CN105375524A - 一种风火打捆直流送出送端电网运行控制方法 - Google Patents
一种风火打捆直流送出送端电网运行控制方法 Download PDFInfo
- Publication number
- CN105375524A CN105375524A CN201510889975.9A CN201510889975A CN105375524A CN 105375524 A CN105375524 A CN 105375524A CN 201510889975 A CN201510889975 A CN 201510889975A CN 105375524 A CN105375524 A CN 105375524A
- Authority
- CN
- China
- Prior art keywords
- wind
- voltage
- skipping
- power
- near region
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/76—Power conversion electric or electronic aspects
Landscapes
- Control Of Eletrric Generators (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
本发明涉及提供一种风火打捆直流送出送端电网运行控制方法,包括步骤1建立基础方式;步骤2考察近区风电场暂态压升水平;步骤3:当暂态压升越限,转步骤4,否则转步骤11;步骤4:当送端电网近区增开调相机,转步骤5,否则转步骤6;步骤5:当增强换流站近区电压控制能力,转步骤2;步骤6:当送端电网近区增开常规电源机组,转步骤7,否则转步骤8;步骤7:当增强换流站近区电压控制能力,转步骤2;步骤8:当暂态过程中风电场近区低电压穿越,转步骤10,否则转步骤9;步骤9:降低直流输送功率,转步骤2;步骤10:分批次停运暂态过程进入低穿状态风电场机组,转步骤2;步骤11:满足风电场稳定运行约束,结束。
Description
技术领域
本发明涉及电网运行控制领域,更具体涉及一种风火打捆直流送出送端电网运行控制方法。
背景技术
大力发展可再生新能源是我国面临能源紧张与环境恶化双重压力的必然选择。受限于自然资源与负荷分布,我国新能源发展主要采取大规模集中开发、高电压等级远距离送电的方式,通过直流系统采用风火打捆方式远距离送出是我国电力发展的必要手段之一。
受限于直流系统自身运行特性,在直流换相失败发生的瞬间,受端直流电压跌落,送端母线电压基本保持不变,直流电流大幅升高,导致送端换流变漏抗无功损耗增加,拉低近区母线电压;之后直流控制系统动作,拉大送端整流侧触发角以及VDCL(低压限流环节)等动作,直流电流下降(通常会降至零),直流输送功率归零,送端换流站由无功不足转为无功盈余。
对于风电机组而言,根据风电场接入电力系统技术规定,风电场应具备一定的低电压穿越能力,但对于高电压耐受能力规定较为简单,仅要求机组机端电压低于1.1p.u时可保持连续运行,对超过0.1p.u的情况并未作出进一步的规定,即允许风电机组在机端电压超过1.1p.u情况下无延时脱网。因此,对于直流送端近区的风电机组而言,直流换相失败的低电压阶段通常来说不会使得风电机组脱网,但过电压阶段使得风电机组脱网风险的比较大。
进一步分析直流换相失败暂态过程与风电场脱网的耦合关系。在直流换相失败暂态过程中,近区母线电压波动过程为先大幅跌落,之后再大幅升高。在电压大幅跌落情况下,则近区风电机组有可能进入低电压穿越模式,而双馈风电机组一旦进入低电压穿越模式,通常伴随CROWBAR电路动作,由双馈风电机组转为异步机组,有功出力大幅降低并从系统吸收无功功率,导致近区电压进一步跌落,形成正反馈过程,可能扩大换相失败造成风电进入低穿状态的范围;而在电压恢复正常水平后,风电退出低穿状态,不再从系统吸收无功功率,但有功功率并不能快速恢复至事故前水平,因此近区呈现轻潮流状态,使得电压水平进一步升高,同样形成正反馈过程,可能扩大换相失败造成风电机组过电压脱网的风险和范围。
根据以上分析可以看出,直流送端近区换相失败造成风电脱网与两个正反馈过程密切相关,在直流送端电网运行控制中需截断正反馈过程,避免风电机组因换相失败而发生大规模脱网事故。故,需提出一种风火打捆直流送出送端电网运行控制方法以克服上述问题。
发明内容
本发明的目的是提供一种风火打捆直流送出送端电网运行控制方法,在确保风火打捆直流送出送端电网风电基地不因直流换相失败电压波动而发生连锁脱网的同时尽可能提高了直流输电功率。
为实现上述目的,本发明采用以下技术方案:一种风火打捆直流送出送端电网运行控制方法,包括:
步骤1:根据电网运行方式,确定交流系统运行方式,直流额定输电功率,风电场高电压耐受能力;
步骤2:计算直流换相失败扰动,查看近区风电场暂态压升水平;
步骤3:判断近区风电场暂态压升是否越限,若越线则转入步骤4,否则转入步骤11;
步骤4:若送端电网近区存在增开调相机,则增开调相机且转入步骤5,否则转入步骤6;
步骤5:增开近区调相机,以增强换流站近区电压控制能力,转入步骤2;
步骤6:当送端电网近区存在增开电源机组,增开电源机组且转入步骤7,否则转入步骤8;
步骤7:增开近区电源机组,以增强换流站近区电压控制能力,转入步骤2;
步骤8:判断暂态过程中风电场是否存在近区低电压穿越状态,若是存在则转入步骤10,否则转入步骤9;
步骤9:降低直流输送功率,转入步骤2
步骤10:按照距换流站电气距离,分批次停运暂态过程进入低穿状态风电场机组,转入步骤2
步骤11:此时,直流换相失败扰动暂态电压波动满足风电场稳定运行约束。
步骤2中,通过仿真计算直流换相失败扰动,扰动前稳态运行风电机组机端电压为Unorm,仿真曲线显示的暂态过程机组机端电压峰值为Upeak,暂态压升ΔU=Upeak-Unorm。
根据电网公司风电并网检测试验暂态压升耐受能力,确定暂态压升ΔU是否越限;未取得并网检测试验暂态压升耐受能力的,按照按照ΔU<0.1p.u判定是否越限。
通过仿真软件判断步骤8中暂态过程中风电场是否存在近区低电压穿越状态。
步骤10中根据停运暂态过程进入低穿状态风电场机组的数量,将同一距换流站电气距离的风电机组在同一批次进行停运。
和最接近的现有技术比,本发明提供技术方案具有以下优异效果
1、本发明技术方案为大力发展可再生新能源提供了良好的基础;
2、本发明技术方案充分考虑了直流换相失败过程中近区电网电压先低后高的暂态过程影响,通过协调送端电网常规电源开机方式、直流送电功率和风电基地运行方式,截断造成风电机组联锁脱网的低电压正反馈和高电压正反馈过程;
3、本发明技术方案提高新能源送电运行的安全性;
4、本发明技术方案减小事故的发生,更方便且稳定的为各类人群提供电能。
附图说明
图1为本发明实施例方法流程图。
具体实施方式
下面结合实施例对发明作进一步的详细说明。
实施例1:
本例的发明提供一种风火打捆直流送出送端电网运行控制方法,包括如图1所示:
步骤1:根据电网运行方式,确定交流系统运行方式,直流额定输电功率,风电场高电压耐受能力;,建立基础方式;
步骤2:计算直流换相失败扰动,查看近区风电场暂态压升水平;
步骤3:判断近区风电场暂态压升是否越限,若越线则转入步骤4,否则转入步骤11;
步骤4:若送端电网近区存在增开调相机,则增开调相机且转入步骤5,否则转入步骤6;
步骤5:增开近区调相机,以增强换流站近区电压控制能力,转入步骤2;
步骤6:当送端电网近区存在增开电源机组,增开电源机组且转入步骤7,否则转入步骤8;
步骤7:增开近区电源机组,以增强换流站近区电压控制能力,转入步骤2;
步骤8:判断暂态过程中风电场是否存在近区低电压穿越状态,若是存在则转入步骤10,否则转入步骤9;
步骤9:降低直流输送功率Pd,降低后的直流输送功率Pd’=Pd-ΔP,转入步骤2
步骤10:按照距换流站电气距离,分批次停运暂态过程进入低穿状态风电场机组,转入步骤2
步骤11:此时,直流换相失败扰动暂态电压波动满足风电场稳定运行约束。
步骤2中,通过仿真计算直流换相失败扰动,扰动前稳态运行风电机组机端电压为Unorm,仿真曲线显示的暂态过程机组机端电压峰值为Upeak,暂态压升ΔU=Upeak-Unorm。
根据电网公司风电并网检测试验暂态压升耐受能力,确定暂态压升ΔU是否越限;未取得并网检测试验暂态压升耐受能力的,按照按照ΔU<0.1p.u判定是否越限。
通过仿真软件判断步骤8中暂态过程中风电场是否存在近区低电压穿越状态。
步骤10中根据停运暂态过程进入低穿状态风电场机组的数量,将同一距换流站电气距离的风电机组在同一批次进行停运。
本发明提供的考虑直流换相失败电压波动的风火打捆直流送出送端电网运行方法,充分考虑了直流换相失败过程中近区电网电压先低后高的暂态过程影响,通过协调送端电网常规电源开机方式、直流送电功率和风电基地运行方式,截断造成风电机组联锁脱网的低电压正反馈和高电压正反馈过程,在确保风火打捆直流送出送端电网风电基地不因直流换相失败电压波动而发生连锁脱网的同时尽可能提高了直流输电功率。
最后应当说明的是:以上实施例仅用以说明本发明的技术方案而非对其限制,所属领域的普通技术人员尽管参照上述实施例应当理解:依然可以对本发明的具体实施方式进行修改或者等同替换,这些未脱离本发明精神和范围的任何修改或者等同替换,均在申请待批的本发明的权利要求保护范围之内。
Claims (5)
1.一种风火打捆直流送出送端电网运行控制方法,其特征在于:包括:
步骤1:根据电网运行方式,确定交流系统运行方式,直流额定输电功率,风电场高电压耐受能力;
步骤2:计算直流换相失败扰动,查看近区风电场暂态压升水平;
步骤3:判断近区风电场暂态压升是否越限,若越线则转入步骤4,否则转入步骤11;
步骤4:若送端电网近区存在增开调相机,则增开调相机且转入步骤5,否则转入步骤6;
步骤5:增开近区调相机,以增强换流站近区电压控制能力,转入步骤2;
步骤6:当送端电网近区存在增开电源机组,增开电源机组且转入步骤7,否则转入步骤8;
步骤7:增开近区电源机组,以增强换流站近区电压控制能力,转入步骤2;
步骤8:判断暂态过程中风电场是否存在近区低电压穿越状态,若是存在则转入步骤10,否则转入步骤9;
步骤9:降低直流输送功率,转入步骤2
步骤10:按照距换流站电气距离,分批次停运暂态过程进入低穿状态风电场机组,转入步骤2
步骤11:此时,直流换相失败扰动暂态电压波动满足风电场稳定运行约束。
2.如权利要求1所述的一种风火打捆直流送出送端电网运行控制方法,其特征在于:步骤2中,通过仿真计算直流换相失败扰动,扰动前稳态运行风电机组机端电压为Unorm,仿真曲线显示的暂态过程机组机端电压峰值为Upeak,暂态压升ΔU=Upeak-Unorm。
3.如权利要求2所述的一种风火打捆直流送出送端电网运行控制方法,其特征在于:根据电网公司风电并网检测试验暂态压升耐受能力,确定暂态压升ΔU是否越限;未取得并网检测试验暂态压升耐受能力的,按照按照ΔU<0.1p.u判定是否越限。
4.如权利要求1所述的一种风火打捆直流送出送端电网运行控制方法,其特征在于:通过仿真软件判断步骤8中暂态过程中风电场是否存在近区低电压穿越状态。
5.如权利要求1所述的一种风火打捆直流送出送端电网运行控制方法,其特征在于:步骤10中根据停运暂态过程进入低穿状态风电场机组的数量,将同一距换流站电气距离的风电机组在同一批次进行停运。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510889975.9A CN105375524B (zh) | 2015-12-07 | 2015-12-07 | 一种风火打捆直流送出送端电网运行控制方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510889975.9A CN105375524B (zh) | 2015-12-07 | 2015-12-07 | 一种风火打捆直流送出送端电网运行控制方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105375524A true CN105375524A (zh) | 2016-03-02 |
CN105375524B CN105375524B (zh) | 2019-05-14 |
Family
ID=55377440
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510889975.9A Active CN105375524B (zh) | 2015-12-07 | 2015-12-07 | 一种风火打捆直流送出送端电网运行控制方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105375524B (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106329579A (zh) * | 2016-09-05 | 2017-01-11 | 国家电网公司 | 一种基于直流传输的风火电打捆发输电系统优化规划方法 |
CN108173285A (zh) * | 2018-01-12 | 2018-06-15 | 福州大学 | 风火打捆外送电线路截面和火电装机容量联合优化方法 |
CN109950913A (zh) * | 2019-04-03 | 2019-06-28 | 国电南瑞科技股份有限公司 | 一种调相机紧急控制方法及其系统 |
CN110854871A (zh) * | 2019-11-20 | 2020-02-28 | 长沙凯泽工程设计有限公司 | 一种高比例新能源电网暂态电压稳定优化控制方法 |
CN111030164A (zh) * | 2019-11-22 | 2020-04-17 | 国网青海省电力公司经济技术研究院 | 一种基于光热确定电网开机方式的方法及系统 |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103746404A (zh) * | 2014-01-24 | 2014-04-23 | 国家电网公司 | 一种风光火打捆直流外送系统稳定性评价方法 |
-
2015
- 2015-12-07 CN CN201510889975.9A patent/CN105375524B/zh active Active
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103746404A (zh) * | 2014-01-24 | 2014-04-23 | 国家电网公司 | 一种风光火打捆直流外送系统稳定性评价方法 |
Non-Patent Citations (2)
Title |
---|
屠竞哲等: "风火打捆直流外送系统直流故障引发风机脱网的问题研究", 《电网技术》 * |
罗煦之等: "计及暂态过电压约束的直流闭锁安控与极控协调控制研究", 《电网技术》 * |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106329579A (zh) * | 2016-09-05 | 2017-01-11 | 国家电网公司 | 一种基于直流传输的风火电打捆发输电系统优化规划方法 |
CN108173285A (zh) * | 2018-01-12 | 2018-06-15 | 福州大学 | 风火打捆外送电线路截面和火电装机容量联合优化方法 |
CN108173285B (zh) * | 2018-01-12 | 2021-09-28 | 福州大学 | 风火打捆外送电线路截面和火电装机容量联合优化方法 |
CN109950913A (zh) * | 2019-04-03 | 2019-06-28 | 国电南瑞科技股份有限公司 | 一种调相机紧急控制方法及其系统 |
CN110854871A (zh) * | 2019-11-20 | 2020-02-28 | 长沙凯泽工程设计有限公司 | 一种高比例新能源电网暂态电压稳定优化控制方法 |
CN110854871B (zh) * | 2019-11-20 | 2021-04-27 | 广东颢能能源科技有限公司 | 一种高比例新能源电网暂态电压稳定优化控制方法 |
CN111030164A (zh) * | 2019-11-22 | 2020-04-17 | 国网青海省电力公司经济技术研究院 | 一种基于光热确定电网开机方式的方法及系统 |
CN111030164B (zh) * | 2019-11-22 | 2023-03-24 | 国网青海省电力公司经济技术研究院 | 一种基于光热确定电网开机方式的方法及系统 |
Also Published As
Publication number | Publication date |
---|---|
CN105375524B (zh) | 2019-05-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Zhou et al. | Connecting wind power plant with weak grid-challenges and solutions | |
Qiao et al. | Grid connection requirements and solutions for DFIG wind turbines | |
CN102822508B (zh) | 采用微分极控制算法的风力涡轮机控制器 | |
CN109347144B (zh) | 一种风电柔性直流送出系统的低电压穿越方法 | |
Alharbi et al. | Application of UPFC to improve the LVRT capability of wind turbine generator | |
CN105375524A (zh) | 一种风火打捆直流送出送端电网运行控制方法 | |
Gomis-Bellmunt et al. | Maximum generation power evaluation of variable frequency offshore wind farms when connected to a single power converter | |
CN107546763B (zh) | 不同调压策略下配电网中光伏发电最大接纳能力计算方法 | |
CN106856333B (zh) | 一种风光火打捆外送系统调峰容量分配确定方法 | |
CN102355009B (zh) | 利用双馈发电机实现风电机组高电压穿越的方法及其系统 | |
US11394204B2 (en) | Enhanced multi voltage dip ride through for renewable energy power plant with battery storage system | |
CN102361324A (zh) | 双馈风电机组无功支撑的机端电压调节方法及其系统 | |
Triggianese et al. | Ancillary services performed by distributed generation in grid integration | |
Devaraj et al. | Impact of wind turbine systems on power system voltage stability | |
CN103138277A (zh) | 一种风电场无功补偿控制方法 | |
Ouyang et al. | An improved control method of fault ride-through for DPMWT-based wind farm considering coupling effect of HVDC transmission system | |
Nawir et al. | Voltage stability analysis and control of wind farms connected to weak grids | |
CN107069797A (zh) | 一种含双馈型风力发电机的分散式风电场并网方法 | |
Prompinit et al. | Ramp rate consideration of a BESS using active power control for PV generation | |
Kuehn | Control and stability of power inverters feeding renewable power to weak AC grids with no or low mechanical inertia | |
CN104393622A (zh) | 一种特高压交直流输电系统暂态稳定控制系统及方法 | |
Luo et al. | Online emergency control and corrective control coordination strategy for UHVDC blocking faults | |
Li et al. | A low voltage ride-through strategy for grid-connected PV converters based on variable power point tracking method | |
Shahdadi et al. | Analyzing Impacts of FACTS devices in dealing with short-term and long-term wind turbine faults | |
CN106021673A (zh) | 一种基于电网在线仿真的直流功率支援预决策方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |