CN105220878A - Movable Scaffold is utilized to carry out combining maintenance storehouse finishing and pipeline construction method of installation - Google Patents

Movable Scaffold is utilized to carry out combining maintenance storehouse finishing and pipeline construction method of installation Download PDF

Info

Publication number
CN105220878A
CN105220878A CN201510518883.XA CN201510518883A CN105220878A CN 105220878 A CN105220878 A CN 105220878A CN 201510518883 A CN201510518883 A CN 201510518883A CN 105220878 A CN105220878 A CN 105220878A
Authority
CN
China
Prior art keywords
scaffold
installation
inspection hole
pipeline
road
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510518883.XA
Other languages
Chinese (zh)
Other versions
CN105220878B (en
Inventor
张磊
霍琨
顾玉峰
吴俊树
薄海
吕翔
李亚林
王渤
谭文博
杨昆昆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
Tianjin Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
Tianjin Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, Tianjin Railway Construction Co Ltd of China Railway Sixth Group Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN201510518883.XA priority Critical patent/CN105220878B/en
Publication of CN105220878A publication Critical patent/CN105220878A/en
Application granted granted Critical
Publication of CN105220878B publication Critical patent/CN105220878B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

One utilizes movable Scaffold to carry out combining maintenance storehouse finishing and pipeline construction method of installation.It is included in built storehouse the construction carrying out first and second inspection hole, road; Around first and second inspection hole, road, carry out indoor banket; Each laying leading track in the backfill of first and second both sides, inspection hole, road, and set up first to fourth scaffold that bottom is provided with roller successively on leading track is cheated outside one end in first and second road inspection, and carry out the installation of ceiling plastering, Puttying, swabbing and various pipeline, light fixture and fire main, electric fixtures at scaffold.All fit up and pipeline installation process until complete in storehouse.The overhead pipelines such as flooring Structural Engineering and ceiling finish engineering, electrical installation project, water supply and sewage work, fire engineering, heating and ventilation engineering and equipment installation project can be formed cross construction successively by the present invention, the interior construction task of specialty separately can be completed rapidly, reduction of erection time greatly, play effect of getting twice the result with half the effort.

Description

Movable Scaffold is utilized to carry out combining maintenance storehouse finishing and pipeline construction method of installation
Technical field
The invention belongs to Subway Facilities construction technique field, particularly relate to one and utilize movable Scaffold to carry out combining maintenance storehouse finishing and pipeline construction method of installation.
Background technology
At present, must arrange and combine maintenance storehouse in subway engineering construction, this storeroom structure form of combining maintenance storehouse mostly is individual layer reinforced concrete frame structure, is provided with many locomotive inspection holes in storehouse, and its effect sails in storehouse for locomotive to carry out maintenance activity.Normal sequence of construction is main body frame slab column construction → infilled wall building construction → indoor inspection hole construction → indoor room heart backfill → ground concrete cushion construction → indoor canopy and wall surfacing → indoor water supply and drainage, heating, ventilation, fire-fighting, electric pipeline and lamp installation → ground surface construction etc. now.A large amount of locomotive inspection holes is there is owing to combining in maintenance storehouse, and check hole all along storehouse longitudinally elongated parallel setting, traditional way is set up the installation that full hall steel pipe scaffold carries out ceiling plastering, Puttying, swabbing and various pipeline, light fixture and fire main, electric fixtures after all checking hole construction again in indoor, if but the duration is very tight, if carry out storehouse interior decoration again after treating all to check hole construction inherently incur loss through delay the construction period
Summary of the invention
In order to solve the problem, one is the object of the present invention is to provide to utilize movable Scaffold to carry out combining maintenance storehouse finishing and pipeline construction method of installation.
In order to achieve the above object, provided by the inventionly movable Scaffold is utilized to carry out combining maintenance storehouse finishing and pipeline construction method of installation comprises the following step carried out in order:
1) in built storehouse, first carry out the construction in first and second inspection hole, road, then carry out the construction that all the other check hole successively;
2) around first and second built inspection hole, road, carry out indoor to banket;
3) each laying leading track in the backfill of first and second both sides, inspection hole, road, and the first scaffold that bottom is provided with roller is set up on leading track is cheated outside one end in first and second road inspection, then on this scaffold, Puttying, the brushing paint operation of ceiling above it is carried out by constructor, after completing, the first scaffold is moved to subsequent work face along leading track, proceed ceiling finish construction, until arrive the other end in first and second inspection hole, road;
4) the crus secunda hand cradle that bottom is provided with roller is set up at the former place of setting up of the first scaffold, then on this scaffold, the electrical install operation of cable conduct, wire through pipe, cable testing bridge, cable laying, light fixture under ceiling above it is carried out by constructor, after completing, crus secunda hand cradle is moved to subsequent work face along leading track, proceed above-mentioned electrical install operation, until arrive the other end in first and second inspection hole, road;
5) the 3rd scaffold that bottom is provided with roller is set up at the former place of setting up of the first scaffold, then on this scaffold, the installation exercise of fire protection pipeline above it is carried out by constructor, after completing, the 3rd scaffold is moved to subsequent work face along leading track, proceed above-mentioned fire protection pipeline installation exercise, until arrive the other end in first and second inspection hole, road;
6) the 4th scaffold that bottom is provided with roller is set up at the former place of setting up of the first scaffold A, then on this scaffold, the installation exercise of caliduct above it is carried out by constructor, after completing, the 4th scaffold is moved to subsequent work face along leading track, proceed above-mentioned caliduct installation exercise, until arrive the other end in first and second inspection hole, road;
7) often complete two road inspections holes construction and after around banketing, repeat step 3) to step 6), all fit up and pipeline installation process until complete in the storehouse in.
The height of the first described scaffold is 13.86m, and length is 10.5m, and width is 12.6m.
The height of described crus secunda hand cradle is 13.86m, and length is 6m, and width is 12.6m.
The height of the 3rd described scaffold is 11.86m, and length is 4.5m, and width is 12.6m.
The height of the 4th described scaffold is 9.86m, and length is 3m, and width is 12.6m.
Provided by the inventionly movable Scaffold is utilized to carry out combining maintenance storehouse finishing and pipeline construction method of installation has following beneficial effect:
(1) scaffold building and dismounting easily fast, have very strong mobility, can meet large-scale job requirements.
(2) set up pattern comparatively flexible, the scaffold of differing heights, Different Plane size, different facade pattern can be set up.
(3) be provided with roller bottom scaffold, whole support body can be made to move.
(4) support body intensity, rigidity, stability can ensure construction safety completely after load design checking computations.
(5) construction method can reduce construction cost in a large number more in the past:
Because this engineering construction area is large, and highly higher, convention of in the past constructing is interior decoration engineering and supporting water, warm, fire-fighting, electrical engineering are all set up full hall and implemented formula steel pipe scaffold.Even if consider scaffold lease time and the number of turnover like this, but still need tear open once by scaffold whole peace within the scope of large storehouse, labour cost is very high.According to this movable Scaffold, by ceiling finish and various aerial pipeline, cross construction is shaping successively, only need spend scaffold rental charge and the installing/dismounting labour cost of minute quantity, greatly can save engineering expenditure, and saving labour cost through measuring and calculating can reach 90%.
(6) construction method can accelerating construction progress greatly more in the past:
Convention of in the past constructing, for first construction is on the ground indoor or ground concrete bed course is carried out by underground infrastructures (as checked hole or equipment Foundations etc.) again, then being carried out ceiling, metope, ground surface finishing, finally being installed various pipeline, equipment etc.According to this construction method, the overhead pipelines such as flooring Structural Engineering and ceiling finish engineering, electrical installation project, water supply and sewage work, fire engineering, heating and ventilation engineering and equipment installation project can be formed cross construction successively.Even locomotive inspection hole and ceiling finish and wind, water, the engineering such as warm, electric can be constructed simultaneously for this engineering, do not interfere with each other up and down, face of jointly organizing work, the construction task in respective specialty can be completed rapidly, substantially reduce the duration, serve the effect of getting twice the result with half the effort.
Accompanying drawing explanation
Fig. 1-Figure 18 is that the movable Scaffold that utilizes provided by the invention carries out combining maintenance storehouse finishing and pipeline construction method of installation work progress schematic diagram.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments to provided by the invention utilize movable Scaffold combine maintenance storehouse finishing and pipeline construction method of installation be described in detail.
As shown in Fig. 1-Figure 18, provided by the inventionly movable Scaffold is utilized to carry out combining maintenance storehouse finishing and pipeline construction method of installation comprises the following step carried out in order:
1) in built storehouse 1, first carry out the construction in first and second inspection hole, road 2, then carry out the construction that all the other check hole 2 successively;
2) around first and second built inspection hole, road 2, carry out indoor to banket;
3) first, respectively in the backfill that 2 both sides are cheated in two road inspections lay a leading track 3, and first, two road inspections are cheated on the leading track 3 outside 2 one end and are set up the first scaffold A that bottom is provided with roller, the height of the first described scaffold A is 13.86m, length is 10.5m, width is 12.6m, then on this scaffold, the Puttying of ceiling above it is carried out by constructor, brushing paint operation, after completing, the first scaffold A is moved to subsequent work face along leading track 3, proceed ceiling finish construction, until arrive first, the other end in two inspection hole, roads 2,
4) the crus secunda hand cradle B that bottom is provided with roller is set up at the former place of setting up of the first scaffold A, the height of described crus secunda hand cradle B is 13.86m, length is 6m, width is 12.6m, then on this scaffold, the electrical install operation of cable conduct, wire through pipe, cable testing bridge, cable laying, light fixture under ceiling above it is carried out by constructor, after completing, crus secunda hand cradle B is moved to subsequent work face along leading track 3, proceed above-mentioned electrical install operation, until arrive the other end in first and second inspection hole, road 2;
5) the 3rd scaffold C that bottom is provided with roller is set up at the former place of setting up of the first scaffold A, then on this scaffold, the installation exercise of fire protection pipeline above it is carried out by constructor, because fire protection pipeline design elevation will lower than ceiling 2m, mainly arrange along frame column both sides, and mounting process is simpler, operating surface is without the need to excessive, therefore the height of the 3rd scaffold C is 11.86m, length is 4.5m, width is 12.6m, after completing, the 3rd scaffold C is moved to subsequent work face along leading track 3, proceed above-mentioned fire protection pipeline installation exercise, until arrive first, the other end in two inspection hole, roads 2,
6) the 4th scaffold D that bottom is provided with roller is set up at the former place of setting up of the first scaffold A, then on this scaffold, the installation exercise of caliduct above it is carried out by constructor, because caliduct design elevation will lower than ceiling 4m, and mounting process is simpler, operating surface is without the need to excessive, therefore the height of the 4th scaffold D is 9.86m, length is 3m, width is 12.6m, after completing, the 4th scaffold D is moved to subsequent work face along leading track 3, proceed above-mentioned caliduct installation exercise, until arrive the other end in first and second inspection hole, road 2;
7) often complete two road inspections holes 2 construction and after around banketing, repeat step 3) to step 6), all fit up and pipeline installation process until complete in the storehouse in.

Claims (5)

1. utilize movable Scaffold to carry out combining maintenance storehouse finishing and a pipeline construction method of installation, it is characterized in that: it comprises the following step carried out in order:
1) in built storehouse (1), first carry out the construction in first and second road inspection hole (2), then carry out the construction that all the other check hole (2) successively;
2) around first and second built road inspection hole (2), carry out indoor to banket;
3) each laying leading track (3) in the backfill of first and second (2) both sides, inspection hole, road, and the first scaffold (A) that bottom is provided with roller set up by leading track (3) outside (2) one end, first and second road inspection hole, then on this scaffold, Puttying, the brushing paint operation of ceiling above it is carried out by constructor, after completing, the first scaffold (A) is moved to subsequent work face along leading track (3), proceed ceiling finish construction, until arrive the other end in first and second road inspection hole (2);
4) the crus secunda hand cradle (B) that bottom is provided with roller is set up at the former place of setting up of the first scaffold (A), then on this scaffold, the electrical install operation of cable conduct, wire through pipe, cable testing bridge, cable laying, light fixture under ceiling above it is carried out by constructor, after completing, crus secunda hand cradle (B) is moved to subsequent work face along leading track (3), proceed above-mentioned electrical install operation, until arrive the other end in first and second road inspection hole (2);
5) the 3rd scaffold (C) that bottom is provided with roller is set up at the former place of setting up of the first scaffold (A), then on this scaffold, the installation exercise of fire protection pipeline above it is carried out by constructor, after completing, the 3rd scaffold (C) is moved to subsequent work face along leading track (3), proceed above-mentioned fire protection pipeline installation exercise, until arrive the other end in first and second road inspection hole (2);
6) the 4th scaffold (D) that bottom is provided with roller is set up at the former place of setting up of the first scaffold (A), then on this scaffold, the installation exercise of caliduct above it is carried out by constructor, after completing, the 4th scaffold (D) is moved to subsequent work face along leading track (3), proceed above-mentioned caliduct installation exercise, until arrive the other end in first and second road inspection hole (2);
7) often complete two roads inspections hole (2) construction and after around banketing, repeat step 3) to step 6), all fit up and pipeline installation process until complete in the storehouse in.
2. the movable Scaffold that utilizes according to claim 1 carries out combining maintenance storehouse finishing and pipeline construction method of installation, it is characterized in that: the height of described the first scaffold (A) is 13.86m, and length is 10.5m, and width is 12.6m.
3. the movable Scaffold that utilizes according to claim 1 carries out combining maintenance storehouse finishing and pipeline construction method of installation, it is characterized in that: the height of described crus secunda hand cradle (B) is 13.86m, and length is 6m, and width is 12.6m.
4. the movable Scaffold that utilizes according to claim 1 carries out combining maintenance storehouse finishing and pipeline construction method of installation, it is characterized in that: the height of the 3rd described scaffold (C) is 11.86m, and length is 4.5m, and width is 12.6m.
5. the movable Scaffold that utilizes according to claim 1 carries out combining maintenance storehouse finishing and pipeline construction method of installation, it is characterized in that: the height of the 4th described scaffold (D) is 9.86m, and length is 3m, and width is 12.6m.
CN201510518883.XA 2015-08-20 2015-08-20 Construction method for jointly decorating maintenance storehouses and installing pipelines by aid of movable scaffolds Active CN105220878B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510518883.XA CN105220878B (en) 2015-08-20 2015-08-20 Construction method for jointly decorating maintenance storehouses and installing pipelines by aid of movable scaffolds

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510518883.XA CN105220878B (en) 2015-08-20 2015-08-20 Construction method for jointly decorating maintenance storehouses and installing pipelines by aid of movable scaffolds

Publications (2)

Publication Number Publication Date
CN105220878A true CN105220878A (en) 2016-01-06
CN105220878B CN105220878B (en) 2017-04-19

Family

ID=54990109

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510518883.XA Active CN105220878B (en) 2015-08-20 2015-08-20 Construction method for jointly decorating maintenance storehouses and installing pipelines by aid of movable scaffolds

Country Status (1)

Country Link
CN (1) CN105220878B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625721A (en) * 2016-03-10 2016-06-01 四川华西安装工程有限公司 Core-drilling method for concrete lamp pits and auxiliary device for core-drilling method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102004038786B3 (en) * 2004-08-09 2006-01-19 Db Regio Ag Side working pit for rail vehicle repair has profiled rails for mobile access staging having locking brake to hold in place
CN1939785A (en) * 2006-09-25 2007-04-04 王树生 Wagon body repairing technology
CN201154712Y (en) * 2007-12-14 2008-11-26 中铁工程设计院有限公司 Stereo operation platform of motor train set inspecting garage
CN201265254Y (en) * 2008-12-29 2009-07-01 中铁建工集团有限公司 Movable operating platform system
CN203797592U (en) * 2014-05-09 2014-08-27 中建七局(上海)有限公司 Movable assembled type engineering lighting table
CN204139569U (en) * 2014-08-28 2015-02-04 江苏南通二建集团有限公司 Sliding scaffold
CN104727538A (en) * 2015-03-30 2015-06-24 山东双得利建设科技有限公司 Scaffold device for plant roof reinforcement and maintenance and scaffold erecting method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102004038786B3 (en) * 2004-08-09 2006-01-19 Db Regio Ag Side working pit for rail vehicle repair has profiled rails for mobile access staging having locking brake to hold in place
CN1939785A (en) * 2006-09-25 2007-04-04 王树生 Wagon body repairing technology
CN201154712Y (en) * 2007-12-14 2008-11-26 中铁工程设计院有限公司 Stereo operation platform of motor train set inspecting garage
CN201265254Y (en) * 2008-12-29 2009-07-01 中铁建工集团有限公司 Movable operating platform system
CN203797592U (en) * 2014-05-09 2014-08-27 中建七局(上海)有限公司 Movable assembled type engineering lighting table
CN204139569U (en) * 2014-08-28 2015-02-04 江苏南通二建集团有限公司 Sliding scaffold
CN104727538A (en) * 2015-03-30 2015-06-24 山东双得利建设科技有限公司 Scaffold device for plant roof reinforcement and maintenance and scaffold erecting method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625721A (en) * 2016-03-10 2016-06-01 四川华西安装工程有限公司 Core-drilling method for concrete lamp pits and auxiliary device for core-drilling method

Also Published As

Publication number Publication date
CN105220878B (en) 2017-04-19

Similar Documents

Publication Publication Date Title
CN103711323B (en) Utilize the anti-ceiling board construction method of portable tubular truss stage+module roofing
ITFI20100096A1 (en) "A COMPLEX OF PREFABRICATED ELEMENTS TO FORM A PREFABRICATED BUILDING AT AT LEAST TWO PLANS AND RELATED BUILDING AND INSTALLATION PROCEDURE"
CN107508245B (en) Foldable cable support
CN202324576U (en) Rail-mounted platform system used for installing cornice and ceiling aluminium sheet curtain wall
CN104878867A (en) Integrated structure of ceiling keel and double-layer construction platform and manufacturing method thereof
CN101775896A (en) Method for installing pipeline scaffold of steel roof equipment and rigid suspended scaffold
CN206134107U (en) Synthesize entity proportion teaching mode
CN204456189U (en) Subway station top Pipe rack
CN110107972A (en) Cabin-type refrigerating plant room and its construction method
CN201635377U (en) Rigid hanging scaffolding for installation of long-span steel roof equipment piping
CN204311622U (en) Saddle-shaped prestressed cable net
CN104533092B (en) The construction method of rack roofing furred ceiling
CN103276840B (en) Nuclear power plant composite floor slab module and construction method thereof
CN105220878A (en) Movable Scaffold is utilized to carry out combining maintenance storehouse finishing and pipeline construction method of installation
CN202865996U (en) Room modular structure for nuclear power plant
CN102733614B (en) A kind of construction method of room module of nuclear power plant
CN104234197A (en) Container portable house
CN203701555U (en) Movable type pipe truss installation platform
CN108331346A (en) The method for executing indoor pipeline integrated morphology
Xue et al. Preservation and adaptive reuse of historical buildings: A case study of the Lin Hall at the former site of Dongwu University
CN106760003B (en) Fire blocking structure under raised floor and construction method thereof
CN207683555U (en) A kind of transport device of assembled wallboard
CN206467815U (en) Fireproof blocking structure below raised floor
TWI719736B (en) Construction method of elastic compartment of multi-story elevated sound-absorbing floor slab
CN103720427A (en) Rail-type window cleaning machine for complex inner-court curtain wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant