CN105155902B - A kind of compact double circuit, which becomes, exhales high shaft tower - Google Patents

A kind of compact double circuit, which becomes, exhales high shaft tower Download PDF

Info

Publication number
CN105155902B
CN105155902B CN201510562142.1A CN201510562142A CN105155902B CN 105155902 B CN105155902 B CN 105155902B CN 201510562142 A CN201510562142 A CN 201510562142A CN 105155902 B CN105155902 B CN 105155902B
Authority
CN
China
Prior art keywords
arm
cross
layer
newly
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510562142.1A
Other languages
Chinese (zh)
Other versions
CN105155902A (en
Inventor
赵晖
王力
罗正帮
于永洋
葛娜
刘西民
陈曦鸣
罗义华
刘勇
计策
吴松
丁波
汪晓光
陈彦焰
夏威
郑少将
梁东跃
周转
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Anhui Electric Power Co Ltd
Anhui Huadian Engineering Consulting and Design Co Ltd
Chuzhou Power Supply Co of State Grid Anhui Electric Power Co Ltd
Original Assignee
State Grid Anhui Electric Power Co Ltd
Anhui Huadian Engineering Consulting and Design Co Ltd
Chuzhou Power Supply Co of State Grid Anhui Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Anhui Electric Power Co Ltd, Anhui Huadian Engineering Consulting and Design Co Ltd, Chuzhou Power Supply Co of State Grid Anhui Electric Power Co Ltd filed Critical State Grid Anhui Electric Power Co Ltd
Priority to CN201510562142.1A priority Critical patent/CN105155902B/en
Publication of CN105155902A publication Critical patent/CN105155902A/en
Application granted granted Critical
Publication of CN105155902B publication Critical patent/CN105155902B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

一种紧凑型双回路变呼高杆塔。它包括塔身、顶层地线横担,所述顶层地线横担共一层,自塔身垂直于新建线路方向布置两边横担,所述上层导线横担分三层,每一层自塔身垂直于新建线路方向布置两边横担,所述中层辅助横担自塔身垂直于新建线路方向布置多层两边横担,所述下层地线横担共一层,自塔身垂直于新建线路方向布置两边横担,所述下层导线横担共两层,每一层自塔身垂直于新建线路方向布置两边横担。本发明避免了对邻塔导线布置的影响,钻越侧导线采用紧凑的三角形排列方式,压缩了导、地线对地高度,进一步优化了钻越方案,降低了老线路改造、电缆入地、单双回路变换的可能。

The utility model relates to a compact dual-circuit call-changing high pole tower. It includes the tower body and the top ground wire cross arm. The top ground wire cross arm has one layer, and the two side cross arms are arranged perpendicular to the direction of the new line from the tower body. The body is perpendicular to the direction of the newly-built line, and the middle-level auxiliary cross-arm is arranged from the tower body perpendicular to the direction of the new line. Arrange cross arms on both sides in the direction, and the lower conductor cross arm has two layers in total, and each layer is arranged on both sides of the cross arms perpendicular to the direction of the new line from the tower body. The invention avoids the influence on the arrangement of adjacent tower conductors, and adopts a compact triangular arrangement for the drilled side conductors, which reduces the height of the conductors and ground wires to the ground, further optimizes the drilled scheme, and reduces the need for reconstruction of old lines, cables entering the ground, Possibility of single and double circuit conversion.

Description

一种紧凑型双回路变呼高杆塔A compact dual-circuit call-changing high pole tower

技术领域:Technical field:

本发明涉及高压输电线路技术领域,尤其涉及一种紧凑型双回路变呼高杆塔。The invention relates to the technical field of high-voltage transmission lines, in particular to a compact double-circuit call-changing high pole tower.

背景技术:Background technique:

输电线路工程建设是电网建设中的重要组成部分,在电力系统中担当着传输、分配、调压的作用,鉴于输电线路对传输走廊的择优原则相同,出于降低成本、减少占地的考虑,输电线路通常平行走线。受新建变电站落点位置的影响,新建线路经常与已建输电线路经常交叉,根据规程要求,宜跨越电压等级较低的线路和钻越电压等级较高的线路,故输电线路先跨后钻(或先钻后跨)的情况屡有发生。Transmission line engineering construction is an important part of power grid construction, and plays the role of transmission, distribution, and voltage regulation in the power system. In view of the same principle of selection of transmission lines for transmission corridors, for the sake of reducing costs and reducing land occupation, Transmission lines are usually run in parallel. Affected by the location of new substations, newly built lines often intersect with existing transmission lines. According to the requirements of regulations, it is advisable to cross lines with lower voltage levels and drill through lines with higher voltage levels. Therefore, transmission lines should be crossed before drilling ( Or drilling first and then crossing) happened frequently.

在实际工程中,对于输电线路先跨后钻(或先钻后跨)的情况,受地形与现场环境影响,仅采用一基杆塔往往难以直接实现,通常需要采取以下几种手段:In actual engineering, for the situation that the transmission line spans first and then drills (or drills first and then spans), due to the influence of terrain and site environment, it is often difficult to directly implement only one base tower, and usually the following methods are required:

1)通过升高电压等级较高线路或者降低电压等级较低线路,但导致线路停电,增加线路建设成本。1) By increasing the line with a higher voltage level or reducing the line with a lower voltage level, it will cause a power outage on the line and increase the cost of line construction.

2)采用架空跨越、电缆钻越的方式,但电缆入地成本较高,线路建成后不易于巡检。2) The method of overhead spanning and cable drilling is adopted, but the cost of cable entry into the ground is relatively high, and it is not easy to inspect after the line is completed.

3)将双回路改为单回路,新建两基单回路钻越塔实现钻越,存在占地面积大、建设成本高的问题。3) Changing the double circuit into a single circuit, and building a two-base single-circuit drill-through tower to achieve drill-through, which has the problems of large footprint and high construction cost.

综上所述,上述方案施工困难且综合造价较高,不利于工程实施。To sum up, the construction of the above scheme is difficult and the comprehensive cost is high, which is not conducive to the implementation of the project.

发明内容:Invention content:

本发明的目的是提供一种紧凑型双回路变呼高杆塔,该杆塔的线路跨越侧导线呈鼓型布置,与常规线路布置方式相同,避免了对邻塔导线布置的影响,钻越侧导线采用紧凑的三角形排列方式,压缩了导、地线对地高度,进一步优化了钻越方案,降低了老线路改造、电缆入地、单双回路变换的可能。The purpose of the present invention is to provide a compact dual-circuit call-changing high pole tower. The line spanning side conductors of the pole tower are arranged in a drum shape, which is the same as the conventional line layout, and the influence on the arrangement of adjacent tower conductors is avoided. The compact triangular arrangement method reduces the height of guide wires and ground wires to the ground, further optimizes the drilling and overrunning scheme, and reduces the possibility of reconstruction of old lines, cables entering the ground, and conversion of single and double circuits.

为了解决背景技术中存在的问题,本发明采用以下技术方案:它包括塔身、顶层地线横担,顶层地线横担下方设置有上层导线横担,上层导线横担下方设置有中层辅助横担,中层辅助横担下方设置下层地线横担,下层地线横担下方设置下层导线横担,所述顶层地线横担共一层,自塔身垂直于新建线路方向布置两边横担,所述上层导线横担分三层,每一层自塔身垂直于新建线路方向布置两边横担,所述中层辅助横担自塔身垂直于新建线路方向布置多层两边横担,所述下层地线横担共一层,自塔身垂直于新建线路方向布置两边横担,所述下层导线横担共两层,每一层自塔身垂直于新建线路方向布置两边横担;In order to solve the problems existing in the background technology, the present invention adopts the following technical solutions: it includes the tower body, the top ground wire cross arm, the upper layer wire cross arm is arranged under the top layer ground wire cross arm, and the middle layer auxiliary cross arm is arranged under the upper layer wire cross arm The lower ground wire cross arm is set under the auxiliary cross arm of the middle layer, the lower layer conductor cross arm is set under the lower ground wire cross arm, and the top ground wire cross arm has a total of one layer. The upper conductor cross-arm is divided into three layers, and each layer is arranged with two-side cross-arms from the tower body perpendicular to the direction of the newly-built line. There is a total of one layer of ground wire cross arms, and the two side cross arms are arranged perpendicular to the direction of the newly built line from the tower body.

