CN105257296A - Working face through-cut tunneling construction once-tunneling process - Google Patents

Working face through-cut tunneling construction once-tunneling process Download PDF

Info

Publication number
CN105257296A
CN105257296A CN201510643537.4A CN201510643537A CN105257296A CN 105257296 A CN105257296 A CN 105257296A CN 201510643537 A CN201510643537 A CN 201510643537A CN 105257296 A CN105257296 A CN 105257296A
Authority
CN
China
Prior art keywords
cut
working face
construction
tunneling
coal mining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510643537.4A
Other languages
Chinese (zh)
Inventor
宋小平
王静
李丰廷
程元
张向阳
李建伟
白春娥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Jincheng Anthracite Mining Group Co Ltd
Original Assignee
Shanxi Jincheng Anthracite Mining Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Jincheng Anthracite Mining Group Co Ltd filed Critical Shanxi Jincheng Anthracite Mining Group Co Ltd
Priority to CN201510643537.4A priority Critical patent/CN105257296A/en
Publication of CN105257296A publication Critical patent/CN105257296A/en
Pending legal-status Critical Current

Links

Abstract

The invention relates to a coal mining process, in particular to a working face through-cut tunneling construction once-tunneling process, which solves the problems of complicated operation, low efficiency and the like of the existing working face through-cut process. The rectangular cross section tunneling is used for coal mining working face through-cut; a left upper of a coal mining working face is provided with an opening, so that an anchor rod and a steel belt are used for combined supporting, and an anchor rope is used for reinforced supporting; the coal mining working face through-cut construction is performed from the left upper opening of the coal mining working face in a direction towards a left roadway; and a circulation and alternation way is used for construction to complete the whole coal mining working face through-cut engineering. The original twice roadway tunneling through-cut forming mode is merged into the once-tunneling mode for construction; the technical flow process is simplified; the problem of gas management in construction is solved; the process that a roadheader needs to be reversed to a through-cut opening during the roadway tunneling for the second time in the prior art is reduced; and the time required by construction through-cut is greatly reduced.

Description

Working face open-off cut eye tunneling construction simultaneous drifting technique
Technical field
The present invention relates to a kind of coal winning technology, be specially a kind of working face open-off cut eye tunneling construction simultaneous drifting technique.
Background technology
The incisor canal of existing coal-face needs twice one-tenth lane, and distance effective distinguished and admirable instability in air channel when being faced with second time digging laneway in work progress, return air gas probe is difficult to management and controls easy overload alarm, and there is the long distance of fully-mechanized digging machine and fall the construction of machine, repeat the problems such as installation also with various auxiliary equipment.
As schematically shown in Figure 1, with Gushuyuan ore deposit 15# coal 154305 working face open-off cut eye construction technology in detail former construction method is described in detail: 1 site environment and technical condition: 154305 working face open-off cut eyes adopt rectangular cross section, by 1543051 left side openings, adopt anchor pole, steel band combined supporting, and carry out reinforce support with anchor cable, cut an overall length 180.660 meters (in in).2 construction operation programs: to be constructed to 1543052 directions, lane 154305 working face open-off cut eyes by the 1543051 left side in lane openings, first adopt the construction of 4.7m × 2.6m section to cut eye and lead cave 180.660 meters to 1523052 lanes side (array pitch 1.5m, advance of working cycle 3m), afterwards fully-mechanized digging machine is caused incisal guide opening part, adopt section hair wide × hair is high=2.5 × 2.6(rice) to carry out cutting eye brush large, 154305 working face open-off cut eye engineerings of having constructed.
Summary of the invention
The present invention cuts a problem such as complicated operation, inefficiency for technique existence to solve work on hand face, provides a kind of working face open-off cut eye tunneling construction simultaneous drifting technique.
Technical scheme of the present invention is, a kind of working face open-off cut eye tunneling construction simultaneous drifting technique, coal-face is cut eye and is adopted rectangular cross section driving, by coal-face left side opening, adopt anchor pole, steel band combined supporting, and carry out reinforce support with anchor cable, cut eye by left side opening direction, the lane construction to the right coal-face of coal-face, adopt circulation mutually to hocket; First adopt the section of a kind of wide a × high b to construct one to circulate, progress is c; , then adopt the large c of section brush of wide c × high b, form one wide (a+c), high b, progress is c cuts a unit, then adopt the method construction that mutually hockets to complete whole coal-face and cut an engineering.
The present invention and prior art compare: adopt former method to lead after cave excavates, forced air duct air outlet is received and is not more than 8m place to apart from leading cave work plane, cut eye brush large time because forced air duct air outlet is apart from cutting a brush large working area air channel distance, the gas that when brushing large, work plane corner is gushed out not easily dilutable, easy generation gas exceeding limit warning accident, and lead after cave excavates, fully-mechanized digging machine need be caused cave mouth, add dismounting to cut eye and lead cave track, the technique of falling machine; Adopt the method for the invention that twice original digging laneway is formed the mode of cutting eye, the mode merging into simultaneous drifting is constructed, simplify technological process, and solve a difficult problem for gas administration in construction, fully-mechanized digging machine need be fallen machine to the technique of cutting eye mouth when decreasing original second time digging laneway, and avoid to tear open and again follow closely, greatly accelerate the time of constructing and cutting required for eye.
Work of the present invention, adopts to complete from circulation propelling when cutting opening driving and wholely cuts an engineering, the mode of simultaneous drifting.Twice original digging laneway is formed the mode of cutting eye, the mode merging into simultaneous drifting is constructed, simplify technological process, and solve a difficult problem for gas administration in construction, fully-mechanized digging machine need be fallen machine to the technique of cutting eye mouth when decreasing original second time digging laneway, greatly accelerate the time of constructing and cutting required for eye.
Accompanying drawing explanation
Fig. 1 is existing construction technology figure; Fig. 2 is artwork of the present invention.
Detailed description of the invention
As schematically shown in Figure 2, with Gushuyuan ore deposit 15# coal 154306 working face open-off cut eye construction technology in detail new construction method is described in detail:
1 site environment and technical condition: 154306 working face open-off cut eyes adopt rectangular cross sections, by 1543061 left side openings, adopt anchor pole, steel band combined supporting, and carry out reinforce support with anchor cable, cuts an overall length 180.660 meters (in in).
2 construction operation programs:
To be constructed to 1543062 directions, lane 154306 working face open-off cut eyes by the 1543061 left side in lane openings, adopt circulation mutually to hocket; First adopt wide 4.7m × high 2.6m section to construct one circulate (array pitch 1.5m, advance of working cycle 3m), adopt afterwards section wide × height=2.5 × 2.6(rice) brush large 3m, then the construction that mutually hockets of employing the method completes 154306 working face open-off cut eye engineerings.

Claims (1)

1. a working face open-off cut eye tunneling construction simultaneous drifting technique, it is characterized in that coal-face is cut eye and adopted rectangular cross section driving, by coal-face left side opening, adopt anchor pole, steel band combined supporting, and carry out reinforce support with anchor cable, cut eye by left side opening direction, the lane construction to the right coal-face of coal-face, adopt circulation mutually to hocket; First adopt the section of a kind of wide a × high b to construct one to circulate, progress is c; Then adopt the large c of section brush of wide c × high b, form one wide (a+c), high b, progress is c cuts a unit, then adopt the method construction that mutually hockets to complete whole coal-face and cut an engineering.
CN201510643537.4A 2015-10-08 2015-10-08 Working face through-cut tunneling construction once-tunneling process Pending CN105257296A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510643537.4A CN105257296A (en) 2015-10-08 2015-10-08 Working face through-cut tunneling construction once-tunneling process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510643537.4A CN105257296A (en) 2015-10-08 2015-10-08 Working face through-cut tunneling construction once-tunneling process

Publications (1)

Publication Number Publication Date
CN105257296A true CN105257296A (en) 2016-01-20

Family

ID=55097186

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510643537.4A Pending CN105257296A (en) 2015-10-08 2015-10-08 Working face through-cut tunneling construction once-tunneling process

Country Status (1)

Country Link
CN (1) CN105257296A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605493A (en) * 2017-10-31 2018-01-19 淮矿西部煤矿投资管理有限公司 A kind of comprehensive pick construction system and method
CN110748352A (en) * 2019-10-17 2020-02-04 山西晋城无烟煤矿业集团有限责任公司 Construction method suitable for rapid hole cutting and enlarging

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102102526A (en) * 2010-12-30 2011-06-22 枣庄矿业集团新安煤业有限公司 Coal mine roadway supporting method and working face hole-cutting anchor mesh ladder and individual supporting device used by same
CN102505942A (en) * 2011-11-11 2012-06-20 山西晋城无烟煤矿业集团有限责任公司 Safe and fast driving method for large-section open-off cut time-by-time tunneling
CN103670426A (en) * 2013-12-31 2014-03-26 四川川煤华荣能源股份有限公司花山煤矿 Large-inclination-angle and large-section roadway construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102102526A (en) * 2010-12-30 2011-06-22 枣庄矿业集团新安煤业有限公司 Coal mine roadway supporting method and working face hole-cutting anchor mesh ladder and individual supporting device used by same
CN102505942A (en) * 2011-11-11 2012-06-20 山西晋城无烟煤矿业集团有限责任公司 Safe and fast driving method for large-section open-off cut time-by-time tunneling
CN103670426A (en) * 2013-12-31 2014-03-26 四川川煤华荣能源股份有限公司花山煤矿 Large-inclination-angle and large-section roadway construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
武立文: "大采高特大断面开切眼一次成巷技术", 《煤矿开采》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605493A (en) * 2017-10-31 2018-01-19 淮矿西部煤矿投资管理有限公司 A kind of comprehensive pick construction system and method
CN110748352A (en) * 2019-10-17 2020-02-04 山西晋城无烟煤矿业集团有限责任公司 Construction method suitable for rapid hole cutting and enlarging

Similar Documents

Publication Publication Date Title
AU2017101825A4 (en) Construction method of strong karst water-rich urban shallow-buried tunnel cantilever boring machine
CN103291308B (en) For boom-type roadheader and the method for tunnel construction of constructing tunnel
CN103061771B (en) Second mining mine fully mechanized coal face cuts eye driving and supporting method thereof
CN108571325A (en) A kind of shape of a hoof tunneling boring rock tunnel development machine and its construction method
CN105134266A (en) Support method for fully-mechanized coal mining face full-negative-pressure withdrawing channel
CN106968671B (en) The filling of underground coal mine coal working face return channel withdraws method
CN108150165B (en) Cantilever type longitudinal shaft digging and anchoring machine comprising hydraulic control loading mechanism
WO2015007133A1 (en) Temporary supporting and permanent supporting parallel operation excavating technology for crawler-type hydraulic combination bracket and equipment using same
CN105257296A (en) Working face through-cut tunneling construction once-tunneling process
CN104912559A (en) Rapid construction method for long and large double-multiple arch tunnel
CN102536229A (en) Tunneling, protecting and anchoring parallel work system and construction technology
CN102418525A (en) Soft coal seam long-wall high-mining-height comprehensive mechanized coal mining end mining method
CN207647510U (en) A kind of pick of coal working face, dress, shield change system
CN107654232B (en) The moat ditch collection mine mining methods of inclined orebody
CN104389605B (en) A kind of coal-face intensive steel cord shielding withdraws method
CN104329117B (en) Installation method of comprehensive mechanized filling, coal mining and open-off cutting equipment
WO2019109535A1 (en) Clean and efficient coal mining method
CN103410550A (en) Method for constructing underground air crossing of coal mine
CN108645298A (en) The micro- blasting construction method that shakes of the leading pilot tunnel of existing tunnel is closed at short skylight point interval
CN103711488A (en) Traction mining method for preventing and disposing leakages or cavities
CN108952722B (en) Sectional open-field method suitable for mining stable and thick ore body of gently inclined surrounding rock
CN105178969A (en) Method for one-time lane forming during working surface hole-cutting and tunneling construction
CN105927237A (en) Chain tool device for undermining-method metro station assembling construction
CN208168883U (en) A kind of shape of a hoof tunneling boring rock tunnel development machine
CN106761791B (en) Tunnel boring machine and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160120

RJ01 Rejection of invention patent application after publication