CN104947599B - 桥梁的顶推施工的方法 - Google Patents
桥梁的顶推施工的方法 Download PDFInfo
- Publication number
- CN104947599B CN104947599B CN201510209804.7A CN201510209804A CN104947599B CN 104947599 B CN104947599 B CN 104947599B CN 201510209804 A CN201510209804 A CN 201510209804A CN 104947599 B CN104947599 B CN 104947599B
- Authority
- CN
- China
- Prior art keywords
- bridge
- incremental launching
- launching construction
- fragment
- construction platform
- Prior art date
Links
- 238000010276 construction Methods 0.000 title claims abstract description 110
- 238000000034 methods Methods 0.000 claims description 10
- 210000001331 Nose Anatomy 0.000 description 11
- 238000004364 calculation methods Methods 0.000 description 3
- 238000005516 engineering processes Methods 0.000 description 3
- 239000000463 materials Substances 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 230000000875 corresponding Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 241001269238 Data Species 0.000 description 1
- 281000135227 Road and Bridge Construction companies 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000000203 mixtures Substances 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006011 modification reactions Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000005070 sampling Methods 0.000 description 1
- 239000007787 solids Substances 0.000 description 1
- 230000017105 transposition Effects 0.000 description 1
- 238000004450 types of analysis Methods 0.000 description 1
- 239000002699 waste materials Substances 0.000 description 1
- 239000011901 water Substances 0.000 description 1
Abstract
Description
技术领域
[0001]本发明涉及一种路桥施工技术,尤其涉及一种桥梁的顶推施工的方法。
背景技术
[0002]顶推施工方法多应用与预应力钢筋混凝土等截面连续梁桥和斜拉桥梁的施工。具体为梁体在桥头逐段浇筑或拼装,用千斤顶纵向顶推,使梁体通过各墩顶的临时滑动支座面就位的施工方法。顶推施工是在桥台的后方设置施工场地,分节段浇筑梁体,并用纵向预应力筋将浇筑节段与已完成的梁体连成整体,在梁体前安装长度为顶推跨径指定比例的钢导梁,然后通过水平千斤顶施力,将梁体向前方顶推出施工场地。重复这些工序即可完成全部梁体施工。
[0003]参考图1,现有的拼装平台长度通常只满足一个轮次主梁拼装长度要求,一轮顶出后平台上没有预留保持线型的梁段,使后续梁段无法实现无应力拼装线型;另一方面,参考图3和图4,现有的平台受力计算方法,考虑了平台上留有梁段下部全部支点的受力情况,却忽略了部分支点脱空对邻近支点受力的重分配的情况,在这个情况下所述邻近的局部支点受力增大,导致该处移位器和平台最大反力均增大。
[0004]导致上述缺点的原因是没有考虑已顶出平台部分主梁在自重作用下前端下挠,弓丨起整体梁底线型变化对后续平台上梁段拼装的影响。
发明内容
[0005]本发明的目的是,提供一种可实现复杂线形桥梁主梁的无应力拼装,确保顶推施工安全的方法,以及该方法所使用的顶推施工平台。
[0006]为达到以上技术目的,本发明采用的技术方案如下:
[0007] —种桥梁的顶推施工的方法,其包括以下步骤:
[0008] (I)搭设顶推施工平台;
[0009] (2)将多个预制的桥梁节段在所述顶推施工平台上拼装为当前桥梁片段;
[0010] (3)利用所述顶推施工平台将所述当前桥梁片段顶推至已顶出的桥梁片段的尾端以进行拼接;
[0011] (4)利用所述顶推施工平台继续顶推已经与已顶出的桥梁片段拼接好的当前桥梁片段,直至用于保持桥梁拼装线形的部分的所述当前桥梁片段预留在所述顶推施工平台上方;
[0012]其中,所述顶推施工平台的最小长度为当前待拼接的桥梁片段的长度与用于保持桥梁拼装线形的部分的已顶出的桥梁片段的长度之和。
[0013]为实现本发明的方法,具体地,所述顶推施工平台包括承重系统和设置在该承重系统上方的滑道系统。
[0014]优选地,所述滑道系统包括设置在所述承重系统上方的在所述顶推施工平台纵长方向延伸的滑道、多个由所述滑道限定移动轨迹的移位器,及用于调整所述移位器高度和水平位置的调节装置。
[0015] 更优地,所述滑道包括至少一条主滑道和至少一条与该主滑道平行的副滑道。
[0016]所述步骤(2)中,所述桥梁片段的形成步骤具体为:所述多个预制的桥梁节段分别吊装至所述顶推施工平台的上方,然后,使每个所述桥梁节段首尾相接得到所述桥梁片段。
[0017]所述步骤(3)和(4)中,所述顶推过程具体为:每顶推出单位长度,控制所述已拼接好的桥梁片段和顶推施工平台的接触位置所受到的力不超过预设的阈值。优选地,所述单位长度为lm。
[0018]所述步骤(4)完成后,所述顶推施工平台回归到执行所述步骤(2)之前的位置。
[0019]具体地,所述顶推施工平台执行步骤(2)之前的位置为:所述移位器位于所述主滑道的中间或尾端位置。
[0020]所述顶推施工平台回归到执行步骤(2)之前的位置的方法为:将位于所述主滑道前端的移位器转移到所述副滑道的前端,所述移位器沿该副滑道滑行到副滑道的尾端,再将该移位器从所述副滑道的尾端转移到所述主滑道的中间或尾端。
[0021]与现有技术相比较,本发明具有如下优势:
[0022] (I)本发明提供的顶推施工方法,在满足主梁稳定性要求的基础上,在所述顶推施工平台上预留部分已顶出的桥梁片段,以用于保证在无应力的情况下保持桥梁的拼装线形,以保证桥梁拼装的准确性,保证施工质量;
[0023] (2)本发明提供的顶推施工方法,按照每顶推Im作为一个施工阶段,足够的数据取样点真实地反映了顶推施工过程中所述顶推施工平台的受力情况,不仅在施工过程中保证了施工安全、保证施工质量,也为计算顶推施工平台的最小长度提供了建模计算的依据;
[0024] (3)结合顶推施工平台最小长度的计算方法以及顶推过程的工序设计,本发明提供的顶推施工方法可以应用在具有复杂线性的桥梁的建设施工过程,使本发明的方法具有广泛的适用性。
附图说明
[0025]图1为现有技术的顶推施工方法的工作状态示意图,其中,顶推施工平台的长度为当前待拼接的桥梁片段的长度。
[0026]图2为本发明的顶推施工方法的工作状态示意图,其中,顶推施工平台的长度为当前待拼接的桥梁片段的长度和用于保持桥梁拼装线形的部分的已顶出的桥梁片段的长度之和。
[0027]图3为现有技术中不考虑已顶出的桥梁片段因自重引起的形变的状态下桥梁片段与顶推施工平台的接触情况,其中,示意桥梁片段与顶推施工平台的所有支点相互接触。
[0028]图4为图3中C部分的局部放大示意图。
[0029]图5为本发明的顶推施工方法中考虑已顶出的桥梁片段因自重引起的形变的状态下桥梁片段与顶推施工平台的接触情况,其中,示意桥梁片段与顶推施工平台的部分支点脱离接触。
[°03°]图6为图5中D部分的局部放大不意图。
具体实施方式
[0031]以下结合附图和具体实施方式对本发明作进一步详细描述。
[0032]参考图2,本发明的桥梁的顶推施工的方法可以应用在比如某大桥的建设中,具体施工工序包括如下步骤:
[0033] (I)搭设顶推施工平台I;
[0034]所述顶推施工平台I包括承重系统11和设置在该承重系统11上方的滑道系统12。优选地,所述滑道系统12包括设置在所述承重系统11上方的在所述顶推施工平台I纵长方向延伸的滑道、多个由所述滑道限定移动轨迹的移位器,及用于调整所述移位器高度和水平位置的调节装置。更优地,所述滑道包括至少一条主滑道和至少一条与该主滑道平行的副滑道。
[0035] (2)将多个预制的桥梁节段在所述顶推施工平台上拼装为当前桥梁片段3b;
[0036]所述桥梁片段3b的形成步骤具体为:所述多个预制的桥梁节段分别吊装至所述顶推施工平台I的上方,具体是吊装至所述移位器上方,使每个所述桥梁节段由若干个所述移位器支撑;然后,使每个所述桥梁节段首尾相接得到所述桥梁片段3b。
[0037] (3)利用所述顶推施工平台I将所述当前桥梁片段3b顶推至已顶出的桥梁片段3a的尾端并且将两者拼接起来。
[0038] (4)利用所述顶推施工平台I继续顶推已经与已顶出的桥梁片段3a拼接好的当前桥梁片段3b,直至用于保持桥梁拼装线形的部分的所述当前桥梁片段3al预留在所述顶推施工平台I上方;
[0039]所述步骤(3)和(4)的顶推过程具体为:每顶推出lm,控制所述已拼接好的桥梁片段3b和顶推施工平台I接触位置所受到的力不超过预设的阈值;所述顶推出的Im被定义为单位长度,该单位长度可根据实际的施工要求进行调整。
[0040] (5)将所述顶推施工平台I回归到执行所述步骤(2)之前的位置;
[0041 ]所述位置具体为:所述移位器位于所述主滑道的中间或尾端位置;所述顶推施工平台I回归到执行步骤(2)之前的位置的方法为:将位于所述主滑道前端的移位器转移到所述副滑道的前端,所述移位器沿该副滑道滑行到副滑道的尾端,再将该移位器从所述副滑道的尾端转移到所述主滑道的中间或尾端。
[0042] (6)重复步骤(2)〜(5),直至完成所有桥梁片段的拼接及顶推。
[0043]根据桥位附近地形条件和顶推工艺要求,所述某大桥南岸的钢槽梁的顶推施工平台I沿桥轴线纵向布置在PS12#墩到接线墩之间,设计长110m,宽16m,其中,该顶推施工平台I的长度为11个预设的桥梁节段的长度之和,所述11个桥梁节段包括3个已顶出的桥梁节段和9个待拼接的桥梁节段。
[0044]所述顶推施工平台I的长度的设计是本发明的桥梁的顶推施工的方法的关键技术之一。所述顶推施工平台I的长度影响了顶推施工工序的工效效率和施工质量:若所述顶推施工平台I的长度过小,每一轮作业所能拼接的桥梁节段的数目或桥梁片段的长度过小,影响施工进度,也浪费人力物力;若所述顶推施工平台I的长度过大,每一轮作业所拼接的桥梁节段数目过多或桥梁片段的长度过大,影响顶推过程的施工安全性,也难于控制无应力状态下的拼接线形;若不充分利用该顶推施工平台I的施工空间,便浪费了该顶推施工平台的材料成本。因此,所述顶推施工平台应当设有“最小长度”,并且,要充分考虑现有顶推施工方法中无应力拼装的要求。
[0045]在桥梁进行顶推施工过程中,本领域技术人员公知需要设置位于主梁体前端的导梁,所述导梁用于引导主梁体在顶推工程中顺利通过预设墩柱(如前述的PS12#墩和接线墩),并且通过检测所述导梁的状态,及时了解主梁的内部应力的变化及线形的变化,以及时调整施工的控制参数。
[0046]本实施例中,所述顶推施工平台的最小长度的确定分如下两步:其一,计算导梁第一次上墩柱前形成最大悬臂状态下的应力情况,此状态下的所述导梁的前端与所述顶推施工平台的前端距离85.5m,该导梁前端下挠65mm;其二,计算后续的与所述导梁依次拼接的组成主梁体的桥梁节段的应力情况。
[0047]具体地,所述导梁和桥梁节段都通过有限元分析方法建立实体模型,设定导梁和桥梁节段相应的材料密度,并且,设定所述导梁和桥梁节段分别与所述顶推施工平台之间只受因导梁和桥梁节段的自重产生压力以及由所述压力引起的形变。所述有限元分析方法,指利用数学近似的方法对真实物理系统(几何和载荷工况)进行模拟,并且,利用简单而又相互作用的元素,即单元,用有限数量的未知量去逼近无限未知量的真实系统。上述关于顶推过程的控制方法,实质上也是所述采用有限元分析方法来建立实体模型的数据收集方法。参考图5和图6,当划分出适当的单元(即单位长度的桥梁段,所述单位长度即顶推的单位长度),可测得靠近所述顶推施工平台I前端的部分移位器121由于所述已顶出的桥梁片段3a在自重作用下产生下挠因而导致脱空,该移位器121的顶端与当前桥梁片段3b之间产生间隙α,从而导致该脱空的移位器121邻近的移位器的受力重新分布,在进行实体建模计算的时候,前述状态下的每个所述移位器121的受力情况是重要的统计数据。
[0048]参考图2,通过上述计算方法,找出每一轮顶推工序后所述已顶出的桥梁片段3a预留在所述顶推施工平台I上的应力最小时的桥梁片段的长度或者相应的桥梁节段的个数,并以此作为用于无应力保持桥梁拼装线性的预留梁段。由此,所述顶推施工平台的最小长度为当前待拼接的桥梁片段3b的长度与用于保持桥梁拼装线形的部分的已顶出的桥梁片段3al的长度之和。
[0049]综上所述,本发明桥梁的顶推施工的方法保证了桥梁拼装的准确性,也保证了施工质量,具有广泛的适用性。
[0050]上述实施例为本发明较佳的实施方式,但并不仅仅受上述实施例的限制,其他的任何未背离本发明的精神实质与原理下所作的改变、修饰、替代、组合、简化,均应为等效的置换方式,均包含在本发明的保护范围之内。
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510209804.7A CN104947599B (zh) | 2015-04-27 | 2015-04-27 | 桥梁的顶推施工的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510209804.7A CN104947599B (zh) | 2015-04-27 | 2015-04-27 | 桥梁的顶推施工的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104947599A CN104947599A (zh) | 2015-09-30 |
CN104947599B true CN104947599B (zh) | 2017-01-25 |
Family
ID=54162624
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510209804.7A CN104947599B (zh) | 2015-04-27 | 2015-04-27 | 桥梁的顶推施工的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104947599B (zh) |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004107972A (ja) * | 2002-09-18 | 2004-04-08 | Mitsubishi Heavy Ind Ltd | 橋梁の送出し工法及び手延機 |
CN100577915C (zh) * | 2007-08-22 | 2010-01-06 | 中铁大桥局股份有限公司 | 大跨度连续钢桁拱的架设方法 |
CN102877421B (zh) * | 2012-09-17 | 2014-07-23 | 长沙理工大学 | 顶推施工梁体无应力线形高精度实现的施工控制方法 |
CN103510475B (zh) * | 2013-09-27 | 2015-09-23 | 中铁大桥局集团有限公司 | 三主桁钢桁梁单联双跨无导梁长距离顶推施工方法 |
-
2015
- 2015-04-27 CN CN201510209804.7A patent/CN104947599B/zh active IP Right Grant
Also Published As
Publication number | Publication date |
---|---|
CN104947599A (zh) | 2015-09-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Do et al. | Three-dimensional numerical simulation for mechanized tunnelling in soft ground: the influence of the joint pattern | |
Cheng et al. | Finite element analysis of tunnel–soil–pile interaction using displacement controlled model | |
Wheeler et al. | Coupling of hydraulic hysteresis and stress–strain behaviour in unsaturated soils | |
Arnau et al. | Experimental and analytical study of the structural response of segmental tunnel linings based on an in situ loading test. Part 2: Numerical simulation | |
Remennikov et al. | Reliability-based conversion of a structural design code for railway prestressed concrete sleepers | |
O'connor et al. | Traffic load modelling and factors influencing the accuracy of predicted extremes | |
Liu et al. | Effects of tunnelling on existing support systems of perpendicularly crossing tunnels | |
Molins et al. | Experimental and analytical study of the structural response of segmental tunnel linings based on an in situ loading test.: Part 1: Test configuration and execution | |
Katebi et al. | Assessment the influence of ground stratification, tunnel and surface buildings specifications on shield tunnel lining loads (by FEM) | |
Karakus | Appraising the methods accounting for 3D tunnelling effects in 2D plane strain FE analysis | |
Bernat et al. | Soil-structure interaction in shield tunnelling in soft soil | |
Marzouk et al. | Implementing earned value management using bridge information modeling | |
Bhasi et al. | Numerical study of basal reinforced embankments supported on floating/end bearing piles considering pile–soil interaction | |
Ji et al. | Evaluation on root-deck fatigue of orthotropic steel bridge deck | |
Casas | Reliability-based assessment of masonry arch bridges | |
Jung et al. | Verification of incremental launching construction safety for the ilsun bridge, the world’s longest and widest prestressed concrete box girder with corrugated steel web section | |
Argyroudis et al. | Fragility functions of highway and railway infrastructure | |
CN104897491B (zh) | 钢桥面铺装疲劳开裂试验装置及方法 | |
EP2803968B1 (en) | A process for calculating fatigue and fatigue failure of structures | |
CN104652279A (zh) | 一种新建框架桥上穿既有地铁结构箱涵顶进施工方法 | |
Hughes et al. | A review of the UK masonry arch assessment methods. | |
Chen et al. | Proposed effective width criteria for composite bridge girders | |
ES2692221T3 (es) | Método implementado en un ordenador para la simulación numérica de un medio poroso | |
Sharifzadeh et al. | Design of sequential excavation tunneling in weak rocks through findings obtained from displacements based back analysis | |
Lowson et al. | Critical assessment of RMR based tunnel design practices: a practical engineer’s approach |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
COR | Change of bibliographic data | ||
CB03 | Change of inventor or designer information |
Inventor after: Liu Huaigang Inventor after: Gao Shiqiang Inventor after: Xiao Xiangrong Inventor after: Ma Shuiying Inventor after: Fei Yongzhong Inventor after: Hu Jianfeng Inventor after: Tan Xinghua Inventor after: Zhang Zheng Inventor after: Ge Jiping Inventor before: Xiao Xiangrong Inventor before: Gao Shiqiang Inventor before: Ma Shuiying Inventor before: Liu Huaigang Inventor before: Hu Jianfeng Inventor before: Tan Xinghua Inventor before: Zhang Zheng Inventor before: Ge Jiping |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Liu Huaigang Inventor after: Gao Shiqiang Inventor after: Xiao Xiangrong Inventor after: Ma Shuiying Inventor after: Fei Yongzhong Inventor after: Hu Jianfeng Inventor after: Tan Xinghua Inventor after: Zhang Zheng Inventor after: Ge Jiping Inventor before: Liu Huaigang Inventor before: Gao Shiqiang Inventor before: Xiao Xiangrong Inventor before: Ma Shuiying Inventor before: Fei Yongzhong Inventor before: Hu Jianfeng Inventor before: Tan Xinghua Inventor before: Zhang Zheng Inventor before: Ge Jiping |