CN104988981A - Construction method of riding well on existing shield drainage pipeline - Google Patents

Construction method of riding well on existing shield drainage pipeline Download PDF

Info

Publication number
CN104988981A
CN104988981A CN201510250348.0A CN201510250348A CN104988981A CN 104988981 A CN104988981 A CN 104988981A CN 201510250348 A CN201510250348 A CN 201510250348A CN 104988981 A CN104988981 A CN 104988981A
Authority
CN
China
Prior art keywords
side wall
well
hole
foundation pit
shield structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510250348.0A
Other languages
Chinese (zh)
Other versions
CN104988981B (en
Inventor
孙九春
薛武强
王建忠
唐俊华
潘荣
卿凇
江育龙
陈银河
奚国栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tengda Construction Group Co Ltd
Original Assignee
Tengda Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tengda Construction Group Co Ltd filed Critical Tengda Construction Group Co Ltd
Priority to CN201510250348.0A priority Critical patent/CN104988981B/en
Publication of CN104988981A publication Critical patent/CN104988981A/en
Application granted granted Critical
Publication of CN104988981B publication Critical patent/CN104988981B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention provides a construction method of a riding well on an existing shield drainage pipeline. The construction method comprises that step 1: a foundation pit retaining structure is constructed on a foundation pit to be excavated, and the bottom of the foundation pit is paved with a shield pipeline; step 2: the foundation pit is divided into at least one section, if the foundation pit is divided into one section, the foundation pit is excavated until a set pit bottom elevation position is reached, and side walls and a base plate of the foundation pit are poured; if the foundation pit is divided into a plurality of sections, sections before the final section are excavated, then the final section is excavated until a set pit bottom elevation position is reached, the base plate of the foundation pit is poured, then the side walls of the final section are poured; step 3: a top pipe communicated with a well chamber is arranged, and a first hole is arranged in the base plate of the foundation pit and the top of the shield pipeline through a diamond barrel saw drilling machine; step 4: a top plate provided with a second hole is arranged on the top of the well chamber; and step 5: a well shaft and a well lid are arranged on the top plate. According to the invention, the riding well is arranged on the existing shield drainage pipeline, top sealing pipe pieces is removed by means of a static force cutting method, and the construction method is simple to implement, low in cost and high in safety.

Description

A kind of well construction method of riding on present situation operation shield method drainage pipe
Technical field
The present invention relates to a kind of construction method of well of riding, the well construction method of riding on especially a kind of present situation operation shield method drainage pipe.
Background technology
Along with the continuous expansion of Metroplises, the sharply expansion of urban population, original drainage pipe is progressively aging, relevant electromechanical equipment is also run ragged, and cannot adapt to the needs of rapid urban, and the transformation of urban district original substandard drainage pipe is imperative.The upper newly-built well of riding of present situation operation (namely existing) shield method drainage pipe (hereinafter referred to as shield structure pipeline) is a difficult problem in the rebuilding construction of substandard drainage pipe, and main construction Difficulties is foundation pit enclosure structure construction, the perforate of existing shield structure pipeline and with the access of present situation shield structure pipeline, guarantee that existing shield structure pipeline is not stopped transport to the protection of existing shield structure pipeline and construction period.
In the prior art, on the one hand, Chinese invention patent CN104404983A provides a kind of ride well device and construction method thereof for jacking construction, and the construction of its well that only carried out riding in conjunction with push pipe, does not relate to the technical scheme of existing shield structure pipeline in this manual.On the other hand, when existing shield structure pipeline is constructed, need the dismounting of the section of jurisdiction of carrying out shield structure pipeline, the stress system of existing shield structure pipeline can be changed the dismounting of the section of jurisdiction of shield structure pipeline, easily produce stress and concentrate, destroy shield structure pipeline.Traditional construction method arranges simple and easy prestressing force tunnel frame in the drainage pipe of opening part both sides, and remove with the section of jurisdiction alleviating shield structure pipeline the adverse effect produced shield structure pipeline, this construction method is comparatively complicated, and cost is higher.Therefore, be necessary to provide a kind of technical scheme of constructing to existing shield structure pipeline under the requirement of the feature such as operation, economy, safety not affecting existing shield structure pipeline.
Summary of the invention
The object of the present invention is to provide the well construction method of riding on a kind of present situation operation shield method drainage pipe; the construction requirement of push pipe received well is met with the well that makes to ride; meet the protection requirement to existing shield structure pipeline; the adverse effect produced shield structure pipeline is removed in the section of jurisdiction alleviating shield structure pipeline, and guarantees that construction method is simple, cost is low and safe and reliable.
In order to achieve the above object, the invention provides the well construction method of riding on a kind of present situation operation shield method drainage pipe, comprising:
Step 1: the foundation ditch to be excavated bottom being equipped with to shield structure pipeline builds foundation pit enclosure structure;
Step 2: described foundation ditch in the vertical direction to be excavated is divided at least one section, if be divided into one section, till then first excavating described foundation ditch absolute altitude place at the bottom of the hole of setting, then on described shield structure pipeline, the first reinforcing bar is implanted, and base plate of foundation pit is built on described shield structure pipeline, make described first reinforcing bar penetrate base plate of foundation pit, and make described base plate of foundation pit and side wall be enclosed to form a well room, build the side wall of described foundation ditch four side, if be divided into multistage, then first excavate some sections before final stage, and often excavating the side wall of one section of this section of after-pouring, and each section of side wall is connected up and down with side wall the last period, till excavating final stage absolute altitude place at the bottom of the hole of setting afterwards, then on described shield structure pipeline, the first reinforcing bar is implanted, and base plate of foundation pit is built on described shield structure pipeline, described first reinforcing bar is made to penetrate base plate of foundation pit, finally build with the final stage side wall that the last period, side wall connected up and down to form the side wall of described foundation ditch, and make the side wall of described foundation ditch and base plate of foundation pit be enclosed to form a well room,
Step 3: carry out jacking construction and pass the side wall of described foundation ditch to make push pipe and be connected with described well room, makes hole, hole to intersect to offer the first hole on described base plate of foundation pit and shield structure pipeline top by the continuous round of static(al) cutting equipment;
Step 4: arrange top board on the top of described well room, described top board is fixed on the side wall of foundation ditch, and offers the second hole;
Step 5: be arranged through the pit shaft that the second hole is connected with well room on described top board, arranges well lid on described pit shaft top.
Further, in step 1, specifically comprise:
Step 1.1: both sides bottom being equipped with to the direction along the pipe laying of described shield structure of the foundation ditch to be excavated of shield structure pipeline all arrange bored pile;
Step 1.2: at side arranged and bored pile overlap the high-pressure rotary jet grouting pile of described bored pile away from foundation ditch.
Further, in step 1, also comprise:
Step 1.3: arrange a position for hole end absolute altitude in described foundation ditch, the below slip casting at absolute altitude place at the bottom of described hole, arranges top beam on the top of described bored pile.
Further, in step 1.1, after bored pile is set, in bored pile described in each, all reinforcing cage is set.
Further, in step 2, after building arbitrary section of side wall, bored pile is punchinged and by the second reinforcing bar, this section of side wall is fixed on the reinforcing cage of described bored pile at the place of punchinging.
Further, in step 1.2, also at described bored pile, high-pressure rotary jet grouting pile is set near the side of foundation ditch, and full hall arranges high-pressure rotary jet grouting pile in described foundation ditch.
Further, in step 2, described foundation ditch in the vertical direction to be excavated is divided into two sections, first paragraph construction saves side wall, under second segment construction, save side wall.
Further, in step 2, by holing, brushing the operation that hole, aperture blowing, injecting glue, bar planting and maintenance realize implantation first reinforcing bar on described shield structure pipeline.
Further, in step 3, base plate of foundation pit that section of jurisdiction and described shield structure bind on section of jurisdiction is bound to offer described first hole by the shield structure cut on described shield structure pipeline.
Further, in step 3, described static(al) cutting equipment is diamond barrel saw auger.
Compared with prior art, the invention provides the well construction method of riding on a kind of present situation operation shield method drainage pipe, present situation operation shield structure pipeline achieves the installation of well of riding, protect present situation operation shield structure pipeline, without the need to the drainage system relevant to present situation shield structure pipeline of stopping transport, achieve significant Social benefit and economic benefit; Complete the ride access of well and existing shield structure pipeline and the access with existing push pipe drainage pipe, make shield structure pipeline, ride well and push pipe integration stressed, shield structure pipeline can not be destroyed, protect the construction quality of engineering, and adopt static(al) patterning method to remove section of jurisdiction of binding, without the need to arranging simple and easy prestressing force tunnel frame, and then make construction very little on the impact of existing shield structure pipeline, easy construction, cost are lower, safety is high; Achieve ground stabilization by slip casting, improve the safety of construction.
Accompanying drawing explanation
The flow chart of the well construction method of riding on the present situation operation shield method drainage pipe that Fig. 1 provides for the embodiment of the present invention;
The top view of the foundation ditch that Fig. 2 provides for the embodiment of the present invention and foundation pit enclosure structure;
The upward view of the foundation ditch that Fig. 3 provides for the embodiment of the present invention and foundation pit enclosure structure;
The partial enlarged drawing of the foundation pit enclosure structure that Fig. 4 provides for the embodiment of the present invention;
The sectional view of the well system of riding after high-pressure rotary jet grouting pile is set in the well construction method of riding on the present situation operation shield method drainage pipe that Fig. 5 provides for the embodiment of the present invention;
The sectional view of the well system of riding after upper joint side wall is set in the well construction method of riding on the present situation operation shield method drainage pipe that Fig. 6 provides for the embodiment of the present invention;
The sectional view of the well system of riding after lower joint side wall is set in the well construction method of riding on the present situation operation shield method drainage pipe that Fig. 7 provides for the embodiment of the present invention;
The sectional view of the well system of riding after push pipe is set in the well construction method of riding on the present situation operation shield method drainage pipe that Fig. 8 provides for the embodiment of the present invention;
The sectional view of the well system of riding after offering the first hole in the well construction method of riding on the present situation operation shield method drainage pipe that Fig. 9 provides for the embodiment of the present invention;
The sectional view of the well system of riding after top board is set in the well construction method of riding on the present situation operation shield method drainage pipe that Figure 10 provides for the embodiment of the present invention;
The sectional view of the well system of riding after pit shaft is set in the well construction method of riding on the present situation operation shield method drainage pipe that Figure 11 provides for the embodiment of the present invention;
In well construction method of riding on the present situation operation shield method drainage pipe that Figure 12 provides for the embodiment of the present invention, well lid is set and carry out pit backfill and present situation road surface recover after the sectional view of well system of riding.
In figure, 1: well lid, 2: pit shaft, 3: well room, 4: shield structure pipeline, 5: base plate of foundation pit, 6: side wall, 7: push pipe, 8: the first reinforcing bars, 9: top board, 10: bored pile, 11: high-pressure rotary jet grouting pile, 12: the second reinforcing bars, 13: top beam, 14: hole end absolute altitude, 15: soil mass consolidation, 61: above save side wall, 62: under save side wall, 100: foundation ditch.
Detailed description of the invention
Below in conjunction with schematic diagram, the specific embodiment of the present invention is described in more detail.According to following description and claims, advantages and features of the invention will be clearer.It should be noted that, accompanying drawing all adopts the form that simplifies very much and all uses non-ratio accurately, only in order to object that is convenient, the aid illustration embodiment of the present invention lucidly.
As shown in figure 12, the utility model embodiment provides one and to ride well system, comprising:
To ride well, comprise well lid 1, pit shaft 2 and well room 3, described well lid 1 lid is located on pit shaft 2, and described pit shaft 2 is arranged on to be communicated with on well room 3 and with well room 3 and arranges;
Shield structure pipeline 4, be arranged in the soil body, described well room 3 is arranged on to be communicated with on shield structure pipeline 4 and with shield structure pipeline 4 and arranges, the bottom of described well room 3 is provided with base plate of foundation pit 5, described base plate of foundation pit 5 is fixed on the external surface of shield structure pipeline 4, described base plate of foundation pit 5 is also fixed on the borehole wall 6 of described well room 3, and described base plate 5 and shield structure pipeline 4 all have hole, and described well room 3 is communicated with shield structure pipeline 4 by described hole and arranges;
Push pipe 7, described push pipe 7 is arranged through the borehole wall 6 being communicated with well room 3 of described well room 3.
In the present embodiment, shield structure pipeline 4 refers to present situation operation shield method drainage pipe, the drainage pipe by shield construction namely runed.
Four sides side wall (also can be described as the borehole wall) 6 (can only provide two sides in Fig. 1) is enclosed to form well room 3, and the one or both sides side wall 6 laying direction along shield structure pipeline 4 of described well room 3 is connected with described push pipe 7.In the present embodiment, the side side wall 6 laying direction along shield structure pipeline 4 of described well room 3 is connected with described push pipe 7.
In the present embodiment, described shield structure pipeline 4 is fixed with the first reinforcing bar 8 exposing outside shield structure pipeline 4, the first reinforcing bar 8 exposing outside described shield structure pipeline is inserted and secured in described base plate of foundation pit 5, the top of described well room 3 is provided with top board 9, described top board 9 is fixed on the side wall 6 of described well room 3, and described pit shaft 2 to be communicated with well room 3 by the described top board 9 that has a hole and to arrange.
As shown in Figure 1, composition graphs 2 ~ 12, the embodiment of the present invention additionally provides the well construction method of riding on a kind of present situation operation shield method drainage pipe, comprising:
Step 1: as shown in Figure 2-5, the foundation ditch 100 to be excavated bottom being equipped with to shield structure pipeline builds foundation pit enclosure structure;
Step 2: as shown in figs. 6-7, described foundation ditch 100 in the vertical direction to be excavated is divided at least one section, if be divided into one section, till then first excavating described foundation ditch 100 absolute altitude 14 place at the bottom of the hole of setting, then on described shield structure pipeline 4, implant the first reinforcing bar 8, and build base plate of foundation pit 5 on described shield structure pipeline 4, make described first reinforcing bar 8 penetrate base plate of foundation pit 5, and make described base plate of foundation pit 5 be enclosed to form a well room 3 with side wall 6, build the side wall 6 of described foundation ditch 100 4 side, if be divided into multistage, then first excavate some sections before final stage, and often excavating the side wall 6 of one section of this section of after-pouring, and each section of side wall 6 about 6 to be connected with side wall the last period, till excavating final stage absolute altitude 14 place at the bottom of the hole of setting afterwards, then on described shield structure pipeline 4, the first reinforcing bar 8 is implanted, and base plate of foundation pit 5 is built on described shield structure pipeline 4, described first reinforcing bar 8 is made to penetrate base plate of foundation pit 5, finally build with the final stage side wall that the last period, side wall connected up and down to form the side wall 6 of described foundation ditch 100, and make the side wall 6 of described foundation ditch 100 be enclosed to form a well room 3 with base plate of foundation pit 5,
Step 3: as shown in Fig. 8 ~ 9, carry out jacking construction to make push pipe 7 through the side wall 6 of described foundation ditch 100 and to be connected with described well room 3, by static(al) cutting equipment continuous round hole, hole intersected to offer the first hole on described base plate of foundation pit 5 and shield structure pipeline 4 top, current are flowed into well room 3 from push pipe 7, and then flows in shield structure pipeline 4 by described first hole;
Step 4: as shown in Figure 10, arranges top board 9 on the top of described well room 3, and described top board 9 is fixed on the side wall 6 of foundation ditch 100, and offers the second hole (scheming not shown);
Step 5: as shown in Figure 11 ~ 12, described top board 9 is arranged through the pit shaft 2 that the second hole is connected with well room 3, arranges well lid 1 on described pit shaft 2 top.
In the present embodiment, in step 1, specifically comprise:
Step 1.1: the both sides along the direction that described shield structure pipeline 4 is laid bottom being equipped with to the foundation ditch 100 to be excavated of shield structure pipeline 4 all arrange bored pile 10, are achieved the function of only soil by the setting of bored pile 10;
Step 1.2: at side arranged and bored pile 10 overlap the high-pressure rotary jet grouting pile 11 of described bored pile 10 away from foundation ditch 100, the high-pressure rotary jet grouting pile 11 overlapped with bored pile 10 is set near the side of foundation ditch 100 at described bored pile 10, and full hall setting (being namely covered with) high-pressure rotary jet grouting pile 11 (please refer to Fig. 5 in described foundation ditch 100, and the high-pressure rotary jet grouting pile 11 in Fig. 2 in not shown foundation ditch 100), and two of arbitrary neighborhood high-pressure rotary jet grouting piles 11 are overlapped, the function of sealing is achieved by the high-pressure rotary jet grouting pile 11 arranging overlap joint with bored pile 10, high-pressure rotary jet grouting pile 11 is set by hall full in foundation ditch 100 and achieves the effect of reinforcing foundation ditch 100,
Step 1.3: arrange a position for hole end absolute altitude 14 in described foundation ditch 100, the below slip casting at absolute altitude 14 place at the bottom of described hole, to form soil mass consolidation 15, arranges top beam 13 on the top of described bored pile 10.
In the present embodiment, in step 1.1, after bored pile 10 is set, reinforcing cage (scheming not shown) is all set in bored pile 10 described in each.
High-pressure rotary jet grouting pile 11 adopts strength grade 42.5 grades of fresh Portland cements, and water/binder ratio is 0.7 ~ 1.0, and cement mixing content is not less than 25%, adopt tri-tube method construction technology, the pressure 28Mpa of cement paste, soil mass consolidation unconfined compression strength qu >=1.2Mpa, overlaps 200mm between stake.Bored pile 10 adopts c30 concrete under water, and main tendon protective layer gets 75mm, adopts the construction of GPS-10 type circulation drilling machine.
Slip casting adopts strength grade 42.5 grades of Portland cements, mix the flyash of 15%, slurries injection rate is 15%, grouting pressure 0.3 ~ 1.0Mpa, water/binder ratio is 0.5 ~ 0.6, injected hole spacing is 1.0m, adopts first peripheral rear inner delamination pour slurry form of construction work, adopts oblique slip casting bottom shield structure pipeline 4.
In step 2, after building arbitrary section of side wall, bored pile 10 is punchinged and by the second reinforcing bar 12, this section of side wall is fixed on the reinforcing cage of described bored pile 10 at the place of punchinging.
In addition, in step 2, if be divided into one section; then can first build base plate of foundation pit 5, then build side wall 6, if this is because first do not build base plate of foundation pit 5; but first build side wall 6, then bottom foundation ditch 100, soil block usually can swell, seep water, and affects construction quality, cost and duration.In like manner, if be divided into multistage, then the some sections of side walls 6 before first building final stage, then build base plate of foundation pit 5, finally build final stage side wall again, reason is the same.
In the present embodiment, described foundation ditch 100 in the vertical direction to be excavated is divided into two sections, first paragraph construction saves side wall 61, under second segment construction, save side wall 62.
Foundation ditch 100 adopts long-armed backacter to excavate, and first applies steel bar concrete top beam 13 before excavation, can excavate after top beam 13 intensity reaches design strength.First time is excavated to bottom joint side wall 61, build joint side wall 61, and by the second reinforcing bar 12, upper joint side wall is fixed on bored pile 10, after upper joint side wall 61 steel bar concrete intensity reaches design strength, continue the position of downward excavation pit 100 to hole end absolute altitude 14.The reinforcing situation of the excavation soil body should be checked in digging process, if any leaking, bubbling phenomenon, should adopt in time and mend slurry measure, run off with the soil body under shield structure pipeline 4.
In step 2, by holing, brushing the operation that hole, aperture blowing, injecting glue, bar planting and maintenance realize implantation first reinforcing bar 8 on described shield structure pipeline 4.In addition, also need to carry out preparation of construction before boring, also need first to carry out reinforcing bar process injecting glue again after aperture blowing, the operation of implanting the first reinforcing bar 8 specifically comprises following step:
1) preparation of construction: bar planting position is cleaned out, carry out bar planting construction by former design drawing distributed steel requirement, as operating mode is complicated, in shield structure pipeline 4, original reinforcing bar is more, the position of original reinforcing bar found out by available reinforcing bar survey meter, avoids former reinforcement location red paint as far as possible and marks bar planting point position;
2) hole: the drill bit selecting coupling according to bar planting specification, and make sounding mark.Then drill bit aims at the bar planting point position startup electric hammer put well, ensures that boring vertical (or level) reaches the degree of depth of setting;
3) hole and aperture blowing is brushed: first use the dust within the scope of row brush cleaning hole limit 20cm, again with hairbrush rotating brush hole 3 times repeatedly up and down, then hole Bottom Blowing is extended to discharging without obvious dust with special inflator (or air pump), repeat aforesaid operations 2 times, to reach clean free from dust in hole, and carry out temporary plugging with staple, enter to prevent foreign material;
4) reinforcing bar process: will imbed part reinforcing bar polishing rust cleaning in hole with sander, polishing rust cleaning length should be greater than bar planting degree of depth 2cm;
5) injecting glue: capsule is put into colloid-injecting gun, extrude initial a bit of glue need not, then stretch at the bottom of hole by glue rifle, glue rifle is extracted on plastic squeeze limit, limit, makes 2/3 degree of depth in glue injection hole;
6) bar planting: reinforcing bar inserts in bar planting hole by eliminating rust, and inserts to same direction slow circumvolve, till bottom arrival hole, now should have anchor adhesive to overflow in hole;
7) maintenance: carry out natural curing in 24 hours after bar planting and forbid to touch reinforcing bar, is beneficial to structure glue solidification, can does pull-out test after three days.
Boring adopts the impact drilling, and bit diameter should about 4 ~ 8mm larger than bar diameter, and bar diameter is Φ 12, and drill bit selects the alloy bit of φ 18.Drilling depth requires according to " concrete structure reinforcement design specifications " GB50367-2006: be not less than 20d (d is bar diameter), actual drilling depth should get 250mm, and drill bit keeps vertical with the section of jurisdiction of shield structure pipeline 4 all the time.
In the present embodiment, in step 3, base plate of foundation pit 5 that section of jurisdiction and described shield structure bind on section of jurisdiction is bound to offer described first hole by the shield structure cut on described shield structure pipeline 4.
In the present embodiment, described static(al) cutting equipment is diamond barrel saw auger.Diamond barrel saw auger is made up of frame, Buddha's warrior attendant drilling pipe, hydraulic oil pump etc., and this technique has that construction operation speed is fast, noise is low, shockproof, the advantages such as no dust pollution.Cutting flow process is location, unwrapping wire → brill fabrication hole (lifting eye) → hang in advance → broken concrete in reeve → cutting → cleaning edge → concrete block lifts by crane, transports.
1) location, unwrapping wire: adopt measuring apparatus, to plan cutting part location, adopts ink fountain to carry out snap the line, determines cutting position, the accuracy of guarantee cutting position;
2) fabrication hole (lifting eye) is bored;
3) hang in advance;
4) reeve;
4) cut: adopt the drilling of diamond barrel saw auger, connect hole and become line, finally make the shaping that punches, boring is general adopts the operation of Φ 102 diamond bit, and require the accurate positioning of drilling hole position, position deviation must not more than 10mm.Boring Duplication is 1.1 (i.e. adjacent holes position overlaps 10%), continuous round, and hole, hole is intersected, i.e. so-called " ten brills add a brill ", after round cutting, limit, hole leaves bent tooth section, uses and pick boring tool by artificial for cut surface chipping in subsequent construction;
5) concrete block lifts by crane, transports: after having cut, concrete block mobile crane is hung out foundation ditch 100, the hole not place of meeting the demands carries out repairing or removing, and is cleared in time by the rubbish of dismounting part.
The construction method of diamond barrel saw auger round drilling is adopted to have following beneficial effect:
1) friction static(al) cutting
Lower grinding is carried out to steel concrete because static(al) cutting is diamond instrument running up, the break flour produced is taken away by cooling water, final formation cut surface, so there is not vibration problem, to former reservation structure without impact, micro-crack can not be produced and destroy, not affect structure stress and application life, this is that the method for dismounting of other type cannot be accomplished, therefore the method is more suitable for withing a hook at the end the concrete Demolition Construction of structure.
2) low noise
Only have the sound of grinding steel concrete in diamond instrument cutting process, electric hydaulic motor running is steady, and do not have ear-piercing sound in whole construction, the volume of generation can control within 44dBA.
3) pollution-free
Adopt the diamond instrument that water cooling runs up in work progress, and the iron filings ground away and concrete break flour are carried away, the cooling water unharmful substance of generation, cooling water can reuse after scene is reclaimed.The splashing of corresponding closed controlling measurement water is taked in construction.
4) mechanization degree is high, and operating personnel's quantity is few
Static(al) cutting is in current demolition reduction field, the mechanized operation work post that labour intensity is minimum, and its technology content, far beyond the concept of traditional Mechanical Crushing, is the preferred plan of international structure retention dismounting of comparatively generally acknowledging at present.On the other hand on certain operational level, not only its efficiency of construction is high, and operating personnel can greatly reduce, and is conducive to the raising of overall economic efficiency.
5) non-destructive Demolishing Technology safeguard
Adopt non-destructive Demolition Scheme significant to reservation safety of structure, its key problem in technology is correct enforcement construction technology technique and arranged rational working procedure in work progress, is equipped with the safe handling of crane.First answer the plant equipment that selectivity is intact, for the height of concrete grade and inner reinforcing bar content number correctly select the performance of diamond instrument, only in this way guarantee is hit the target smoothly task within the control duration.
In steps of 5, specifically comprise:
Step 5.1: pit shaft 2 is set on described top board 9, described pit shaft 2 is connected with described well room 3 by the second hole;
Step 5.2: well lid 1 is set on described pit shaft 2 top.
In addition, after step 5.2, also need to carry out pit backfill and the recovery operation of present situation road surface.
Compared with prior art, the invention provides the well construction method of riding on a kind of present situation operation shield method drainage pipe, present situation operation shield structure pipeline achieves the installation of well of riding, protect present situation operation shield structure pipeline, without the need to the drainage system relevant to present situation shield structure pipeline of stopping transport, achieve significant Social benefit and economic benefit; Complete the ride access of well and existing shield structure pipeline and the access with existing push pipe drainage pipe, make shield structure pipeline, ride well and push pipe integration stressed, shield structure pipeline can not be destroyed, protect the construction quality of engineering, and adopt static(al) patterning method to remove section of jurisdiction of binding, without the need to arranging simple and easy prestressing force tunnel frame, and then make construction very little on the impact of existing shield structure pipeline, easy construction, cost are lower, safety is high; Achieve ground stabilization by slip casting, improve the safety of construction.
Above are only the preferred embodiments of the present invention, any restriction is not played to the present invention.Any person of ordinary skill in the field; in the scope not departing from technical scheme of the present invention; the technical scheme disclose the present invention and technology contents make the variations such as any type of equivalent replacement or amendment; all belong to the content not departing from technical scheme of the present invention, still belong within protection scope of the present invention.

Claims (10)

1. the well construction method of riding on present situation operation shield method drainage pipe, is characterized in that, comprising:
Step 1: the foundation ditch to be excavated bottom being equipped with to shield structure pipeline builds foundation pit enclosure structure;
Step 2: described foundation ditch in the vertical direction to be excavated is divided at least one section, if be divided into one section, till then first excavating described foundation ditch absolute altitude place at the bottom of the hole of setting, then on described shield structure pipeline, the first reinforcing bar is implanted, and base plate of foundation pit is built on described shield structure pipeline, make described first reinforcing bar penetrate base plate of foundation pit, and make described base plate of foundation pit and side wall be enclosed to form a well room, build the side wall of described foundation ditch four side, if be divided into multistage, then first excavate some sections before final stage, and often excavating the side wall of one section of this section of after-pouring, and each section of side wall is connected up and down with side wall the last period, till excavating final stage absolute altitude place at the bottom of the hole of setting afterwards, then on described shield structure pipeline, the first reinforcing bar is implanted, and base plate of foundation pit is built on described shield structure pipeline, described first reinforcing bar is made to penetrate base plate of foundation pit, finally build with the final stage side wall that the last period, side wall connected up and down to form the side wall of described foundation ditch, and make the side wall of described foundation ditch and base plate of foundation pit be enclosed to form a well room,
Step 3: carry out jacking construction and pass the side wall of described foundation ditch to make push pipe and be connected with described well room, makes hole, hole to intersect to offer the first hole on described base plate of foundation pit and shield structure pipeline top by the continuous round of static(al) cutting equipment;
Step 4: arrange top board on the top of described well room, described top board is fixed on the side wall of foundation ditch, and offers the second hole;
Step 5: be arranged through the pit shaft that the second hole is connected with well room on described top board, arranges well lid on described pit shaft top.
2. the well construction method of riding on present situation operation shield method drainage pipe as claimed in claim 1, is characterized in that, in step 1, specifically comprise:
Step 1.1: both sides bottom being equipped with to the direction along the pipe laying of described shield structure of the foundation ditch to be excavated of shield structure pipeline all arrange bored pile;
Step 1.2: at side arranged and bored pile overlap the high-pressure rotary jet grouting pile of described bored pile away from foundation ditch.
3. the well construction method of riding on present situation operation shield method drainage pipe as claimed in claim 2, is characterized in that, in step 1, also comprise:
Step 1.3: arrange a position for hole end absolute altitude in described foundation ditch, the below slip casting at absolute altitude place at the bottom of described hole, arranges top beam on the top of described bored pile.
4. the well construction method of riding on present situation operation shield method drainage pipe as claimed in claim 2, is characterized in that, in step 1.1, after arranging bored pile, all arrange reinforcing cage in bored pile described in each.
5. the well construction method of riding on present situation operation shield method drainage pipe as claimed in claim 4, it is characterized in that, in step 2, after building arbitrary section of side wall, bored pile is punchinged and by the second reinforcing bar, this section of side wall is fixed on the reinforcing cage of described bored pile at the place of punchinging.
6. the well construction method of riding on present situation operation shield method drainage pipe as claimed in claim 2, it is characterized in that, in step 1.2, also at described bored pile, high-pressure rotary jet grouting pile is set near the side of foundation ditch, and full hall arranges high-pressure rotary jet grouting pile in described foundation ditch.
7. the well construction method of riding on present situation operation shield method drainage pipe as claimed in claim 1, it is characterized in that, in step 2, described foundation ditch in the vertical direction to be excavated is divided into two sections, first paragraph construction saves side wall, under second segment construction, saves side wall.
8. the well construction method of riding on present situation operation shield method drainage pipe as claimed in claim 1, is characterized in that, in step 2, by holing, brushing the operation that hole, aperture blowing, injecting glue, bar planting and maintenance realize implantation first reinforcing bar on described shield structure pipeline.
9. the well construction method of riding on present situation operation shield method drainage pipe as claimed in claim 1, it is characterized in that, in step 3, base plate of foundation pit that section of jurisdiction and described shield structure bind on section of jurisdiction is bound to offer described first hole by the shield structure cut on described shield structure pipeline.
10. the well construction method of riding on present situation operation shield method drainage pipe as claimed in claim 1, it is characterized in that, in step 3, described static(al) cutting equipment is diamond barrel saw auger.
CN201510250348.0A 2015-05-15 2015-05-15 A kind of well construction method of riding on present situation operation shield method drainage pipeline Active CN104988981B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510250348.0A CN104988981B (en) 2015-05-15 2015-05-15 A kind of well construction method of riding on present situation operation shield method drainage pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510250348.0A CN104988981B (en) 2015-05-15 2015-05-15 A kind of well construction method of riding on present situation operation shield method drainage pipeline

Publications (2)

Publication Number Publication Date
CN104988981A true CN104988981A (en) 2015-10-21
CN104988981B CN104988981B (en) 2016-07-06

Family

ID=54300862

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510250348.0A Active CN104988981B (en) 2015-05-15 2015-05-15 A kind of well construction method of riding on present situation operation shield method drainage pipeline

Country Status (1)

Country Link
CN (1) CN104988981B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120860A (en) * 2016-07-05 2016-11-16 陈俊光 A kind of assembled work well installation method in reconstruction and extension project
CN106193123A (en) * 2016-07-05 2016-12-07 陈俊光 A kind of assembled work well standard knot and the installation method in reconstruction and extension project thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU781283A2 (en) * 1979-01-04 1980-11-23 Центральный научно-исследовательский институт комплексного использования водных ресурсов Arrangement for pumping liquid from a well
DK172197B1 (en) * 1996-02-09 1997-12-22 Justi Poulsen Collecting drain with sediment collecting bag and stench trap
CN103821219A (en) * 2014-03-03 2014-05-28 永升建设集团有限公司 Top pipe construction modification inspection well construction method
CN203729424U (en) * 2014-03-03 2014-07-23 永升建设集团有限公司 Modified horseback-riding inspection well for top pipe construction
CN204163178U (en) * 2014-10-21 2015-02-18 合肥市市政设计院有限公司 Push pipe interval combinations manhole
CN204326104U (en) * 2014-12-08 2015-05-13 宁波市政工程建设集团股份有限公司 A kind of well device of riding for jacking construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU781283A2 (en) * 1979-01-04 1980-11-23 Центральный научно-исследовательский институт комплексного использования водных ресурсов Arrangement for pumping liquid from a well
DK172197B1 (en) * 1996-02-09 1997-12-22 Justi Poulsen Collecting drain with sediment collecting bag and stench trap
CN103821219A (en) * 2014-03-03 2014-05-28 永升建设集团有限公司 Top pipe construction modification inspection well construction method
CN203729424U (en) * 2014-03-03 2014-07-23 永升建设集团有限公司 Modified horseback-riding inspection well for top pipe construction
CN204163178U (en) * 2014-10-21 2015-02-18 合肥市市政设计院有限公司 Push pipe interval combinations manhole
CN204326104U (en) * 2014-12-08 2015-05-13 宁波市政工程建设集团股份有限公司 A kind of well device of riding for jacking construction

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120860A (en) * 2016-07-05 2016-11-16 陈俊光 A kind of assembled work well installation method in reconstruction and extension project
CN106193123A (en) * 2016-07-05 2016-12-07 陈俊光 A kind of assembled work well standard knot and the installation method in reconstruction and extension project thereof
CN106120860B (en) * 2016-07-05 2018-04-13 陈俊光 A kind of installation method of assembly type work well in reconstruction and extension project
CN106193123B (en) * 2016-07-05 2018-04-24 陈俊光 A kind of assembled work well standard knot and its installation method in reconstruction and extension project

Also Published As

Publication number Publication date
CN104988981B (en) 2016-07-06

Similar Documents

Publication Publication Date Title
CN104032758B (en) Extra-high reinforced construction method in discarded pit
CN110344400B (en) Hole-forming pile-forming construction process for rotary drilling rig in hard rock
CN110512892B (en) Construction method for repairing existing ancient city wall
CN110359467A (en) A kind of construction method that base pit engineering high-pressure rotary jet grouting pile is reinforced
CN102758458B (en) Underground continuous wall repairing method
CN105442605B (en) Extract PHC and be reused in deep foundation pit supporting construction method
CN107574834A (en) A kind of old basic transformation reinforcement means of power machine
CN111519679A (en) Rapid grooving construction method for micro-weathering rock of diaphragm wall
CN107524141B (en) Construction method of cast-in-situ bored pile of rock soil foundation
CN102505709A (en) Concrete-formwork-precast foundation construction method
CN105155550A (en) Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
CN105442532A (en) Construction method for pile-head-expanded bored pile
CN113235601A (en) Deep foundation pit construction risk control structure and method for collapsible loess adjacent building
CN110984221A (en) Construction method for reinforcing end socket at initial end of air shaft and guide wall structure
CN107989049A (en) A kind of construction method of frame bank protection
CN111778941A (en) High-standard farmland channel construction method and structure
CN105386610A (en) Protective construction method for natural-foundation ancient architectures at top of asymmetric deep foundation pit
CN101994314A (en) Longhole rectangular terraced antiskid pile jump-preventing excavating construction
CN104988981B (en) A kind of well construction method of riding on present situation operation shield method drainage pipeline
CN117449423A (en) Construction process for newly-built inspection well under state of maintaining water flowing state of existing pipeline
CN211898541U (en) Guide wall structure for reinforced structure of air shaft initial end head
CN204715502U (en) To ride well system
CN105002891B (en) A kind of cast-in-situ bored pile exempts from inter-pile soil excavation construction method
CN111561262A (en) Hole forming method of rotary drilling rig for large-size pile hole in karst area
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant