distribution cabinet base and on power distribution cabinet move on cable Jing Chu ground;
4, the cable passed from cable well to be connected in power distribution cabinet on corresponding controller switching equipment, and at the inner bottom part of power distribution cabinet base and outer bottom mulching concrete respectively, concrete thickness is 3cm-5cm, and concrete height is the 1/3-1/2 of mounting height;
5, around concrete, arrange a circle isolation strip, natural Health preservation 10 days, after concrete setting, removes isolation strip.
The invention has the beneficial effects as follows: because this assemblied distribution base is by mounting, is connected to the brace summer split between mounting and the connecting plate be connected between adjacent two brace summer splits is formed, according to brace summer split and the connecting plate of the quantity assembling respective amount of power distribution cabinet, installation dimension precision is high, and applicability is strong; Power distribution cabinet can be installed on this assemblied distribution base by bolt, mounting structure is stablized, power distribution cabinet base is caused to destroy without the need to digging into earth anchor, and power distribution cabinet is directly seated in after being installed to assemblied distribution base on the ground of cable Jing Chu, and at this assemblied distribution base inner bottom part and outer bottom mulching concrete, swift to operate, convenient, shorten the installation exercise time greatly, ensure that power supply is normal.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is the A-A cutaway view of Fig. 1;
Fig. 3 is the A portion enlarged drawing in Fig. 1;
Fig. 4 is the B portion enlarged drawing in Fig. 1;
Fig. 5 is Construction State schematic diagram of the present invention;
In figure: 1-mounting, 2-air vent hole, the split of 3-brace summer, 4-connecting plate is formed, 5-circular hole, 6-strip hole, 7-connecting hole I, 8-connecting hole II, 9-power distribution cabinet installing hole, 10-waterproof coating, 11-power distribution cabinet, 12-isolation strip, 13-concrete.
Embodiment
As shown in the figure, the present invention is for four power distribution cabinets, a kind of assemblied distribution base, comprise two channel-section steels to make and the mounting 1 of dehiscing just right, air vent hole 2 is respectively equipped with on the end face top, left and right of two mountings 1, brace summer is connected between the front side wall of two mountings 1 and between rear wall, described brace summer is the brace summer split 3 of being made up of two joint channel-section steels, the connecting plate 4 be connected between adjacent two joint brace summer splits 3 is formed, the front-rear side walls of described mounting 1 is respectively equipped with circular hole 5, strip hole 6 is respectively equipped with at the sidewall two ends of described brace summer split 3, bolt is installed with in the circular hole 5 and strip hole 6 of correspondence.The sidewall of described brace summer split 3 is positioned at strip hole about 6 both sides and is respectively equipped with connecting hole I7, be respectively equipped with connecting hole II8 at four angles place of described connecting plate 4, in the connecting hole I7 and connecting hole II8 of correspondence, be installed with bolt.Be respectively equipped with power distribution cabinet installing hole 9 at the end face of described mounting 1 and brace summer split 3, scribble waterproof coating 10 on described mounting 1, brace summer split 3 and connecting plate 4 surface.
An installation exercise method for assemblied distribution base, its concrete steps are as follows:
1, select 1, four the brace summer splits 3 of two mountings and two connecting plates 4 according to the quantity of power distribution cabinet 11, and be linked and packed between each parts by bolt;
2, adjust spacing between mounting 1 and corresponding brace summer split 3, and four power distribution cabinets 11 are arranged in corresponding mounting 1 and brace summer split 3 by bolt;
3, by the ground of cable Jing Chu repair smooth after, by power distribution cabinet base and on power distribution cabinet 11 move on this ground, place;
4, the cable passed from cable well is connected on controller switching equipment corresponding in power distribution cabinet 11, and at the inner bottom part of power distribution cabinet base and outer bottom mulching concrete 13 respectively, the thickness of concrete 13 is 3cm, and the height of concrete 13 is 1/3 of mounting 1 height;
5, one circle isolation strip 12 is set around concrete, natural Health preservation 10 days, after concrete 13 solidifies, removes isolation strip 12.
These are only specific embodiments of the invention, be not limited to the present invention, for a person skilled in the art, the present invention can have various modifications and variations.Within the spirit and principles in the present invention all, any amendment done, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (6)

1. an assemblied distribution base, it is characterized in that: comprise two channel-section steels and make and just right mounting of dehiscing, brace summer is connected between the front side wall of two mountings and between rear wall, described brace summer is the brace summer split of being made up of more piece channel-section steel, the connecting plate be connected between adjacent two joint brace summer splits is formed, and is respectively equipped with power distribution cabinet installing hole at the end face of described mounting and brace summer split.
2. assemblied distribution base according to claim 1, is characterized in that: on the front-rear side walls of described mounting, be respectively equipped with circular hole, is respectively equipped with strip hole at the sidewall two ends of described brace summer split, in the circular hole and strip hole of correspondence, be installed with bolt.
3. assemblied distribution base according to claim 1, it is characterized in that: on the sidewall of described brace summer split, be positioned at the upper and lower both sides of strip hole be respectively equipped with connecting hole I, be respectively equipped with connecting hole II at four angles place of described connecting plate, in the connecting hole I and connecting hole II of correspondence, be installed with bolt.
4. assemblied distribution base according to claim 1, is characterized in that: be respectively equipped with air vent hole on the end face top, left and right of two mountings.
5. assemblied distribution base according to claim 1, is characterized in that: scribble waterproof coating on described mounting, brace summer split and connecting plate surface.
6. an installation exercise method for assemblied distribution base, its concrete steps are as follows:
(1) select the mounting of respective amount, brace summer split and connecting plate according to the quantity of power distribution cabinet, and connected between each parts by bolt;
(2) adjust spacing between mounting and corresponding brace summer split, and each power distribution cabinet is arranged in corresponding mounting and brace summer split by bolt;
(3) by the ground of cable Jing Chu repair smooth after, by power distribution cabinet base and on power distribution cabinet move on cable Jing Chu ground;
(4) cable passed from cable well is connected on controller switching equipment corresponding in power distribution cabinet, and at the inner bottom part of power distribution cabinet base and outer bottom mulching concrete respectively, concrete thickness is 3cm-5cm, and concrete height is the 1/3-1/2 of mounting height;
(5) around concrete, arrange a circle isolation strip, natural Health preservation 10 days, after concrete setting, removes isolation strip.
CN201510822172.1A 2015-11-25 2015-11-25 Combined-type power distribution cabinet pedestal and installation operation method thereof CN105449546A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510822172.1A CN105449546A (en) 2015-11-25 2015-11-25 Combined-type power distribution cabinet pedestal and installation operation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510822172.1A CN105449546A (en) 2015-11-25 2015-11-25 Combined-type power distribution cabinet pedestal and installation operation method thereof

Publications (1)

Publication Number Publication Date
CN105449546A true CN105449546A (en) 2016-03-30

Family

ID=55559468

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510822172.1A CN105449546A (en) 2015-11-25 2015-11-25 Combined-type power distribution cabinet pedestal and installation operation method thereof

Country Status (1)

Country Link
CN (1) CN105449546A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0946054A (en) * 1995-07-28 1997-02-14 Toshiba Corp Base for self-supporting cabinet
CN201134632Y (en) * 2007-12-14 2008-10-15 天津市正本电气有限公司 Bottom base of cabinet body
CN201328223Y (en) * 2008-12-16 2009-10-14 覃政良 Outdoor cabinet of mobile base station
CN202384660U (en) * 2011-12-22 2012-08-15 福建森达电气有限公司 Base of low-voltage distribution cabinet
CN203150936U (en) * 2013-02-05 2013-08-21 安徽得润电气技术有限公司 Power distribution cabinet pedestal

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0946054A (en) * 1995-07-28 1997-02-14 Toshiba Corp Base for self-supporting cabinet
CN201134632Y (en) * 2007-12-14 2008-10-15 天津市正本电气有限公司 Bottom base of cabinet body
CN201328223Y (en) * 2008-12-16 2009-10-14 覃政良 Outdoor cabinet of mobile base station
CN202384660U (en) * 2011-12-22 2012-08-15 福建森达电气有限公司 Base of low-voltage distribution cabinet
CN203150936U (en) * 2013-02-05 2013-08-21 安徽得润电气技术有限公司 Power distribution cabinet pedestal

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
百度文库: "基础型钢的制作以及配电盘的安装", 《百度文库》 *

Similar Documents

Publication Publication Date Title
CN104972554A (en) Automatic spray and maintenance system for T-shaped prefabricated beam
CN203150936U (en) Power distribution cabinet pedestal
CN204059395U (en) The pre-buried location structure of stone bolt
CN203229965U (en) 10 kV box-type substation basic standard module
CN203924349U (en) A kind of prefabricated panel and superposed beam rapid installing connection structure
CN204290230U (en) Assembled high voltage single-core cable concrete groove
NZ615512A (en) Composite wall panel, wall system and components thereof, and a method of construction thereof
CN104563130B (en) A kind of cross fender post and the double construction method doing agent structure of space enclosing structure
CN104389349A (en) Novel house capable of being fast disassembled and assembled and assembling method thereof
CN204826615U (en) Building energy conservation template is exempted from to tear open by modular
CN105908777A (en) Comprehensive pipe gallery sliding mold and application method thereof
CN103722297B (en) Steel box-girder open web type transverse wall group is welded standby and manufacture craft
CN204959771U (en) Prestressing force H shaped steel bearing structure
CN204983662U (en) To drawing screw rod and steel pipe framed bent combination unilateral formwork device
CN103061995A (en) Pre-buried screw processing method for blade roots of Megawatt-level wind turbine generator set
CN102926538B (en) Reaction box and construction method of reaction wall
CN105544605B (en) A kind of modular assembly formula pipe gallery
CN109372262A (en) A kind of basement formwork support structure and construction method
CN103291065B (en) A kind of assembly concrete bracing or strutting arrangement and lifting localization method
CN204001436U (en) A kind of constructing structure that guarantees topping at the bottom of beam, deck-molding and thickness of slab
US20180002144A1 (en) Method for hoisting and transporting assemblies in underground nuclear power plant
CN203404877U (en) Modular unit of integral type cold and heat source tower heat pump air-conditioning system
CN201297030Y (en) Movable template
CN104594361A (en) Construction method of H-shaped enclosure pile and enclosure structure as main structure
CN203821405U (en) Four-vertical-rod soil pressure balancing beam with triangular end parts

Legal Events

Date Code Title Description
PB01 Publication
C06 Publication
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160330