所述上层导线横担较高一层两边横担均设置有带支撑管的跳线串,并且在下面两层的每层两边横担梢部均设置有两个支柱绝缘子,其中一个支柱绝缘子垂直于新建线路方向,另一个平行于新建线路方向且位于钻越线路一侧;The cross-arms of the upper layer of the upper layer are equipped with jumper strings with support tubes on both sides of the higher layer, and two post insulators are provided at the tips of the cross-arms on both sides of each layer of the lower two layers, one of which is vertical In the direction of the new line, the other is parallel to the direction of the new line and located on the side of the drilled line;

所述中层辅助横担在每一层两边横担梢部均设置有三个支柱绝缘子,其中一个支柱绝缘子垂直于新建线路方向,一个平行于新建线路方向且位于钻越线路一侧,另一个平行于新建线路方向且位于跨越线路一侧;The auxiliary cross arm of the middle layer is provided with three post insulators at the tips of the cross arms on both sides of each layer, one of which is perpendicular to the direction of the new line, one is parallel to the direction of the new line and is located on the side of the drilled line, and the other is parallel to the The direction of the newly created line is located on the side of the crossing line;

所述下层地线横担在每一层两边横担上设置有三个支柱绝缘子,其中有一个设置在横担梢部且平行于新建线路方向,另外两个分别设置在横担中部两侧且均平行于新建线路方向;The ground wire crossarm of the lower layer is provided with three post insulators on the crossarms on both sides of each layer, one of which is arranged at the tip of the crossarm and parallel to the direction of the new line, and the other two are respectively arranged on both sides of the middle of the crossarm and are Parallel to the direction of the new line;

所述下层导线横担在每一层两边横担上均设置有两个支柱绝缘子,其中有一个设置在横担梢部且平行于新建线路方向,另外一个设置在横担中部跨越线路一侧且平行于新建线路方向,在较低一层两边横担的梢部和中部分别各设置有一个带支撑管的跳线串。The cross-arms of the lower layer conductors are provided with two post insulators on the cross-arms on both sides of each layer, one of which is arranged at the tip of the cross-arm and parallel to the direction of the newly-built line, and the other is arranged in the middle of the cross-arm across the side of the line and Parallel to the direction of the new line, a jumper string with a support tube is respectively arranged at the tip and middle of the cross arms on both sides of the lower floor.

本发明通过一基杆塔实现了双回路变呼高钻跨越,降低了先跨后钻(或先钻后跨)工程中交叉线路改造、电缆入地、单双回路变换的几率,避免了交叉线路的停电,增加了电网可靠性,缩减了建设成本,同时进一步压缩了钻越档的新建线路导地线对地距离。The invention realizes double-circuit change-call high-drilling crossing through a base pole tower, reduces the probability of cross-circuit reconstruction, cable entry into the ground, and single-double circuit conversion in the project of spanning first and then drilling (or drilling first and then spanning), and avoids the possibility of crossing lines The power outage increases the reliability of the power grid, reduces the construction cost, and further reduces the distance between the ground conductor and the ground of the newly built line of the drilling overpass.

附图说明:Description of drawings:

图1为本发明的结构示意图;Fig. 1 is a structural representation of the present invention;

图2为本发明的接线示意图。Fig. 2 is a wiring diagram of the present invention.

具体实施方式:detailed description:

参照图1-2,它包括塔身1、顶层地线横担2,顶层地线横担2下方设置有上层导线横担3,上层导线横担3下方设置有中层辅助横担4,中层辅助横担4下方设置下层地线横担5,下层地线横担5下方设置下层导线横担6,所述顶层地线横担2共一层,自塔身1垂直于新建线路方向布置两边横担,所述上层导线横担3分三层,每一层自塔身1垂直于新建线路方向布置两边横担,所述中层辅助横担4自塔身垂直于新建线路方向布置多层两边横担,所述下层地线横担5共一层,自塔身1垂直于新建线路方向布置两边横担,所述下层导线横担6共两层,每一层自塔身1垂直于新建线路方向布置两边横担。所述顶层地线横担2的长度及与导线横担的间距,需满足防雷保护,导地线间距的要求,所述上层导线横担3、中层辅助横担4、下层地线横担5、下层导线横担6的长度及层间距需满足电气要求,所述上层跨越横担3的长度与间距还需参照跨越侧线路导线布置形式,所述中层辅助横担4的层数由钻越点与跨越点之间的高差决定,高差越高中层辅助横担4的层数越多,所述下层地线横担5长度及与导线横担的间距需满足导地线间距、防雷保护的要求。Referring to Figure 1-2, it includes a tower body 1, a top-level ground wire cross-arm 2, an upper-level conductor cross-arm 3 is arranged below the top-level ground wire cross-arm 3, a middle-level auxiliary cross-arm 4 is arranged under the upper-level wire cross-arm 3, and the middle-level auxiliary The lower ground wire cross arm 5 is set under the cross arm 4, the lower ground wire cross arm 6 is set under the lower ground wire cross arm 5, and the top ground wire cross arm 2 has a total of one layer, and the two sides of the tower body 1 are arranged perpendicular to the direction of the new line. The upper-level conductor cross-arm 3 is divided into three layers, and each layer is arranged with two-side cross-arms from the tower body 1 perpendicular to the direction of the newly-built line, and the middle-level auxiliary cross-arm 4 is arranged from the tower body perpendicular to the direction of the newly-built line. Bearer, the lower ground wire cross arm 5 is a total of one layer, and the cross arms on both sides are arranged perpendicular to the direction of the new line from the tower body 1. The direction is arranged on both sides of the crossarm. The length of the top-layer ground wire cross-arm 2 and the distance between the wire cross-arm and the wire cross-arm must meet the requirements for lightning protection and ground wire spacing. The upper-layer wire cross-arm 3, the middle-layer auxiliary cross-arm 4, and the lower-layer ground wire 5. The length and layer spacing of the lower conductor cross-arm 6 must meet the electrical requirements. The length and spacing of the upper-layer cross-arm 3 also need to refer to the layout of the cross-side line wires. The number of layers of the middle auxiliary cross-arm 4 is determined by the drill The height difference between the crossing point and the crossing point is determined. The higher the height difference is, the more layers there are in the auxiliary cross arm 4 of the middle layer. Lightning protection requirements.

所述上层导线横担3较高一层两边横担均设置有带支撑管的跳线串7,并且在下面两层的每层两边横担梢部均设置有两个支柱绝缘子8,其中一个支柱绝缘子8垂直于新建线路方向,另一个平行于新建线路方向且位于钻越线路一侧。The upper layer conductor cross arm 3 is provided with a jumper string 7 with support tubes on both sides of the upper layer, and two post insulators 8 are arranged at the tip of each side cross arm of the lower two layers, one of which is The post insulator 8 is perpendicular to the direction of the new line, and the other is parallel to the direction of the new line and located on one side of the drilled line.

所述中层辅助横担4在每一层两边横担梢部均设置有三个支柱绝缘子8,其中一个支柱绝缘子8垂直于新建线路方向,一个平行于新建线路方向且位于钻越线路一侧,另一个平行于新建线路方向且位于跨越线路一侧。The auxiliary cross-arm 4 in the middle layer is provided with three post insulators 8 at the tips of the cross-arms on both sides of each layer, one of the post insulators 8 is perpendicular to the direction of the new line, one is parallel to the direction of the new line and is located on the side of the drilled line, and the other One parallel to the direction of the new route and on the side of the crossing route.

所述下层地线横担5在每一层两边横担上均设置有三个支柱绝缘子8,其中有一个设置在横担梢部且平行于新建线路方向,另外两个分别设置在横担中部两侧且均平行于新建线路方向。The ground wire crossarm 5 of the lower layer is provided with three post insulators 8 on both sides of each layer, one of which is arranged at the tip of the crossarm and parallel to the direction of the new line, and the other two are respectively arranged on the two sides of the middle of the crossarm. side and parallel to the direction of the new line.

所述下层导线横担6在每一层两边横担上均设置有两个支柱绝缘子8,其中有一个设置在横担梢部且平行于新建线路方向,另外一个设置在横担中部跨越线路一侧且平行于新建线路方向,在较低一层两边横担的梢部和中部分别各设置有一个带支撑管的跳线串7。The lower conductor cross-arm 6 is provided with two post insulators 8 on both sides of each layer, one of which is arranged at the tip of the cross-arm and parallel to the direction of the new line, and the other is arranged in the middle of the cross-arm across the line. Side and parallel to the direction of the new line, a jumper string 7 with a support tube is respectively provided at the tip and middle of the cross arms on both sides of the lower floor.

所述支柱绝缘子8带电点间距、带电点与导线、地线间距,带电点与塔身的间距,应满足电气要求。The distance between the charged point of the post insulator 8, the distance between the charged point and the wire and the ground wire, and the distance between the charged point and the tower body should meet the electrical requirements.

所述跨越侧地线悬挂于顶层地线横担2上,所述钻越侧地线悬挂在下层地线横担5,根据防雷保护、导地线间距的要求,确定地线的根数和悬挂位置。The ground wire on the crossing side is suspended on the top ground wire cross arm 2, and the drilled side ground wire is suspended on the ground wire cross arm 5 on the lower layer. The number of ground wires is determined according to the requirements for lightning protection and ground wire spacing and hanging position.

参照图2,在钻越线路与跨越线路之间新建一基本发明紧凑型双回路变呼高杆塔,跨越侧导线悬挂在上层导线横担3处,跨越侧地线悬挂在顶层地线横担2处,钻越侧导线悬挂在下层导线横担6处,钻越侧地线悬挂在下层地线横担5处,跨越侧上相导线利用上层导线横担3最高一层带支撑管的跳线串7和上层导线横担3下面两层、中层辅助横担4、下层地线横担5钻越线路一侧支柱绝缘子8,接至钻越侧上相导线,跨越侧中相导线利用上层导线横担3中间一层垂直于新建线路方向的支柱绝缘子8和上层导线横担3下面两层、中层辅助横担4垂直新建线路方向的支柱绝缘子8及下层地线横担5、下层导线横担6跨越线路一侧支柱绝缘子8、下层导线横担6较低一层横担上的带支撑管绝缘子串7,接至钻越侧远离塔身的下相导线,跨越侧下相导线利用上层导线横担3最低一层、中层辅助横担4、下层地线横担5、下层导线横担6跨越线路一侧支柱绝缘子8,下层导线横担6较低一层横担上的带支撑管绝缘子串7,接至钻越侧靠近塔身的下相导线,实施后跨越档导线呈鼓型布置,钻越档导线呈三角型布置。Referring to Fig. 2, a compact dual-circuit call-changing high pole tower of the basic invention is built between the drilling line and the crossing line. Drilling side conductors are suspended at 6 positions of the lower conductor cross arm, drilled side ground wires are suspended at 5 positions of the lower ground conductor cross arm, and the upper phase conductors on the crossing side use the upper conductor cross arm 3 and jumpers with support tubes on the highest layer The string 7 and the upper layer conductor cross arm 3 are two layers below, the middle layer auxiliary cross arm 4, and the lower layer ground wire cross arm 5 are drilled through the support insulator 8 on one side of the line, connected to the upper phase conductor on the drilled side, and the middle phase conductor on the crossing side uses the upper conductor The middle layer of cross arm 3 is a post insulator 8 perpendicular to the direction of the newly built line, the upper layer of wire cross arm 3 is two layers below, the middle layer of auxiliary cross arm 4 is a post insulator 8 perpendicular to the direction of the newly built line, the lower layer of ground wire cross arm 5, and the lower layer of wire cross arm 6 The support insulator on one side of the line across the line 8, the lower layer conductor cross arm 6 The insulator string 7 with support tube on the lower layer cross arm is connected to the lower phase conductor on the drilled side away from the tower body, and the upper layer conductor is used for the lower phase conductor on the crossover side Cross arm 3 lowest level, middle level auxiliary cross arm 4, lower ground wire cross arm 5, lower level wire cross arm 6 spanning post insulator 8 on one side of the line, lower level wire cross arm 6 with support tube insulator on the lower level cross arm String 7 is connected to the lower phase wire near the tower body on the drilling side. After the implementation, the crossing wire is arranged in a drum shape, and the drilling wire is arranged in a triangular shape.

根据防雷保护、导地线间距的要求,当需要保留地线时,需满足跨越侧导线与被跨越线路地线、钻越侧地线与被钻越线路导线的间距,当取消地线时,需满足跨越侧导线与被跨越线路地线、钻越侧导线与被钻越线路导线的间距,取消下层地线横担。According to the requirements of lightning protection and distance between conductors and ground wires, when the ground wire needs to be reserved, the distance between the crossing side wire and the ground wire of the crossed line, and the distance between the drilled side ground wire and the drilled line wire must be met. When the ground wire is canceled , it is necessary to meet the spacing between the crossing side conductor and the ground wire of the crossed line, and the distance between the drilling side conductor and the drilled line conductor, and cancel the ground wire cross arm of the lower layer.

Claims (1)

1. a kind of compact double circuit, which becomes, exhales high shaft tower, it is characterised in that it includes tower body, top layer ground wire cross-arm, top layer ground wire Topping wire cross-arm is provided with below cross-arm, middle level auxiliary cross-arm is provided with below topping wire cross-arm, middle level is aided under cross-arm Setting lower floor of side ground wire cross-arm, layer conductor cross-arm under lower floor's ground wire cross-arm lower section is set, totally one layer of the top layer ground wire cross-arm, from Tower body arranges both sides cross-arm perpendicular to newly-built line direction, the topping wire cross-arm points three layers, each layer from tower body perpendicular to Newly-built line direction arranges both sides cross-arm, and the middle level aids in cross-arm from tower body perpendicular to newly-built line direction arranging multiplayer both sides Cross-arm, totally one layer of lower floor's ground wire cross-arm, both sides cross-arm, the lower layer conductor are arranged perpendicular to newly-built line direction from tower body Two layers totally of cross-arm, each layer arrange both sides cross-arm from tower body perpendicular to newly-built line direction;
The higher one layer of both sides cross-arm of topping wire cross-arm is provided with the jumper string with support tube, and two layers below Every layer of both sides cross-arm taper is provided with two support insulators, one of support insulator perpendicular to newly-built line direction, Another gets over circuit side parallel to newly-built line direction and positioned at boring;
The middle level auxiliary cross-arm is provided with three support insulators in each layer of both sides cross-arm taper, and one of pillar is exhausted For edge perpendicular to newly-built line direction, one is got over circuit side parallel to newly-built line direction and positioned at boring, another parallel to Newly-built line direction and it is located at span line side;
Lower floor's ground wire cross-arm is provided with three support insulators on each layer of both sides cross-arm, wherein there is one to be arranged on horizontal stroke Carry on a shoulder pole taper and parallel to newly-built line direction, two other is separately positioned on cross-arm on both sides of the middle and each parallel to newly-built circuit side To;
The lower layer conductor cross-arm is provided with two support insulators on each layer of both sides cross-arm, wherein there is one to be arranged on Cross-arm taper and parallel to newly-built line direction, another is arranged in the middle part of cross-arm span line side and parallel to newly-built line Road direction, a jumper string with support tube is each provided with respectively in the taper of relatively low one layer of both sides cross-arm and middle part.
CN201510562142.1A 2015-09-07 2015-09-07 A kind of compact double circuit, which becomes, exhales high shaft tower Active CN105155902B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510562142.1A CN105155902B (en) 2015-09-07 2015-09-07 A kind of compact double circuit, which becomes, exhales high shaft tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510562142.1A CN105155902B (en) 2015-09-07 2015-09-07 A kind of compact double circuit, which becomes, exhales high shaft tower

Publications (2)

Publication Number Publication Date
CN105155902A CN105155902A (en) 2015-12-16
CN105155902B true CN105155902B (en) 2017-11-24

Family

ID=54796908

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510562142.1A Active CN105155902B (en) 2015-09-07 2015-09-07 A kind of compact double circuit, which becomes, exhales high shaft tower

Country Status (1)

Country Link
CN (1) CN105155902B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106320789B (en) * 2016-09-14 2018-08-31 国网山东省电力公司德州供电公司 A kind of OPGW optical cables, which move down formula and bore, gets over tower
CN106567597A (en) * 2016-09-26 2017-04-19 安徽华电工程咨询设计有限公司 Novel double-loop variable-norminal-height tower
CN110259252A (en) * 2019-07-05 2019-09-20 荆州市荆力工程设计咨询有限责任公司 A kind of 110 kilovolts are bored across dual-purpose anchor support
CN111119553A (en) * 2019-12-28 2020-05-08 国网安徽省电力有限公司经济技术研究院 Double-loop drilling and crossing angle steel tower

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006311774A (en) * 2005-05-02 2006-11-09 Chugoku Electric Power Co Inc:The Cable-mounting arm
CN202416965U (en) * 2011-12-27 2012-09-05 江苏省电力设计院 Mixed voltage multiloop cross-shaped crossover tower
CN202810314U (en) * 2012-09-11 2013-03-20 河北省电力勘测设计研究院 220kV T-shaped double-circuit drilling tower
CN103603536B (en) * 2013-10-25 2016-02-10 国家电网公司 Multiloop cross is handed over across steel pipe pole
CN203951136U (en) * 2014-07-03 2014-11-19 福建永福工程顾问有限公司 The switching Wiring device of overhead power transmission conducting wire and cable
CN205046908U (en) * 2015-09-07 2016-02-24 安徽华电工程咨询设计有限公司 Two return circuits of compact become exhales high shaft tower

Also Published As

Publication number Publication date
CN105155902A (en) 2015-12-16

Similar Documents

Publication Publication Date Title
CN105257061B (en) A kind of single loop, which becomes, exhales high shaft tower
CN105155902B (en) A kind of compact double circuit, which becomes, exhales high shaft tower
CN103362343B (en) A kind of with tower six circuit pole tower
CN203951136U (en) The switching Wiring device of overhead power transmission conducting wire and cable
CN109779373B (en) Cable terminal rod for breaking one circuit in double-circuit same-rod parallel-rack transmission line
CN106567597A (en) Novel double-loop variable-norminal-height tower
CN105155914A (en) Cut-off angle steel tower for single-loop power transmission line
CN206016392U (en) A kind of double loop bilateral cut-offs electric power line pole tower
CN105735731B (en) A kind of double T connection steel pipe poles in double loop
CN205577567U (en) Two return circuits double T connects steel pipe pole
CN210127695U (en) Cable terminal tower with novel cable supporting structure
CN205046908U (en) Two return circuits of compact become exhales high shaft tower
CN105155903B (en) A kind of double loop, which becomes, exhales high shaft tower
CN205036145U (en) Single loop becomes exhales high shaft tower
CN110453959A (en) A dual-circuit drill-through steel pipe pole and power transmission system
CN204983860U (en) Two return circuits become exhales high shaft tower
CN206189980U (en) Communication and sending end integral type shaft tower
CN208479132U (en) A special transposition facility suitable for existing double-circuit tension towers
CN210622429U (en) 110 kilovolt bores and strides dual-purpose strain insulator tower
CN207847235U (en) No ground pole DC transmission line line pole tower
CN107294034A (en) cable terminal pole
CN206128797U (en) Novel two return circuits become exhales high tower
CN211115091U (en) Double-loop drill span integrated tower
CN105178678A (en) Two-circuit line breaking and four-circuit cable leading-down tower
CN110259252A (en) A kind of 110 kilovolts are bored across dual-purpose anchor support

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant