CN105059484B - It goes ashore on a kind of Large Offshore Structures operating type - Google Patents
It goes ashore on a kind of Large Offshore Structures operating type Download PDFInfo
- Publication number
- CN105059484B CN105059484B CN201510486886.XA CN201510486886A CN105059484B CN 105059484 B CN105059484 B CN 105059484B CN 201510486886 A CN201510486886 A CN 201510486886A CN 105059484 B CN105059484 B CN 105059484B
- Authority
- CN
- China
- Prior art keywords
- ship
- marine structure
- ashore
- going
- cable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Jib Cranes (AREA)
- Water Treatment By Sorption (AREA)
Abstract
The invention discloses operating type of going ashore on a kind of Large Offshore Structures, including operation and the operation of going ashore of going on board;The main deck tail portion of ship used offers the groove that size is more than marine structure shape;For work flow of going on board for ship tail inclines, recycles marine structure, ship top-ups, operation of going ashore is the inverse process of operation of going on board.When the marine structure for operating same scale and weight, the present invention only need using small displacement ship can be achieved with Large Offshore Structures on go ashore, both risky operation of the crane ship using marine lifting operation mode had been avoided, semi-submerged ship has been in turn avoided and numerous ballast tanks is set and cause the hull space waste problem below the complete dive to the water surface of cargo deck.
Description
Technical field
The present invention relates to Large Offshore Structures marine transportation technical field, specifically a kind of Large Offshore Structures it is upper
It goes ashore operating type.
Background technology
With the development of science and technology, various marine structures continue to bring out, and also more next in terms of size and weight
More tend to maximize.Due to various, the construction and use of these marine structures are general not in same place, build
End will transport marine structure.During the marine transportation of Large Offshore Structures, how to realize go on board and under
Ship operation becomes one of transport key technology.There are mainly two types of the operating types gone ashore on existing Large Offshore Structures:Lifting
Ship lifting method and semi-submerged ship lift mode.Since the scale and weight of Large Offshore Structures are very huge, both works
Industry mode is required to that vessel displacement is big, ship type is plentiful, causes the drawbacks such as shipbuilding cost is high, the speed of a ship or plane is slow.
Invention content
The purpose of the present invention is to provide the operators that goes ashore on a kind of fast, low cost the Large Offshore Structures of transport
Formula.
To achieve the above object, the present invention provides following technical solution:
It goes ashore on a kind of Large Offshore Structures operating type, the main deck tail portion of ship used offers size and is more than
The groove of marine structure shape, it is described on go ashore operating type include below scheme:
(1) it goes on board and operates operation, idiographic flow is:
11) ship tail inclines:Ballast water is pumped to ship tail portion ballast tank by ballast pump, ship tail inclines, until ship
Tail portion freeboard is not less than 0.005 times of ship load line captain, keeps the drinking water state, opens Ship Dynamic Positioning Systems Based;
12) marine structure is recycled:The towing gear of two sides of a ship is connected by the cable of two side of a ship of stern with marine structure on ship
Connect, in indulge place towing gear by stern indulge place cable connect with marine structure, confirmation ship be located at ocean structure
At above the direction of flow of object location, cable is slowly pulled, marine structure is pulled in groove;
13) ship top-ups:By the ballast water of ballast pump discharge tail portion ballast tank to outboard, ship top-ups, binding
Marine structure completes marine structure and goes on board operation.
(2) it goes ashore operation, for the inverse process for operation of going on board, idiographic flow is:
21) ship tail inclines:The towing gear of two sides of a ship is connect by the cable of two side of a ship of stern with marine structure on ship, in indulge
The towing gear at place is connect by indulging the cable at place in stern with marine structure, is released marine structure binding piece, is passed through pressure
It carries water pump and pumps ballast water to ship tail portion ballast tank, ship tail inclines, until ship tail portion freeboard is not less than ship load line ship
Long 0.005 times, at this time marine structure be in floating state, keep the drinking water state;
22) marine structure is laid:At confirming that ship is located above the direction of flow of ocean structure object location, slowly forward
Ship is driven, while cable is unclasped by towing gear, until marine structure floating completely is at sea, releases marine structure
Cable and be recycled on ship;
23) ship top-ups:By the ballast water of ballast pump discharge tail portion ballast tank to outboard, ship top-ups, and completes
Marine structure is gone ashore operation.
As further embodiment of the present invention:The bottom of the groove is higher than ship waterline.
Compared with prior art, the beneficial effects of the invention are as follows:The present invention on ship tail portion deck by there are one opening up
Size is more than the groove of the shape of marine structure, as long as ship tail inclines, you can by deck haulage gear by marine structure
It is pulled to binding in groove and completes operation of going on board;Operation of going ashore be go on board operation inverse process and ship tail incline, lay ocean
Works, you can operation of going ashore is completed by ship forward drive.When the marine structure for operating same scale and weight, this
Invention only needs to go ashore on the ship realization Large Offshore Structures using small displacement, has both avoided Large Offshore Structures sea
The risky operation of upper lifting (crane ship), in turn avoid setting numerous ballast tanks (semi-submerged ship) and under causing cargo deck completely
The hull space waste problem dived to below the water surface.
Description of the drawings
Fig. 1 is the schematic diagram that ship tail portion deck opens up groove;
Fig. 2 is to adjust ballast water, the schematic diagram that ship tail inclines;
Fig. 3 is the schematic side view that Large Offshore Structures are pulled in groove by deck towing equipment;
Fig. 4 is the schematic top plan view that Large Offshore Structures are pulled in groove by deck towing equipment;
Fig. 5 is to adjust ballast water, the schematic side view that ship top-ups;
Fig. 6 is to adjust ballast water, the schematic top plan view that ship top-ups.
Specific embodiment
Below in conjunction with the embodiment of the present invention, the technical solution in the embodiment of the present invention is clearly and completely described,
Obviously, described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.Based in the present invention
Embodiment, those of ordinary skill in the art's all other embodiments obtained without making creative work, all
Belong to the scope of protection of the invention.
Please refer to Fig.1~6, in the embodiment of the present invention, operating type of going ashore on a kind of Large Offshore Structures is tied first
The specific shape for closing marine structure is designed ship main deck retaining groove form, the big Yu Haiyang knot of size of groove
The shape of structure object, so that marine structure can smoothly enter, and bottom portion of groove (water balcony) is higher than ship waterline;On described
Operating type of going ashore includes go on board operation and operation of going ashore.
The idiographic flow of operation of going on board is:
11) ship tail inclines:Ballast water is pumped to ship tail portion ballast tank by ballast pump, ship tail inclines, until ship
Tail portion freeboard is not less than 0.005L (L is ship load line captain), keeps the drinking water state, opens Ship Dynamic Positioning Systems Based,
As shown in Figure 2;
12) marine structure is recycled:Take certain measure so that on cable and ship of the marine structure by two side of a ship of stern
The towing gear connection of two sides of a ship, the towing gear that marine structure indulges place by indulging the cable at place in stern in connect, confirm
Ship slowly pulls cable, marine structure is pulled in groove, such as at being located above the direction of flow of ocean structure object location
Shown in Fig. 3 and Fig. 4;
13) ship top-ups:By the ballast water of ballast pump discharge tail portion ballast tank to outboard, ship top-ups, binding
Marine structure completes marine structure and goes on board operation, as shown in Figure 5 and Figure 6;
It goes ashore operation, for the inverse process for operation operation of going on board, idiographic flow is:
21) ship tail inclines:The towing gear of two sides of a ship is connect by the cable of two side of a ship of stern with marine structure on ship, in indulge
The towing gear at place is connect by indulging the cable at place in stern with marine structure, is released marine structure binding piece, is passed through pressure
It carries water pump and pumps ballast water to ship tail portion ballast tank, ship tail inclines, until ship tail portion freeboard is not less than ship load line ship
Long 0.005 times, at this time marine structure be in floating state, keep the drinking water state;
22) marine structure is laid:At confirming that ship is located above the direction of flow of ocean structure object location, slowly forward
Ship is driven, while cable is unclasped by towing gear, until marine structure floating completely at sea, takes certain measure solution
It opens the cable of marine structure and is recycled on ship;
23) ship top-ups:By the ballast water of ballast pump discharge tail portion ballast tank to outboard, ship top-ups, and completes
Marine structure is gone ashore operation.
The present invention by opened up on ship tail portion deck there are one size be more than marine structure shape groove, as long as
Ship tail inclines, you can marine structure is pulled to binding in groove by deck haulage gear and completes operation of going on board;It goes ashore work
Industry be go on board operation inverse process and ship tail incline, lay marine structure, you can pass through ship forward slowly drive complete
It goes ashore operation.When the marine structure for operating same scale and weight, the present invention only need using small displacement ship just
It can realize and go ashore on Large Offshore Structures, both avoid the risky operation of Large Offshore Structures sea lifting (crane ship),
It in turn avoids setting numerous ballast tanks (semi-submerged ship) and causing the hull space wave below the complete dive to the water surface of cargo deck
Take problem.
It is obvious to a person skilled in the art that the present invention is not limited to the details of above-mentioned exemplary embodiment, Er Qie
In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter
From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power
Profit requirement rather than above description limit, it is intended that all by what is fallen within the meaning and scope of the equivalent requirements of the claims
Variation is included within the present invention.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped
Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should
It considers the specification as a whole, the technical solutions in each embodiment can also be properly combined, forms those skilled in the art
The other embodiment being appreciated that.
Claims (2)
1. operating type of going ashore on a kind of Large Offshore Structures, the main deck tail portion of ship used offers size and is more than sea
The groove of foreign works shape, which is characterized in that operating type of going ashore on described, including below scheme:
(1) it goes on board operation, idiographic flow is:
11) ship tail inclines:Ballast water is pumped to ship tail portion ballast tank by ballast pump, ship tail inclines, until ship tail portion
Freeboard is not less than 0.005 times of ship load line captain, keeps the drinking water state, opens Ship Dynamic Positioning Systems Based;
12) marine structure is recycled:The towing gear of two sides of a ship is connect by the cable of two side of a ship of stern with marine structure on ship, in
The towing gear at vertical place is connect by indulging the cable at place in stern with marine structure, confirms that ship is located at ocean structure object location
Direction of flow above at, slowly pull cable, marine structure be pulled in groove;
13) ship top-ups:By the ballast water of ballast pump discharge tail portion ballast tank to outboard, ship top-ups, and binds ocean
Works completes marine structure and goes on board operation;
(2) it goes ashore operation, for the inverse process for operation of going on board, idiographic flow is:
21) ship tail inclines:The towing gear of two sides of a ship is connect by the cable of two side of a ship of stern with marine structure on ship, in indulge place
Towing gear is connect by indulging the cable at place in stern with marine structure, is released marine structure binding piece, is passed through ballast water
Pumping send ballast water, and to ship tail portion ballast tank, ship tail inclines, until ship tail portion freeboard is not less than ship load line captain's
0.005 times, at this time marine structure be in floating state, keep the drinking water state;
22) marine structure is laid:At confirming that ship is located above the direction of flow of ocean structure object location, slow forward drive
Ship, while cable is unclasped by towing gear, until marine structure floating completely at sea, releases the cable of marine structure
Rope is simultaneously recycled on ship;
23) ship top-ups:By the ballast water of ballast pump discharge tail portion ballast tank to outboard, ship top-ups, and completes ocean
Works is gone ashore operation.
2. operating type of going ashore on Large Offshore Structures according to claim 1, which is characterized in that the groove
Bottom is higher than ship waterline.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510486886.XA CN105059484B (en) | 2015-08-11 | 2015-08-11 | It goes ashore on a kind of Large Offshore Structures operating type |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510486886.XA CN105059484B (en) | 2015-08-11 | 2015-08-11 | It goes ashore on a kind of Large Offshore Structures operating type |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105059484A CN105059484A (en) | 2015-11-18 |
CN105059484B true CN105059484B (en) | 2018-06-29 |
Family
ID=54489083
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510486886.XA Active CN105059484B (en) | 2015-08-11 | 2015-08-11 | It goes ashore on a kind of Large Offshore Structures operating type |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105059484B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112407171B (en) * | 2020-12-28 | 2021-08-24 | 上海大学 | Unmanned underwater vehicle deployment and recovery system and deployment and recovery method |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2463697B (en) * | 2008-09-22 | 2012-06-27 | Technip France | Method of locating a subsea structure for deployment |
CN201358156Y (en) * | 2009-03-06 | 2009-12-09 | 中国海洋石油总公司 | Large ocean structure dragging device |
CN103112553B (en) * | 2013-02-04 | 2015-11-25 | 大连海事大学 | The latent maintenance and repair ship of self-propulsion type half and using method |
CN103910044B (en) * | 2014-04-14 | 2016-08-17 | 大连理工大学 | A kind of large-scale the floating structures semi-submersible type lifting platform and application process thereof |
-
2015
- 2015-08-11 CN CN201510486886.XA patent/CN105059484B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN105059484A (en) | 2015-11-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101920766B (en) | Shipbuilding method | |
CN103910044B (en) | A kind of large-scale the floating structures semi-submersible type lifting platform and application process thereof | |
CN101920771B (en) | Method for undock ballasting in ship building | |
US20120308358A1 (en) | Partially submersible wind turbine transport vessel | |
US10526046B2 (en) | Cargo transfer vessel | |
CN103661801B (en) | The installation ancillary system of ocean engineering underwater propeller and installation method | |
CN207346050U (en) | A kind of onshore terminals are to barge, the device of transferring of barge to barge | |
CN108860481B (en) | Omnibearing floating fuel oil supply system and operation method thereof | |
WO2019000757A1 (en) | Method for adding water in vessel lightering | |
CN104002923B (en) | A kind of knockdown half latent ships that transport and method of work thereof | |
CN207060358U (en) | Large Offshore Structures semi-submerged ship floats installing and applied | |
CN206635654U (en) | A kind of barging device of underwater narrow-bore tunnel super long type prefabricated case beam | |
CN104002931B (en) | U-shaped ocean engineering installation ship and catheterostat upper module installation method | |
CN204916099U (en) | Semi -submerged barge tilting dive stern deadwood | |
CN105059484B (en) | It goes ashore on a kind of Large Offshore Structures operating type | |
CN204432979U (en) | Ton horizontal launching building berth | |
CN104097750A (en) | Multifunctional maintenance ship | |
CN107618626A (en) | Improved deep water semi-submersible pipe laying crane ship | |
CN203902800U (en) | Semi-submersible type lifting platform for large floating offshore structure | |
EP3243734B1 (en) | Assembly of a vessel and a floating module | |
CN108583811B (en) | A kind of floating and transportation method | |
CN202828014U (en) | Ship stevedoring and replenishment device | |
RU2403168C1 (en) | Pontoon-type floating vessel | |
CN206087215U (en) | A flotation pontoon on water for oil delivery | |
CN107128459A (en) | Large Offshore Structures semi-submerged ship floats installing and applied |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: No.28, Zhejiang Road, Shinan District, Qingdao City, Shandong Province Patentee after: Shandong Ocean Instrument Technology Center Co.,Ltd. Address before: No.28, Zhejiang Road, Shinan District, Qingdao City, Shandong Province Patentee before: SHANDONG PROVINCE OCEANOGRAPHIC INSTRUMENTATION TECHNOLOGY CENTER |