CN105442614A - 一种基坑围护的施工方法 - Google Patents

一种基坑围护的施工方法 Download PDF

Info

Publication number
CN105442614A
CN105442614A CN201510801229.XA CN201510801229A CN105442614A CN 105442614 A CN105442614 A CN 105442614A CN 201510801229 A CN201510801229 A CN 201510801229A CN 105442614 A CN105442614 A CN 105442614A
Authority
CN
China
Prior art keywords
wall
construction
ground
foundation pit
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510801229.XA
Other languages
English (en)
Inventor
徐栋雷
顾培林
富严恺
沈阳
钱孙斌
张铤
徐威
陈晓清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Tongyan Building Planning Design Co Ltd
Original Assignee
Zhejiang Tongyan Building Planning Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Tongyan Building Planning Design Co Ltd filed Critical Zhejiang Tongyan Building Planning Design Co Ltd
Priority to CN201510801229.XA priority Critical patent/CN105442614A/zh
Publication of CN105442614A publication Critical patent/CN105442614A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

本发明公开了一种基坑围护的施工方法,包括如下步骤:第一步,在拟定施工的连续墙内侧设置模板,往模板内浇注混凝土,第二步,施做连续墙的导墙;第三步,将槽段分幅进行成槽施工,成槽用于预制地墙孔的拼装入槽满足围护结构施工需要;第四步,使用旋挖钻机和冲击钻机,对岩层进行旋挖破碎,钻出钻渣,直至设计深度;第五步,将岩石碎渣捞起,在槽段内按要求插入型钢定位,引导预制地墙吊入成槽中;第六步,对地墙进行拼接,形成一幅地墙,然后转入下幅施工,直至整个基坑连续墙的完成,并对预制地墙的孔内二次注浆,使型钢和预制地墙合为一体。该基坑围护的施工方法施工成本低,安全可靠。

Description

一种基坑围护的施工方法
技术领域:
本发明涉及建筑领域,具体是一种基坑围护的施工方法。
背景技术:
在城市建筑施工时经常遇见地质情况复杂的情形,如地层由上至下分别为:杂填土、素填土、老城杂填土、砂质粉土、砂质粘土、粘土(膨胀土)、全风化钙质页岩、强风化钙质页岩、中风化及微风化钙质页岩,局部还存在溶洞。
这类土层对结构施工影响大,必须采用合适的方法,加强支护、防水等工程措施。膨胀土遇水膨胀,失水收缩,对基坑开挖易造成边坡开裂变形破坏,对加固等防护工程产生挤压破坏等;风化岩:岩层成份不均,经施工扰动后或渗水,强度明显降低,不利于基坑围岩稳定。溶洞的大小存在不确定性,如不采取措施对围护施工时浇筑的混凝土将造成极大浪费,而且,目前的基坑在实际施工过程中基坑围护处于一个较为薄弱的状态,围护的日变形较大,对基坑围护结构变形的控制较难把握,进而产生安全隐患。
发明内容:
本发明所要解决的技术问题是,提供一种有效稳定基坑结构,使之不易变形,并降低施工成本的基坑围护的施工方法。
本发明的技术解决方案是,提供一种基坑围护的施工方法,包括如下步骤:
第一步,在拟定施工的连续墙内侧设置模板,往模板内浇注混凝土,并用三轴水泥土搅拌桩对连续墙槽壁土体进行加固;
第二步,施做连续墙的导墙;
第三步,根据设计要求,将槽段分幅进行成槽施工,成槽用于预制地墙孔的拼装入槽满足围护结构施工需要,在此过程中,用液压抓斗成槽机抓到岩层为止;
第四步,使用旋挖钻机和冲击钻机,对岩层进行旋挖破碎,钻出钻渣,直至设计深度;
第五步,将岩石碎渣捞起,在槽段内按要求插入型钢定位,引导预制地墙吊入成槽中;
第六步,对地墙进行拼接,形成一幅地墙,然后转入下幅施工,直至整个基坑连续墙的完成,并对预制地墙的孔内二次注浆,使型钢和预制地墙合为一体。
本发明的有益效果是:用预制地墙降低了施工难度,提高了施工质量,缩短了工时,节约了成本,而连续墙内侧设置模板,浇筑混凝土,增加了施工安全性,同时,机械改进,提升了搅拌桩性能,并减少了费用投入。
具体实施方式:
下面结合具体实施方式对本发明作进一步说明:
一种基坑围护的施工方法,包括如下步骤:
第一步,在拟定施工的连续墙内侧设置模板,往模板内浇注混凝土,并用三轴水泥土搅拌桩对连续墙槽壁土体进行加固;
第二步,施做连续墙的导墙;
第三步,根据设计要求,将槽段分幅进行成槽施工,成槽用于预制地墙孔的拼装入槽满足围护结构施工需要,在此过程中,用液压抓斗成槽机抓到岩层为止;
第四步,使用旋挖钻机和冲击钻机,对岩层进行旋挖破碎,钻出钻渣,直至设计深度;
第五步,将岩石碎渣捞起,在槽段内按要求插入型钢定位,引导预制地墙吊入成槽中;
第六步,对地墙进行拼接,形成一幅地墙,然后转入下幅施工,直至整个基坑连续墙的完成,并对预制地墙的孔内二次注浆,使型钢和预制地墙合为一体。

Claims (1)

1.一种基坑围护的施工方法,其特征在于,包括如下步骤:
第一步,在拟定施工的连续墙内侧设置模板,往模板内浇注混凝土,并用三轴水泥土搅拌桩对连续墙槽壁土体进行加固;
第二步,施做连续墙的导墙;
第三步,根据设计要求,将槽段分幅进行成槽施工,成槽用于预制地墙孔的拼装入槽满足围护结构施工需要,在此过程中,用液压抓斗成槽机抓到岩层为止;
第四步,使用旋挖钻机和冲击钻机,对岩层进行旋挖破碎,钻出钻渣,直至设计深度;
第五步,将岩石碎渣捞起,在槽段内按要求插入型钢定位,引导预制地墙吊入成槽中;
第六步,对地墙进行拼接,形成一幅地墙,然后转入下幅施工,直至整个基坑连续墙的完成,并对预制地墙的孔内二次注浆,使型钢和预制地墙合为一体。
CN201510801229.XA 2015-11-19 2015-11-19 一种基坑围护的施工方法 Pending CN105442614A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510801229.XA CN105442614A (zh) 2015-11-19 2015-11-19 一种基坑围护的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510801229.XA CN105442614A (zh) 2015-11-19 2015-11-19 一种基坑围护的施工方法

Publications (1)

Publication Number Publication Date
CN105442614A true CN105442614A (zh) 2016-03-30

Family

ID=55553209

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510801229.XA Pending CN105442614A (zh) 2015-11-19 2015-11-19 一种基坑围护的施工方法

Country Status (1)

Country Link
CN (1) CN105442614A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120807A (zh) * 2016-07-27 2016-11-16 东通岩土科技(杭州)有限公司 永久性基坑围护水泥土刚性墙及其施工方法
CN107165170A (zh) * 2017-06-09 2017-09-15 上海市机械施工集团有限公司 一种基坑施工方法
CN108517874A (zh) * 2018-04-11 2018-09-11 浙江桐砚建筑规划设计有限公司 一种基坑围护的施工方法
CN108894210A (zh) * 2018-07-12 2018-11-27 中铁隧道局集团有限公司 一种用于海域复杂混合地层条件下连续墙成槽的综合施工方法
CN113152559A (zh) * 2021-05-07 2021-07-23 深圳大学 一种抛石填海区地连墙抓锤铣成槽的施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2959253A1 (fr) * 2010-04-26 2011-10-28 Soletanche Freyssinet Paroi moulee avec parement prefabrique
CN203334270U (zh) * 2013-06-26 2013-12-11 中国建筑股份有限公司 一种可装配埋入式预制空心地下连续墙
CN103469801A (zh) * 2013-09-03 2013-12-25 上海建科工程咨询有限公司 基于预制地墙的基坑围护结构施工方法
CN203475439U (zh) * 2013-09-03 2014-03-12 上海建科工程咨询有限公司 基于预制地墙的基坑围护结构施工方法中的专用预制地墙
CN104963346A (zh) * 2015-06-30 2015-10-07 中国二十冶集团有限公司 复杂地质的深基坑围护施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2959253A1 (fr) * 2010-04-26 2011-10-28 Soletanche Freyssinet Paroi moulee avec parement prefabrique
CN203334270U (zh) * 2013-06-26 2013-12-11 中国建筑股份有限公司 一种可装配埋入式预制空心地下连续墙
CN103469801A (zh) * 2013-09-03 2013-12-25 上海建科工程咨询有限公司 基于预制地墙的基坑围护结构施工方法
CN203475439U (zh) * 2013-09-03 2014-03-12 上海建科工程咨询有限公司 基于预制地墙的基坑围护结构施工方法中的专用预制地墙
CN104963346A (zh) * 2015-06-30 2015-10-07 中国二十冶集团有限公司 复杂地质的深基坑围护施工方法

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120807A (zh) * 2016-07-27 2016-11-16 东通岩土科技(杭州)有限公司 永久性基坑围护水泥土刚性墙及其施工方法
CN107165170A (zh) * 2017-06-09 2017-09-15 上海市机械施工集团有限公司 一种基坑施工方法
CN107165170B (zh) * 2017-06-09 2019-11-26 上海市机械施工集团有限公司 一种基坑施工方法
CN108517874A (zh) * 2018-04-11 2018-09-11 浙江桐砚建筑规划设计有限公司 一种基坑围护的施工方法
CN108894210A (zh) * 2018-07-12 2018-11-27 中铁隧道局集团有限公司 一种用于海域复杂混合地层条件下连续墙成槽的综合施工方法
CN113152559A (zh) * 2021-05-07 2021-07-23 深圳大学 一种抛石填海区地连墙抓锤铣成槽的施工方法

Similar Documents

Publication Publication Date Title
CN101139838B (zh) 高承压水地区超深基坑的施工方法
CN105442614A (zh) 一种基坑围护的施工方法
CN104264688A (zh) 人工挖孔变截面桩支护施工工艺
CN104963346A (zh) 复杂地质的深基坑围护施工方法
CN110735600B (zh) 一种用于喀斯特地质的机械成孔桩施工工艺
CN102660955B (zh) 一种基坑边坡支护的快速施工方法
CN105239578B (zh) 富水砂层深基坑水下施工方法
CN111236387B (zh) 新建污水管与既有污水管接驳施工方法
CN106545007A (zh) 在下部为硬质岩层的地层中成桩的方法
CN104404974A (zh) 高承压水厚砂卵石地层深基坑注浆封底结构及其施工工艺
CN103046931A (zh) 一种竖井/导井冲击式钻机冲击成孔施工方法
CN105442605A (zh) 拔出phc桩再利用于深基坑支护施工方法
CN106065628B (zh) 基于永临结合理念的大直径自来水管安全防护施工方法
CN110284885A (zh) 盾构检修井施工方法
CN112761076A (zh) 一种应用于水位变化条件下的锁扣钢管桩围堰及施工方法
CN110905536A (zh) 复杂地层土压盾构在暗挖隧道内接收的施工方法
CN106677166A (zh) 卵砾石――风化岩地层钻孔灌注桩双机联合成桩流水施工方法
CN105714748A (zh) 一种碎石沙土层中的调压井开挖施工方法
KR100803921B1 (ko) 엘리베이터 지하층 연장 운행을 위한 공동부 시공방법
CN108071110A (zh) 复杂地质条件下旋挖钻机嵌岩桩施工方法
CN101481913A (zh) 嵌岩地下连续墙冲孔槽段施工方法
CN105672309A (zh) 岩溶地区嵌岩桩成孔可回收超长钢护筒护壁方法
CN111877321A (zh) 一种地下钢筋混凝土结构处施作的灌注桩及其施工方法
CN204252148U (zh) 高承压水厚砂卵石地层深基坑注浆封底结构
CN106049467A (zh) 复杂地质下冲击钻钻孔灌注桩漏浆处理方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160330

RJ01 Rejection of invention patent application after publication