CN105442619B - Cable duct bottom board slope controls smears pressure instrument and its application method with ditch in ditch - Google Patents
Cable duct bottom board slope controls smears pressure instrument and its application method with ditch in ditch Download PDFInfo
- Publication number
- CN105442619B CN105442619B CN201511015295.0A CN201511015295A CN105442619B CN 105442619 B CN105442619 B CN 105442619B CN 201511015295 A CN201511015295 A CN 201511015295A CN 105442619 B CN105442619 B CN 105442619B
- Authority
- CN
- China
- Prior art keywords
- ditch
- slope
- rod
- slope control
- cable duct
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/06—Foundation trenches ditches or narrow shafts
- E02D17/08—Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- Laying Of Electric Cables Or Lines Outside (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
电缆沟底板坡度控制和沟中沟抹压工具及其使用方法,涉及变电站电缆沟施工领域。目前,施工单位对沟中沟的施工没有统一的工艺标准,小沟的施工工具不统一,标高及坡度控制不精确。本发明包括支架杆、坡度控制杆、落地杆及操作手杆,支架杆为4根,两支架杆与一位于支架杆之间的落地杆连接形成一支架;两支架左右设置,坡度控制杆设于两支架之间形成坡度控制架;支架杆竖直放置,坡度控制杆斜向设于左右两支架杆的中下部,落地杆垂直设于支架杆的底部,操作手杆垂直设于支架杆的顶部,落地杆为圆形钢管。本技术方案通过不同的组合实现两种工具的装配,可以快速有效地进行电缆沟坡度和沟中沟的施工,提升了施工速度和质量。
The utility model relates to a tool for controlling the slope of the bottom plate of a cable trench, a tool for wiping and pressing the trench in the trench, and a method of use thereof, and relates to the field of construction of cable trenches in substations. At present, the construction unit does not have a unified process standard for the construction of the ditch in the middle of the ditch, the construction tools of the small ditch are not uniform, and the elevation and slope control is not accurate. The present invention comprises a support rod, a slope control rod, a landing rod and an operating hand rod. There are 4 support rods. A slope control frame is formed between the two supports; the support rods are placed vertically, the slope control rods are arranged obliquely at the middle and lower parts of the left and right support rods, the landing rods are vertically arranged at the bottom of the support rods, and the operating handle rods are vertically arranged at the bottom of the support rods. The top, drop bars are round steel tubes. The technical solution realizes the assembly of the two tools through different combinations, can quickly and effectively carry out the construction of the slope of the cable trench and the trench in the trench, and improves the construction speed and quality.
Description
技术领域technical field
本发明涉及变电站电缆沟施工领域,尤其是电缆沟底板坡度的控制及沟中沟抹压的施工技术。The invention relates to the field of substation cable trench construction, in particular to the control of the slope of the bottom plate of the cable trench and the construction technique for wiping and pressing the trench in the trench.
背景技术Background technique
目前,变电站设计多采用电缆沟中设置支沟进行排水。根据国家电网公司标准工艺要求,电缆沟中设置R30mm的沟中沟至集水井排水,最终汇集至就近的雨水检查井。目前,施工单位对沟中沟的施工没有统一的工艺标准,小沟的施工工具不统一,有些在沟底找坡时采用预埋PVC管;有采用人工分段用PVC管抹压成型。不美观,且标高及坡度控制不精确。At present, the design of substations mostly uses branch ditches in cable trenches for drainage. According to the standard technical requirements of the State Grid Corporation of China, a ditch of R30mm is set in the cable trench to drain water from the water collection well, and finally collect it to the nearest rainwater inspection well. At present, the construction unit does not have a unified process standard for the construction of the ditch in the ditch, and the construction tools of the small ditch are not uniform. Some use pre-embedded PVC pipes when finding slopes at the bottom of the ditch; Unsightly, and the level and slope control is imprecise.
发明内容Contents of the invention
本发明要解决的技术问题和提出的技术任务是对现有技术方案进行完善与改进,提供电缆沟底板坡度控制和沟中沟抹压工具及其使用方法,以提升电缆沟底板坡度和沟中沟抹压施工质量和速度为目的。为此,本发明采取以下技术方案。The technical problem to be solved and the technical task proposed by the present invention are to perfect and improve the existing technical solutions, to provide tools for controlling the slope of the cable trench bottom plate and for mopping the trench in the trench and its use method, so as to improve the slope of the cable trench bottom plate and The purpose of ditch wiping is construction quality and speed. For this reason, the present invention takes the following technical solutions.
电缆沟底板坡度控制和沟中沟抹压工具,包括支架杆、坡度控制杆、落地杆及操作手杆,所述的支架杆为4根,两支架杆与一位于支架杆之间的落地杆连接形成一支架;两支架左右设置,所述的坡度控制杆设于两支架之间形成坡度控制架;支架杆竖直放置,所述的坡度控制杆斜向设于左右两支架杆的中下部,所述的落地杆垂直设于支架杆的底部,所述的操作手杆垂直设于支架杆的顶部,所述的落地杆为圆形钢管。通过不同的组合实现两种工具的装配,可以快速有效地进行电缆沟坡度和沟中沟的施工,提升了施工速度和质量。The tool for controlling the slope of the bottom plate of the cable trench and wiping the ditch in the ditch includes a support rod, a slope control rod, a landing rod and an operating hand rod. There are 4 support rods, two support rods and a landing rod between the support rods Connect to form a bracket; two brackets are arranged on the left and right, and the slope control rod is arranged between the two brackets to form a slope control frame; the bracket rods are placed vertically, and the slope control rod is obliquely arranged on the middle and lower parts of the left and right two bracket rods , the landing rod is vertically arranged at the bottom of the support rod, the operating handle rod is vertically arranged at the top of the support rod, and the landing rod is a circular steel pipe. The assembly of the two tools through different combinations can quickly and effectively carry out the construction of the slope of the cable trench and the trench in the trench, which improves the construction speed and quality.
作为对上述技术方案的进一步完善和补充,本发明还包括以下附加技术特征。As a further improvement and supplement to the above technical solutions, the present invention also includes the following additional technical features.
所述的支架杆、落地杆之间通过焊接固定,坡度控制杆与支架杆之间、操作手杆与支架杆之间为可拆卸式连接或焊接固定。焊接方式成熟简单牢固,可拆卸式连接便于进行不同工具的组合。The support bar and the landing bar are fixed by welding, and the slope control bar and the support bar, and between the operating handle bar and the support bar are detachably connected or fixed by welding. The welding method is mature, simple and firm, and the detachable connection is convenient for the combination of different tools.
所述的支架杆、坡度控制杆、落地杆及操作手杆均采用镀锌圆形钢管或镀锌方形钢管。镀锌钢管光洁度高,粘性小,对坡度面的抹平效率高,面光效果好,移动方便。The support rods, slope control rods, landing rods and operating handle rods are all made of galvanized circular steel pipes or galvanized square steel pipes. Galvanized steel pipe has high smoothness, low viscosity, high smoothing efficiency on the slope surface, good surface gloss effect, and easy movement.
所述的坡度控制杆与支架杆之间、操作手杆与支架杆之间为可拆卸式连接,所述的支架杆的一侧的中下部设有位控制杆,位控制杆与支架垂直设置构成沟中沟抹压架。可拆卸式连接便于拆装,位控制杆便于控制沟与沟侧壁的距离。There is a detachable connection between the slope control rod and the support rod, and between the operating handle rod and the support rod. The middle and lower part of one side of the support rod is provided with a position control rod, and the position control rod is vertically arranged with the support It forms a ditch-in-ditch mopping frame. The detachable connection is convenient for disassembly and assembly, and the position control lever is convenient for controlling the distance between the ditch and the side wall of the ditch.
所述的落地杆的半径为R30mm。符合国家电网公司标准工艺要求,电缆沟中设置R30mm的沟中沟至集水井排水,最终汇集至就近的雨水检查井。The radius of the landing pole is R30mm. In line with the standard process requirements of the State Grid Corporation of China, a R30mm ditch in the ditch is set in the cable trench to drain water from the water collection well, and finally collect it into the nearest rainwater inspection well.
所述的坡度控制杆截面呈方形。方形截面的抹光效果好。The section of the slope control rod is square. Good troweling effect for square sections.
所述的操作手杆设有定位件以实现操作手杆方向调整固定。操作手杆实现换向便于操作手杆在两种不同使用状态下切换方向。The operating handle bar is provided with a positioning member to realize the adjustment and fixation of the operating handle bar. The operation handle lever realizes the reversing, which is convenient for the operation handle lever to switch directions under two different use states.
电缆沟底板坡度控制和沟中沟抹压工具的使用方法,包括电缆沟底板坡度控制步骤及沟中沟抹压步骤,The usage method of cable trench floor slope control and ditch-in-ditch wiping tools, including the steps of cable ditch floor slope control and ditch-in-ditch wiping steps,
电缆沟底板坡度控制步骤为:The slope control steps of the cable trench bottom plate are as follows:
11)将两支架通过坡度控制杆连接形成坡度控制架;11) Connect the two supports through the slope control rod to form a slope control frame;
12)在混凝土底板斜面施工完毕后,通过移动操作手杆从电缆沟的一端向另一端移动而实现混凝土底板坡度面的面层收光操作;12) After the construction of the inclined surface of the concrete floor is completed, the surface layer receiving operation of the slope surface of the concrete floor is realized by moving the operating handle from one end of the cable trench to the other end;
13)在面层收光完成后,拉出工具,并对拉出部位进行抹平操作;13) After the finishing of the surface layer, pull out the tool and smooth the pulled out part;
沟中沟抹压步骤为:The steps of wiping and pressing in the ditch are as follows:
21)拆除坡度控制架的坡度控制杆,保留一支架,并在支架的支架杆的中下部加装位控制杆形成沟中沟抹压架;操作手杆换向,使其与支架垂直;21) Remove the slope control rod of the slope control frame, retain a bracket, and install a position control rod at the middle and lower part of the bracket rod to form a ditch-in-ditch wiping frame; operate the hand lever to change direction so that it is perpendicular to the bracket;
22)在电缆沟侧壁上进行弹线,在电缆沟中沟施工时,施工人员握住操作手杆,将位控制杆对准弹线,通过按压操作手杆,使得落地杆深入混凝土一半,即形成电缆沟沟中沟。22) Carry out springing on the side wall of the cable trench. When constructing in the middle of the cable trench, the construction personnel hold the operating handle bar, align the control bar with the springing line, and press the operating handle bar so that the landing bar penetrates halfway into the concrete. That is to form the cable ditch in the ditch.
有益效果:方便定位、标高,可以进行不间断作业施工,人员操作简单,移动方面,施工效率高,可以重复循环使用。Beneficial effects: convenient positioning, high elevation, uninterrupted construction, easy operation by personnel, high construction efficiency in terms of movement, and can be used repeatedly.
附图说明Description of drawings
图1是本发明电缆沟底板坡面光面施工原理图。Fig. 1 is a construction principle diagram of the smooth surface of the slope surface of the cable trench bottom plate of the present invention.
图2是本发明沟中沟抹压工具示意图。Fig. 2 is a schematic diagram of a ditch-in-ditch wiping tool of the present invention.
图3是本发明沟中沟抹压工具抹压示意图。Fig. 3 is a schematic diagram of a wiping tool for wiping a ditch in a ditch of the present invention.
图中:1-支架杆;2-操作手杆;3-落地杆;4-坡度控制杆;5-电缆沟侧壁;6-电缆沟底板7-位控制杆。In the figure: 1-support rod; 2-operating handle rod; 3-floor rod; 4-slope control rod; 5-cable trench side wall; 6-cable trench bottom plate 7-position control rod.
具体实施方式Detailed ways
以下结合说明书附图对本发明的技术方案做进一步的详细说明。The technical solution of the present invention will be further described in detail below in conjunction with the accompanying drawings.
实例一:如图1-3所示,电缆沟底板坡度控制和沟中沟抹压工具,包括支架杆1、坡度控制杆4、落地杆3及操作手杆2,支架杆1为4根,两支架杆1与一位于支架杆1之间的落地杆3连接形成一支架;两支架左右设置,坡度控制杆4设于两支架之间形成坡度控制架;支架杆1竖直放置,坡度控制杆4斜向设于左右两支架杆1的中下部,落地杆3垂直设于支架杆1的底部,操作手杆2垂直设于支架杆1的顶部,落地杆3为圆形钢管。Example 1: As shown in Figure 1-3, the tool for controlling the slope of the cable trench floor and wiping the trench in the ditch includes a support rod 1, a slope control rod 4, a floor rod 3 and an operating handle rod 2, and the support rod 1 is 4 pieces. Two support rods 1 are connected with a floor rod 3 positioned between the support rods 1 to form a support; the two supports are arranged left and right, and the slope control rod 4 is arranged between the two supports to form a slope control frame; the support rod 1 is placed vertically, and the slope is controlled Bar 4 is arranged obliquely at the middle and lower part of two support bars 1 on the left and right, floor bar 3 is vertically located at the bottom of support bar 1, and operating handle bar 2 is vertically located at the top of support bar 1, and floor bar 3 is a circular steel pipe.
为了便于进行不同使用方式的组合,支架杆1、落地杆3之间通过焊接固定,坡度控制杆4与支架杆1之间、操作手杆2与支架杆1之间为可拆卸式连接固定。支架杆1与落地杆3之间不需要拆卸可直接焊接固定,坡度控制杆4与支架杆1之间、操作手杆2与支架杆1之间的可拆卸式连接固定方式便于在不同使用方式下拆卸合组合。In order to facilitate the combination of different usage modes, the support bar 1 and the floor bar 3 are fixed by welding, and the slope control bar 4 and the support bar 1, and between the operating handle bar 2 and the support bar 1 are detachably connected and fixed. The bracket rod 1 and the floor rod 3 can be directly welded and fixed without disassembly, and the detachable connection and fixing methods between the slope control rod 4 and the bracket rod 1, and between the operating handle rod 2 and the bracket rod 1 are convenient for different use modes. Disassemble the combination below.
为了便于抹光操作,支架杆1、坡度控制杆4、落地杆3及操作手杆2均采用镀锌圆形钢管。镀锌钢管光洁度高,粘性小,对坡度面的抹平效率高,面光效果好,移动阻力小。In order to facilitate the troweling operation, the support rod 1, the slope control rod 4, the landing rod 3 and the operating handle rod 2 are all made of galvanized circular steel pipes. The galvanized steel pipe has high smoothness, low viscosity, high smoothing efficiency on the slope surface, good surface gloss effect, and small movement resistance.
为了实现沟中沟抹压的操作使用方式,所述的坡度控制杆4与支架杆1之间、操作手杆2与支架杆1之间为可拆卸式连接,支架杆1的一侧的中下部设有位控制杆7,位控制杆7与支架垂直设置构成沟中沟抹压架。便于切换使用方式,位控制杆7可以确定沟中沟的位置。In order to realize the operation and use mode of mopping in the ditch, the slope control rod 4 and the support rod 1, the operating handle rod 2 and the support rod 1 are detachably connected, and the middle of one side of the support rod 1 The lower part is provided with a position control rod 7, and the position control rod 7 is vertically arranged with the support to form a ditch wiping press frame in the ditch. It is convenient to switch the use mode, and the position control lever 7 can determine the position of the ditch in the ditch.
为了便于排水和符合国家电网公司标准工艺要求,落地杆3的半径为R30mm。In order to facilitate drainage and comply with the standard technical requirements of the State Grid Corporation, the radius of the landing pole 3 is R30mm.
为了实现操作手杆2的方向切换和定位,操作手杆2设有定位件以实现操作手杆2方向调整固定。In order to realize the direction switching and positioning of the operating handle bar 2 , the operating handle bar 2 is provided with a positioning member to realize the direction adjustment and fixation of the operating handle bar 2 .
电缆沟底板坡度控制和沟中沟抹压工具的使用方法,包括电缆沟底板坡度控制步骤及沟中沟抹压步骤,The usage method of cable trench floor slope control and ditch-in-ditch wiping tools, including the steps of cable ditch floor slope control and ditch-in-ditch wiping steps,
电缆沟底板坡度控制步骤为:The slope control steps of the cable trench bottom plate are as follows:
11)将两支架通过坡度控制杆4连接形成坡度控制架;11) Connect the two supports through the slope control rod 4 to form a slope control frame;
12)在混凝土底板6斜面施工完毕后,通过移动操作手杆2从电缆沟的一端向另一端移动而实现混凝土底板6坡度面的面层收光操作;12) After the construction of the inclined surface of the concrete base plate 6 is completed, the surface layer receiving operation of the slope surface of the concrete base plate 6 is realized by moving the operating handle 2 from one end of the cable trench to the other end;
13)在面层收光完成后,拉出工具,并对拉出部位进行抹平操作;13) After the finishing of the surface layer, pull out the tool and smooth the pulled out part;
沟中沟抹压步骤为:The steps of wiping and pressing in the ditch are as follows:
21)拆除坡度控制架的坡度控制杆4,保留一支架,并在支架的支架杆1的中下部加装位控制杆7形成沟中沟抹压架;操作手杆2换向,使其与支架垂直;21) Remove the slope control rod 4 of the slope control frame, retain a bracket, and install a position control rod 7 on the middle and lower part of the bracket rod 1 of the bracket to form a ditch-in-ditch wiping frame; stand vertical;
22)在电缆沟侧壁5上进行弹线,在电缆沟中沟施工时,施工人员握住操作手杆2,将位控制杆7对准弹线,通过按压操作手杆2,使得落地杆3深入混凝土一半,即形成电缆沟沟中沟。22) Carry out springing on the side wall 5 of the cable trench. During construction in the middle of the cable trench, the construction worker holds the operating handle 2, aligns the position control lever 7 with the springing line, and presses the operating handle 2 to make the landing pole 3. Go deep into the concrete halfway, that is, form the ditch in the cable ditch.
实例二:与以上实例一的不同之处在于坡度控制杆4与支架杆1之间、操作手杆2与支架杆1之间为采用镀锌方形钢管焊接固定。Example 2: The difference from the above example 1 is that between the slope control rod 4 and the support rod 1, and between the operating handle rod 2 and the support rod 1, galvanized square steel pipes are used for welding and fixing.
以上图1-3所示的电缆沟底板坡度控制和沟中沟抹压工具及其使用方法是本发明的具体实施例,已经体现出本发明实质性特点和进步,可根据实际的使用需要,在本发明的启示下,对其进行形状、结构等方面的等同修改,均在本方案的保护范围之列。The cable trench floor slope control shown in Figure 1-3 above and the tool for wiping and pressing the trench in the trench and its use method are specific embodiments of the present invention, which have already reflected the substantive features and progress of the present invention, and can be used according to actual needs. Under the enlightenment of the present invention, equivalent modifications to it in terms of shape, structure, etc., all fall within the scope of protection of this proposal.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201511015295.0A CN105442619B (en) | 2015-12-31 | 2015-12-31 | Cable duct bottom board slope controls smears pressure instrument and its application method with ditch in ditch |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201511015295.0A CN105442619B (en) | 2015-12-31 | 2015-12-31 | Cable duct bottom board slope controls smears pressure instrument and its application method with ditch in ditch |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN105442619A CN105442619A (en) | 2016-03-30 |
| CN105442619B true CN105442619B (en) | 2018-03-09 |
Family
ID=55553214
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201511015295.0A Active CN105442619B (en) | 2015-12-31 | 2015-12-31 | Cable duct bottom board slope controls smears pressure instrument and its application method with ditch in ditch |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105442619B (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106436753B (en) * | 2016-09-23 | 2018-09-28 | 安徽送变电工程有限公司 | A kind of cable duct bottom of trench operation unified platform |
| CN108755707A (en) * | 2018-06-22 | 2018-11-06 | 五冶集团上海有限公司 | A kind of cable duct sliding form apparatus |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR100854718B1 (en) * | 2006-09-09 | 2008-08-27 | 김동욱 | Cable Trough Drainage Method and Cable Troughs Used in the Drainage Method |
| CN201388032Y (en) * | 2009-04-07 | 2010-01-20 | 湖北省输变电工程公司 | A kind of cable trench for easy drainage |
| CN202817674U (en) * | 2012-09-20 | 2013-03-20 | 国家电网公司 | Cable trench for keeping cable away from moisture |
| CN203755423U (en) * | 2014-04-10 | 2014-08-06 | 福建省闽南建筑工程有限公司 | Novel drainage ditch shaping device |
| CN205259196U (en) * | 2015-12-31 | 2016-05-25 | 浙江省送变电工程公司 | Pressure instrument is smeared to grade control of cable pit bottom plate and ditch median gutter |
-
2015
- 2015-12-31 CN CN201511015295.0A patent/CN105442619B/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| CN105442619A (en) | 2016-03-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102518300B (en) | Embedded conical bearing joint type steel structure support and construction method thereof | |
| CN202194394U (en) | Rapid hoisting, positioning and adjusting piece for prefabricated wall board | |
| CN112064676A (en) | Movable formwork structure and construction method thereof | |
| CN105442619B (en) | Cable duct bottom board slope controls smears pressure instrument and its application method with ditch in ditch | |
| CN207177102U (en) | Prefabricated conversion layer reserves sleeve joint bar accurate-location device | |
| CN109057339A (en) | A kind of one-time-concreting construction method of the anti-bank in toilet | |
| CN204479572U (en) | The change slope formula soil loss monitoring test unit that a kind of pulley blocks controls | |
| CN205259196U (en) | Pressure instrument is smeared to grade control of cable pit bottom plate and ditch median gutter | |
| CN210659228U (en) | A movable single-sided formwork system for subway construction | |
| CN208034022U (en) | A kind of nozzle for Large Diameter Pipeline steel pipe and nozzle docking facilities | |
| CN218239433U (en) | Water intaking ware is used in hydrology reconnaissance | |
| CN105839914A (en) | Adjustable steel beam supporting device and adjustable steel beam supporting system | |
| CN203145475U (en) | Foundation of floor concrete leveling device | |
| CN204284655U (en) | Direct-burried underground spigot and socket type concrete pressure pipeline pushing installation machine | |
| CN203213143U (en) | Construction structure of diversion trench for water pump installation base | |
| CN203795431U (en) | Drill exploration rod up-pulling device | |
| CN213461027U (en) | A simple cable trench support structure | |
| CN217539856U (en) | Pipeline connecting device for hydraulic engineering | |
| CN204491953U (en) | Floor slab structure between architecture pipe | |
| CN213804761U (en) | Concrete strickle device for civil engineering construction | |
| CN210563413U (en) | A indent device for cast-in-place horizontal floor | |
| CN221255486U (en) | A mesh sprayed concrete flatness control device | |
| CN206353102U (en) | A kind of Concrete and reinforced concrete drainage and sewer pipes external load test device | |
| CN210025832U (en) | A cable trench opening booster | |
| CN206128118U (en) | Operation integration platform at bottom of cable pit ditch |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||