CN105403427B - The tunnel model supporting construction and installation method and production method of 3D printing - Google Patents

The tunnel model supporting construction and installation method and production method of 3D printing Download PDF

Info

Publication number
CN105403427B
CN105403427B CN201510980751.9A CN201510980751A CN105403427B CN 105403427 B CN105403427 B CN 105403427B CN 201510980751 A CN201510980751 A CN 201510980751A CN 105403427 B CN105403427 B CN 105403427B
Authority
CN
China
Prior art keywords
supporting
liner
support plate
tunnel
supporting construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510980751.9A
Other languages
Chinese (zh)
Other versions
CN105403427A (en
Inventor
张霄
张庆松
戚厚羿
李术才
李梦天
刘振国
李鹏
李相辉
左金鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University
Original Assignee
Shandong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University filed Critical Shandong University
Priority to CN201510980751.9A priority Critical patent/CN105403427B/en
Publication of CN105403427A publication Critical patent/CN105403427A/en
Application granted granted Critical
Publication of CN105403427B publication Critical patent/CN105403427B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M99/00Subject matter not provided for in other groups of this subclass

Abstract

The invention discloses the tunnel model supporting construction and installation method and production method of 3D printing, supporting construction includes several sections of supporting sections spliced successively, every section of supporting section includes the liner of several splicings, and each liner is 3D printing part, and support plate is equipped in the outside of supporting section.The beneficial effects of the invention are as follows:Supporting liner is printed using 3D printer, enormously simplify the supporting arrangement of tunnel model test, it is more convenient, and can make experimenter according to actual conditions be the customized supporting construction of tunnel test model, and supporting construction model can recycle after and carry out test of many times, realize recycling;Entire supporting construction is relatively simple and conveniently, can effectively prevent surrouding rock deformation in tunnel model, eliminate the bothersome laborious work such as traditional gunning concrete, addition anchor pole.

Description

The tunnel model supporting construction and installation method and production method of 3D printing
Technical field
The present invention relates to tunnel model test technologies, and in particular to the tunnel model supporting construction and installation method of 3D printing And production method.
Background technology
In Tunnel Engineering, the prototype of Practical Project and structure is usually that size is larger and complex, mechanical property It can not usually be obtained by directly studying structure with force-mechanism, and model test must be used.It is certain meeting Under the premise of the principle of similitude, model test can be more convenient, comprehensive, intuitive, accurate relative to on-the-spot test and mathematical model Ground reflects each item data and performance in tunnel, to probing into underground engineering mechanism and engineering is practical plays directive function.
Currently, the supporting construction of tunnel model test is typically all gunning concrete, or addition wire netting, small anchor pole are again Carry out gunning concrete.However this is not well positioned to meet the principle of similitude of model test, can generate shadow to subsequent experiment It rings.Also, due to the limitation of size and structure, consider the setting time of gunning concrete, tunnel model driving speed and distance It will control in a certain range, when allowing for test fee in this way, laborious, not be well positioned to meet simulation supporting construction also Effect.
Invention content
The purpose of the invention is to overcome the shortcomings of existing tunnel model test supporting construction, the tunnel of the 3D printing provided Road model supporting construction and installation method and production method.
In order to achieve the above objectives, the present invention adopts the following technical scheme that:
The tunnel model supporting construction of 3D printing, including several sections of supporting sections spliced successively, if every section of supporting section includes The liner of dry splicing, each liner is 3D printing part, is equipped with support plate in the outside of supporting section, passes through the liner of 3D printing It is aided with support plate as supporting construction, enormously simplifies the supporting arrangement of tunnel model test, it is more simple and convenient.
Further, the shape of the shape of the support plate and the supporting section just as.
Further, the support plate includes multistage, and adjacent support plate is fixed by chain connecting plate with clamp device.
Further, the shape of the supporting section is obtained by the true form in tunnel by proportional zoom.
Further, the supporting section at the both ends of the supporting construction is fixed on by tabletting in the support plate of end.
Further, the support plate is located between two adjacent supporting sections, and the inside of supporting section passes through tabletting and support plate Connection.
Further, the material for printing the liner is poly-lactic acid material.
Further, the adjacent liner one is equipped with boss, another is equipped with the groove coordinated with boss, by convex Platform coordinates with groove, realizes the fixation of two liners.
The installation method of supporting construction, is as follows:
1) several sections of liners are spliced successively, splices several sections of supporting sections;
2) multistage support plate is located to the outside of supporting section, fixed adjacent support plate constitutes one section of supporting construction, by one The end of section supporting construction is fixed end support plate with liner using tabletting;
3) one section of supporting construction is placed in tunnel model, is bonded the inner wall dug out;
4) continue to dig into tunnel, the support plate in second segment supporting construction is placed in tunnel and is spliced;
5) several sections of liners are spliced successively inside support plate, liner and support plate is fixed;
6) tunnel continuation is dug into forward, is repeated step 4) and is arrived step 5);
7) finally, end support plate and end liner are fixed, complete complete supporting construction.
The manufacturing method of supporting construction, is as follows:
1) according to the likelihood ratio condition for meeting experiment, actual tunnel model is contracted to desirability, determines tunnel model The basic size of supporting construction;
2) it is that simulation actual tunnel excavates situation and ensures stability when tunnel model test excavates, by liner in tunnel Extending direction is divided into multistage, and width is depending on actual conditions;
3) 3D printer is used to print liner.
The beneficial effects of the invention are as follows:
1) it uses 3D printer to print supporting liner, enormously simplifies the supporting arrangement of tunnel model test, it is more convenient Fast, and experimenter can be made according to actual conditions to be the customized supporting construction of tunnel test model, and supporting construction mould Type can recycle after carries out test of many times, realizes recycling.
2) entire supporting construction is relatively simple and conveniently, can effectively prevent surrouding rock deformation in tunnel model, eliminate biography The bothersome laborious work such as gunning concrete, the addition anchor pole of system.
Description of the drawings
Fig. 1 is the structure structural map of the present invention.
Fig. 2 is the structure front view of the present invention.
1-the first liner in figure;The second liners of 2--;3-- third liners;4-the four liner;5-the five liner;6-the Six liners;7-end upper backup pads;8-end lower supporting plates;9-upper backup pads;10-lower supporting plates;11-end tablettings; 12-tablettings;13-connecting plates.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Whole description.
As shown in Figure 1, tunnel test model supporting construction includes several sections of supporting sections spliced successively, every section of supporting Duan Jun Be 6 sections specifically including several sections of liners, i.e. the first liner 1, the second liner 2, third liner 3, the 4th liner 4, in the 5th Lining 5, the 6th liner 6, end upper backup pad 7, end lower supporting plate 8, upper backup pad 9, lower supporting plate 10, end tabletting 11 and pressure Piece 12, chain connecting plate 13, the 4th liner 4, the 5th liner 5, the 6th liner 6 have certain bump, are because this is a tunnel Model, here it is the liner structures in actual tunnel.
Wherein, there are boss and groove on inner lining structure part, can be spliced into an entirety, such as Fig. 2 supporting knots The front view of structure.Inner liner portion is fixed to end upper backup pad by integrally-built stem and tail portion by end tabletting 11 7 and end lower supporting plate 8 on, two of which support plate is then linked together with hexagon socket head cap screw in outside by chain connecting plate 13. Intermediate position inner liner portion is fixed by tabletting 12 and upper backup pad 9 and lower supporting plate 10, upper backup pad 9 and lower supporting plate 10 Divide and is linked together in inside with hexagon socket head cap screw again by chain connecting plate 13.
Inner lining structure part is all 3D printing part.In view of actual tests precision prescribed is not high and printing cost issues, choosing Select all moderate 3D printer MakerBot ReplicatorZ18 printings of printing precision and expense.Polylactic acid (PLA) is a kind of Novel biodegradation material, the starch raw material proposed (such as corn) using reproducible plant resources are made.Mechanical performance And physical property is good.PLA Ke Yi in the case that No have heating bed printing heavy parts model and corner will not tilt, have compared with Low shrinking percentage, performance is good when the model of printing large-size.Meanwhile PLA has lower melt strength, printing Model is more easily moulding.So choosing printed material of the PLA material as supporting construction model.
Support plate is bracing members class, is stamping parts.Suitable diel is first made, then is put into low to cold rolling on forcing press Carbon sheet carries out punch process, obtains the steel bracing plate of respective shapes.End tabletting 11 and tabletting 12 are then to pass through forcing press Q235 sheet metal bendings are obtained.
Its installation method is illustrated with reference to experiment:
1, first, outside tunnel model by liner splicing together, upper backup pad 9 and the chain connecting plate 13 of lower supporting plate 10 connect To together, liner is fixed on upper backup pad 9 and lower supporting plate 10 using tabletting 12.
2, model will have been assembled to place into tunnel test model, has been put into tunnel model, be bonded the inner wall dug out.
3, it digs into a distance forward in tunnel model, then puts upper backup pad 9 and lower supporting plate 10 into tunnel respectively, It is spliced together using chain connecting plate 13 in tunnel.
4, liner 1-6 is put into tunnel again, is spliced together in tunnel.
5, the front and back liner being stitched together twice is pressed onto on steel bracing plate using tabletting 12, blending bolt consolidates tabletting It is fixed.
6, tunnel continuation is dug into forward, and step 3 arrives step 5 before repeating, until meeting test requirements document.
7, last, with end upper backup pad 7, the splicing of end lower supporting plate 8 is fixed, using end tabletting 11 will be last in Lining is fixed, and complete supporting construction is completed.
The tunnel model supporting construction of 3D printing changes the supporting construction analogy method of conventional spray paint material so that supporting Structural simulation more simply and conveniently, can effectively prevent surrouding rock deformation in tunnel model.And after use can fast quick-detach, weight It is multiple to utilize.
Design method is:
One, according to the likelihood ratio condition for meeting experiment, actual tunnel model is contracted to desirability, determines tunnel model The basic size of supporting construction, such as tunnel model supporting construction width, length, road surface to spring of arch.Wherein, it can be beaten according to 3D Material, thickness and filling rate when print adjust tunnel model supporting construction thickness;
Two, it is the convenience for ensureing transport and being placed to experiment tunnel, inner liner portion is divided into six parts, and in contact site There are boss and groove.Six part of liner, which divides, should follow rational principle, and visual actual conditions determine;
Stability when three, excavating situation for simulation actual tunnel and ensure that tunnel model test excavates, by liner in tunnel Road extending direction is divided into multistage, and length is depending on actual conditions;
Four, in view of the stressing conditions and globality of supporting construction model, steel bracing plate is made in head and the tail and intermediate position For the support frame of liner, steel bracing plate thickness and width can be selected according to actual tunnel stress.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, various improvements and modifications may be made without departing from the principle of the present invention, these improvements and modifications are also answered It is considered as protection scope of the present invention.

Claims (4)

  1. The tunnel model supporting construction of 1.3D printings, which is characterized in that the supporting section spliced successively including several sections, the supporting The shape of section is obtained by the true form in tunnel by proportional zoom, and every section of supporting section includes the liner of several splicings, each Liner is 3D printing part, and support plate is equipped in the outside of supporting section;
    The shape of the support plate is identical as the shape of supporting section;
    The support plate includes multistage, and adjacent support plate is fixed by chain connecting plate with clamp device;
    The support plate is located between two adjacent supporting sections, and the inside of supporting section is connect by tabletting with support plate;
    The supporting section at the both ends of the supporting construction is fixed on by tabletting in the support plate of end;
    Adjacent liner one is equipped with boss, another is equipped with the groove coordinated with boss.
  2. 2. supporting construction as described in claim 1, which is characterized in that the material for printing the liner is poly-lactic acid material.
  3. 3. the installation method of supporting construction as claimed in claim 1 or 2, which is characterized in that be as follows:
    1) several sections of liners are spliced successively, splices several sections of supporting sections;
    2) multistage support plate is located to the outside of supporting section, fixed adjacent support plate constitutes one section of supporting construction, by one section of branch The end of protection structure is fixed end support plate with liner using tabletting;
    3) one section of supporting construction is placed in tunnel model, is bonded the inner wall dug out;
    4) continue to dig into tunnel, the support plate in second segment supporting construction is placed in tunnel and is spliced;
    5) several sections of liners are spliced successively inside support plate, liner and support plate is fixed;
    6) tunnel continuation is dug into forward, is repeated step 4) and is arrived step 5);
    7) finally, end support plate and end liner are fixed, complete complete supporting construction.
  4. 4. the manufacturing method of supporting construction as described in any one of claims 1-3, which is characterized in that be as follows:
    1) according to the likelihood ratio condition for meeting experiment, actual tunnel model is contracted to desirability, determines tunnel model supporting The basic size of structure;
    2) it is that simulation actual tunnel excavates situation and ensures stability when tunnel model test excavates, liner is extended in tunnel Direction is divided into multistage, and width is depending on actual conditions;
    3) 3D printer is used to print liner.
CN201510980751.9A 2015-12-23 2015-12-23 The tunnel model supporting construction and installation method and production method of 3D printing Active CN105403427B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510980751.9A CN105403427B (en) 2015-12-23 2015-12-23 The tunnel model supporting construction and installation method and production method of 3D printing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510980751.9A CN105403427B (en) 2015-12-23 2015-12-23 The tunnel model supporting construction and installation method and production method of 3D printing

Publications (2)

Publication Number Publication Date
CN105403427A CN105403427A (en) 2016-03-16
CN105403427B true CN105403427B (en) 2018-10-12

Family

ID=55469052

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510980751.9A Active CN105403427B (en) 2015-12-23 2015-12-23 The tunnel model supporting construction and installation method and production method of 3D printing

Country Status (1)

Country Link
CN (1) CN105403427B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108447381A (en) * 2017-07-04 2018-08-24 河南理工大学 A method of printing analog simulation test model holder by 3D printer
CN113533001B (en) * 2021-09-04 2023-09-26 山东科技大学 Manufacturing method of artificial experiment sample imitating natural rock sample

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8506160B2 (en) * 2008-11-07 2013-08-13 Textron Innovations Inc. Liquid based ice protection test systems and methods
CN101592033B (en) * 2009-07-03 2011-12-28 北京工业大学 Assembly form and supporting method for in-soil assembled plastic pipes
CN104196546B (en) * 2014-08-06 2016-04-06 山东大学 A kind of constructing tunnel process interrupt layer zone of fracture Treatment for collapse method
CN105114105B (en) * 2015-09-18 2016-06-29 南京联众建设工程技术有限公司 Steel-concrete combined type tunnel-liner support structure and making thereof and construction method

Also Published As

Publication number Publication date
CN105403427A (en) 2016-03-16

Similar Documents

Publication Publication Date Title
CN105403427B (en) The tunnel model supporting construction and installation method and production method of 3D printing
CN204152521U (en) A kind of tunnel supporting and protection structure
CN203129026U (en) Reinforced concrete arch bridge reinforced structure
CN105863734A (en) Device for simulating and monitoring existing tunnel during excavation of double-track tunnel
CN105951608A (en) Pushing construction method for corrugated steel web prestressed concrete combination beam
CN203362169U (en) Attitude adjusting device of miniature shield machine
CN103938663A (en) Correction device of inclined power transmission tower made of signal-splicing steel angle principal material
CN204420343U (en) Large diameter wound pipe
CN207600836U (en) A kind of reinforced bar sleeve grouting jointing molding fixing device
CN203429623U (en) Overwater pile foundation reinforcement cage structure
CN205172038U (en) Interim stair
CN203256756U (en) Pre-reaming flexible pile structure of integral abutment bridge
CN108978496A (en) A kind of bridge intelligence incremental launching construction system and its push construction method
CN205225331U (en) A link device can be dismantled to rotation type for tunnel convergence detects
CN103233480A (en) Pre-reamed hole flexible file structure of integrated abutment and bridge and construction method thereof
CN102953684A (en) Drill rod with ream bit
CN205296592U (en) Stride across antitorque muscle connecting device of shaped steel concrete beam
CN105114089B (en) Shield formula TBM originates split type reaction frame in hole
CN207240917U (en) 57 Series Blade web auxiliary flange forming frocks
CN109518555A (en) A kind of karst area continuous reinforced concrete pavement crossing method
CN206034321U (en) Outdoor sign
CN207564659U (en) Side form embeds tensioning box and die side mode structure in a kind of prefabricated pipe gallery
CN107476200A (en) A kind of full framing dislocation set takes structure and method
CN207363116U (en) A kind of bent cap skeleton reinforcing steel bar location structure
CN209040500U (en) A kind of half pillar type column of stability under loading

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant