CN105227402B - A kind of integrated test method of the more specification communications of intelligent substation - Google Patents

A kind of integrated test method of the more specification communications of intelligent substation Download PDF

Info

Publication number
CN105227402B
CN105227402B CN201510637939.3A CN201510637939A CN105227402B CN 105227402 B CN105227402 B CN 105227402B CN 201510637939 A CN201510637939 A CN 201510637939A CN 105227402 B CN105227402 B CN 105227402B
Authority
CN
China
Prior art keywords
test
real
communication
equipment
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510637939.3A
Other languages
Chinese (zh)
Other versions
CN105227402A (en
Inventor
唐志军
林国栋
邓超平
翟博龙
陈锦山
申仲涛
李冰
侯鹏
刘润花
马晓光
陈翔宇
曹楠
王冬青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Nari Group Company Beijing Monitoring Technology Center
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Fujian Electric Power Co Ltd
State Grid Fujian Electric Power Co Ltd
Original Assignee
Nanjing Nari Group Company Beijing Monitoring Technology Center
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Fujian Electric Power Co Ltd
State Grid Fujian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Nari Group Company Beijing Monitoring Technology Center, State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Fujian Electric Power Co Ltd, State Grid Fujian Electric Power Co Ltd filed Critical Nanjing Nari Group Company Beijing Monitoring Technology Center
Priority to CN201510637939.3A priority Critical patent/CN105227402B/en
Publication of CN105227402A publication Critical patent/CN105227402A/en
Application granted granted Critical
Publication of CN105227402B publication Critical patent/CN105227402B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention relates to a kind of integrated test methods of the more specification communications of intelligent substation.There is provided includes protocol convert template configuration module, interface display module, key parameter configuration module, test run module, data processing module and destination file memory module, and each intermodule realizes the interaction of information by real-time database and template library.Test method according to the present invention, system can complete the integrated test of communication of each equipment in station, can synchronize the collaborative work situation for detecting each communication protocol.

Description

A kind of integrated test method of the more specification communications of intelligent substation
Technical field
The invention belongs to power system automatic field, it is related to a kind of the integrated of more specifications communications of intelligent substation Test method.
Background technique
In intelligent substation, communication directly participates in the acquisition of field data and the control of primary equipment, security reliability Directly affect the safety and stability of system.Intelligent station has that a variety of communication protocols are parallel at present, to mitigate field adjustable work It measures, needs to detect the communication protocol of plurality of devices.Detection mode can be divided into two classes at present, be built with physical device It detects environment or actual environment is simulated by simulation software and realize.Realize and detect have and realize simply, be easy to using simulation software Simulate various kinds of equipment, can standard operation, testing result realize standardization, high degree of automation the advantages that, in intelligent substation Important function has been played in debugging and detection.Existing intelligent substation communication inspection software exists for various specifications, all kinds of The equipment even test software of types of functionality not yet realize the integrated test of a variety of specifications.
Summary of the invention
The purpose of the present invention is to provide the integrated test of communication that one kind can complete each equipment in station, Ke Yitong Step detects the integrated test method of the more specification communications of intelligent substation of the collaborative work situation of each communication protocol.
To achieve the above object, the technical scheme is that a kind of more specifications communication of intelligent substation it is integrated Change test method, include the following steps,
Step S1: protocol convert template configuration module: providing test template design interface, is the different tests of different specifications Item setup includes testing process, test item and test parameter;
Step S2: interface display module: progress human-computer interaction management, built-in key parameter set interface, test process Monitor the displaying interface of control interface and result;
Step S3: key parameter configuration module: by user inputted from the interface of step S2 include test parameter, selection The demand data of specification is saved in real-time database;
Step S4: test run module: it is responsible for extracting preset parameter from real-time database, according to the test mould of systemic presupposition Plate configures testing process, executes actual test function, realize the monitoring of test process, the data of test process is stored in real Shi Ku completes test operation;
Step S5: data processing module: for tracking the data for reflecting test process in real-time database, the reality of processing step S4 The various data and signal that border test phase generates, generate data result, are stored in real-time database;
Step S6: destination file memory module: for storing test result, the test that step S5 is stored in real-time database As a result various file formats are converted to be exported.
In an embodiment of the present invention, for the communication test of 110kV intelligent substation, the intelligent substation included Journey layer equipment, bay device and station level equipment, and the communications applications IEC61850 specification between three-layer equipment, telecontrol equipment are answered It is communicated with IEC61850 specification with power transformation station equipment, and uses IEC60870-5-101 specification with distant place regulation center to center communications, Including following test process:
(1) station level equipment issues test packet in imitating substation, including remote control, remote regulating, clock synchronization, signal return, fixed The simulation test message of value modification and definite value switching, manual recording, the communication response of test interval layer equipment, inspection intervals layer are logical The realization of each corresponding function of letter;
(2) in imitating substation bay device on send infomational message, including telemetering, remote signalling, remote pulse, pressing plate, definite value Area, definite value, operating condition, SOE, event, alarm on send message information, the function of measuring station control layer system is realized, while being detected remote The IEC60870-5-101 specification message response that dynamic equipment issues checks and synchronous compares the logical of station level system and telecontrol system Believe transferring content, checks and send correctness on the communication message of telecontrol equipment;
(3) by telecontrol equipment, the bay device into substation issues test packet at simulation distant place regulation center, including Remote control, remote regulating, clock synchronization, signal return simulation test message, test IEC60870-5-101 specification and IEC61850 specification Convert correctness, the consistency of the communications key parameter of different specifications, according to the communication response of bay device, between inspection The realization of each corresponding function of interlayer communication.
Compared to the prior art, the invention has the following advantages: test method according to the present invention, system can be complete At the integrated test of communication of each equipment in standing, the collaborative work situation for detecting each communication protocol can be synchronized.
Detailed description of the invention
Fig. 1 is the structural block diagram of the integrated test macro of a variety of communication protocols of intelligent substation of the present invention.
Specific embodiment
With reference to the accompanying drawing, technical solution of the present invention is specifically described.
As shown in Figure 1, a kind of integrated test method of the more specification communications of intelligent substation of the present invention, including it is as follows Step,
Step S1: protocol convert template configuration module: providing test template design interface, is the different tests of different specifications Item setup includes testing process, test item and test parameter;
Step S2: interface display module: progress human-computer interaction management, built-in key parameter set interface, test process Monitor the displaying interface of control interface and result;
Step S3: key parameter configuration module: by user inputted from the interface of step S2 include test parameter, selection The demand data of specification is saved in real-time database;
Step S4: test run module: it is responsible for extracting preset parameter from real-time database, according to the test mould of systemic presupposition Plate configures testing process, executes actual test function, realize the monitoring of test process, the data of test process is stored in real Shi Ku completes test operation;
Step S5: data processing module: for tracking the data for reflecting test process in real-time database, the reality of processing step S4 The various data and signal that border test phase generates, generate data result, are stored in real-time database;
Step S6: destination file memory module: for storing test result, the test that step S5 is stored in real-time database As a result various file formats are converted to be exported.
The following are specific embodiments of the present invention, in the present invention, realization software corresponding to integrated test method Including protocol convert template configuration module, interface display module, key parameter configuration module, test run module, data processing Module and destination file memory module, each intermodule realizes the interaction of information by real-time database and template library, such as 1 institute of attached drawing Show.Protocol convert template configuration module provides test template design interface, is that test is arranged in the different test items of different specifications Process, test item, test parameter etc..Interface display module is substantially carried out human-computer interaction management, and boundary is arranged in built-in key parameter Face, the monitoring control interface of test process and the displaying interface of result etc..The function of key parameter configuration is by user from interface The test parameter of input, selection the demand datas such as specification be saved in real-time database.Test run module is responsible for extracting from real-time database Preset parameter configures testing process according to the test template of systemic presupposition, executes actual test function, and realization was tested The data of test process are stored in real-time database, complete test operation by the monitoring of journey.Data processing module is for tracking in real-time database Reflect the data of test process, the various data and signal that the processing actual test stage generates generate data result, are stored in real time Library.Test result in real-time database is converted to various file formats and added by destination file memory module for storing test result With output.
All modules needed for test require to obtain from real-time database or storing data carrys out complete design, therefore in real time The design in library has great importance to the normal operation of test.The survey of each intermediate item of in store each protocol convert in template library Die trial plate, then in store identification of function result, testing attribute configuration parameter, test template data and test extension in real-time database The parameter value etc. of function.
By taking the communication test for 110kV intelligent substation as an example, in the substation illustrated, there are process layers, interval Layer and station level three-layer equipment.Process layer, wall and station level communication between devices application IEC61850 specification.Telecontrol equipment It is communicated using IEC61850 specification with station equipment, uses IEC60870-5-101 specification with distant place regulation center to center communications.
Test method according to the present invention, system can complete to stand in each equipment the integrated test of communication, can be with The synchronous collaborative work situation for detecting each communication protocol.The integration testing function of IEC61850 specification and 101 specifications is arranged in system, The protocol template library of default IEC61850 and 101 specifications, set configurable for test parameter corresponding in each test item Variable is stored in real-time database.In test process, the Various types of data and information in real-time database can be checked, monitor and to test Implementation Process artificially controls.System is directed to test result, according to publication message and intended response, compares each under different communication specification Whether the response contents of equipment are consistent, if correct and response time etc., provide real-time database for multi-angular analysis test result Data, test process and result information.
Test item can be configured by test function.
Such as: the following test packet of station level monitoring system publication in station can be simulated and such as issue remote control, remote regulating, clock synchronization, letter The simulation tests message such as number involution, fixed value modification and definite value switching, manual recording, the communication response of test interval layer equipment, inspection Look into the realization of each corresponding function of wall communication.
Meanwhile also analog bay device on send infomational message, such as the telemetering of dummy spacers layer equipment, remote signalling, distant Message information is sent in arteries and veins, pressing plate, definite value area, definite value, operating condition, SOE, event, alarm etc., the function of measuring station control layer system is real It is existing, while detecting 101 specification message responses of telecontrol equipment sending, it checks and synchronous station level system and the telecontrol system of comparing Communications content, checks and send correctness on the communication message of telecontrol equipment.
By telecontrol equipment, the bay device into station issues following test packet and such as issues remote control, distant at simulation regulation center The simulation tests message such as tune, clock synchronization, signal return tests the conversion correctness of 101 specifications and IEC61850 specification, different specifications Communications key parameter consistency, according to the communication response of bay device, inspection intervals layer communication each correspondence The realization of function.
The above are preferred embodiments of the present invention, all any changes made according to the technical solution of the present invention, and generated function is made When with range without departing from technical solution of the present invention, all belong to the scope of protection of the present invention.

Claims (1)

1. a kind of integrated test method of the more specification communications of intelligent substation, it is characterised in that: include the following steps,
Step S1: protocol convert template configuration module: providing test template design interface, is the different test items of different specifications Setting includes testing process, test item and test parameter;
Step S2: human-computer interaction management, built-in key parameter set interface, the monitoring of test process interface display module: are carried out The displaying interface of control interface and result;
Step S3: key parameter configuration module: the specification including test parameter, selection that user is inputted from the interface of step S2 Demand data be saved in real-time database;
Step S4: test run module: it is responsible for matching from the preset parameter of real-time database extraction according to the test template of systemic presupposition Testing process is set, actual test function is executed, realizes the monitoring of test process, the data of test process are stored in real-time database, Complete test operation;
Step S5: data processing module: for tracking the data for reflecting test process in real-time database, the practical survey of processing step S4 The various data and signal that the examination stage generates, generate data result, are stored in real-time database;
Step S6: destination file memory module: for storing test result, the test result that step S5 is stored in real-time database Various file formats are converted to be exported;
For the communication test of 110kV intelligent substation, the intelligent substation includes process layer devices, bay device and station Control layer equipment, and the communications applications IEC61850 specification between three-layer equipment, telecontrol equipment application IEC61850 specification and substation Interior equipment communication, and IEC60870-5-101 specification, including following test process are used with distant place regulation center to center communications:
(1) station level equipment issues test packet in imitating substation, including remote control, remote regulating, clock synchronization, signal return, definite value are repaired Change and definite value switching, manual recording simulation test message, the communication response of test interval layer equipment, inspection intervals layer communication The realization of each corresponding function;
(2) in imitating substation bay device on send infomational message, including it is telemetering, remote signalling, remote pulse, pressing plate, definite value area, fixed Value, operating condition, SOE, event, alarm on send message information, the function of measuring station control layer system is realized, while detecting telecontrol equipment The IEC60870-5-101 specification message response of sending checks and synchronizes the communications for comparing station level system and telecontrol system Content checks and send correctness on the communication message of telecontrol equipment;
(3) by telecontrol equipment, the bay device into substation issues test packet at simulation distant place regulation center, including be remotely controlled, Remote regulating, clock synchronization, signal return simulation test message, testing the conversion of IEC60870-5-101 specification and IEC61850 specification just True property, the consistency of the communications key parameter of different specifications, according to the communication response of bay device, inspection intervals layer is logical The realization of each corresponding function of letter.
CN201510637939.3A 2015-09-29 2015-09-29 A kind of integrated test method of the more specification communications of intelligent substation Active CN105227402B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510637939.3A CN105227402B (en) 2015-09-29 2015-09-29 A kind of integrated test method of the more specification communications of intelligent substation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510637939.3A CN105227402B (en) 2015-09-29 2015-09-29 A kind of integrated test method of the more specification communications of intelligent substation

Publications (2)

Publication Number Publication Date
CN105227402A CN105227402A (en) 2016-01-06
CN105227402B true CN105227402B (en) 2019-04-26

Family

ID=54996112

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510637939.3A Active CN105227402B (en) 2015-09-29 2015-09-29 A kind of integrated test method of the more specification communications of intelligent substation

Country Status (1)

Country Link
CN (1) CN105227402B (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105656720A (en) * 2016-01-26 2016-06-08 云南电网有限责任公司电力科学研究院 Test method based on IEC60870-5-101 protocol of telecontrol device
CN105827596A (en) * 2016-03-10 2016-08-03 国网福建省电力有限公司泉州供电公司 Communication management system
CN106100932B (en) * 2016-07-01 2019-03-15 国网山东省电力公司博兴县供电公司 A kind of substation data processing system based on data sharing
CN106708742B (en) * 2017-02-20 2020-06-23 许继集团有限公司 Automatic testing method and device for communication protocol module testing framework
CN107203392B (en) * 2017-04-01 2020-07-14 宁波三星医疗电气股份有限公司 Multi-protocol implementation method of small system terminal product
CN107342904B (en) * 2017-08-22 2023-07-14 广东电网有限责任公司电力科学研究院 Data simulation method and device for testing substation control layer equipment of transformer substation
CN107592244A (en) * 2017-10-31 2018-01-16 广东电网有限责任公司电力科学研究院 A kind of judgement no system for realizing unified collocation of exchange of electric power function
CN111193322A (en) * 2020-01-02 2020-05-22 国网北京市电力公司 Dispatching system and method of transformer substation
CN111800624A (en) * 2020-07-01 2020-10-20 浪潮云信息技术股份公司 Integrated testing method for multi-video-protocol communication of intelligent video monitoring platform
CN111949456A (en) * 2020-07-14 2020-11-17 许继集团有限公司 Serial port protocol automatic test system and method based on configuration updating
CN114062886B (en) * 2020-07-30 2023-12-12 合肥本源量子计算科技有限责任公司 Quantum chip testing method, device and system
CN112003378A (en) * 2020-08-31 2020-11-27 广东电网有限责任公司肇庆供电局 Transformer substation message analysis device
CN115514658B (en) * 2022-11-23 2023-03-10 博智安全科技股份有限公司 Simulation construction method and device for industrial control protocol

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103344850A (en) * 2013-06-20 2013-10-09 国家电网公司 System and method of intelligent substation automatic testing based on test formwork technology
CN103926917A (en) * 2014-04-25 2014-07-16 国家电网公司 Intelligent transformer substation master control device testing system and method
CN104052633A (en) * 2014-05-29 2014-09-17 国家电网公司 Integrated testing method for intelligent station 61850 and telecontrol 104 protocol
CN104820635A (en) * 2015-04-07 2015-08-05 南京国电南自电网自动化有限公司 Method of testing robustness of closed loop protocol based on semantic analysis of dynamic script

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2088444A1 (en) * 2008-02-11 2009-08-12 ABB Research Ltd. System level testing for substation automation systems

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103344850A (en) * 2013-06-20 2013-10-09 国家电网公司 System and method of intelligent substation automatic testing based on test formwork technology
CN103926917A (en) * 2014-04-25 2014-07-16 国家电网公司 Intelligent transformer substation master control device testing system and method
CN104052633A (en) * 2014-05-29 2014-09-17 国家电网公司 Integrated testing method for intelligent station 61850 and telecontrol 104 protocol
CN104820635A (en) * 2015-04-07 2015-08-05 南京国电南自电网自动化有限公司 Method of testing robustness of closed loop protocol based on semantic analysis of dynamic script

Also Published As

Publication number Publication date
CN105227402A (en) 2016-01-06

Similar Documents

Publication Publication Date Title
CN105227402B (en) A kind of integrated test method of the more specification communications of intelligent substation
CN109855651B (en) Ground test system and test method for modern aircraft radio communication navigation system
CN103439612B (en) Based on the intelligent substation Auto-Test System of SCD
CN104536436B (en) A kind of Auto-Test System of industrial processes control logic and method
CN110488630B (en) Test system and test method for controlling stability-increasing flight control computer
CN103885438B (en) The Auto-Test System of a kind of transformer station measuring and controlling equipment and method
CN103869190A (en) Real time simulation system-based power distribution terminal automatic closed-loop test platform
CN107257304B (en) Telecontrol point-aligning-free configuration test system
CN102054377A (en) Remote simulation training system for electrical tests of transformer
CN103165014B (en) Monitoring teaching demonstration method and system of internet-of-things-based discrete manufacturing workshop
CN103106565A (en) Power grid information real-time display method and device which are based on geographic information system (GIS) and supervisory control and data acquisition (SCADA)
CN110059402A (en) A kind of intelligent substation method for optimizing configuration based on semantic modeling
CN103676661B (en) Multifunction emulation verifies system and its emulation verification method
CN108108403A (en) Based on bay device Logical Configuration Visualization Platform system and its construction method
CN102968096A (en) Safe error proof verifying method for master station type comprehensive intelligent error proof system
CN105680441A (en) Simulated replacement technique-based simulated point-alignment device
CN102624476A (en) Wireless sensor network time synchronization testing method based on model checking
CN115967169A (en) Test system and method for intelligent distribution transformer terminal
CN102821010A (en) Simulator for protector
CN112181549B (en) System and method for recognizing dynamic perception of power icon of transformer substation monitoring interface
CN104765024A (en) Onboard radar jamming automatic detection system
CN106789290B (en) Data access method and system based on Modbus RTU protocol
CN110611312A (en) On-line simulation system and method for panoramic data of substation bay level
CN203720647U (en) Air data computer testing system
CN206610099U (en) The configurable time synchronization test system in scene

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant