CN105041313A - Long and narrow ore body accurate mining engineering ore-controlling method - Google Patents

Long and narrow ore body accurate mining engineering ore-controlling method Download PDF

Info

Publication number
CN105041313A
CN105041313A CN201510314702.1A CN201510314702A CN105041313A CN 105041313 A CN105041313 A CN 105041313A CN 201510314702 A CN201510314702 A CN 201510314702A CN 105041313 A CN105041313 A CN 105041313A
Authority
CN
China
Prior art keywords
ore
ore body
narrow
engineering
mining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510314702.1A
Other languages
Chinese (zh)
Inventor
田宏海
杜锦峰
任国芳
程国华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Jiu Steel Group Hongxing Iron and Steel Co Ltd
Original Assignee
Gansu Jiu Steel Group Hongxing Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Jiu Steel Group Hongxing Iron and Steel Co Ltd filed Critical Gansu Jiu Steel Group Hongxing Iron and Steel Co Ltd
Priority to CN201510314702.1A priority Critical patent/CN105041313A/en
Publication of CN105041313A publication Critical patent/CN105041313A/en
Pending legal-status Critical Current

Links

Abstract

The invention provides a long and narrow ore body accurate mining engineering ore-controlling method. The long and narrow ore body accurate mining engineering ore-controlling method comprises the following steps of arranging an accurate mining tunnel in advance; designing the accurate mining tunnel according to exploration engineering; arranging an exploration access road penetrating ore body in a direction perpendicular to the trend of an ore body; determining a tendency ore rock boundary of the ore body and the thickness of the ore body; and arranging an extracting drift in the middle along the trend after the thickness of the ore body is determined. A prospection tunnel is required to be arranged in a perpendicular trend when the extracting drift along the trend of the ore body advances for a certain distance so as to ensure accuracy of the direction. The long and narrow ore body accurate mining engineering ore-controlling method has the advantages that the engineering amount of the accurate mining tunnel is greatly reduced under the condition that requirements on production exploration engineering and requirements on engineering geological conditions, equipment level and a mining technology are met. The tunneling ratio is reduced, and the integrated mining cost is also reduced. Unnecessary loss on ends of a heading side is avoided, and the mining cost, the dilution ratio and the loss ratio are reduced.

Description

A kind of long and narrow narrow ore body adopts accurate engineering control ore deposit method
Technical field
The invention belongs to mining technique field, relate to long and narrow narrow ore body and adopt accurate engineering control ore deposit method.
Background technology
Long and narrow narrow ore body is less due to its ore body scale form, lacks the exploitation method of scientific system, and industrialization exploitation difficulty is large, cost is high.Ore body is in production mine locating process, and development heading engineering will both farthest in conjunction with prospecting drift engineering, to reduce costs; Take into full account the maximization of block stoping rate again, to avoid the loss of resource.Therefore, adopting accurate Control Engineering should reach claimed accuracy, has the requirement of its technique rate of extraction again.Wear arteries and veins then can cause as extracting drift with traditional in narrow ore body: 1. Dai Yan is many, and rock mixing in rock intersection ore deposit, ore deposit causes unnecessary dilution, loss; 2. roadway engineering amount is bigger than normal, cost high (cutting lane, 2-boundary line of ore bed and rock, 3-lane, 4-ore removal gallery, 5-drop shaft along the pulse see Fig. 1,1-).
Summary of the invention
The present invention solves the problem that long and narrow narrow orebody mining difficulty is large, cost is high, proposes long and narrow narrow ore body and adopts accurate engineering control ore deposit method.
Technical scheme: long and narrow narrow ore body adopts accurate engineering control ore deposit method, pre-arranged development heading, in conjunction with the design development heading of mineral exploration engineering tunnel, vertical orebody trend arranges that a mine locating route penetrates ore body, determine rock border, orebody strike ore deposit and orebody thickness, after orebody thickness is determined, extracting drift is arranged in middle, across pitch direction, extracting drift along orebody trend advances certain distance must do mine locating lane on capwise, to guarantee the accuracy in direction, when orebody thickness be greater than 20m be less than 40m time, the increase parallel lane parallel with extracting drift is arranged in ore body, within the scope of 150m, digging wear arteries and veins and an arteries and veins perpendicular to trend, lane is through along the pulse outward, as ore removal gallery, horizontal vertical direction is done every 15m spacing the development heading of next segmentation.
Beneficial effect: 1, for the long and narrow narrow ore body in down-hole and thick large high-dipping ore block irregularity boundary part, extracting drift is arranged in the middle of the ore body of orebody trend, the demand of production mineral exploration engineering can taken into account, under the condition of engineering geological conditions, equipment equipment, mining technology demand can be taken into account again, significantly reducing the engineering quantity of development heading.Compare with conventional method, vertical wear wearing in arteries and veins part engineering quantity and ore body of rock mass with ore body and partly wear arteries and veins engineering quantity and have and significantly reduce, thus reduce digging ratio, reduce mining integrated cost.
2, extracting drift is arranged at the middle across pitch of long and narrow narrow ore body and thick large high-dipping ore block irregularity boundary part, greatly can improve the rate of extraction, avoid unnecessary lower wall blade-end loss (fill blade-end loss see Fig. 5,8-shovel, 9-lower wall falls ore deposit recovery permanent loss, 10-lower wall end Industry Control permanent loss).Thus reach the object improving the rate of extraction, reduce loss late.
3, according to engineering geological conditions, narrow orebody thickness is this technical scheme all available when being less than 40m.The art of this patent is then for the long and narrow narrow ore body in down-hole and thick large high-dipping ore block irregularity boundary part, controlling ore body with adopting accurate stage maximum capacity, optimum condition is created, to reach the object reducing mining cost, the rate of dilution, loss late for recovery phase improves the rate of extraction in maximum efficiency.
Accompanying drawing explanation
Fig. 1 is that narrow ore body capwise is arranged to wear arteries and veins for main extracting drift mode figure;
Fig. 2 is that narrow ore body across pitch arranges to be main extracting drift mode figure in ore body along the pulse;
Fig. 3 is that narrow ore body across pitch arranges that increasing parallel is main extracting drift mode figure along the pulse;
Fig. 4 is narrow ore body development heading Discrete control height map;
Fig. 5 is the blade-end loss schematic diagram that the development heading of narrow ore body capwise causes;
Fig. 6 is that thick large high-dipping ore block irregularity boundary part across pitch arranges extracting drift.
Detailed description of the invention
For the long and narrow narrow ore body in down-hole and thick large high-dipping ore block irregularity boundary part then in the middle of ore body, arrange crosscut along orebody trend, do main back production lane; When ore body from right flank move back adopt to most left wing time, then crosscut becomes back production lane (see Fig. 2,6-stope drift active workings).
2, the layout of development heading must be combined closely process for stoping and equipment equipment situation, and when using sublevel caving method without sill pillar and LH409E electric LHD and ore deposit rock Polodyakonov coefficient f=12-14, it is main extracting drift mode that tradition wears arteries and veins, and wearing arteries and veins route is 18m; To change between ore body along the pulse at extracting drift, only need the maximum and best transportation range of electric LHD, reality is about 150m.
3, when orebody thickness is less than 20, in conjunction with mining codes, extracting drift 6 can arrange that one in the middle of ore body; Orebody thickness is greater than 20m when being less than 40m, and will consider in follow-up development heading to arrange in ore body that an increase parallel lane 7(parallel with prospect tunnel (namely Hou Gai lane of prospecting changes extracting drift 6 into) is shown in Fig. 3,7-increases parallel lane again).
4, be that 15m(is shown in Fig. 4 in conjunction with sublevel caving method without sill pillar narrow ore body development heading Discrete control height).Extracting drift in upper and lower level is spatially in parallel relation.
As shown in Figure 6, certain mining area I-II ore body 2655m level is the main intake horizon of whole ore body, and thing two along the pulse lane is main air intake footrill.Owing to considering that construction works amount is minimum and taking into account the problem of mining skill, inserted by vent level in ore body, make two south, the ore deposits wings have part to leave over, forming big thick ore body irregularity boundary feature, is also independent long and narrow narrow ore body characteristic feature.Cause Engineering Control in local defect to some extent.After the long and narrow narrow ore body of employing adopts accurate engineering control ore deposit technology, compensate for engineering defect, compared with arranging extracting drift mode with vertical orebody trend, roadway engineering amount saves 1/3rd, and unnecessary country rock will be avoided in exploitation process to be mixed into, also will improve the rate of extraction further.

Claims (1)

1. a long and narrow narrow ore body adopts accurate engineering control ore deposit method, it is characterized in that, pre-arranged development heading, in conjunction with the design development heading of mineral exploration engineering tunnel, vertical orebody trend arranges that a mine locating route penetrates ore body, determine rock border, orebody strike ore deposit and orebody thickness, after orebody thickness is determined, extracting drift (6) is arranged in middle, across pitch direction, extracting drift (6) along orebody trend advances certain distance must do mine locating lane (11) on capwise, to guarantee the accuracy in direction, when orebody thickness be greater than 20m be less than 40m time, the increase parallel lane (7) parallel with extracting drift (6) is arranged in ore body, within the scope of 150m, digging wear arteries and veins and an arteries and veins perpendicular to trend, lane is through along the pulse outward, as ore removal gallery (4), horizontal vertical direction is done every 15m spacing the development heading of next segmentation.
CN201510314702.1A 2015-08-26 2015-08-26 Long and narrow ore body accurate mining engineering ore-controlling method Pending CN105041313A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510314702.1A CN105041313A (en) 2015-08-26 2015-08-26 Long and narrow ore body accurate mining engineering ore-controlling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510314702.1A CN105041313A (en) 2015-08-26 2015-08-26 Long and narrow ore body accurate mining engineering ore-controlling method

Publications (1)

Publication Number Publication Date
CN105041313A true CN105041313A (en) 2015-11-11

Family

ID=54448235

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510314702.1A Pending CN105041313A (en) 2015-08-26 2015-08-26 Long and narrow ore body accurate mining engineering ore-controlling method

Country Status (1)

Country Link
CN (1) CN105041313A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1114712A (en) * 1994-06-04 1996-01-10 崔正洙 Mining and ore dressing process new modle for mine
RU2312219C2 (en) * 2005-07-26 2007-12-10 Институт горного дела Севера им. Н.В. Черского Сибирского отделения Российской академии наук Method for difficult-to-cave roof preparation for initial caving
CN101424186A (en) * 2007-11-01 2009-05-06 宝钢集团上海梅山有限公司 Method for recovering disc ore on incline ore block
CN101598031A (en) * 2009-06-17 2009-12-09 山东黄金矿业(莱州)有限公司焦家金矿 Barren rock backfill and can improve the mining methods of ore recovery ratio on the spot
CN103147759A (en) * 2013-03-02 2013-06-12 玉溪大红山矿业有限公司 Prospecting and short-hole shrinkage mining method of small inclined ore body

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1114712A (en) * 1994-06-04 1996-01-10 崔正洙 Mining and ore dressing process new modle for mine
RU2312219C2 (en) * 2005-07-26 2007-12-10 Институт горного дела Севера им. Н.В. Черского Сибирского отделения Российской академии наук Method for difficult-to-cave roof preparation for initial caving
CN101424186A (en) * 2007-11-01 2009-05-06 宝钢集团上海梅山有限公司 Method for recovering disc ore on incline ore block
CN101598031A (en) * 2009-06-17 2009-12-09 山东黄金矿业(莱州)有限公司焦家金矿 Barren rock backfill and can improve the mining methods of ore recovery ratio on the spot
CN103147759A (en) * 2013-03-02 2013-06-12 玉溪大红山矿业有限公司 Prospecting and short-hole shrinkage mining method of small inclined ore body

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李建云: "无底柱分段崩落法在云南昆钢大红山铁矿中的应用", 《四川建材》 *
胡家峪铜矿技术科: "在矿区开发中实行探采结合", 《地质与勘探》 *

Similar Documents

Publication Publication Date Title
CN107313778B (en) A kind of second mining super high seam stops the method for adopting line coal column
CN103557002B (en) A kind of mechanized concentrates drop shaft filling-up method
CN102080518B (en) Method for extracting gas from coal seam roof complex branched well
CN103902780B (en) Solid filling coal mining earth's surface Deformation prediction method
CN102392641B (en) Point pillar type full-ore-deposit middle-section-free upward high-layering continuous propelling fill mining method
CN103362510B (en) Sublevel-drilling bench-combination ore-removal sublevel-room mining method
CN107559008B (en) A method of joint second mining super high seam stops adopting line coal column
CN101424186A (en) Method for recovering disc ore on incline ore block
CN104100270A (en) Trackless mining method for gently inclined ore vein
CN105626054A (en) Method for subtly depicting broken edges of thick-layer fault block oil reservoir
CN103628878A (en) Crushed surrounding rock ore downward drift layered sublevel-free tunnel filling mining method
CN101915118A (en) Method for progressive gas drainage in high gas medium-hard coal seam
CN106194188A (en) The quick-fried power of scraper collaborative carrying puppet tilts room and pillar stoping
CN103557001B (en) A kind of low section high oper cylinler shrink afterwards filling mining method
CN103147759B (en) Prospecting and short-hole shrinkage mining method of small inclined ore body
CN106640080A (en) Deep part high-stress environment self-stabilizing arched stope arrangement mining method
CN101042051B (en) Arrangement method for initial mining sublevel stoping drift with sublevel caving method
CN102777179B (en) Method for controlling mine power capacity source by using region power planning
CN104808257A (en) Complex mined-out area drilling and exploration method in steep-dipping hostinng ore body
CN104153782B (en) Progressive caving mining method
CN108825241A (en) The back production blasting mining technique of big thick ore body
CN105041313A (en) Long and narrow ore body accurate mining engineering ore-controlling method
CN103615251B (en) Thin type ore body bar shaped mining methods
CN110671110A (en) Extravenous mining and exploration mining combined concealed broken residual ore mining structure and mining method thereof
CN103742144A (en) Ore loss and dilution control method and application thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20151111