CN105021923B CN201510404846.6A CN201510404846A CN105021923B CN 105021923 B CN105021923 B CN 105021923B CN 201510404846 A CN201510404846 A CN 201510404846A CN 105021923 B CN105021923 B CN 105021923B
Authority
CN
China
Prior art keywords
new energy
power station
time
energy power
moment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510404846.6A
Other languages
Chinese (zh)
Other versions
CN105021923A (en
Inventor
柳玉
白恺
吴宇辉
刘京波
刘晓鹏
宋鹏
张扬帆
任巍曦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
STATE GRID XINYUAN ZHANGJIAKOU SCENERY STORAGE DEMONSTRATION POWER PLANT CO Ltd
State Grid Corp of China SGCC
North China Electric Power Research Institute Co Ltd
Electric Power Research Institute of State Grid Jibei Electric Power Co Ltd
Original Assignee
STATE GRID XINYUAN ZHANGJIAKOU SCENERY STORAGE DEMONSTRATION POWER PLANT CO Ltd
State Grid Corp of China SGCC
North China Electric Power Research Institute Co Ltd
Electric Power Research Institute of State Grid Jibei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by STATE GRID XINYUAN ZHANGJIAKOU SCENERY STORAGE DEMONSTRATION POWER PLANT CO Ltd, State Grid Corp of China SGCC, North China Electric Power Research Institute Co Ltd, Electric Power Research Institute of State Grid Jibei Electric Power Co Ltd filed Critical STATE GRID XINYUAN ZHANGJIAKOU SCENERY STORAGE DEMONSTRATION POWER PLANT CO Ltd
Priority to CN201510404846.6A priority Critical patent/CN105021923B/en
Publication of CN105021923A publication Critical patent/CN105021923A/en
Application granted granted Critical
Publication of CN105021923B publication Critical patent/CN105021923B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention provides a kind of test system and method for the control performance of new energy power station, it is related to technical field of new energy power generation.The system includes a new energy power station centralized monitoring system;New energy power station centralized monitoring system is connected with the first test equipment;New energy power station centralized monitoring system is connected with host exchange, and host exchange is connected with many sub- switch communications respectively by optical fiber;Each sub- interchanger is connected with new energy unit to be tested;New energy unit to be tested is connected with the second test equipment;First test equipment and the second test equipment are connected with time dissemination system.Each unit is tested using cloth test equipment is punished in new energy unit to be measured, ensure that the markers at each test equipment is synchronous by time dissemination system simultaneously, can avoid it is current the need for the point tested it is in larger distance to each other, it is difficult to the problem of testing the control performance of new energy power station.

