CN105421448A - 一种双壁波纹管预制管桩接桩结构及其工艺 - Google Patents
一种双壁波纹管预制管桩接桩结构及其工艺 Download PDFInfo
- Publication number
- CN105421448A CN105421448A CN201510961840.9A CN201510961840A CN105421448A CN 105421448 A CN105421448 A CN 105421448A CN 201510961840 A CN201510961840 A CN 201510961840A CN 105421448 A CN105421448 A CN 105421448A
- Authority
- CN
- China
- Prior art keywords
- pile
- pile body
- pipe
- double
- extension adapter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 14
- 238000010276 construction Methods 0.000 claims abstract description 16
- 239000002689 soil Substances 0.000 claims description 6
- 230000003014 reinforcing effect Effects 0.000 claims description 4
- 238000007789 sealing Methods 0.000 claims description 4
- 238000005485 electric heating Methods 0.000 claims description 3
- 238000012423 maintenance Methods 0.000 claims description 3
- 239000000463 material Substances 0.000 claims description 3
- 238000002844 melting Methods 0.000 claims description 3
- 230000008018 melting Effects 0.000 claims description 3
- 239000004576 sand Substances 0.000 abstract description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 2
- 238000004904 shortening Methods 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 4
- 239000003673 groundwater Substances 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 239000011449 brick Substances 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/52—Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
- E02D5/523—Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
- E02D5/526—Connection means between pile segments
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/50—Piles comprising both precast concrete portions and concrete portions cast in situ
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明公开了一种双壁波纹管预制管桩接桩结构及其工艺,包括材质为双壁波纹管的上桩体、下桩体、设置在上桩体和下桩体内的混凝土,所述上桩体和下桩体之间设置有接桩接头,所述接桩接头为中间设置有卡接圈的空心圆管,所述卡接圈与接桩接头一体成型,所述接桩接头的直径小于上桩体、下桩体的直径。本发明工序简单、效率高且适用于地质复杂、地下水位高、流沙多的施工地区,能有效节约工期、节约成本。
Description
技术领域
本发明涉及土木工程地基与基础施工中的接桩结构领域,特别是涉及一种双壁波纹管预制管桩接桩结构及其工艺。
背景技术
随着社会的发展,建筑物不仅仅是满足人们生活的需要,而且在生活中扮演着越来越重要的角色,人们对于建筑物的质量要求也越来越高。一直以来,在预制管桩基础施工过程中,我国建筑工程中管桩接桩施工大多采用开挖→浇垫层→焊接接长钢筋→砌筑转胎模→侧壁回填→浇筑混凝土的施工工艺。该技术虽然成熟可靠,但是考虑房产开发进度及施工工期、安全方面,该技术工序多,耗时长,人工耗用多,综合费用高,未能有效节约工期、节约成本。
发明内容
为克服上述不足,本发明提供了一种工序简单、效率高且适用于地质复杂、地下水位高、流沙多施工地区的双壁波纹管预制管桩接桩结构及其工艺。
本发明采用的技术方案是:一种双壁波纹管预制管桩接桩结构,包括材质为双壁波纹管的上桩体、下桩体、设置在上桩体和下桩体内的混凝土,所述上桩体和下桩体之间设置有接桩接头。
作为上述方案的进一步设置,所述接桩接头为中间设置有卡接圈的空心圆管,所述卡接圈与接桩接头一体成型,所述接桩接头的直径小于上桩体、下桩体的直径。
作为上述方案的进一步设置,所述接桩接头与上桩体、下桩体之间设置有密封圈。
作为上述方案的进一步设置,所述接桩接头为上桩体、下桩体的承插结构,所述接桩接头处的下桩体管口管径大于下桩体的管径,所述接桩接头处的上桩体管口外圈设置有承接台。
一种双壁波纹管预制管桩接桩工艺,包括以下步骤,
A、将一根材质为双壁波纹管的预制管桩作为下桩体置入施工的土壤中,并使其部分凸出地面;
B、对下桩体凸出地面部分进行清洗,将接桩接头套接在下桩体凸出地面的管口上,并在接桩接头的另一端连接另一根接口已清洗的双壁波纹管预制管桩作为上桩体;
C、用密封橡胶及电热熔方式对接桩接头进行加固;
D、将步骤C中经加固后的连接桩继续下沉置入施工土壤,并使上桩体的部分凸出地面;
E、将焊接有托板的钢筋笼从上桩体凸出地面的管口中放入上桩体和下桩体的管体内,并用砼浇筑振捣;
F、经养护后做载荷试验,符合承载要求后,工艺完成。
本发明用双壁波纹管桩替代现有的混凝土管桩及钢管管桩,具有工序简单、效率高的特点,适用于地质复杂、地下水位高、流沙多的施工地区,能有效节约工期、节约成本。
附图说明
图1为本发明实施例1的结构示意图;
图2为本发明实施例2的结构示意图。
图中:1、上桩体;11、承接台;2、下桩体;3、混凝土;4、接桩接头;41、卡接圈;5、密封圈。
具体实施方式
下面结合附图及实施例对本发明做进一步描述。
如图1、图2所示,一种双壁波纹管预制管桩接桩结构,包括材质为双壁波纹管的上桩体1、下桩体2、设置在上桩体1和下桩体2内的混凝土3,所述上桩体1和下桩体2之间设置有接桩接头4。
一种双壁波纹管预制管桩接桩工艺,包括以下步骤,
A、将一根材质为双壁波纹管的预制管桩作为下桩体2置入施工的土壤中,并使其部分凸出地面;
B、对下桩体2凸出地面部分进行清洗,将接桩接头4套接在下桩体2凸出地面的管口上,并在接桩接头4,的另一端连接另一根接口已清洗的双壁波纹管预制管桩作为上桩体1;
C、用密封橡胶及电热熔方式对接桩接头4进行加固;
D、将步骤C中经加固后的连接桩继续下沉置入施工土壤,并使上桩体1的部分凸出地面;
E、将焊接有托板的钢筋笼从上桩体1凸出地面的管口中放入上桩体1和下桩体2的管体内,并用砼浇筑振捣;
F、经养护后做载荷试验,符合承载要求后,工艺完成。
实施例1
所述接桩接头4为中间设置有卡接圈41的空心圆管,所述卡接圈41与接桩接头4一体成型,所述接桩接头4的直径小于上桩体1、下桩体2的直径,所述接桩接头4与上桩体1、下桩体2之间设置有密封圈5。
实施例2
所述接桩接头4为上桩体1、下桩体2的承插结构,所述接桩接头4处的下桩体2管口管径大于下桩体1的管径,所述接桩接头4处的上桩体1管口外圈设置有承接台11。
上面结合附图对本发明的具体实施方式作了详细说明,但是本发明并不限于上述实施方式,在本领域普通技术人员所具备的知识范围内,还可以在不脱离本发明宗旨的前提下作出各种变化。
Claims (5)
1.一种双壁波纹管预制管桩接桩结构,其特征在于:包括材质为双壁波纹管的上桩体(1)、下桩体(2)、设置在上桩体(1)和下桩体(2)内的混凝土(3),所述上桩体(1)和下桩体(2)之间设置有接桩接头(4)。
2.根据权利要求1所述的一种双壁波纹管预制管桩接桩结构,其特征在于:所述接桩接头(4)为中间设置有卡接圈(41)的空心圆管,所述卡接圈(41)与接桩接头(4)一体成型,所述接桩接头(4)的直径小于上桩体(1)、下桩体(2)的直径。
3.根据权利要求1或2所述的一种双壁波纹管预制管桩接桩结构,其特征在于:所述接桩接头(4)与上桩体(1)、下桩体(2)之间设置有密封圈(5)。
4.根据权利要求1所速的一种双壁波绞管预制管桩接桩结构,其特征在于:所述接桩接头(4)为上桩体(1)、下桩体(2)的承插结构,所述接桩接头(4)处的下桩体(2)管口管径大于下桩体(1)的管径,所述接桩接头(4)处的上桩体(1)管口外圈设置有承接台(11)。
5.一种双壁波纹管预制管桩接桩工艺,其特征在于:包括以下步骤,
A、将一根材质为双壁波纹管的预制管桩作为下桩体(2)置入施工的土壤中,并使其部分凸出地面;
B、对下桩体(2)凸出地面部分进行清洗,将接桩接头(4)套接在下桩体(2)凸出地面的管口上,并在接桩接头(4)的另一端连接另一根接口已清洗的双壁波纹管预制管桩作为上桩体(1);
C、用密封橡胶及电热熔方式对接桩接头(4)进行加固;
D、将步骤C中经加固后的连接桩继续下沉置入施工土壤,并使上桩体(1)的部分凸出地面;
E、将焊接有托板的钢筋笼从上桩体(1)凸出地面的管口中放入上桩体(1)和下桩体(2)的管体内,并用砼浇筑振捣;
F、经养护后做载荷试验,符合承载要求后,工艺完成。
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510961840.9A CN105421448A (zh) | 2015-12-22 | 2015-12-22 | 一种双壁波纹管预制管桩接桩结构及其工艺 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510961840.9A CN105421448A (zh) | 2015-12-22 | 2015-12-22 | 一种双壁波纹管预制管桩接桩结构及其工艺 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN105421448A true CN105421448A (zh) | 2016-03-23 |
Family
ID=55499959
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510961840.9A Pending CN105421448A (zh) | 2015-12-22 | 2015-12-22 | 一种双壁波纹管预制管桩接桩结构及其工艺 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105421448A (zh) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106245765A (zh) * | 2016-09-23 | 2016-12-21 | 沈阳建筑大学 | 注浆连接钢管装置结构及连接方法 |
| CN108517900A (zh) * | 2018-03-23 | 2018-09-11 | 国网甘肃省电力公司经济技术研究院 | 一种盐渍土地区输电线路灌注桩基础的防腐方法 |
| WO2019090409A1 (pt) | 2017-11-13 | 2019-05-16 | Tuper S/A | Disposição construtiva introduzida em luva de conexão de diversas seções para estacas tubulares metálicas |
| CN112281830A (zh) * | 2019-07-24 | 2021-01-29 | 江苏千汇泵业有限公司 | 一种具有抗震功能的快捷接头 |
| CN114045815A (zh) * | 2021-12-03 | 2022-02-15 | 广东建基基础工程有限公司 | 一种深基坑支护用prc管桩及其接桩方法 |
| CN114382075A (zh) * | 2020-10-20 | 2022-04-22 | 宝山钢铁股份有限公司 | 一种菱形钢管混凝土管桩及其制备模具、制备安装方法 |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO1987002726A1 (en) * | 1985-10-28 | 1987-05-07 | Kjell Landaeus | Means for joining concrete piles |
| CN201512784U (zh) * | 2009-08-27 | 2010-06-23 | 王庆革 | 混凝土管桩接桩器 |
| CN202144590U (zh) * | 2011-07-12 | 2012-02-15 | 中国建筑西南勘察设计研究院有限公司 | 一种变截面管桩接桩器 |
| CN102535453A (zh) * | 2012-02-01 | 2012-07-04 | 钟阳 | 一种管桩接头 |
| CN202416301U (zh) * | 2012-02-01 | 2012-09-05 | 钟阳 | 新型管桩接头 |
| CN205954618U (zh) * | 2015-12-22 | 2017-02-15 | 钱俊 | 一种双壁波纹管预制管桩接桩结构 |
-
2015
- 2015-12-22 CN CN201510961840.9A patent/CN105421448A/zh active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO1987002726A1 (en) * | 1985-10-28 | 1987-05-07 | Kjell Landaeus | Means for joining concrete piles |
| CN201512784U (zh) * | 2009-08-27 | 2010-06-23 | 王庆革 | 混凝土管桩接桩器 |
| CN202144590U (zh) * | 2011-07-12 | 2012-02-15 | 中国建筑西南勘察设计研究院有限公司 | 一种变截面管桩接桩器 |
| CN102535453A (zh) * | 2012-02-01 | 2012-07-04 | 钟阳 | 一种管桩接头 |
| CN202416301U (zh) * | 2012-02-01 | 2012-09-05 | 钟阳 | 新型管桩接头 |
| CN205954618U (zh) * | 2015-12-22 | 2017-02-15 | 钱俊 | 一种双壁波纹管预制管桩接桩结构 |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106245765A (zh) * | 2016-09-23 | 2016-12-21 | 沈阳建筑大学 | 注浆连接钢管装置结构及连接方法 |
| WO2019090409A1 (pt) | 2017-11-13 | 2019-05-16 | Tuper S/A | Disposição construtiva introduzida em luva de conexão de diversas seções para estacas tubulares metálicas |
| CN108517900A (zh) * | 2018-03-23 | 2018-09-11 | 国网甘肃省电力公司经济技术研究院 | 一种盐渍土地区输电线路灌注桩基础的防腐方法 |
| CN112281830A (zh) * | 2019-07-24 | 2021-01-29 | 江苏千汇泵业有限公司 | 一种具有抗震功能的快捷接头 |
| CN114382075A (zh) * | 2020-10-20 | 2022-04-22 | 宝山钢铁股份有限公司 | 一种菱形钢管混凝土管桩及其制备模具、制备安装方法 |
| CN114045815A (zh) * | 2021-12-03 | 2022-02-15 | 广东建基基础工程有限公司 | 一种深基坑支护用prc管桩及其接桩方法 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP7257086B2 (ja) | トンネルの低土被り区間の総合的な工法 | |
| CN103669866B (zh) | 地下室钢筋混凝土柱节点连接结构的施工方法 | |
| CN101545270B (zh) | 桩基试验用双套管及其施工工艺方法 | |
| CN103670446B (zh) | 圆形引水隧洞2/3圆砼衬砌施工方法 | |
| CN104404983A (zh) | 一种用于顶管施工的骑马井装置及其施工方法 | |
| CN104988915A (zh) | 一种可拆卸钢护筒装置及水下联系梁预制安装方法 | |
| CN205676882U (zh) | 一种新型的支护结构 | |
| CN102518129B (zh) | 后压浆预应力空心方桩的制作方法 | |
| CN205954618U (zh) | 一种双壁波纹管预制管桩接桩结构 | |
| CN220080031U (zh) | 一种环框梁兼做围檩的结构构件 | |
| CN103758122A (zh) | 一种环保型模块化混凝土管柱及其施工方法 | |
| CN205712123U (zh) | 一种基于双排预应力管桩的基坑永久支护结构 | |
| CN205636749U (zh) | 用于砂卵石漂石地质层的基坑支护体系 | |
| CN211735364U (zh) | 预制装配式护壁人工挖孔桩 | |
| CN110952453B (zh) | 一种桥台结构的施工方法 | |
| CN115749836A (zh) | 中短程地下管线顶管隧道施工方法 | |
| CN107326912A (zh) | 一种对扣式内注浆异型预制支护桩及施工方法 | |
| CN204982873U (zh) | 一种快速安装复合地基phc桩承载板 | |
| CN115772917A (zh) | 一种环箍套管控制钢管立柱桩竖向位移的限位装置 | |
| CN106400832A (zh) | 一种环保型装配式后注浆钢筒桩基础及其施工方法 | |
| CN116335093B (zh) | 一种钢管混凝土地下水库人工坝体 | |
| CN205152973U (zh) | 树根桩 | |
| CN223136141U (zh) | 一种富水黄土地层隧洞暗挖法的施工结构 | |
| CN202064348U (zh) | 加固预应力管桩 | |
| CN211446570U (zh) | 一种桥台结构 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20160323 |
|
| WD01 | Invention patent application deemed withdrawn after publication |