CN105019666B - Installation method of the last section of vestibule connected with blast furnace - Google Patents
Installation method of the last section of vestibule connected with blast furnace Download PDFInfo
- Publication number
- CN105019666B CN105019666B CN201510441732.9A CN201510441732A CN105019666B CN 105019666 B CN105019666 B CN 105019666B CN 201510441732 A CN201510441732 A CN 201510441732A CN 105019666 B CN105019666 B CN 105019666B
- Authority
- CN
- China
- Prior art keywords
- corridor
- hoisting
- crawler crane
- last
- height
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Jib Cranes (AREA)
Abstract
一种与高炉连接的最后一节通廊的安装方法,属于高空钢结构安装技术领域。具体安装步骤为:通过最重通廊HJ6选择履带吊、吊车工况及钢丝绳;不变吊车工况反算最不利条件通廊适用性及确定通廊吊点;考虑与高炉连接的通廊吊装时的各种不利因素,改变通廊吊装角度,确定吊车站位及吊车吊装行走路线。该方法是在施工区域利用大型履带吊作业半径、起重量大,使用灵活的特点,综合考虑现场各种不利因素条件进行钢结构施工。优点在于,通过整体吊装思路综合考虑后可以减少大型吊车工况现场组对次数,以及避免了在炉顶框架内对通廊进行二次组对,缩短了工期,节省大型吊装设备的使用费用,提高了施工的安全性及效率。
The invention relates to an installation method of the last corridor connected with a blast furnace, which belongs to the technical field of high-altitude steel structure installation. The specific installation steps are: select crawler crane, crane working condition and steel wire rope through the heaviest corridor HJ6; inversely calculate the applicability of the most unfavorable corridor under the same crane working condition and determine the corridor lifting point; consider the corridor connecting with the blast furnace for hoisting Various unfavorable factors at the time, change the hoisting angle of the corridor, determine the location of the crane station and the hoisting route of the crane. This method utilizes the large-scale crawler crane's operating radius, large lifting capacity, and flexible use characteristics in the construction area, and comprehensively considers various unfavorable factors and conditions on site to carry out steel structure construction. The advantage is that, after comprehensive consideration of the overall hoisting idea, the number of on-site pairings of large cranes can be reduced, and the secondary pairing of corridors in the furnace roof frame is avoided, the construction period is shortened, and the cost of large-scale hoisting equipment is saved. Improve the safety and efficiency of construction.
Description
技术领域technical field
本发明属于高空钢结构安装技术领域,特别是提供了一种与高炉连接的最后一节通廊的安装方法,依照各节通廊整体吊装思路,通过对高炉主皮带各节通廊综合考虑,减少了大型吊车现场工况组对次数,主钢丝绳用量。特别是在施工场地受限,多种因素制约通廊安装的情况。The invention belongs to the technical field of high-altitude steel structure installation, and in particular provides an installation method for the last section of corridor connected to the blast furnace. According to the overall hoisting idea of each section of corridor, through comprehensive consideration of each section of the main belt of the blast furnace, The number of pairing times and the amount of main steel wire ropes for large cranes have been reduced. Especially when the construction site is limited and many factors restrict the installation of corridors.
背景技术Background technique
最后一节通廊插入炉顶框架内的鹰嘴结构件,传统方法是在施工炉顶框架时通廊鹰嘴结构件先吊装进入炉顶框架,待通廊安装就位后再与通廊进行对接。采用整体吊装后其优点在于与高炉连接的最后一节通廊吊装时减少了一次大型吊车工况现场组对次数,避免了在炉顶框架内对通廊进行二次组对,缩短了工期,提高了施工的安全性。The last corridor is inserted into the olecranon structure in the furnace roof frame. The traditional method is to hoist the corridor olecranon structure into the furnace roof frame first when constructing the furnace roof frame, and then connect with the corridor after the corridor is installed in place. butt. The advantage of the overall hoisting is that the number of on-site pairings in the last section of the corridor connected to the blast furnace is reduced, and the second pairing of the corridor in the furnace roof frame is avoided, and the construction period is shortened. Improve the safety of construction.
发明内容Contents of the invention
本发明的目的在于提供一种与高炉连接的最后一节通廊的安装方法,通过对现场各种不利因素及通廊本身的考虑后,提供一种大型钢通廊因场地限制,使用大型吊装设备整体安装通廊的安装法。该方法是在施工区域利用大型履带吊作业半径、起重量大,使用灵活的特点,综合考虑现场各种不利因素条件进行钢结构施工。The purpose of the present invention is to provide an installation method for the last corridor connected to the blast furnace. After considering various unfavorable factors on site and the corridor itself, a large-scale steel corridor is provided. The installation method of the overall installation corridor of the equipment. This method utilizes the large-scale crawler crane's operating radius, large lifting capacity, and flexible use characteristics in the construction area, and comprehensively considers various unfavorable factors and conditions on site to carry out steel structure construction.
本发明采用在一个区域内使用履带吊进行钢结构安装,具体安装步骤如下:The present invention uses a crawler crane to install the steel structure in an area, and the specific installation steps are as follows:
1、通过最重通廊(HJ6)选择履带吊、吊车工况及钢丝绳1. Select crawler cranes, crane working conditions and wire ropes through the heaviest corridor (HJ6)
1)依据最重通廊的重量、安装高度及现场站位条件初步确定起重机械:HJ6钢通廊水平投影长62.878m,安装高度高端57.114m、底端标高45.21m,坡度为10.620°,重180t,选用650履带起重机安装,当工作半径是28m,杆长102m,后配重180t,中央压重40t,超起配重0~300t,超起半径是15m时,额定起重量是213.3t,满足吊装要求。1) Preliminary determination of the hoisting machinery based on the weight of the heaviest corridor, the installation height and site site conditions: the horizontal projection length of the HJ6 steel corridor is 62.878m, the high-end installation height is 57.114m, the bottom elevation is 45.21m, and the slope is 10.620°. The weight is 180t, and the 650 crawler crane is used for installation. When the working radius is 28m, the pole length is 102m, the rear counterweight is 180t, the central ballast is 40t, the superlift counterweight is 0-300t, and the superlift radius is 15m, the rated lifting capacity is 213.3t , to meet the hoisting requirements.
2)依据通廊数据,根据公式:L1=L÷COSθ÷2+h×tgθ÷2(L—通廊长:m,θ—通廊倾角:°,h—通廊高:m,L1—重心点距通廊底端长度:m)计算通廊重心点。2) According to the corridor data, according to the formula: L1=L÷COSθ÷2+h×tgθ÷2(L—corridor length: m, θ—corridor inclination angle: °, h—corridor height: m, L1— The length between the center of gravity point and the bottom end of the corridor: m) Calculate the center of gravity point of the corridor.
3)钢丝绳吊点一般选择位于距通廊重心1/2~1/3处,钢丝绳与水平夹角一般为45°~60°,按照选定的通廊底端钢丝绳吊点及钢丝绳与水平最大夹角用作图法确定钢丝绳长度并计算钢丝绳直径。3) The wire rope lifting point is generally selected to be located at 1/2 to 1/3 from the center of gravity of the corridor, and the angle between the wire rope and the horizontal is generally 45° to 60°. According to the selected wire rope lifting point at the bottom of the corridor and the wire rope and the horizontal maximum The included angle is used graphically to determine the length of the wire rope and to calculate the diameter of the wire rope.
2、不变吊车工况反算最不利条件通廊(与高炉连接的通廊HJ7)适用性及确定通廊吊点2. Back-calculate the applicability of the most unfavorable corridor (corridor HJ7 connected to the blast furnace) under the same crane working condition and determine the corridor lifting point
精确测量现场吊耳尺寸、到场的83mm钢丝绳实际长度、吊装卡环尺寸;根据HJ7各项数据,计算通廊重心;在只考虑正常吊装条件的情况下,采用作图法确定吊钩起升高度并计算钢丝绳直径,确保现场83mm钢丝绳满足要求。作图法一般不能一次就能确定吊钩起升高度满足要求,存在钢丝绳过长问题,需要变更吊点反复作图,用来验算适用性。确定选用650t履带吊工况为102主杆起重性能,工作半径是38m,额定起重量是129t,后配重180t,中央压重40t,超起配重0~300t,钩头最大起升高度为92m。Accurately measure the size of the on-site lifting lug, the actual length of the 83mm steel wire rope on site, and the size of the hoisting snap ring; calculate the center of gravity of the corridor according to the data of HJ7; when only considering the normal hoisting conditions, use the drawing method to determine the lifting height of the hook And calculate the diameter of the steel wire rope to ensure that the 83mm steel wire rope on site meets the requirements. The drawing method generally cannot confirm that the lifting height of the hook meets the requirements at one time. There is a problem that the wire rope is too long. It is necessary to change the lifting point and draw repeatedly to check the applicability. The working condition of the 650t crawler crane is determined to be the lifting performance of the 102 main pole, the working radius is 38m, the rated lifting capacity is 129t, the rear counterweight is 180t, the central pressure is 40t, the superlift counterweight is 0-300t, and the maximum lifting height of the hook head It is 92m.
3、考虑与高炉连接的通廊吊装时的各种不利因素,改变通廊吊装角度,确定吊车站位及吊车吊装行走路线。3. Consider various unfavorable factors during hoisting of the corridor connected to the blast furnace, change the hoisting angle of the corridor, and determine the location of the crane and the hoisting route of the crane.
1)查看现场,确定吊装时不利因素条件:出铁场屋面、ZJ6、64m炉顶框架洞口及除尘管道。1) Check the site and determine the unfavorable factors and conditions during hoisting: casthouse roof, ZJ6, 64m furnace roof frame opening and dust removal pipeline.
2)测量现场影响吊装的实际尺寸、位置及标高:地面标高、出铁场屋面标高、水池标高、ZJ6尺寸及标高、炉顶框架64m平台标高及洞口尺寸。2) Measure the actual size, position and elevation that affect the hoisting on site: ground elevation, casthouse roof elevation, pool elevation, ZJ6 size and elevation, furnace roof frame 64m platform elevation and opening size.
3)将吊车主杆过出铁场屋面最高处、主杆与ZJ6相交时、通廊位于图1(通廊高端位于炉顶框架外,正要插入64m平台)所示位置、通廊斜插入64m平台极限(通廊底端刚要旋转入ZJ6时)这几个位置,作为吊车主杆是否卡杆及吊装高度是否满足的最不利验算位置。3) Pass the main rod of the crane over the highest point of the roof of the casthouse, when the main rod intersects ZJ6, the corridor is located at the position shown in Figure 1 (the high end of the corridor is located outside the furnace roof frame, and is about to be inserted into the 64m platform), and the corridor is inserted obliquely The positions of the 64m platform limit (when the bottom of the corridor is just about to rotate into ZJ6) are the most unfavorable positions for checking whether the main rod of the crane is stuck and whether the hoisting height is satisfied.
4)在选定的履带吊工况范围内,依据现场实际情况,初步确定履带吊站位位置。以图1所示通廊不利位置为例采用投影法核算钩头高度及履带吊主杆是否卡杆(见图4),履带吊车高2.5m,钩头长3.5m。4) Within the selected working conditions of the crawler crane, according to the actual situation on site, initially determine the location of the crawler crane. Taking the unfavorable position of the corridor shown in Figure 1 as an example, use the projection method to calculate the height of the hook head and whether the main rod of the crawler crane is stuck (see Figure 4). The height of the crawler crane is 2.5m, and the length of the hook head is 3.5m.
5)HJ7通廊所用履带吊若站位固定、一次旋转吊装是无法吊装就位的,需要不断调整履带吊站位、反复采用投影法核算钩头高度及履带吊主杆是否卡杆,使所有不利条件状况下履带吊处于同一条行走路线上,才能满足通廊吊装要求。5) If the crawler crane used in the corridor of HJ7 has a fixed station, it cannot be hoisted in place by one rotation and hoisting. It is necessary to continuously adjust the crawler crane station, repeatedly use the projection method to check the height of the hook head and whether the main rod of the crawler crane is stuck, so that all Under unfavorable conditions, the crawler cranes are on the same walking route to meet the hoisting requirements of the corridor.
6)改变通廊吊装角度,炉顶框架64m平台实际净高6.8m;通廊斜插入后,通廊最高点与最低点实际高度达到6.7m;为便于插入炉顶框架,并保证通廊最低点高于ZJ6,将通廊最低点人为稍微抬高,通廊吊装夹角由10,62度改为10,43度。6) Changing the hoisting angle of the corridor, the actual net height of the 64m platform of the furnace roof frame is 6.8m; after the corridor is inserted obliquely, the actual height of the highest point and the lowest point of the corridor reaches 6.7m; in order to facilitate the insertion of the furnace roof frame and ensure the lowest The point is higher than ZJ6, the lowest point of the corridor is artificially raised slightly, and the angle of the corridor hoisting is changed from 10,62 degrees to 10,43 degrees.
步骤1中,通廊安装顺序:施工准备→吊车选择→最重通廊(HJ6)确定吊车工况、吊挂钢丝绳长度及直径确定→不变吊车工况反算最不利条件通廊(HJ6)适用性→投影放线法确定通廊(HJ7)吊车站位及吊车吊装行走路线→通廊吊装。In step 1, the corridor installation sequence: construction preparation→crane selection→the heaviest corridor (HJ6) to determine the working condition of the crane, the length and diameter of the hanging wire rope to determine→the most unfavorable condition corridor (HJ6) inversely calculated under the same crane working condition Applicability→Determination of corridor (HJ7) crane station location and crane hoisting route by projection setting-out method→corridor hoisting.
本发明的优点是:采用整体吊装思路并综合考虑后,减少了大型吊车工况现场组对次数,避免了在炉顶框架内对通廊进行二次组对,缩短了工期,提高了施工的安全性。可以有效地解决在场地受限的情况下,大型吊车及吊车工况的选用方法。The advantages of the present invention are: after adopting the overall hoisting idea and comprehensive consideration, the number of on-site pairings in the working condition of large cranes is reduced, and the second pairing of corridors in the furnace roof frame is avoided, the construction period is shortened, and the construction efficiency is improved. safety. It can effectively solve the selection method of large cranes and crane working conditions when the site is limited.
附图说明Description of drawings
图1为通廊安装方法的整体平面布置示意图。Figure 1 is a schematic diagram of the overall layout of the corridor installation method.
图2为作图法确定HJ6钩头起升高度及钢丝绳长度。Figure 2 is a drawing method to determine the lifting height of the HJ6 hook head and the length of the wire rope.
图3为作图法确定HJ7钩头起升高度及吊点位置。Figure 3 shows the drawing method to determine the lifting height of the HJ7 hook head and the location of the lifting point.
图4为投影法核算一种通廊不利位置钩头高度及履带吊主杆是否卡杆。Figure 4 shows the projection method to calculate the height of the hook head at a disadvantageous position in the corridor and whether the main rod of the crawler crane is stuck.
具体实施方式detailed description
1、吊车及钢丝绳确定:HJ6重180t,依据该段钢通廊自身条件及现场的场地条件,选用650履带起重机安装,当工作半径是28m,杆长102m,后配重180t,中央压重40t,超起配重0~300t,超起半径是15m时,额定起重量是213.3t,满足吊装要求。现场容易采购的钢丝绳直径为83mm,将通廊减重至160t进行钢丝绳直径验算。1. Determination of the crane and wire rope: HJ6 weighs 180t. According to the conditions of the steel corridor itself and the site conditions, a 650 crawler crane is selected for installation. When the working radius is 28m, the pole length is 102m, the rear counterweight is 180t, and the central weight is 40t. , super lifting counterweight 0 ~ 300t, when the super lifting radius is 15m, the rated lifting capacity is 213.3t, which meets the hoisting requirements. The diameter of the steel wire rope that is easy to purchase on site is 83mm, and the weight of the passageway is reduced to 160t to check the diameter of the wire rope.
依据吊车的参数和通廊的安装高度确定吊钩的起升高度,依据节距选择吊挂点位于距通廊重心1/2~1/3处,钢丝绳与水平夹角一般为45°~60°,用作图法确定钢丝绳长度。(见图2)The lifting height of the hook is determined according to the parameters of the crane and the installation height of the corridor, and the hanging point is selected according to the pitch to be located at 1/2~1/3 from the center of gravity of the corridor, and the angle between the wire rope and the horizontal is generally 45°~60° °, which is used to determine the length of the wire rope by the graph method. (See Figure 2)
确定钢丝绳S1长度为25.189m两根,S2长度为58.610m一根,钢丝绳S1与通廊夹角为63°,钢丝绳S2与通廊夹角为50°。It is determined that the length of the steel wire rope S1 is two 25.189m, and the length of S2 is one 58.610m. The angle between the steel wire rope S1 and the corridor is 63°, and the angle between the steel wire rope S2 and the corridor is 50°.
吊挂钢丝绳直径的确定,设4个吊挂点平均受力,则每个起挂点的起重量为:160÷4=40t。To determine the diameter of the hanging steel wire rope, assuming the average force of the 4 hanging points, the lifting capacity of each hanging point is: 160÷4=40t.
钢丝绳张力为:The tension of the wire rope is:
S1=40÷Sin(63°-10.62°)=50.6tS1=40÷Sin(63°-10.62°)=50.6t
S2=40÷Sin(50°+10.62°)=45.9tS2=40÷Sin(50°+10.62°)=45.9t
S1的最大吊挂钢丝绳受力最大为50.6tThe maximum force of the hanging wire rope of S1 is 50.6t
取工作等级为8,安全系数8,则选择系数0.118Take the work level as 8 and the safety factor as 8, then choose the factor of 0.118
钢丝绳d=0.118×(50.6×1000×9.800)1/2=83mm,Wire rope d=0.118×(50.6×1000×9.800)1/2=83mm,
选取直径为Φ83的钢丝绳,规格6*61公称抗拉强度1700N/mm2。Select a steel wire rope with a diameter of Φ83 and a specification of 6*61 with a nominal tensile strength of 1700N/mm2.
2、不变吊车工况反算最不利条件通廊(与高炉连接的通廊HJ7)适用性:2. The applicability of the most unfavorable condition corridor (corridor HJ7 connected to the blast furnace) in the back calculation of the crane working condition:
HJ7投影长37.695m,安装高度高端64.650m、底端标高57.114m,坡度为10.620°,重121t。以两侧第一个节距为吊点,采用第六节通廊选择的钢丝绳,用作图法核算吊 车钩头起升高度。(见图3)The projection length of HJ7 is 37.695m, the high-end installation height is 64.650m, the bottom elevation is 57.114m, the slope is 10.620°, and the weight is 121t. Take the first pitch on both sides as the lifting point, and use the steel wire rope selected in the corridor of the sixth section to calculate the lifting height of the hook head of the crane by the diagram method. (See Figure 3)
经作图法计算吊车钩头的最小起升高度为85.539m;依据现场情况及通廊各项参数,吊车选用650t履带吊102主杆起重性能,工作半径是38m,额定起重量是129t,后配重180t,中央压重40t,超起配重0~300t,钩头最大起升高度为92m,满足高度要求。The minimum lifting height of the crane hook head is calculated by the drawing method to be 85.539m; according to the site conditions and the parameters of the corridor, the crane uses a 650t crawler crane with a 102 main pole lifting performance, a working radius of 38m, and a rated lifting capacity of 129t. The rear counterweight is 180t, the central counterweight is 40t, the overlift counterweight is 0-300t, and the maximum lifting height of the hook head is 92m, meeting the height requirements.
3、考虑与高炉连接的通廊吊装时的各种不利因素,改变通廊吊装角度,确定通廊吊点、吊车站位及吊车吊装行走路线:3. Consider various unfavorable factors during the hoisting of the corridor connected to the blast furnace, change the hoisting angle of the corridor, and determine the hoisting point of the corridor, the location of the crane station and the hoisting route of the crane:
结合现场实际情况,对周边建筑物平面及高度尺寸进行实测实量,考虑四种因素影响,一是吊车站位,热风炉框架及水池侧壁不影响超级配重旋转,二是出铁场框架不卡杆,三是ZJ6不卡杆,四是炉顶框架64m平台净尺寸能够保证通廊斜着插入安装并保证钢丝绳与高炉平台不冲突;炉顶框架64m平台实际净高6.8m,宽度7.05m,且外侧上升管、除尘管道及内侧除尘管道已安装完,通廊斜插入后,实际净高达到6.7m,宽度6m,为便于插入炉顶框架,并保证通廊高于ZJ6,将通廊吊装夹角由10,62度改为10,43度,并将插入炉顶框架的通廊顶面、侧面C型钢拆除,扩大操作面,更有可操作性。利用投影法进行放样,通廊在各不利位置处的吊车起升高度满足要求。Combined with the actual situation on the site, the plane and height dimensions of the surrounding buildings were measured and measured, considering the influence of four factors, one is the position of the crane, the frame of the hot blast stove and the side wall of the pool will not affect the rotation of the super counterweight, and the other is the frame of the casthouse The third is that the ZJ6 is not stuck. The fourth is that the net size of the 64m platform of the furnace roof frame can ensure that the corridor can be inserted and installed obliquely and ensure that the steel wire rope does not conflict with the blast furnace platform; the actual net height of the 64m platform of the furnace roof frame is 6.8m, and the width is 7.05 m, and the outer rising pipe, dust removal pipe and inner dust removal pipe have been installed. After the corridor is inserted obliquely, the actual clear height reaches 6.7m and the width is 6m. In order to facilitate insertion into the furnace roof frame and ensure that the corridor is higher than ZJ6, the passage The included angle of the gallery hoisting was changed from 10,62 degrees to 10,43 degrees, and the top surface and side C-shaped steel of the corridor inserted into the furnace roof frame were removed to expand the operation surface and make it more operable. The projection method is used for stakeout, and the hoisting height of the crane at each unfavorable position of the corridor meets the requirements.
2、通廊安装2. Corridor installation
1)安装使用机械及工具介绍:650t履带吊进行构件吊装,构件运输采用40t板车,50t履带吊进行构件组对,电焊机,10t、5t倒链,10t、5t千斤顶等。1) Installation and use of machinery and tools introduction: 650t crawler crane for component hoisting, component transportation using 40t trolley, 50t crawler crane for component assembly, electric welding machine, 10t, 5t back chain, 10t, 5t jack, etc.
2)HJ6水平投影长37.695m,安装高度高端64.650m、底端标高57.114m,重121t。按照通廊组对位置,提前搭设好临时组对平台,将HJ7在现场组对。组对完成后,检查构件各项指标,达到技术要求后,标注好中心线。在安装前,在炉顶框架平台及ZJ6上标注好安装中心线。2) HJ6 has a horizontal projection length of 37.695m, an installation height of 64.650m at the high end, a bottom elevation of 57.114m, and a weight of 121t. According to the pairing position of the corridor, a temporary pairing platform is set up in advance, and the HJ7 is paired on site. After the assembly is completed, check the indicators of the components, and mark the centerline after meeting the technical requirements. Before installation, mark the installation center line on the furnace roof frame platform and ZJ6.
3)将650t履带吊移动至站位位置,挂好钢丝绳后采用50t履带吊安装超级配重。吊装时650t履带吊要按照验算好的行走路线进行行走吊装,避开周围建筑物的影响。通廊插入炉顶框架达到安装位置后,进行滑动支座安装,最后通廊就位。3) Move the 650t crawler crane to the station position, and use the 50t crawler crane to install the super counterweight after hanging the wire rope. During hoisting, the 650t crawler crane should be hoisted according to the checked and calculated walking route, avoiding the influence of surrounding buildings. After the corridor is inserted into the roof frame and reaches the installation position, the sliding support is installed, and finally the corridor is in place.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510441732.9A CN105019666B (en) | 2015-07-25 | 2015-07-25 | Installation method of the last section of vestibule connected with blast furnace |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510441732.9A CN105019666B (en) | 2015-07-25 | 2015-07-25 | Installation method of the last section of vestibule connected with blast furnace |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN105019666A CN105019666A (en) | 2015-11-04 |
| CN105019666B true CN105019666B (en) | 2017-02-01 |
Family
ID=54409932
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510441732.9A Active CN105019666B (en) | 2015-07-25 | 2015-07-25 | Installation method of the last section of vestibule connected with blast furnace |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105019666B (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110713117A (en) * | 2019-09-02 | 2020-01-21 | 上海二十冶建设有限公司 | Sintering machine primary mixer and secondary mixer hoisting method |
| CN112065109B (en) * | 2020-09-02 | 2022-05-10 | 中国一冶集团有限公司 | Rapid installation method for small steel pipe corridor structure |
| CN116639608B (en) * | 2023-05-10 | 2026-04-03 | 五冶集团上海有限公司 | A method for adjusting and lifting the counterweight of a large crawler crane in a coke oven renovation project. |
Family Cites Families (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2702204A1 (en) * | 1993-03-01 | 1994-09-09 | Fontanel Sa Entr | Load-balancing support |
| JPH0899795A (en) * | 1994-08-05 | 1996-04-16 | Akira Tanaka | Construction crane device and construction method |
| CN101899904B (en) * | 2010-07-23 | 2011-06-29 | 中冶建工有限公司 | Method for two-way hoisting construction of converter tower steel structure |
| CN202245861U (en) * | 2011-08-30 | 2012-05-30 | 中冶天工集团有限公司 | Device capable of integrally elevating ultrahigh large-span heavy-duty steel vestibule |
| CN102619341A (en) * | 2012-04-06 | 2012-08-01 | 中国十七冶集团有限公司 | Workshop-across longspan two-crane walking hoisting method for steel vestibules |
| CN104060838B (en) * | 2014-06-18 | 2016-05-18 | 北京首钢建设集团有限公司 | A kind of vestibule divides into groups aerial group to Method for Installation |
-
2015
- 2015-07-25 CN CN201510441732.9A patent/CN105019666B/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| CN105019666A (en) | 2015-11-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108455451B (en) | A kind of 600 tons of gantry cranes hold the method for hanging installation superelevation flare tower | |
| CN102953553B (en) | Method for mounting large-span pipe truss by using boom luffing mechanism | |
| CN204782031U (en) | Interior climbing tower hangs entrance to a cave from promoting safety protection platform | |
| CN102121273A (en) | Hydraulic lifting inversion method for reinforced concrete chimney steel inner cylinder | |
| CN106315426A (en) | Block form tower crane mounting and jacking method for assembled building | |
| CN114368672A (en) | Lifting-lug-free self-aligning lifting method for inclined and straight flue of steel-making system | |
| CN105019666A (en) | Installation method of the last section of vestibule connected with blast furnace | |
| CN205716004U (en) | A kind of high pressure vertical shaft penstock erecting device | |
| CN102992203B (en) | Simple hoisting device for steel structure bridge installation | |
| CN104234636B (en) | Jack-up unit derrick installation method | |
| CN104695425A (en) | Hoisting construction technology of steel bar cage | |
| CN211712490U (en) | Pipe well pipe hoisting device | |
| CN108118885A (en) | Vertical transport protective platform and its application in steel structure column docking construction | |
| CN202864675U (en) | Shaft-type part hoisting tool | |
| CN202729645U (en) | Tower crane with elevator | |
| CN102556850A (en) | Hoisting adjusting device and component hoisting method | |
| CN103922232B (en) | A kind of tower crane fall tower process | |
| CN203794505U (en) | Internal climbing steel beam conveying device of internal climbing movable arm tower crane | |
| CN111411624A (en) | Hoisting method for reinforcement cage of underground continuous wall in height-limited area | |
| CN209872102U (en) | Hoisting device | |
| CN205132977U (en) | Movable swing arm tower machine installation wire rope | |
| CN212475780U (en) | Counter weight formula lifting device | |
| CN201896016U (en) | Lifting basket device for storage tank maintenance | |
| CN104495645A (en) | Structure capable of mounting and dismounting balancing weight automatically by tower crane | |
| CN207046708U (en) | A kind of short group's davit lifts the Lift-on/Lift-off System of tall and big anaerobism tank body |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| PP01 | Preservation of patent right |
Effective date of registration: 20251029 Granted publication date: 20170201 |
|
| PP01 | Preservation of patent right |