Description

The test system and method for the control performance of new energy power station
Technical field
The present invention relates to technical field of new energy power generation, more particularly to a kind of test system of the control performance of new energy power station System and method.
Background technology
At present, new energy power station is quickly grown.New energy power station generally comprises wind power plant, photovoltaic plant etc..With new The development in energy power station, some new energy power station problem encountered also gradually show.
For example, currently for the Control performance standard of the unit in new energy power station and new energy power station, current techniques Also it is difficult to measure.Its reason is that controlled device (such as each new energy unit) quantity of new energy power station is more, and arrangement is excessively divided Dissipate, the instruction issuing place of new energy power station is general at new energy monitoring system, and new energy power station entirety is active/idle Measuring point at electrical secondary equipment, the test point of new energy unit in Wind turbines on the spot.Currently, each test point to each other may It is in larger distance apart from 1km to 20km, it is difficult to which that the control performance of new energy power station is tested.
The content of the invention
Embodiments of the invention provide a kind of test system and method for the control performance of new energy power station, current to solve The problem of being difficult to test the control performance of new energy power station.
To reach above-mentioned purpose, the present invention is adopted the following technical scheme that:
A kind of test system of the control performance of new energy power station, including a new energy power station centralized monitoring system;It is described New energy power station centralized monitoring system is connected with the first test equipment;The new energy power station centralized monitoring system and host exchange Connection, the host exchange is connected with many sub- switch communications respectively by optical fiber;Each sub- interchanger is connected with to be tested New energy unit;The new energy unit to be tested is connected with the second test equipment;First test equipment and second is surveyed Examination equipment is connected with time dissemination system.
Further, the host exchange also communicates to connect monitoring system of electric substation;The monitoring system of electric substation also divides Voltage transformer summation current transformer is not connected with;The voltage transformer is connected new energy power station master with current transformer respectively Transformer high-voltage side outlet, and the voltage transformer is connected one the 3rd test equipment with current transformer respectively;Described Three test equipments are connected with the time dissemination system.
Specifically, first test equipment, the second test equipment and the 3rd test equipment are oscillograph.
Specifically, the time dissemination system is aeronautical satellite timing and range-measurement system or global positioning system, or GLONASS GPS, either Beidou satellite navigation and positioning system or television clocks system, or OMEGA clock systems.
A kind of method of testing of the control performance of new energy power station, the control performance applied to above-mentioned new energy power station Test system, methods described includes:
Time service is carried out to the first test equipment and the second test equipment according to time dissemination system;
When new energy power station centralized monitoring system sends unit instruction to one or more new energy unit to be tested, root Send instructions the moment under being determined according to the first test equipment;The unit instruction includes active power instruction, reactive power instruction;
When new energy unit to be tested receives the active power instruction, reactive power instruction, surveyed according to second Examination equipment determines that each new energy unit to be tested receives the instruction moment, and the reception is referred to by second test equipment Make the reactive power in moment, the active power in active power instruction and reactive power instruction carry out recording, form recording letter Breath;The wave-record chart includes the markers of each response curve and second test equipment, wherein each second test equipment Markers it is identical;
According to send instructions under described moment and the wave-record chart, determine the new energy power station centralized monitoring system to each The Control performance standard of new energy unit to be tested.
Specifically, it is described according to send instructions under described moment and the wave-record chart, determine that the new energy power station is concentrated Monitoring system to the Control performance standard of each new energy unit to be tested, including:
According to it is described receive instruct the moment and it is described under send instructions and determine the new energy power station centralized monitoring system constantly With the communication time of new energy unit to be tested;Wherein, the communication time receives the instruction moment and described issued to be described Instruct the difference at moment.
Further, it is described according to send instructions under described moment and the wave-record chart, determine the new energy power station collection Middle monitoring system to the Control performance standard of each new energy unit to be tested, in addition to:
According to the response curve, the steady-state value of the response curve, initial value, maximum overshoot, time to peak are determined And each rise time index;Wherein, the maximum overshoot is the maximum that the response curve deviates the steady-state value;Institute State time to peak for the response curve from the initial value to the time of first peak value of response curve;
Each rise time index includes:First rise time, the second rise time, on the 3rd rise time and the 4th The time of liter;
First rise time be the response curve from the initial value for the first time rise to the steady-state value when Between;
Second rise time is that the response curve rises to the steady-state value for the first time from the initial value 90% time;
3rd rise time is that the response curve rises to the stable state from 10% first time of the steady-state value 90% time of value;
4th rise time is that the response curve rises to the steady-state value from 5% first time of the steady-state value 95% time.
Further, it is described according to send instructions under described moment and the wave-record chart, determine the new energy power station collection Middle monitoring system to the Control performance standard of each new energy unit to be tested, in addition to:
According to second rise time and it is described under send instructions and determine the sound of the new energy unit to be tested constantly Between seasonable;The response time is second rise time and the difference at moment that sends instructions under described.
Further, it is described according to send instructions under described moment and the wave-record chart, determine the new energy power station collection Middle monitoring system to the Control performance standard of each new energy unit to be tested, in addition to:
It is interval according to the steady-state error that the response curve, the steady-state value and one pre-set, determine that a unit is adjusted Moment in place;The moment is that the response curve enters steady-state error interval and no longer beyond described in place for the unit regulation When steady-state error is interval, at the time of the interval point of first entrance steady-state error is corresponding;
According to unit regulation in place the moment and it is described under send instructions and determine the new energy unit to be tested constantly Regulating time;The regulating time is that the unit adjusts the moment in place and the difference at the moment that sends instructions under described.
Specifically, the method for testing of the control performance of the new energy power station, in addition to:
Time service is carried out to the first test equipment and the 3rd test equipment according to time dissemination system;
When new energy power station centralized monitoring system sends power station instruction to equipment between new energy power station electric secondary, according to First test equipment sends instructions the moment under determining;The power station instruction includes active power instruction, reactive power instruction;It is described new Equipment includes voltage transformer summation current transformer between the electric secondary of energy power station;
When equipment receives the active power instruction, reactive power instruction between new energy power station electric secondary, according to Equipment receives the instruction moment between 3rd test equipment determines new energy power station electric secondary, and passes through the 3rd test equipment pair The reactive power received in instruction moment, the active power in active power instruction and reactive power instruction carries out recording, Form wave-record chart;The wave-record chart includes the markers of response curve and the 3rd test equipment;
According to send instructions under described moment and the wave-record chart, determine the new energy power station centralized monitoring system to new The Control performance standard in energy power station.
In addition, this determines the new energy power station Centralized Monitoring according to send instructions under described moment and the wave-record chart System to the Control performance standard of new energy power station, including:
According to the response curve, the steady-state value of the response curve, initial value, maximum overshoot, time to peak are determined And each rise time index;Wherein, the maximum overshoot is the maximum that the response curve deviates the steady-state value;Institute State time to peak for the response curve from the initial value to the time of first peak value of response curve;
Each rise time index includes:First rise time, the second rise time, on the 3rd rise time and the 4th The time of liter;
First rise time be the response curve from the initial value for the first time rise to the steady-state value when Between;
Second rise time is that the response curve rises to the steady-state value for the first time from the initial value 90% time;
3rd rise time is that the response curve rises to the stable state from 10% first time of the steady-state value 90% time of value;
4th rise time is that the response curve rises to the steady-state value from 5% first time of the steady-state value 95% time.
Further, it is described according to send instructions under described moment and the wave-record chart, determine the new energy power station collection Middle monitoring system to the Control performance standard of new energy power station, in addition to:
According to second rise time and it is described under send instructions and determine to set between the new energy power station electric secondary constantly The standby response time;Equipment is second rise time and sent instructions the moment under described between the new energy power station electric secondary Difference.
Further, it is described according to send instructions under described moment and the wave-record chart, determine the new energy power station collection Middle monitoring system to the Control performance standard of new energy power station, in addition to:
It is interval according to the steady-state error that the response curve, the steady-state value and one pre-set, determine new energy electricity Stand and adjust the moment in place;New energy power station regulation in place the moment be the response curve enter the steady-state error it is interval and When no longer beyond steady-state error interval, at the time of the interval point of first entrance steady-state error is corresponding;
According to new energy power station regulation in place the moment and it is described under send instructions and determine new energy power station electricity constantly The regulating time of secondary equipment of gas;The regulating time is that the new energy power station adjusts the moment in place and sent instructions under described The difference at moment.
The test system and method for the control performance of new energy power station provided in an embodiment of the present invention, the new energy power station The test system of control performance, including a new energy power station centralized monitoring system;New energy power station centralized monitoring system and first Test equipment is connected;New energy power station centralized monitoring system is connected with host exchange, host exchange by optical fiber respectively with it is multiple Sub- switch communication connection;Each sub- interchanger is connected with new energy unit to be tested;New energy unit to be tested and second Test equipment is connected;First test equipment and the second test equipment are connected with time dissemination system.Using in new energy unit to be measured Locate distribution test equipment to test each unit, while ensureing that the markers at each test equipment is same by time dissemination system Step, the point tested the need for can avoiding currently is in larger distance to each other, it is difficult to which the control performance of new energy power station is surveyed The problem of examination.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the accompanying drawing used required in technology description to be briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, without having to pay creative labor, may be used also To obtain other accompanying drawings according to these accompanying drawings.
Fig. 1 is a kind of structural representation of the test system of the control performance of new energy power station provided in an embodiment of the present invention Figure;
Fig. 2 is a kind of flow chart one of the method for testing of the control performance of new energy power station provided in an embodiment of the present invention;
Fig. 3 is a kind of flowchart 2 of the method for testing of the control performance of new energy power station provided in an embodiment of the present invention;
Fig. 4 is a kind of flow chart 3 of the method for testing of the control performance of new energy power station provided in an embodiment of the present invention;
Fig. 5 is the response curve schematic diagram in the embodiment of the present invention.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made Embodiment, belongs to the scope of protection of the invention.
As shown in figure 1, a kind of test system of the control performance of new energy power station provided in an embodiment of the present invention, including one New energy power station centralized monitoring system 101;New energy power station centralized monitoring system 101 is connected with the first test equipment 102;New energy Source power station centralized monitoring system 101 is connected with host exchange 103, and the host exchange 103 is exchanged with many height respectively by optical fiber Machine 104 is communicated to connect;Each sub- interchanger 104 is connected with new energy unit 105 to be tested;New energy unit 105 to be tested It is connected with the second test equipment 106;First test equipment 102 and the second test equipment 106 are connected with time dissemination system 107.
In addition, the new energy power station centralized monitoring system 101 is connected with host exchange 103 and can connected by netting twine.
Further, as shown in figure 1, the host exchange 103 also communicates to connect monitoring system of electric substation 108;Transformer station supervises Control system 108 has been also respectively connected with the summation current transformer 110 of voltage transformer 109;Voltage transformer 109 and current transformer 110 connection new energy power station main transformer high pressure side outlets 111, and 110 points of voltage transformer 109 and current transformer respectively Lian Jie not one the 3rd test equipment 112;3rd test equipment 112 is also connected with time dissemination system 107.
What deserves to be explained is, first test equipment 102, the second test equipment 106 and the 3rd test equipment 112 can be Oscillograph.First test equipment 102 can be located at new energy power station master control room, and the second test equipment 106 can be located at new energy On the spot, the 3rd test equipment 112 can be located between the secondary device of new energy power station unit.
In addition, the time dissemination system 107 in the embodiment of the present invention can be that aeronautical satellite timing and range-measurement system or the whole world are fixed Position system, either GLONASS GPSs or Beidou satellite navigation and positioning system, or television clocks system, Or OMEGA clock systems etc..
In the present embodiment, new energy unit to be tested can have multiple, be not limited solely to the quantity shown in Fig. 1.
In addition, can be to the first test equipment 102, the second test equipment 106 and the 3rd test equipment by time dissemination system Time service is carried out at 112, time service error is generally less than 1ms.
In embodiments of the present invention, the new energy power station centralized monitoring system can not directly control each new energy unit, Can also dispose second control system in the test system of the control performance of new energy power station provided in an embodiment of the present invention, The second control system is controlled by new energy power station centralized monitoring system, and new energy power station concentration is received by second control system The instruction of monitoring system, and send an instruction to each new energy unit.
The test system of the control performance of new energy power station provided in an embodiment of the present invention, the controlling of the new energy power station The test system of energy, including a new energy power station centralized monitoring system;New energy power station centralized monitoring system is set with the first test Standby connection;New energy power station centralized monitoring system is connected with host exchange, and host exchange is exchanged with many height respectively by optical fiber Machine is communicated to connect;Each sub- interchanger is connected with new energy unit to be tested;New energy unit to be tested is set with the second test Standby connection;First test equipment and the second test equipment are connected with time dissemination system.Cloth is punished using in new energy unit to be measured Test equipment is tested each unit, while ensure that the markers at each test equipment is synchronous by time dissemination system, can The point tested the need for avoiding currently is in larger distance to each other, it is difficult to asking that the control performance of new energy power station is tested Topic.
Corresponding to the test system of the control performance of the new energy power station corresponding to Fig. 1, as shown in Fig. 2 the present invention is implemented Example provides a kind of method of testing of the control performance of new energy power station, the controlling applied to the new energy power station in above-mentioned Fig. 1 The test system of energy, method includes:
Step 201, time service carried out to the first test equipment and the second test equipment according to time dissemination system.
Step 202, in new energy power station centralized monitoring system to one or more new energy unit to be tested send unit During instruction, send instructions the moment under being determined according to the first test equipment.
Wherein, unit instruction includes active power instruction, reactive power instruction.
Step 203, when new energy unit to be tested receives active power instruction, reactive power instruction, according to the Two test equipments determine that each new energy unit to be tested receives the instruction moment, and when being instructed by the second test equipment to receiving Carve, the active power in active power instruction and the reactive power in reactive power instruction carry out recording, form wave-record chart.
Wherein, the wave-record chart includes the markers of each response curve and the second test equipment, wherein each second test equipment Markers it is identical.
Send instructions moment and wave-record chart under step 204, basis, determines new energy power station centralized monitoring system to each to be measured The Control performance standard of the new energy unit of examination.
The method of testing of the control performance of new energy power station provided in an embodiment of the present invention, by new energy unit to be measured Locate distribution test equipment to test each unit, while ensureing that the markers at each test equipment is same by time dissemination system Step, the point tested the need for can avoiding currently is in larger distance to each other, it is difficult to which the control performance of new energy power station is surveyed The problem of examination.
In order that those skilled in the art is better understood by the present invention, a more detailed embodiment is set forth below, As shown in figure 3, the method for testing of the control performance of new energy power station provided in an embodiment of the present invention, including:
Step 301, time service carried out to the first test equipment and the second test equipment according to time dissemination system.
Step 302, in new energy power station centralized monitoring system to one or more new energy unit to be tested send unit During instruction, send instructions the moment under being determined according to the first test equipment.
Wherein, unit instruction includes active power instruction, reactive power instruction.
Step 303, when new energy unit to be tested receives active power instruction, reactive power instruction, according to the Two test equipments determine that each new energy unit to be tested receives the instruction moment, and when being instructed by the second test equipment to receiving Carve, the active power in active power instruction and the reactive power in reactive power instruction carry out recording, form wave-record chart.
Wherein, the wave-record chart includes the markers of each response curve and the second test equipment, wherein each second test equipment Markers it is identical.
Step 304, according to receive instruction the moment and under send instructions constantly determine new energy power station centralized monitoring system with treating The communication time of the new energy unit of test.
Wherein, the communication time is to receive the difference for instructing the moment to send instructions the moment with.
Step 305, according to response curve, determine the steady-state value of response curve, initial value, maximum overshoot, time to peak And each rise time index.
Wherein, the response curve can be as shown in Figure 5:
Wherein, maximum overshoot is the σ in the maximum that response curve deviates steady-state value, such as Fig. 5pValue;Time to peak is T in the time of response curve first peak value from initial value to response curve, such as Fig. 5pValue.
Each rise time index can include:First rise time, the second rise time, on the 3rd rise time and the 4th The time of liter.
First rise time was the time that response curve rises to steady-state value from initial value for the first time.
Second rise time was 90% time that response curve rises to steady-state value from initial value for the first time.
3rd rise time was 90% time that response curve rises to steady-state value from 10% first time of steady-state value, such as T in Fig. 5rValue.
4th rise time was 95% time that response curve rises to steady-state value from 5% first time of steady-state value.
Step 306, according to the second rise time and under send instructions the response for determining new energy unit to be tested constantly when Between.
Wherein, the response time be the second rise time and under send instructions the difference at moment.
Step 307, the steady-state error interval pre-set according to response curve, steady-state value and one, determine that a unit is adjusted Moment in place.
Wherein, the moment is that response curve enters steady-state error interval and no longer exceeds steady-state error area in place for unit regulation Between when, first at the time of enter steady-state error interval point correspondence, such as t in Fig. 5sValue.The stable state pre-set is missed It is poor interval for ± 0.02 or ± 0.05.
Step 308, according to unit regulation in place the moment and under send instructions and determine the tune of new energy unit to be tested constantly The section time.
Wherein, regulating time be unit adjust the moment in place and under send instructions the difference at moment.
In addition, as shown in figure 4, the method for testing of the control performance of new energy power station provided in an embodiment of the present invention can be with Carry out:
Step 401, time service carried out to the first test equipment and the 3rd test equipment according to time dissemination system.
Step 402, new energy power station centralized monitoring system between new energy power station electric secondary equipment send power station refer to When making, send instructions the moment under being determined according to the first test equipment.
Power station instruction includes active power instruction, reactive power instruction;Equipment includes between new energy power station electric secondary Voltage transformer summation current transformer.
Step 403, between new energy power station electric secondary equipment receive active power instruction, reactive power instruction when, Equipment receives the instruction moment between determining new energy power station electric secondary according to the 3rd test equipment, and passes through the 3rd test equipment pair The reactive power received in instruction moment, the active power in active power instruction and reactive power instruction carries out recording, is formed Wave-record chart.
Wherein, the wave-record chart includes the markers of response curve and the 3rd test equipment.
Step 404, according to response curve, determine the steady-state value of response curve, initial value, maximum overshoot, time to peak And each rise time index.
Wherein, the response curve can be as shown in Figure 5:
Wherein, maximum overshoot is the σ in the maximum that response curve deviates steady-state value, such as Fig. 5pValue;Time to peak is T in the time of response curve first peak value from initial value to response curve, such as Fig. 5pValue.
Each rise time index can include:First rise time, the second rise time, the 3rd rise time and the 4th Rise time;
First rise time was the time that response curve rises to steady-state value from initial value for the first time;
Second rise time was 90% time that response curve rises to steady-state value from initial value for the first time;
3rd rise time was 90% time that response curve rises to steady-state value from 10% first time of steady-state value, such as T in Fig. 5rValue.;
4th rise time was 95% time that response curve rises to steady-state value from 5% first time of steady-state value.
Step 405, according to the second rise time and under send instructions and determine equipment between new energy power station electric secondary constantly Response time.
Wherein, between the new energy power station electric secondary equipment be the second rise time and under send instructions the difference at moment.
Step 406, the steady-state error interval pre-set according to response curve, steady-state value and one, determine new energy electricity Stand and adjust the moment in place.
Wherein, the moment is that response curve enters steady-state error interval and no longer missed beyond stable state in place for new energy power station regulation When poor interval, at the time of first point for entering steady-state error interval is corresponding, such as the t in Fig. 5sValue.
Step 407, according to new energy power station regulation in place the moment and under send instructions constantly determine new energy power station electric two The regulating time of equipment between secondary.
Wherein, the regulating time be new energy power station adjust the moment in place and under send instructions the difference at moment.
The method of testing of the control performance of new energy power station provided in an embodiment of the present invention, by new energy unit to be measured Locate distribution test equipment to test each unit, while ensureing that the markers at each test equipment is same by time dissemination system Step, the point tested the need for can avoiding currently is in larger distance to each other, it is difficult to which the control performance of new energy power station is surveyed The problem of examination.
It should be understood by those skilled in the art that, embodiments of the invention can be provided as method, system or computer program Product.Therefore, the present invention can be using the reality in terms of complete hardware embodiment, complete software embodiment or combination software and hardware Apply the form of example.Moreover, the present invention can be used in one or more computers for wherein including computer usable program code The computer program production that usable storage medium is implemented on (including but is not limited to magnetic disk storage, CD-ROM, optical memory etc.) The form of product.
The present invention is the flow with reference to method according to embodiments of the present invention, equipment (system) and computer program product Figure and/or block diagram are described.It should be understood that can be by every first-class in computer program instructions implementation process figure and/or block diagram Journey and/or the flow in square frame and flow chart and/or block diagram and/or the combination of square frame.These computer programs can be provided The processor of all-purpose computer, special-purpose computer, Embedded Processor or other programmable data processing devices is instructed to produce A raw machine so that produced by the instruction of computer or the computing device of other programmable data processing devices for real The device for the function of being specified in present one flow of flow chart or one square frame of multiple flows and/or block diagram or multiple square frames.
These computer program instructions, which may be alternatively stored in, can guide computer or other programmable data processing devices with spy Determine in the computer-readable memory that mode works so that the instruction being stored in the computer-readable memory, which is produced, to be included referring to Make the manufacture of device, the command device realize in one flow of flow chart or multiple flows and/or one square frame of block diagram or The function of being specified in multiple square frames.
These computer program instructions can be also loaded into computer or other programmable data processing devices so that in meter Series of operation steps is performed on calculation machine or other programmable devices to produce computer implemented processing, thus in computer or The instruction performed on other programmable devices is provided for realizing in one flow of flow chart or multiple flows and/or block diagram one The step of function of being specified in individual square frame or multiple square frames.
Apply specific embodiment in the present invention to be set forth the principle and embodiment of the present invention, above example Explanation be only intended to help to understand the method and its core concept of the present invention;Simultaneously for those of ordinary skill in the art, According to the thought of the present invention, it will change in specific embodiments and applications, in summary, in this specification Appearance should not be construed as limiting the invention.

Claims (9)

1. a kind of method of testing of the control performance of new energy power station, it is characterised in that applied to a kind of control of new energy power station The test system of performance processed, including a new energy power station centralized monitoring system;The new energy power station centralized monitoring system and the One test equipment is connected;The new energy power station centralized monitoring system is connected with host exchange, and the host exchange passes through optical fiber It is connected respectively with many sub- switch communications;Each sub- interchanger is connected with new energy unit to be tested;It is described to be tested new Energy unit is connected with the second test equipment;First test equipment and the second test equipment are connected with time dissemination system;Institute State host exchange and also communicate to connect monitoring system of electric substation;The monitoring system of electric substation be also respectively connected with voltage transformer and Current transformer;The voltage transformer is connected new energy power station main transformer high pressure side outlet with current transformer respectively, and And the voltage transformer is connected one the 3rd test equipment with current transformer respectively;3rd test equipment and the time service System is connected;First test equipment, the second test equipment and the 3rd test equipment are oscillograph;The time dissemination system is to lead Boat timing by satellite and range-measurement system or global positioning system, either GLONASS GPSs or big-dipper satellite are led Navigate alignment system, either television clocks system or OMEGA clock systems;
Methods described includes:
Time service is carried out to the first test equipment and the second test equipment according to time dissemination system;
When new energy power station centralized monitoring system sends unit instruction to one or more new energy unit to be tested, according to the One test equipment sends instructions the moment under determining;The unit instruction includes active power instruction, reactive power instruction;
When new energy unit to be tested receives the active power instruction, reactive power instruction, set according to the second test It is standby to determine that each new energy unit to be tested receives the instruction moment, and when being instructed by second test equipment to the reception Carve, the active power in active power instruction and the reactive power in reactive power instruction carry out recording, form wave-record chart;Institute Markers of the wave-record chart including each response curve and second test equipment is stated, wherein the markers of each second test equipment It is identical;
According to send instructions under described moment and the wave-record chart, determine the new energy power station centralized monitoring system to each to be measured The Control performance standard of the new energy unit of examination.
2. the method for testing of the control performance of new energy power station according to claim 1, it is characterised in that described according to institute Send instructions moment and the wave-record chart are stated down, determines the new energy power station centralized monitoring system to each new energy to be tested The Control performance standard of unit, including:
According to it is described receive instruct the moment and it is described under send instructions and determine the new energy power station centralized monitoring system with treating constantly The communication time of the new energy unit of test;Wherein, the communication time is that described receive instructs the moment and sent instructions under described The difference at moment.
3. the method for testing of the control performance of new energy power station according to claim 2, it is characterised in that described according to institute Send instructions moment and the wave-record chart are stated down, determines the new energy power station centralized monitoring system to each new energy to be tested The Control performance standard of unit, in addition to:
According to the response curve, determine the steady-state value of the response curve, initial value, maximum overshoot, time to peak and Each rise time index;Wherein, the maximum overshoot is the maximum that the response curve deviates the steady-state value;The peak The value time is the response curve from the initial value to the time of first peak value of response curve;
Each rise time index includes:When first rise time, the second rise time, the 3rd rise time and the 4th rise Between;
First rise time is the time that the response curve rises to the steady-state value from the initial value for the first time;
Second rise time is that the response curve rises to the 90% of the steady-state value from the initial value for the first time Time;
3rd rise time is that the response curve rises to the steady-state value from 10% first time of the steady-state value 90% time;
4th rise time is that the response curve rises to the steady-state value from 5% first time of the steady-state value 95% time.
4. the method for testing of the control performance of new energy power station according to claim 3, it is characterised in that described according to institute Send instructions moment and the wave-record chart are stated down, determines the new energy power station centralized monitoring system to each new energy to be tested The Control performance standard of unit, in addition to:
According to second rise time and it is described under send instructions the response for determining the new energy unit to be tested constantly when Between;The response time is second rise time and the difference at moment that sends instructions under described.
5. the method for testing of the control performance of new energy power station according to claim 3, it is characterised in that described according to institute Send instructions moment and the wave-record chart are stated down, determines the new energy power station centralized monitoring system to each new energy to be tested The Control performance standard of unit, in addition to:
It is interval according to the steady-state error that the response curve, the steady-state value and one pre-set, determine unit regulation in place Moment;The moment is that the response curve enters steady-state error interval and no longer exceeds the stable state in place for the unit regulation During error burst, at the time of the interval point of first entrance steady-state error is corresponding;
According to unit regulation in place the moment and it is described under send instructions and determine the tune of the new energy unit to be tested constantly The section time;The regulating time is that the unit adjusts the moment in place and the difference at the moment that sends instructions under described.
6. the method for testing of the control performance of new energy power station according to claim 1, it is characterised in that also include:
Time service is carried out to the first test equipment and the 3rd test equipment according to time dissemination system;
When new energy power station centralized monitoring system sends power station instruction to equipment between new energy power station electric secondary, according to first Test equipment sends instructions the moment under determining;The power station instruction includes active power instruction, reactive power instruction;The new energy Equipment includes voltage transformer summation current transformer between the electric secondary of power station;
When equipment receives the active power instruction, reactive power instruction between new energy power station electric secondary, according to the 3rd Equipment receives the instruction moment between test equipment determines new energy power station electric secondary, and by the 3rd test equipment to described The reactive power received in instruction moment, the active power in active power instruction and reactive power instruction carries out recording, is formed Wave-record chart;The wave-record chart includes the markers of response curve and the 3rd test equipment;
According to send instructions under described moment and the wave-record chart, determine the new energy power station centralized monitoring system to new energy The Control performance standard in power station.
7. the method for testing of the control performance of new energy power station according to claim 6, it is characterised in that described according to institute Send instructions moment and the wave-record chart are stated down, control of the new energy power station centralized monitoring system to new energy power station is determined Performance indications, including:
According to the response curve, determine the steady-state value of the response curve, initial value, maximum overshoot, time to peak and Each rise time index;Wherein, the maximum overshoot is the maximum that the response curve deviates the steady-state value;The peak The value time is the response curve from the initial value to the time of first peak value of response curve;
Each rise time index includes:When first rise time, the second rise time, the 3rd rise time and the 4th rise Between;
First rise time is the time that the response curve rises to the steady-state value from the initial value for the first time;
Second rise time is that the response curve rises to the 90% of the steady-state value from the initial value for the first time Time;
3rd rise time is that the response curve rises to the steady-state value from 10% first time of the steady-state value 90% time;
4th rise time is that the response curve rises to the steady-state value from 5% first time of the steady-state value 95% time.
8. the method for testing of the control performance of new energy power station according to claim 7, it is characterised in that described according to institute Send instructions moment and the wave-record chart are stated down, control of the new energy power station centralized monitoring system to new energy power station is determined Performance indications, in addition to:
According to second rise time and it is described under send instructions and determine equipment between the new energy power station electric secondary constantly Response time;Equipment is second rise time and sent instructions the moment under described between the new energy power station electric secondary Difference.
9. the method for testing of the control performance of new energy power station according to claim 7, it is characterised in that described according to institute Send instructions moment and the wave-record chart are stated down, control of the new energy power station centralized monitoring system to new energy power station is determined Performance indications, in addition to:
It is interval according to the steady-state error that the response curve, the steady-state value and one pre-set, determine that a new energy power station is adjusted Save the moment in place;To be that the response curve enters the steady-state error interval and no longer the moment in place for new energy power station regulation During beyond steady-state error interval, at the time of the interval point of first entrance steady-state error is corresponding;
According to new energy power station regulation in place the moment and it is described under send instructions and determine the new energy power station electric two constantly The regulating time of equipment between secondary;The regulating time is that the new energy power station adjusts the moment in place and sent instructions the moment under described Difference.
CN201510404846.6A 2015-07-10 2015-07-10 The test system and method for the control performance of new energy power station Active CN105021923B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510404846.6A CN105021923B (en) 2015-07-10 2015-07-10 The test system and method for the control performance of new energy power station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510404846.6A CN105021923B (en) 2015-07-10 2015-07-10 The test system and method for the control performance of new energy power station

Publications (2)

Publication Number Publication Date
CN105021923A CN105021923A (en) 2015-11-04
CN105021923B true CN105021923B (en) 2017-08-11

Family

ID=54412037

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510404846.6A Active CN105021923B (en) 2015-07-10 2015-07-10 The test system and method for the control performance of new energy power station

Country Status (1)

Country Link
CN (1) CN105021923B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108445862A (en) * 2018-02-06 2018-08-24 国网江西省电力有限公司电力科学研究院 A kind of test system and method for new energy power station control performance

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102043115A (en) * 2010-11-02 2011-05-04 深圳市双合电气股份有限公司 Network on-line live line measurement method for line parameter of power system
CN102175934A (en) * 2011-01-13 2011-09-07 上海自动化仪表股份有限公司 Data collection method of wave recording module
CN102510131A (en) * 2011-11-03 2012-06-20 四川电力科学研究院 Method and device for testing overall performance of intelligent transformer substation
CN102751737A (en) * 2012-05-14 2012-10-24 中国电力科学研究院 Method for simulating and analyzing automatic generation control of electrical power system containing wind power
CN102759920A (en) * 2012-07-10 2012-10-31 中国电力科学研究院 Wind farm AGC (auto gain control) functional test system and test method thereof
CN102901881A (en) * 2011-07-26 2013-01-30 上海市电力公司 On-site debugging method for digital substation
CN102937685A (en) * 2012-12-11 2013-02-20 上海市电力公司 Real-time simulation technique-based integrated testing platform for substation
CN203166626U (en) * 2012-12-27 2013-08-28 天津凯发电气股份有限公司 Intelligent traction substation
CN103605360A (en) * 2013-12-02 2014-02-26 国家电网公司 System and method for testing wind farm power control strategy
CN103675526A (en) * 2013-11-19 2014-03-26 广东电网公司电力调度控制中心 Prudential sub-station test system
CN103762620A (en) * 2013-05-10 2014-04-30 南京南瑞集团公司 New-energy connected-grid power control method based on prediction and adjustment performance and safety constraint
CN203630311U (en) * 2013-09-03 2014-06-04 郭红 Wind turbine generator electric energy quality data collection system based on wireless sensing technology
CN104505856A (en) * 2014-12-17 2015-04-08 北京四方继保自动化股份有限公司 Photovoltaic power optimization control system
CN104502753A (en) * 2014-12-15 2015-04-08 国家电网公司 Networked on-line real-time analysis system for electric power fault recording device and application of system
CN104579839A (en) * 2015-01-05 2015-04-29 广州至德电力科技有限公司 Transformer substation communication network state online monitoring system and method
CN204789810U (en) * 2015-07-10 2015-11-18 华北电力科学研究院有限责任公司 Control performance's in new forms of energy power station test system

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09222445A (en) * 1996-02-19 1997-08-26 Hitachi Ltd Monitoring and control device of power system, and oscillographed waveform data collection method

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102043115A (en) * 2010-11-02 2011-05-04 深圳市双合电气股份有限公司 Network on-line live line measurement method for line parameter of power system
CN102175934A (en) * 2011-01-13 2011-09-07 上海自动化仪表股份有限公司 Data collection method of wave recording module
CN102901881A (en) * 2011-07-26 2013-01-30 上海市电力公司 On-site debugging method for digital substation
CN102510131A (en) * 2011-11-03 2012-06-20 四川电力科学研究院 Method and device for testing overall performance of intelligent transformer substation
CN102751737A (en) * 2012-05-14 2012-10-24 中国电力科学研究院 Method for simulating and analyzing automatic generation control of electrical power system containing wind power
CN102759920A (en) * 2012-07-10 2012-10-31 中国电力科学研究院 Wind farm AGC (auto gain control) functional test system and test method thereof
CN102937685A (en) * 2012-12-11 2013-02-20 上海市电力公司 Real-time simulation technique-based integrated testing platform for substation
CN203166626U (en) * 2012-12-27 2013-08-28 天津凯发电气股份有限公司 Intelligent traction substation
CN103762620A (en) * 2013-05-10 2014-04-30 南京南瑞集团公司 New-energy connected-grid power control method based on prediction and adjustment performance and safety constraint
CN203630311U (en) * 2013-09-03 2014-06-04 郭红 Wind turbine generator electric energy quality data collection system based on wireless sensing technology
CN103675526A (en) * 2013-11-19 2014-03-26 广东电网公司电力调度控制中心 Prudential sub-station test system
CN103605360A (en) * 2013-12-02 2014-02-26 国家电网公司 System and method for testing wind farm power control strategy
CN104502753A (en) * 2014-12-15 2015-04-08 国家电网公司 Networked on-line real-time analysis system for electric power fault recording device and application of system
CN104505856A (en) * 2014-12-17 2015-04-08 北京四方继保自动化股份有限公司 Photovoltaic power optimization control system
CN104579839A (en) * 2015-01-05 2015-04-29 广州至德电力科技有限公司 Transformer substation communication network state online monitoring system and method
CN204789810U (en) * 2015-07-10 2015-11-18 华北电力科学研究院有限责任公司 Control performance's in new forms of energy power station test system

Also Published As

Publication number Publication date
CN105021923A (en) 2015-11-04

Similar Documents

Publication Publication Date Title
US9784799B2 (en) Multi-node synchronous on-site test method
CN101105520B (en) Generating set primary frequency regulation test method and emulating instrument for test
CN105958654B (en) A kind of line loss per unit method for real-time monitoring and system
KR20180090805A (en) Testing and control device, system and method for wind power plant
CN107741549A (en) The intelligent substation synchronism tester synchronously occurred based on analog quantity and digital quantity
CN104217127A (en) PMU (Power Management Unit) dynamic data simulation generating method
CN108964280A (en) A kind of automation of transformation substations equipment remote detecting system and method
CN110501667B (en) Test system and ground test method of ultrashort wave orientation instrument
CN106786565B (en) Meter and the electric network safety steady cooperativeness control method of virtual synchronous generator access
CN105954700A (en) Electronic mutual inductor temperature characteristic test system and test method
CN102136735B (en) Device for monitoring leading phase operation stability of generator and working method thereof
CN110187270A (en) Active primary frequency modulation Online Transaction Processing and method based on WAMS
CN105847076B (en) Signal testing system, method and device for substation control level equipment of transformer substation
CN103592531B (en) A kind of parameter detection method of wind energy turbine set static reacance generator and system
CN111123186A (en) Device and method for testing broadband characteristics of optical fiber current sensor
CN105021923B (en) The test system and method for the control performance of new energy power station
CN109586272A (en) A kind of generation method and system of power grid continuous operation emulation section
KR20100037317A (en) Multiple facts control system and method therefor
CN112799373A (en) New energy power station power control system test platform and method
CN116404680A (en) Rapid coordination control method and system for large-scale energy storage transformer substation
CN105305959A (en) Photovoltaic property intelligent detection system
Kezunovic Verifying interoperability and application performance of PMUs and PMU-enabled IEDs at the device and system level
CN106053986B (en) A kind of test method of alternating current filter switching strategy
CN113452035B (en) Frequency modulation control method, frequency modulation control device, frequency modulation control storage medium, and frequency modulation control program product
CN109298705A (en) A kind of digitlization measure and control device off-line checking system and method based on combining unit

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant