CN104841725B - Rolling method for head-to-tail connection of jaw cylinder - Google Patents

Rolling method for head-to-tail connection of jaw cylinder Download PDF

Info

Publication number
CN104841725B
CN104841725B CN201410050278.XA CN201410050278A CN104841725B CN 104841725 B CN104841725 B CN 104841725B CN 201410050278 A CN201410050278 A CN 201410050278A CN 104841725 B CN104841725 B CN 104841725B
Authority
CN
China
Prior art keywords
steel coil
head
reel
tail
strip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410050278.XA
Other languages
Chinese (zh)
Other versions
CN104841725A (en
Inventor
刘涛
杨征
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baoshan Iron and Steel Co Ltd
Original Assignee
Baoshan Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baoshan Iron and Steel Co Ltd filed Critical Baoshan Iron and Steel Co Ltd
Priority to CN201410050278.XA priority Critical patent/CN104841725B/en
Publication of CN104841725A publication Critical patent/CN104841725A/en
Application granted granted Critical
Publication of CN104841725B publication Critical patent/CN104841725B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Winding, Rewinding, Material Storage Devices (AREA)

Abstract

本发明是一种钳口式卷筒头尾连接的卷取方法,包括:在前一个钢卷成卷后将压紧辊压下并将钢卷带钢尾部停留在大约时钟12点钟方向;将带钢头部穿带在上一钢卷带钢尾部的下层,并使其头部位置固定在上一钢卷尾部最外圈与倒数第二圈之间;使钢卷穿带前进到带钢头部到达夹层顶部至轻微拱起为止;使卷筒倒转使钢卷尾部倒出一段距离;手动使卷筒正转进行卷取,通过压紧辊将下一钢卷带钢的头部咬入到卷筒上前一钢卷的夹层中,使手动咬入长度达到卷筒上前一钢卷至少2圈的长度;使上一钢卷的带钢头部通过夹层间的接触摩擦力完全固定,以便由自动切入张力对接入的钢卷进行卷取。本发明解决了小卷成卷周期短、而设备卸卷周期较长的矛盾,提高了生产效率。

The present invention is a coiling method for connecting the head and the tail of a jaw-type reel, comprising: after the previous steel coil is coiled, the pinch roller is pressed down and the tail of the steel coil and strip stays at about 12 o'clock of the clock; Thread the head of the strip on the lower layer of the tail of the previous steel coil, and fix the position of the head between the outermost circle and the penultimate circle of the tail of the previous steel coil; make the steel coil thread forward to the belt The steel head reaches the top of the interlayer until it is slightly arched; the reel is turned upside down to make the tail of the steel coil fall out for a certain distance; Insert it into the interlayer of the previous steel coil on the reel, so that the manual biting length reaches the length of at least 2 turns of the previous steel coil on the reel; make the strip head of the previous steel coil pass through the contact friction between the interlayers completely. Fixed so that the incoming coil is coiled by automatic cut-in tension. The invention solves the contradiction that the period of forming small rolls is short and the period of equipment unloading is long, and improves the production efficiency.

Description

钳口式卷筒头尾连接的卷取方法Coiling method of head-to-tail connection of jaw type reel

技术领域technical field

本发明涉及一种卷线机卷筒的带钢卷取方法,尤其是指一种钳口式卷筒头尾连接的卷取方法。The invention relates to a strip steel coiling method for a reel of a winding machine, in particular to a coiling method for connecting the head and the tail of a jaw type reel.

背景技术Background technique

卷线机组基本配备的大多是钳口式卷筒,该类卷筒每次卷取带钢要求钢卷头部放入钳口,钳口收紧夹住带钢头部后进行卷取。在生产过程中由于卸卷小车送卷后归位需要一定的周期,存在小车等待卸卷的现象。Most of the coiling units are basically equipped with jaw-type reels. Each time the coil is coiled, the head of the steel coil is required to be placed in the jaws, and the jaws are tightened to clamp the head of the strip before coiling. In the production process, it takes a certain period of time for the roll unloading trolley to return to the original position after delivering the roll, so there is a phenomenon that the roll unloading trolley waits for unloading.

以一种2050型热轧平整机组为例,在带钢经过入口步进梁、上料小车、开卷机、带钢平整机并分切割和卷取机生产完成1卷钢带后,其卸卷过程需要经过卸卷小车到位、小车上升、支撑臂打开、卷筒卸卷、卸卷小车送卷至出口步进梁、步进梁关闭、卸卷小车将钢卷送至步进梁后回位等一系列步骤,即如图1所示,在钳口咬入、卷取成卷后的卸卷操作过程如下:Taking a 2050 type hot-rolled tempering unit as an example, after the strip passes through the entrance walking beam, feeding trolley, uncoiler, strip tempering machine and is divided into cutting and coiling machines to produce a coil of steel strip, its unloading The coiling process needs to go through the unloading trolley in place, the trolley rises, the support arm opens, the reel is unloaded, the unloading trolley sends the coil to the exit walking beam, the walking beam closes, the coil unloading trolley sends the steel coil to the walking beam and returns A series of steps such as positioning, that is, as shown in Figure 1, the unloading operation process after the jaws are bitten and rolled into a roll is as follows:

①卸卷小车到位、小车上升;①The unloading trolley is in place and the trolley rises;

②支撑臂打开、卷筒卸卷、卸卷小车送卷至出口步进梁;②The support arm is opened, the roll is unloaded, and the unloading trolley sends the roll to the exit walking beam;

③卸卷小车逆时针旋转;③The unloading trolley rotates counterclockwise;

④出口步进梁前进接卷;④The exit walking beam advances to pick up coils;

⑤出口步进梁后退送卷;⑤Exit the walking beam and send the roll back;

⑥卸卷小车顺时针旋转;⑥The unloading trolley rotates clockwise;

⑦卸卷小车回位。⑦The roll unloading trolley returns to its position.

要待卸卷小车到位完成后才能进行下一钢卷的卸卷。卸卷小车从卸卷到回位的周期较长,而钢卷头、尾由于质量原因往往要收取小卷作尾卷(一种降级品),其卷取周期普遍较短。这样由于从卸卷开始到卸卷小车回位整个步骤时间较长,而在生产小卷时节奏较快,因此普遍存在停机等待卸卷的现象,导致了作业效率的下降和时间的浪费。例如,三个钢卷连续生产时,钢卷均为头、尾各收取一个尾卷,中间收取一个正品;生产时共需要卸卷9次产生3个正品卷和6个尾卷,由于尾卷卷取周期小于卸卷周期,其中6次会发生停机等待卸卷的现象,因此造成生产效率下降和时间的浪费。The unloading of the next steel coil can only be carried out after the unloading trolley is in place. The coil unloading trolley has a long cycle from unloading to returning to its position, while the steel coil head and tail often need to collect small coils as tail coils (a degraded product) due to quality reasons, and the coiling cycle is generally short. In this way, it takes a long time from the beginning of unloading to the return of the unloading trolley, and the rhythm is faster when producing small rolls, so there is a common phenomenon of stopping and waiting for unloading, resulting in a decrease in operating efficiency and a waste of time. For example, when three steel coils are produced continuously, one tail coil is collected at the head and the tail of the steel coil, and one genuine product is collected in the middle; a total of 9 coils need to be unloaded during production to produce 3 genuine coils and 6 tail coils. The coiling cycle is shorter than the unloading cycle, and 6 of them will stop and wait for the unloading, which will cause a decrease in production efficiency and a waste of time.

发明内容Contents of the invention

本发明的目的是提供一种钳口式卷筒头尾连接的卷取方法,通过头、尾连接卷取方式解决小卷成卷周期短、而设备卸卷周期较长的矛盾,避免该类生产效率的下降。The purpose of the present invention is to provide a winding method of head-to-tail connection of a jaw type reel, which solves the contradiction that the cycle of small rolls is short and the cycle of equipment unloading is long, and avoids such problems. A drop in production efficiency.

本发明的技术方案如下:Technical scheme of the present invention is as follows:

一种钳口式卷筒头尾连接的卷取方法,包括使前一个钢卷带钢头部进入卷筒钳口咬入固定后卷取的步骤,还包括以下步骤:A coiling method for connecting the head and the tail of a jaw-type reel, including the step of making the head of the previous steel coil and strip enter the jaws of the reel to bite into and fix it, and then coiling, and also includes the following steps:

第一步:在前一个钢卷成卷后将压紧辊压下并将钢卷带钢尾部停留在大约时钟12点钟方向;The first step: After the previous steel coil is rolled, press down the pinch roller and stop the tail of the steel coil at about 12 o'clock in the clock;

第二步:使下一钢卷带钢头部通过夹送辊、转向辊后继续穿带前进,将带钢头部穿带在上一钢卷带钢尾部的下层,并使其头部位置固定在上一钢卷尾部最外圈与倒数第二圈之间;使钢卷穿带前进到带钢头部到达夹层顶部,穿带的带钢开始轻微拱起为止;Step 2: Make the strip head of the next steel coil pass through the pinch roller and the steering roller, and then continue to thread the strip forward, thread the strip head on the lower layer of the strip tail of the previous steel coil, and make the head position It is fixed between the outermost circle and the penultimate circle at the tail of the previous steel coil; the steel coil is threaded forward until the head of the strip reaches the top of the interlayer, and the strip steel that is threaded begins to arch slightly;

第三步:使卷筒倒转以使卷筒上的钢卷尾部倒出一段距离;Step 3: Reverse the reel so that the tail of the steel coil on the reel can be poured out for a certain distance;

第四步:手动使卷筒正转进行卷取,通过压紧辊将下一钢卷带钢的头部咬入到卷筒上上一钢卷的夹层中,使手动咬入长度达到卷筒上前一钢卷至少2圈的长度;Step 4: Manually turn the reel forward for coiling, bite the head of the next steel coil into the interlayer of the previous steel coil on the reel through the pinch roller, so that the manual biting length reaches the reel The length of the previous steel coil is at least 2 turns;

第五步:待带钢卷头部完全咬入前一钢卷至少2圈时,使上一钢卷的带钢头部通过夹层间的接触摩擦力完全固定,以便由自动切入张力对接入的钢卷进行卷取。Step 5: When the head of the strip steel coil is completely bitten into the previous steel coil for at least 2 turns, the strip steel head of the previous steel coil is completely fixed by the contact friction force between the interlayers, so that it can be connected by automatic cutting tension The steel coil is coiled.

在第三步中使卷筒倒转以使卷筒上的钢卷尾部倒出的一段距离为5-10米长距离。In the third step, the reel is reversed so that the steel coil tail on the reel is poured out of a distance of 5-10 meters.

在第四步和第五步中所述的至少2圈为2圈。The at least 2 turns described in the fourth step and the fifth step are 2 turns.

本发明的有益效果是:The beneficial effects of the present invention are:

采用头尾连接卷取方法可解决目前钢卷的头、尾由于质量原因普遍需要收取尾卷以和正品分开的问题,以实现钢卷的尾部尾卷和下一钢卷的头部尾卷合并后一起收取,从而将两次卸卷周期有效缩短为1次卸卷周期,有效提高了机组的生产效率,且该方法对于生产节奏越快的卷线机组效果越明显。The head-to-tail connection coiling method can solve the problem that the head and tail of the steel coil generally need to be collected to separate from the genuine product due to quality reasons, so as to realize the merger of the tail and tail coils of the steel coil and the head and tail coils of the next steel coil Collecting together at the end, so that the two unloading cycles are effectively shortened to one unloading cycle, which effectively improves the production efficiency of the unit, and the effect of this method is more obvious for the coiling unit with a faster production rhythm.

附图说明Description of drawings

图1是现有的钢卷卸卷过程的示意图;Fig. 1 is the schematic diagram of existing coil unloading process;

图2是本发明的钳口式卷筒头尾连接的卷取方法的第一步骤示意图;Fig. 2 is the schematic diagram of the first step of the coiling method of the end-to-end connection of the jaw type reel of the present invention;

图3是本发明的钳口式卷筒头尾连接的卷取方法的第二步骤示意图;Fig. 3 is the second step schematic diagram of the coiling method of the jaw type reel head-to-tail connection of the present invention;

图4是本发明的钳口式卷筒头尾连接的卷取方法的第三步骤示意图;Fig. 4 is a schematic diagram of the third step of the winding method of the end-to-end connection of the jaw type reel of the present invention;

图5是本发明的钳口式卷筒头尾连接的卷取方法的第四步骤示意图。Fig. 5 is a schematic diagram of the fourth step of the winding method of the end-to-end connection of the jaw type reel according to the present invention.

具体实施方式detailed description

为让本发明的上述目的、特征和优点能更明显易懂,以下结合附图对本发明的具体实施方式作详细说明。首先需要说明的是,本发明并不限于下述具体实施方式,本领域的技术人员应该从下述实施方式所体现的精神来理解本发明,各技术术语可以基于本发明的精神实质来作最宽泛的理解。In order to make the above objects, features and advantages of the present invention more comprehensible, specific implementations of the present invention will be described in detail below in conjunction with the accompanying drawings. First of all, it should be noted that the present invention is not limited to the following specific embodiments. Those skilled in the art should understand the present invention from the spirit embodied in the following embodiments, and each technical term can be optimized based on the spirit of the present invention. broad understanding.

本发明一个实施例的钳口式卷筒头尾连接的卷取方法,如图2至图5所示,包括以下步骤:The winding method of the end-to-end connection of the jaw type reel according to an embodiment of the present invention, as shown in Fig. 2 to Fig. 5, comprises the following steps:

第一步:使前一个钢卷通过常规方式进行卷取:使带钢头部进入卷筒钳口咬入固定后卷取;如图2所示,在成卷后将压紧辊压下并将钢卷带钢尾部停留在大约时钟12点钟方向。The first step: Coil the previous steel coil in a conventional way: make the head of the strip steel enter the jaws of the reel, bite into it and fix it, and then coil it; Leave the tail of the steel coil at about 12 o'clock.

第二步:使下一钢卷带钢头部通过夹送辊、转向辊后继续穿带前进,将带钢头部穿带在上一钢卷带钢尾部的下层,如图3所示,并使其头部位置固定在上一钢卷尾部最外圈与倒数第二圈之间;使钢卷穿带前进到带钢头部到达夹层顶部,穿带的带钢开始轻微拱起为止;Step 2: make the strip head of the next steel coil pass through the pinch roller and the steering roller and continue to thread the strip forward, and thread the strip head on the lower layer of the strip tail of the previous steel coil, as shown in Figure 3. And fix the position of the head between the outermost circle and the penultimate circle at the tail of the previous steel coil; make the steel coil thread forward until the strip head reaches the top of the interlayer, and the threaded strip begins to arch slightly;

第三步:如图4所示,使卷筒倒转以使卷筒上的钢卷尾部倒出5-10米长距离;The third step: as shown in Figure 4, the reel is reversed so that the tail of the steel coil on the reel is poured out a long distance of 5-10 meters;

第四步:手动使卷筒正转进行卷取,通过压紧辊将下一钢卷带钢的头部咬入到卷筒上上一钢卷的夹层中,如图5所示,使手动咬入长度达到卷筒上前一钢卷2圈的长度;Step 4: Manually turn the reel forward for coiling, and bite the head of the next steel coil into the interlayer of the previous steel coil on the reel through the pinch roller, as shown in Figure 5, manually The biting length reaches the length of 2 turns of the previous steel coil on the reel;

第五步:待带钢卷头部完全咬入前一钢卷2圈时,使上一钢卷的带钢头部通过夹层间的接触摩擦力完全固定,以便由自动切入张力对接入的钢卷进行卷取。Step 5: When the head of the strip steel coil completely bites into the previous steel coil for 2 turns, the strip steel head of the previous steel coil is completely fixed by the contact friction force between the interlayers, so that the automatic cutting tension can be used to match the incoming steel coil. Steel coils are coiled.

在第三步中所述的5-10米长距离,以及在第四步和第五步中所述的2圈只是例举性的而不是限制性的,因在不违背本发明的精神的情况下,还可以作出改变。The 5-10 meter long distance described in the third step, and the 2 circles described in the fourth step and the fifth step are only illustrative and not limiting, because they do not violate the spirit of the present invention. Circumstances, changes can also be made.

综上所述,本发明在不增加设备的情况下,取代了原有钢卷必须通过钳口进行卷取的方法,创造了一种全新的卷取方法:通过使上一个钢卷的尾部和下一个钢卷的头部实现连接卷取,从而可实现将两次钢卷卷卸卷过程合并为一次卸卷,有效节约了卸卷的周期等待,提高了生产效率,且该方法对于生产节奏越快的卷线机组效果越明显。In summary, the present invention replaces the original method in which steel coils must be coiled through the jaws without increasing equipment, and creates a brand-new coiling method: by making the tail of the previous steel coil and The head of the next steel coil is connected and coiled, so that the two unloading processes of steel coils can be combined into one unloading process, which effectively saves the cycle waiting for coil unloading and improves production efficiency. The faster the winding unit, the more obvious the effect.

该方法在一种热轧2050型平整机组、纵切机组均可使用,以平整机组为例,平均生产一个1分切钢卷同时头尾收取尾卷总共需要20分钟左右,采用头尾连接卷取可减少一次卸卷从而节约5分钟左右,可提高生产效率25%。This method can be used in a hot-rolled 2050-type tempering unit and slitting unit. Taking the tempering unit as an example, it takes about 20 minutes to produce a 1-slit steel coil and collect the tail coil at the same time. The head-to-tail connection coil is used It can save about 5 minutes by reducing one time of unloading, and can increase production efficiency by 25%.

应理解,在阅读了本发明的上述讲授内容之后,本领域技术人员可以对本发明作各种改动或修改,这些等价形式同样落于本申请所附权利要求书所限定的范围。It should be understood that after reading the above teaching content of the present invention, those skilled in the art can make various changes or modifications to the present invention, and these equivalent forms also fall within the scope defined by the appended claims of the present application.

Claims (3)

1.一种钳口式卷筒头尾连接的卷取方法,包括使前一个钢卷带钢头部进入卷筒钳口咬入固定后卷取,其特征在于,还包括以下步骤:1. A coiling method for the head-to-tail connection of a jaw-type reel, comprising making the previous steel coil strip steel head enter the reel jaws to bite into the fixed rear coiling, it is characterized in that it also includes the following steps: 第一步:在前一个钢卷成卷后将压紧辊压下并将钢卷带钢尾部停留在大约时钟12点钟方向;The first step: After the previous steel coil is rolled, press down the pinch roller and stop the tail of the steel coil at about 12 o'clock in the clock; 第二步:使下一钢卷带钢头部通过夹送辊、转向辊后继续穿带前进,将带钢头部穿带在上一钢卷带钢尾部的下层,并使其头部位置固定在上一钢卷尾部最外圈与倒数第二圈之间;使钢卷穿带前进到带钢头部到达夹层顶部,穿带的带钢开始轻微拱起为止;Step 2: Make the strip head of the next steel coil pass through the pinch roller and the steering roller, and then continue to thread the strip forward, thread the strip head on the lower layer of the strip tail of the previous steel coil, and make the head position It is fixed between the outermost circle and the penultimate circle at the tail of the previous steel coil; the steel coil is threaded forward until the head of the strip reaches the top of the interlayer, and the strip steel that is threaded begins to arch slightly; 第三步:使卷筒倒转以使卷筒上的钢卷尾部倒出一段距离;Step 3: Turn the reel upside down so that the tail of the steel coil on the reel can be poured out for a certain distance; 第四步:手动使卷筒正转进行卷取,通过压紧辊将下一钢卷带钢的头部咬入到卷筒上上一钢卷的夹层中,使手动咬入长度达到卷筒上前一钢卷至少2圈的长度;Step 4: Manually turn the reel forward for coiling, bite the head of the next steel coil into the interlayer of the previous steel coil on the reel through the pinch roller, so that the manual biting length reaches the reel The length of the previous steel coil is at least 2 turns; 第五步:待带钢卷头部完全咬入前一钢卷至少2圈时,使上一钢卷的带钢头部通过夹层间的接触摩擦力完全固定,以便由自动切入张力对接入的钢卷进行卷取。Step 5: When the head of the strip steel coil is completely bitten into the previous steel coil for at least 2 turns, the strip steel head of the previous steel coil is completely fixed by the contact friction force between the interlayers, so that it can be connected by automatic cutting tension The steel coil is coiled. 2.根据权利要求1所述的钳口式卷筒头尾连接的卷取方法,其特征在于,在第三步中使卷筒倒转以使卷筒上的钢卷尾部倒出的一段距离为5-10米长的距离。2. The coiling method of the end-to-end connection of the jaw type reel according to claim 1, wherein in the third step, the reel is turned upside down so that the steel coil tail on the reel is poured out from a distance of 5-10 meters long distance. 3.根据权利要求1或2所述的钳口式卷筒头尾连接的卷取方法,其特征在于,在第四步和第五步中所述的至少2圈为2圈。3. The winding method for end-to-end connection of jaw type reels according to claim 1 or 2, characterized in that the at least 2 turns described in the fourth step and the fifth step are 2 turns.
CN201410050278.XA 2014-02-13 2014-02-13 Rolling method for head-to-tail connection of jaw cylinder Active CN104841725B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410050278.XA CN104841725B (en) 2014-02-13 2014-02-13 Rolling method for head-to-tail connection of jaw cylinder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410050278.XA CN104841725B (en) 2014-02-13 2014-02-13 Rolling method for head-to-tail connection of jaw cylinder

Publications (2)

Publication Number Publication Date
CN104841725A CN104841725A (en) 2015-08-19
CN104841725B true CN104841725B (en) 2017-02-22

Family

ID=53841923

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410050278.XA Active CN104841725B (en) 2014-02-13 2014-02-13 Rolling method for head-to-tail connection of jaw cylinder

Country Status (1)

Country Link
CN (1) CN104841725B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105689434B (en) * 2016-01-29 2017-11-07 灵宝金源朝辉铜业有限公司 A kind of fixing means between metal foil end and steel sleeve
KR102020442B1 (en) * 2017-08-18 2019-09-10 주식회사 포스코 Apparatus for coiling
CN111215455A (en) * 2018-11-26 2020-06-02 宝山钢铁股份有限公司 A kind of hot-rolled thin strip flatness control device and method
CN110142311B (en) * 2019-05-15 2020-08-14 柳州钢铁股份有限公司 Uncoiling operation method of uncoiler
CN117399459A (en) * 2023-10-30 2024-01-16 邯郸正大制管集团股份有限公司 An auxiliary uncoiling device for strip steel

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS53122658A (en) * 1977-03-31 1978-10-26 Sumitomo Metal Ind Ltd Method of taking up strip in temper rolling line
JPS54157752A (en) * 1978-06-01 1979-12-12 Sumitomo Metal Ind Ltd Coiling of hot rolled steel strip
CN100478094C (en) * 2007-05-16 2009-04-15 山西太钢不锈钢股份有限公司 Method for eliminating pinch of jaw opening for fetching coil of cold rolled steel strip
CN102430612B (en) * 2011-10-20 2014-02-05 攀钢集团西昌钢钒有限公司 Operation method for controlling tower shapes of inner and outer rings of steel coils
CN103223420B (en) * 2012-01-29 2014-12-24 宝山钢铁股份有限公司 Method for controlling inner ring indentations of hot-rolled steel coil, and system
CN103480688B (en) * 2013-09-22 2015-11-25 首钢京唐钢铁联合有限责任公司 Strip steel head end coiling method

Also Published As

Publication number Publication date
CN104841725A (en) 2015-08-19

Similar Documents

Publication Publication Date Title
CN104841725B (en) Rolling method for head-to-tail connection of jaw cylinder
CN103372583B (en) Control method of hot rolling coiling tension
CN102430612B (en) Operation method for controlling tower shapes of inner and outer rings of steel coils
CN218692687U (en) A wire take-up device for a copper wire drawing machine
CN108501232A (en) A kind of Buddha's warrior attendant wire-electrode cutting device and cutting method for polysilicon
CN103084413A (en) Leading tape lead-in method of traction steel coil of twenty-roller unit
CN109290374B (en) A method for straightening the head
CN104550230A (en) Novel black stainless steel strip rolling process and unit
WO2021047681A1 (en) Processing technology for npr steel bar coil
CN103386420B (en) A kind of cold-strip steel threading method
CN202845435U (en) Hoisting equipment capable of improving stainless steel yield
CN103447310A (en) Rapid threading control method for five cold rolling mills
CN207325590U (en) A kind of positive waste product of coil of strip separates coiling system
CN203495705U (en) On-line chamfering device for bars
CN203678835U (en) Novel stainless steel cold continuous rolling technology and unit thereof
JP5323999B2 (en) Method for rolling strip shaped rolled material, especially metal strip
CN204912274U (en) Special strip rolling technology professional equipment of tape measure
CN101690950B (en) Method of reeling stainless strip steel for railway vehicle
CN106493182A (en) Rustless steel tandem rolling outlet section equipment and its continuous rolling process
CN205463694U (en) Take pinch roller to fall line alarming function's steel wire re -reeler
CN201540775U (en) A processing equipment for cable shielding tape
CN204237312U (en) One puts paper tinsel machine continuously
CN112547804B (en) Method for stably reeling ultrathin checkered plate
CN204639616U (en) A kind of device of band continuous shear stress
JP2013515609A5 (en)

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant