CN104996022A - Secondary equal division and peeling construction method of field lifting cultivated soil layer of hydro-junction project reservoir region - Google Patents

Secondary equal division and peeling construction method of field lifting cultivated soil layer of hydro-junction project reservoir region Download PDF

Info

Publication number
CN104996022A
CN104996022A CN201510389248.6A CN201510389248A CN104996022A CN 104996022 A CN104996022 A CN 104996022A CN 201510389248 A CN201510389248 A CN 201510389248A CN 104996022 A CN104996022 A CN 104996022A
Authority
CN
China
Prior art keywords
construction
field
mold
agric
peeling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510389248.6A
Other languages
Chinese (zh)
Inventor
郭洪有
胡鸿煌
彭灿华
李金瑞
彭红军
刘愚
周贯华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Water And Hydropower Construction Co Ltd
Original Assignee
Jiangxi Water And Hydropower Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Water And Hydropower Construction Co Ltd filed Critical Jiangxi Water And Hydropower Construction Co Ltd
Priority to CN201510389248.6A priority Critical patent/CN104996022A/en
Publication of CN104996022A publication Critical patent/CN104996022A/en
Pending legal-status Critical Current

Links

Landscapes

  • Cultivation Of Plants (AREA)

Abstract

The present invention discloses a secondary equal division and peeling construction method of a field lifting cultivated soil layer of a hydro-junction project reservoir region. The secondary equal division and peeling construction method comprises the specific steps of: A, dividing a primary peeling and stacking block of the cultivated soil layer; B, carrying out primary peeling and stacking of the cultivated soil layer; C, filling, checking, and accepting a foundation booster layer; D, filling, checking, and accepting a clay moisture-keeping layer; and E, transferring stacked cultivated soil and peeling off the cultivated soil of the lower part; then carrying out construction work of filling, checking, and accepting the foundation booster layer, filling, checking, and accepting the clay moisture-keeping layer, carrying out an in-field project, and carrying out a soil material paving procedure of the cultivated soil layer; and finishing field lifting construction after completely finishing a field lifting construction project. By virtue of the secondary equal division and peeling construction method, the construction working efficiency of peeling the cultivated soil layer of the field lifting project of the hydro-junction project reservoir region can be improved, the construction speed of the field lifting project is accelerated; a field lifting contract project construction task is finished during a controlling working period required by a contract; and contract risks that economic compensation is needed as cultivated land is occupied over the seasons due to the fact that the contract working period is delayed are reduced, and a target of contract project economic benefits is realized.

Description

Water-control project reservoir area is lifted field agric secondary and is divided equally stripping construction method
Technical field
The present invention relates to agric and peel off construction method, especially relate to a kind of water-control project reservoir area and lift field agric secondary and divide equally stripping construction method.
Background technology
In consolidation, shallow arable land of flooding, Reservoir region is raised in the work progress of (hereinafter referred to as lifting field), unit in charge of construction often adopts the protection of former mold and takes off ridge stacking on the spot, after depression is raised, the former mold stacked is re-started again and pave, because the pilling up time of former mold is longer, farming earth material safeguard measure is poor, water in farming earth material, fertilizer will run off and totally form desertification, the fertility and air capacity of soils that reach native soil again cannot be restored, cause that crops are in poor harvest has a shortfall in output, larger to impact of agricultural production, several years is needed to recover, larger economic loss is caused to agricultural production.In order to effectively improve farmland quality, safekeeping must be given to consolidation region and the former mold of lifting region, field.
The feature that field engineering is lifted in water-control project reservoir area, the Xiajiang, Jiangxi Province is that (totally 20, field is lifted in reservoir area to area greatly, lift field area and reach 3.75 ten thousand mu, its scale still belongs to the first at home in similar water-control project), the duration, tight (controlling construction period was: lift field and answer block construction, require that each piece of construction infection time is no more than the crop growth time in season, more than the crop growth time in season, it occupies cultivated land to compensate and is responsible for by contractor.Compensation standard is 600 yuan of/mu of seasons.); therefore; if the agric stripping that field engineering construction is lifted in water-control project reservoir area, the Xiajiang does not use new construction method; and continue to use consolidation in the past and lift the tiling method mold protection construction method construction that field engineering uses, lift field engineering construction and cannot complete within the Contract Control duration and lift field contract work construction task.
Summary of the invention
Object of the present invention is just to provide one can make consolidation, can there be good soil quality in the arable land of lifting field at short notice, the fertility of effective maintenance native soil and air capacity of soils, meet and cultivate needs, the water-control project reservoir area of convenient and simple practicality is lifted field agric secondary and is divided equally stripping construction method, the method can improve the construction efficiency that field engineering agric stripping is lifted in water-control project reservoir area, accelerate to lift field engineering construction speed, ensure to complete within the controlling duration of contract requirement to lift field contract work construction task, reduce the economic compensation Contract Risk that occupies cultivated land in super season produced because time limit for contract incurs loss through delay, realize the target of contract item economic benefit.
The object of the present invention is achieved like this:
A kind of water-control project reservoir area is lifted field agric secondary and is divided equally stripping construction method, and feature is: concrete steps are as follows:
A, division agric are once peeled off and stack plot: by the area lifting field field, landform, the water system condition of lifting field detail design diagram root, by lift field field be divided into some parallel spaced-apart arrange agric peel off plot and peel off mold stack plot, accomplish fluently boundary timber and the powder that limes carry out line of demarcation mark;
B, agric are once peeled off and are stacked: arrange according to constructing, in different agrics stripping plot, carry out agric by multiple stage hydraulic backhoe simultaneously and once peel off construction operation, it must take center line as boundary that every block agric peels off plot, the mold of stripping is deposited in respectively the stripping mold being stripped both sides, agric plot and stacks in plot;
C, base mat high level fill and examination: complete the plot that agric is once peeled off, and after qualified by inspection, then fill with clay material or sand gravel material or ballast material, carry out the high-rise filling construction of base mat;
D, clay water conservation layer fill and examination: after the high-rise filling construction of base mat terminates and be qualified by inspection, then fill clay material, carry out clay water conservation layer filling construction;
E, the mold that transfer is stacked also peels off bottom mold: clay water conservation layer filling construction terminate and qualified by inspection after, then stripping mold being stacked the intramassif mold once peeling off stacking transfers on the clay water conservation layer of both sides, and to stripping mold stack intramassif bottom agric carry out secondary peel off construction operation, it will take center line as boundary that every block peels off mold stacking plot, the mold that the mold and secondary of once peeling off stacking are peeled off is deposited on the clay water conservation layer of both sides respectively, and then carry out base mat high level and fill and examination, clay water conservation layer fills and examination, irrigation facility, agric earth material shakeouts the construction operation of operation, lift after field project under construction all completes to design and lift field construction end.
The present invention compares with " consolidation and lift field engineering tiling method mold protect construction method ", has following characteristics:
1, construction organization mode is more advanced.What the present invention adopted is parallel construction organizational form, make use of working face fully, has striven for the time, can shorten the construction period; And the employing of tiling method mold protection construction method is construction organization mode successively, not making full use of working face goes to race against time, so the construction period is long.Therefore, construction organization mode of the present invention is more advanced.
2, speed of application is fast.Owing to present invention employs advanced parallel construction organizational form, and the earth and rock works construction equipment resource abundance on earth and rock works construction equipment leasing market, meet to organize and morely lift the precondition that field construction operation team carries out parallel construction operation simultaneously, achieve multiple field field of lifting to carry out lifting field parallel construction operation simultaneously, therefore, speed of application is fast.
3, significantly reduce and can not meet time limit for contract requirement and the economic compensation Contract Risk that occupies cultivated land in super season produced because lifting field construction speed.Owing to present invention employs parallel mode construction organization, achieve multiple field field of lifting to carry out lifting field parallel construction operation simultaneously, accelerate and lift field job execution progress, highly shortened the construction period, therefore, significantly reduce and can not meet time limit for contract requirement and the economic compensation Contract Risk that occupies cultivated land in super season produced because lifting field construction speed.
Therefore, the present invention has can make consolidation, can there be good soil quality in the arable land of lifting field at short notice, the fertility of effective maintenance native soil and air capacity of soils, meet and cultivate needs, the advantage of convenient and simple practicality, it can improve the construction efficiency that field engineering agric stripping is lifted in water-control project reservoir area, accelerate to lift field engineering construction speed, ensure to complete within the controlling duration of contract requirement to lift field contract work construction task, reduce the economic compensation Contract Risk that occupies cultivated land in super season produced because time limit for contract incurs loss through delay, realize the target of contract item economic benefit.It makes consolidation and lifts the former mold that field takes full advantage of original fertile soil; the soil of former mold, fertile loss can not be caused; improved arable land can play benefit in the short time; not only there is very large society and environmental benefit; and effectively protect the integrated production capacity of China's grain; maintain the grain security of country; be widely used in hydroelectric pivotal project, field engineering is lifted in navigation power key project reservoir area; low-lying easy flooded field () improvement project, land leveling project and other land control engineerings.
Accompanying drawing explanation
Fig. 1 lifts field field mold once to peel off and the schematic diagram stacking Parcel division, in figure: L is the length of lifting field field, and M is the width lifting field field, and a is the width that agric is once peeled off, and b is the width once peeling off agric stacking.
Embodiment
Contrast accompanying drawing below in conjunction with embodiment the present invention is described in further detail.
A kind of water-control project reservoir area is lifted field agric secondary and is divided equally stripping construction method, and Specific construction step is as follows:
A, division agric are once peeled off and stack plot:
According to the area lifting field field lifting field detail design diagram root, (long is L rice, wide is M rice), the condition such as landform, water system, construction equipment job area is peeled off in conjunction with agric, by lift field field be divided into some parallel spaced-apart arrange agric peel off plot and peel off mold stack plot, accomplish fluently boundary timber and the powder that limes carry out line of demarcation mark;
B, agric are once peeled off and are stacked:
(1) carry out agric stripping according to sequence of construction arrangement, large hydraulic backacter should be used to peel off mold.
(2) should separate enough farming earth materials as required, general stripping depth is 15cm ~ 25cm.
(3) the farming earth material be stripped in agric is deposited in by planning the both sides that agric peels off plot, stacks height≤2.0m, and takes Mulching methods to prevent from making farming earth material not produce water and soil loss, with the original liquid manure of Maintaining cultivation earth material.
3, base mat high level fills and examination:
(1) base mat high level fills the cleaning of material top layer, stock ground: should carry out top layer cleaning before selected stock ground excavation, the table soil in cleaning excavation region, weeds, rubbish, waste residue, tree root and supervisor indicate other hinder thing.
(2) uncultivated area lifts the cleaning of construction area earth's surface, field:
1) lifting field construction area present situation is uncultivated area, and during the filling-up thickness < 30cm of the padded basic bed of material in bottom, lift region, field and strictly should carry out base clearly, table soil, weeds, rubbish, waste residue, tree root and supervisor indicate other hinder thing and should clear up.
2) lifting field construction area present situation is uncultivated area, and during the padded basic bed of material filling-up thickness >=30cm in bottom, forest land requires that the tree root of maximum gauge >=20cm must excavate waste, the forest earth's surfaces such as shrub indicate with upper part, rubbish, waste residue and supervisor other hinder thing and should remove, table soil, weeds etc. can not be removed; Table soil, weeds etc. can not be removed for beach, wasteland etc., but the forest earth's surfaces such as shrub indicate with upper part, rubbish, waste residue and supervisor other hinder thing and should remove.
(3) basestocks is exploited from selected stock ground or is utilized excavated material, and the direct entrucking of available excavator is exploited in stock ground, and dump truck transports, and material is not limit, but must not contain the impurity such as plant roots and stems, rubbish, largest block footpath < 50cm.
(4) the construction technical data placement in layers that should determine by field roll compaction test of basestocks, layered rolling.
(5) every layer of basestocks rolls end and can carry out the construction of next procedure after Site Detection is qualified.
4, clay water conservation layer fills and examination:
(1) borrow pit top layer cleaning.Should top layer cleaning be carried out before borrow pit excavation, the table soil in cleaning excavation region, weeds, rubbish, waste residue, tree root and supervisor indicate other hinder thing.
(2) earth material is exploited field from selected earth material or is utilized excavated material, and require uniform soil quality, earth material must not contain the impurity such as plant roots and stems, brick and tile, rubbish, soil block restriction diameter < 15cm.
(3) construction technical data that should determine by field roll compaction test of clay water conservation layer, paving is filled out after one deck clay reaches construction requirement thickness, then carries out the operation of clay roller compaction construction, until compactness terminates roller compaction construction operation after meeting designing requirement.
(4) clay water conservation layer rolls end and can carry out the construction of next procedure after Site Detection is qualified.
5, shift the mold stacked and peel off bottom mold:
Clay water conservation layer filling construction terminate and qualified by inspection after, then stripping mold being stacked the intramassif mold once peeling off stacking transfers on the clay water conservation layer of both sides, and to stripping mold stack intramassif bottom agric carry out secondary peel off construction operation, it will take center line as boundary that every block peels off mold stacking plot, the mold that the mold and secondary of once peeling off stacking are peeled off is deposited on the clay water conservation layer of both sides respectively, and then carry out base mat high level and fill and examination, clay water conservation layer fills and examination, irrigation facility, agric earth material shakeouts the construction operation of operation, lift after field project under construction all completes to design and lift field construction end.

Claims (1)

1. water-control project reservoir area is lifted field agric secondary and is divided equally a stripping construction method, it is characterized in that:
A, division agric are once peeled off and stack plot: by the area lifting field field, landform, the water system condition of lifting field detail design diagram root, by lift field field be divided into some parallel spaced-apart arrange agric peel off plot and peel off mold stack plot, accomplish fluently boundary timber and the powder that limes carry out line of demarcation mark;
B, agric are once peeled off and are stacked: arrange according to constructing, in different agrics stripping plot, carry out agric by multiple stage hydraulic backhoe simultaneously and once peel off construction operation, it must take center line as boundary that every block agric peels off plot, the mold of stripping is deposited in respectively the stripping mold being stripped both sides, agric plot and stacks in plot;
C, base mat high level fill and examination: complete the plot that agric is once peeled off, and after qualified by inspection, then fill with clay material or sand gravel material or ballast material, carry out the high-rise filling construction of base mat;
D, clay water conservation layer fill and examination: after the high-rise filling construction of base mat terminates and be qualified by inspection, then fill clay material, carry out clay water conservation layer filling construction;
E, the mold that transfer is stacked also peels off bottom mold: clay water conservation layer filling construction terminate and qualified by inspection after, then stripping mold being stacked the intramassif mold once peeling off stacking transfers on the clay water conservation layer of both sides, and to stripping mold stack intramassif bottom agric carry out secondary peel off construction operation, it will take center line as boundary that every block peels off mold stacking plot, the mold that the mold and secondary of once peeling off stacking are peeled off is deposited on the clay water conservation layer of both sides respectively, and then carry out base mat high level and fill and examination, clay water conservation layer fills and examination, irrigation facility, agric earth material shakeouts the construction operation of operation, lift after field project under construction all completes to design and lift field construction end.
CN201510389248.6A 2015-07-06 2015-07-06 Secondary equal division and peeling construction method of field lifting cultivated soil layer of hydro-junction project reservoir region Pending CN104996022A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510389248.6A CN104996022A (en) 2015-07-06 2015-07-06 Secondary equal division and peeling construction method of field lifting cultivated soil layer of hydro-junction project reservoir region

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510389248.6A CN104996022A (en) 2015-07-06 2015-07-06 Secondary equal division and peeling construction method of field lifting cultivated soil layer of hydro-junction project reservoir region

Publications (1)

Publication Number Publication Date
CN104996022A true CN104996022A (en) 2015-10-28

Family

ID=54369159

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510389248.6A Pending CN104996022A (en) 2015-07-06 2015-07-06 Secondary equal division and peeling construction method of field lifting cultivated soil layer of hydro-junction project reservoir region

Country Status (1)

Country Link
CN (1) CN104996022A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105672198A (en) * 2016-03-25 2016-06-15 中国电建集团贵阳勘测设计研究院有限公司 Land-building and plowing structure for reservoir inundation and immersion area and construction method thereof
CN114660268A (en) * 2022-03-22 2022-06-24 中铁水利水电规划设计集团有限公司 The seepage monitoring system for the aquifer of the cultivated land in the uplift area of the submerged area of the reservoir

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105672198A (en) * 2016-03-25 2016-06-15 中国电建集团贵阳勘测设计研究院有限公司 Land-building and plowing structure for reservoir inundation and immersion area and construction method thereof
CN114660268A (en) * 2022-03-22 2022-06-24 中铁水利水电规划设计集团有限公司 The seepage monitoring system for the aquifer of the cultivated land in the uplift area of the submerged area of the reservoir

Similar Documents

Publication Publication Date Title
CN103039147B (en) Reclamation method for sunk paddy field caused by mining in mountainous regions
CN202652889U (en) Spontaneous combustion coal gangue mountain comprehensive treatment system
CN104012361B (en) A kind of method preventing the soil liquid manure loss when gravel soil ground cultivating grape
CN106818167A (en) A kind of method for administering the discarded ground of khoai in-situ ionic rare earth leaching ore deposit
CN103556642B (en) High rock slope green covered plant underground habitat reconstruction method
CN103081602A (en) Method of soil reclamation project topsoil stripping
CN107736100A (en) A kind of fast and effective construction method for forming farming plough sole
CN107950310A (en) A kind of discarded pit exploitation reparation pattern and evaluation method
CN101974910A (en) Ecological restoration method for side slope of tailing pond later dam under condition of no earthing
CN109588077B (en) Method for constructing paddy field on sandy surface soil
CN106759399A (en) A kind of side slope vegetation ecological recovery system and method
CN106105470B (en) A healthy soil construction method based on rural empty and waste land remediation
CN116868841A (en) A method of ecological construction on exposed rock surfaces
CN103039233A (en) Root guiding and seedling raising method of arbor species for roof greening
CN113767806A (en) Karst region stony desertification land comprehensive treatment method
CN104996022A (en) Secondary equal division and peeling construction method of field lifting cultivated soil layer of hydro-junction project reservoir region
CN105672198B (en) Land-building and plowing structure for reservoir inundation and immersion area and construction method thereof
CN201571375U (en) Protection ecology bag
CN103088835B (en) Three gorge reservoir region slope cropland bank building method and slope cropland bank
CN103821131B (en) The restorative procedure of development construction item soil and water conservation ecological
CN201785950U (en) Light-duty greening roof
CN111236271A (en) A kind of slope ecological restoration system and restoration method
CN209234523U (en) A kind of plantation paddy field soil structure in alluvial plain
CN110245452A (en) A kind of Loess Region coal mining subsidence area crack administering method
CN110169228A (en) Grape fixed-value ditch excavation and fertilization method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20151028

WD01 Invention patent application deemed withdrawn after publication