CN104836214A - Distributed generation-based grid connection transition operation mode coordination comprehensive protection method - Google Patents

Distributed generation-based grid connection transition operation mode coordination comprehensive protection method Download PDF

Info

Publication number
CN104836214A
CN104836214A CN201510185147.7A CN201510185147A CN104836214A CN 104836214 A CN104836214 A CN 104836214A CN 201510185147 A CN201510185147 A CN 201510185147A CN 104836214 A CN104836214 A CN 104836214A
Authority
CN
China
Prior art keywords
protection
grid
switch
transformer
load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510185147.7A
Other languages
Chinese (zh)
Other versions
CN104836214B (en
Inventor
林霞
李强
李瑶
朱新颖
张英彬
王群
魏鑫
薛会
李可
石磊
时永
冯相军
廉震
王祥军
刘朋
万卫东
孔令元
种法超
聂坤凯
胡太元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zaozhuang Power Supply Co of State Grid Shandong Electric Power Co Ltd
State Grid Corp of China SGCC
Original Assignee
Zaozhuang Power Supply Co of State Grid Shandong Electric Power Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zaozhuang Power Supply Co of State Grid Shandong Electric Power Co Ltd, State Grid Corp of China SGCC filed Critical Zaozhuang Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority to CN201510185147.7A priority Critical patent/CN104836214B/en
Publication of CN104836214A publication Critical patent/CN104836214A/en
Application granted granted Critical
Publication of CN104836214B publication Critical patent/CN104836214B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a distributed generation-based grid connection transition operation mode coordination comprehensive protection method. When the DG capacity is continuously increased, the short-circuit current level is improved, the DG is changed from a "pure load" into a "small power supply", and a problem that conventional protection and switching breakpoints cannot meet the transition condition is solved. Based on the conventional protection and the switching breakpoints, the scheme provided by the invention performs continuous matching with a primary operation model and is continuously optimized, and the information and the state quantity are continuously exchanged to form a protection control interface adapted to a primary system, so that dual purposes of safe operation of a system and continuous power supplying are achieved. The fault isolation range is determined by collecting a new boundary which is determined by the switching breakpoints, and that whether the system sectionalizing and the island operation mode generated as a boundary point is determined is stable or not is comprehensively considered.

Description

一种基于分布式发电并网过渡运行方式协调综合保护方法A Coordinated Comprehensive Protection Method Based on Distributed Generation Grid-connected Transition Operation Mode

技术领域technical field

本发明涉及一种基于分布式发电并网过渡运行方式协调综合保护方法。The invention relates to a coordinated comprehensive protection method based on distributed power generation grid-connected transition operation mode.

背景技术Background technique

在分布式电源网络建设初期,由于其规模具有不确定性,并网容量较小,对系统提供的短路电流有限,对已有系统保护影响较小,此时可将其视为“纯负荷”性质。但是当分布式电源容量不断增加(>5MVA),DG就有了提供相对高故障电流的馈送能力,例如,在10~35kV母线上直接连接的DG,可在很短的持续时间里提供大约6倍额定电流,通过逆变器连接DG单元故障电流也可以达到4倍额定电流。这时就不能再以负荷性质进行对待,但此时系统侧相应的保护装置并未跟进,影响电网的稳定运行。In the early stage of distributed power network construction, due to its uncertain scale and small grid-connected capacity, the short-circuit current provided to the system is limited and has little impact on the protection of existing systems. At this time, it can be regarded as a "pure load" nature. However, when the capacity of distributed power sources continues to increase (>5MVA), DGs have the ability to provide relatively high fault current feeds. For example, DGs directly connected to 10-35kV buses can provide about 6 times the rated current, and the fault current of the DG unit connected to the inverter can also reach 4 times the rated current. At this time, it can no longer be treated as the nature of the load, but at this time the corresponding protection devices on the system side have not followed up, affecting the stable operation of the power grid.

因此研究如何DG过渡方式下,以有限的保护资源获得最有效的保护方案是有着积极意义的。同时在这种过渡方式下,考虑如何在系统发生故障时,充分体现DG对重要负荷的持续供电优势也是应该兼顾考虑的目标。Therefore, it is of positive significance to study how to obtain the most effective protection scheme with limited protection resources under the transition mode of DG. At the same time, in this transition mode, considering how to fully reflect the advantages of DG's continuous power supply to important loads when the system fails is also a goal that should be considered.

发明内容Contents of the invention

本发明为了解决上述问题,提出了一种基于分布式发电并网过渡运行方式协调综合保护方法,本方法通过接地方式及二次保护系统的优化,解决了DG由单纯“负荷”性质向“小电源”性质过渡的复杂性问题,在现有的保护及自动装置不变的情况下,通过相关技术手段,达到基本满足DG接入后地区电网安全运行的目的。In order to solve the above problems, the present invention proposes a coordinated comprehensive protection method based on the distributed power generation grid-connected transition operation mode. This method solves the problem of DG changing from a simple "load" property to a "small load" through the optimization of the grounding mode and the secondary protection system. The complexity of the transition of the nature of "power supply", under the condition that the existing protection and automatic devices remain unchanged, through relevant technical means, the purpose of basically meeting the safe operation of the regional power grid after DG access is achieved.

为了实现上述目的,本发明采用如下技术方案:In order to achieve the above object, the present invention adopts the following technical solutions:

一种基于分布式发电并网过渡运行方式协调综合保护方法,包括以下步骤:A coordinated comprehensive protection method based on distributed power generation grid-connected transition operation mode, comprising the following steps:

(1)明确DG容量的故障隔离边界,调整其保护定值,确定故障隔离后孤岛运行方式下边界点,在DG容量增大到设定值后,将并网变电站的变压器接地方式进行调整;(1) Define the fault isolation boundary of DG capacity, adjust its protection setting, determine the lower boundary point of island operation mode after fault isolation, and adjust the transformer grounding mode of grid-connected substation after the DG capacity increases to the set value;

(2)在已有的保护配置条件下,使当地低频低压装置与配电自动化系统相协调,完成事故后负荷转移及孤岛划分;(2) Under the existing protection configuration conditions, coordinate the local low-frequency and low-voltage devices with the distribution automation system, and complete the post-accident load transfer and island division;

(3)根据孤岛运行方式,制定保护配置方案,进行故障响应分析,实现对一级重要负荷故障期间的持续供电,以及岛内相应的微网保护调整。(3) According to the island operation mode, formulate a protection configuration plan, conduct fault response analysis, realize continuous power supply during the fault period of the first-level important load, and corresponding micro-grid protection adjustment in the island.

所述步骤(1)中,当本地DG容量不断增大,达到设定的容量值时,DG就不能当作单纯的负荷考虑,而应该将其视为与系统相连的、与发电机组性质不同的分布式电源。In the above step (1), when the capacity of the local DG continues to increase and reaches the set capacity value, the DG cannot be considered as a simple load, but should be regarded as connected to the system and different in nature from the generator set. distributed power supply.

所述步骤(1)中,首先要明确DG容量在增长到哪个点时引起保护的不配合,因而需要调整保护定值;其次是由于DG容量小于50MW保护及开关配置在DG作为“小电源”考虑时将是不完善的,如果想要在故障发生时有效的隔离故障,这时的故障断开点需要进行以下调整:跳DG上网变电站主变高压侧及桥开关,同时联切并网线开关。In the above step (1), it is first necessary to clarify at which point the DG capacity increases to cause the protection mismatch, so the protection setting needs to be adjusted; secondly, because the DG capacity is less than 50MW protection and the switch configuration is in the DG as a "small power source" It will be incomplete when considering it. If you want to effectively isolate the fault when the fault occurs, the fault disconnection point at this time needs to be adjusted as follows: jump the high-voltage side of the main transformer of the DG grid-connected substation and the bridge switch, and simultaneously cut off the parallel switch. .

所述步骤(1)中,DG容量增大到设定值程度时,需要考虑在哪个开关断点断开,形成孤岛运行方式,同时,在形成孤岛后,兼顾考虑对于岛内微网保护;对于故障隔离后的负荷重新分配,同样也是要在充分考虑负荷重要性及与当地供配平衡关系的前提下,通过解列及低频低压减载装置将负荷损失降至最低。In the step (1), when the DG capacity is increased to the set value, it is necessary to consider which switch breakpoint is disconnected to form an island operation mode. At the same time, after the island is formed, the protection of the micro-grid in the island should also be considered; For the load redistribution after fault isolation, it is also necessary to minimize the load loss through decoupling and low-frequency low-voltage load shedding devices under the premise of fully considering the importance of the load and the relationship with the local supply and distribution balance.

所述步骤(2)中,在过渡运行方式下,由于开关断开点的分布及可备用电源的不足需要相应的保护及安全自动装置方案作适应性调整;在进行方案确定的时候,首先故障隔离范围的确定需要收集开关断开点所确定的新边界,并且还要综合考虑这一边界点一旦确定而随之产生的系统解列及孤岛运行方式是否可稳定运行。In the step (2), in the transition mode of operation, due to the distribution of switch disconnection points and the lack of available backup power supply, the corresponding protection and safety automatic device schemes need to be adaptively adjusted; when the scheme is determined, the first failure The determination of the isolation range needs to collect the new boundary determined by the disconnection point of the switch, and it is also necessary to comprehensively consider whether the system disconnection and the island operation mode that will occur once this boundary point is determined can operate stably.

所述步骤(2)中,为了实现在精确隔离故障后的重要负荷的可靠运行,需要综合考虑成本与能源信息、管理与环境信息、控制与测量信息、临界状态信息和负荷用户信息;在电源资源紧张的情况下,需要对网络拓扑结构、潮流分布、开关分布、保护配置及当地DG的负荷平衡能力和当地供电负荷的性质因素进行综合分析考虑,才能确定适用于当前运行方式下的可靠、经济保护及安全自动装置方案,方案确定各个开关及保护配置点的配合关系,用来实现以最小隔离范围隔离故障以及以最小的成本来获得最优的负荷转移方案。In the step (2), in order to realize the reliable operation of important loads after accurate isolation of faults, it is necessary to comprehensively consider cost and energy information, management and environmental information, control and measurement information, critical state information and load user information; In the case of tight resources, it is necessary to comprehensively analyze and consider the network topology, power flow distribution, switch distribution, protection configuration, local DG load balancing capability and the nature of the local power supply load, in order to determine the reliable, Economic protection and safety automatic device scheme, the scheme determines the coordination relationship of each switch and protection configuration point, which is used to isolate faults with the minimum isolation range and obtain the optimal load transfer scheme at the minimum cost.

所述步骤(3)中,由于DG性质发生了变化,将并网变压器高压侧接地,对侧系统线路保护由原来的距离、零序I段伸入变压器,改为保线路85%,并借助于本站变压器高压侧的零序保护作为线路主保护,跳高压侧及桥开关,同时联切并网线开关。In the described step (3), because the DG property has changed, the high-voltage side of the grid-connected transformer is grounded, and the line protection of the opposite side system is stretched into the transformer from the original distance, and the zero-sequence I section is changed to 85% of the line protection, and by means of The zero-sequence protection on the high-voltage side of the transformer in this station is used as the main protection of the line, tripping the high-voltage side and the bridge switch, and simultaneously switching off the grid line switch.

所述步骤(3)中,保护动作如下:线路故障时两端断路器跳开不重合,备投动作,联切DG并网线的模式,此时局部区域将进入孤岛运行方式;作为低压侧近后备及低压侧母线主保护的低压侧限时速断保护跳开本侧开关,联切DG并网线,闭锁低压侧分段备投;主变差动及非电量保护动作,不闭锁变电站进线及低压侧分段备投。In the step (3), the protection action is as follows: when the line is faulty, the circuit breakers at both ends are tripped and do not overlap, and the backup operation is performed, and the mode of cutting the DG grid-connected line is connected. At this time, the local area will enter the island operation mode; as the low-voltage side near The time-limited quick-break protection of the low-voltage side of the backup and low-voltage side bus main protection trips the switch on this side, cuts off the DG grid-connected line, and blocks the low-voltage side segmental backup switching; the main transformer differential and non-electrical protection action does not block the incoming line of the substation and the low-voltage side Segmentation preparation.

所述步骤(3)中,当一台变运行时,系统侧线路发生故障,将备投联切装置的变压器高压侧开关动作,直接切断光伏与系统的联络通道,高压侧母线失压,不会影响备自投的正常动作,但对于两台变同时运行的方式,变压器高压侧开关动作并不能完全切断分布式电源的通道,因此会影响备自投的成功率,为此高后备保护动作的同时需要联切本站光伏的并网线,并且由原来的两台变并列运行改由一台变运行后,需要低压侧的低频、低压装置动作,对相应负荷进行均衡,以达到保证供电质量的问题。In the step (3), when one substation is running and the system side line fails, the switch on the high voltage side of the transformer of the backup switching device is activated to directly cut off the communication channel between the photovoltaic and the system, and the bus bar on the high voltage side loses voltage, and no It will affect the normal operation of standby automatic switching, but for the mode of simultaneous operation of two transformers, the switching action of the high-voltage side of the transformer cannot completely cut off the channel of distributed power supply, so it will affect the success rate of standby automatic switching, so the high backup protection action At the same time, it is necessary to cut the photovoltaic grid-connected line of the station, and after the parallel operation of the original two substations is changed to one substation operation, the low-frequency and low-voltage devices on the low-voltage side need to operate to balance the corresponding loads to ensure the quality of power supply The problem.

所述步骤(3)中,选择在分布式电源并网变电站高压侧装设母差保护,当母线发生故障时,由母差保护动作节点输出闭锁备投装置;如果没有配置母差保护,通过比较流过进线变电站侧开关与变压器高压侧刀闸的故障电流大小来判断是否为母线故障。In the step (3), choose to install the bus differential protection on the high-voltage side of the distributed power grid-connected substation. When the bus fails, the bus differential protection action node outputs the blocking standby switching device; if the bus differential protection is not configured, pass Compare the magnitude of the fault current flowing through the switch on the incoming substation side and the switch on the high voltage side of the transformer to determine whether it is a bus fault.

所述步骤(3)中,当进线变电站侧开关流过的电流大于变压器高压侧刀流过的故障电流时,说明为母线故障;因为,只有故障点位于两开关之间时,才会出现进线变电站侧开关感受到的由系统提供的短路电流远大于变压器高压侧刀闸由分布式电源提供的短路电流。In the step (3), when the current flowing through the switch on the incoming line substation side is greater than the fault current flowing through the high-voltage side blade of the transformer, it is explained as a bus fault; because only when the fault point is located between the two switches, will it appear The short-circuit current provided by the system felt by the switch on the incoming line substation side is much greater than the short-circuit current provided by the distributed power source on the high-voltage side switch of the transformer.

所述步骤(3)中,在不会导致DG相关设备损害的前提下,DG侧不论是频率还是电压继电器都比系统侧对应保护高出一个配合级差,这也就保证了当系统侧发生故障时,DG不会先于系统侧相对应继电器动作而导致无法实现对系统的有效支持。In the step (3), under the premise of not causing damage to DG-related equipment, both the frequency and voltage relays on the DG side are higher than the corresponding protection on the system side by a cooperation level difference, which also ensures that when the system side fails At this time, the DG will not act before the corresponding relay on the system side, resulting in failure to achieve effective support for the system.

本发明的有益效果为:The beneficial effects of the present invention are:

(1)当DG容量不断增加,使的其短路电流水平增加,DG性质也由原来的“纯负荷”转换为“小电源”性质,现有的保护及开关断点已经无法满足过渡情况的需要,本发明在已有的保护及开关断点条件下,通过与一次运行方式的不断匹配,方案的不断优化,信息及状态量的不断交流,形成与一次系统相适应的保护控制接口,达到系统安全运行及供电持续的双重目的;(1) When the capacity of DG continues to increase, its short-circuit current level increases, and the nature of DG is also converted from the original "pure load" to "small power supply". The existing protection and switch breakpoints can no longer meet the needs of the transitional situation , under the existing protection and switch breakpoint conditions, the present invention forms a protection control interface adapted to the primary system through continuous matching with the primary operation mode, continuous optimization of the scheme, and continuous exchange of information and state quantities to achieve system The dual purpose of safe operation and continuous power supply;

(2)通过改变变压器接地方式,确保系统故障时可以有效发现故障;(2) By changing the grounding method of the transformer, it is ensured that the fault can be effectively found when the system fails;

(3)同时借助于变压器高压侧零序过流及开关实现了对系统故障的有效隔离;(3) At the same time, the effective isolation of system faults is realized by means of zero-sequence overcurrent and switches on the high-voltage side of the transformer;

(4)通过保护及自动装置的定值配合,保证了在故障隔离后,有效转移负荷;通过DG孤岛运行操作,保持了DG对当地负荷的持续供电,并且其保护也实现了微网保护功能,对于大量DG不断增长接入当地的情况提供了有效的解决手段。(4) Through the coordination of the protection and the fixed value of the automatic device, it is ensured that the load is effectively transferred after the fault is isolated; through the operation of the DG isolated island, the continuous power supply of the DG to the local load is maintained, and its protection also realizes the protection function of the micro-grid , which provides an effective solution to the situation that a large number of DGs are continuously connected to the local area.

附图说明Description of drawings

图1为本发明的基于DG性质转变时相关方案选择流程图;Fig. 1 is a flow chart of related scheme selection based on DG property transition of the present invention;

图2为本发明基于信息高度融合的保护及安全自动装置方案原理示意图;Fig. 2 is a schematic diagram of the principle of the protection and safety automatic device scheme based on the high degree of information fusion of the present invention;

图3为本发明分布式电源接入110kV变电站接线图;Fig. 3 is the wiring diagram of distributed power supply access 110kV substation of the present invention;

图4为由DG性质转变及开关断开点确定最初保护及解列方案;Figure 4 is the initial protection and de-listing scheme determined by the DG property transition and switch disconnection point;

图5为保护方案的具体实施示意图;Figure 5 is a schematic diagram of the specific implementation of the protection scheme;

图6为故障响应分析示意图;Figure 6 is a schematic diagram of fault response analysis;

图7(a)为适用于孤岛运行方式的微网保护配合关系示意图;Figure 7(a) is a schematic diagram of the microgrid protection cooperation relationship applicable to the island operation mode;

图7(b)为适用于孤岛运行方式的微网保护配合关系示意图;Figure 7(b) is a schematic diagram of the microgrid protection cooperation relationship applicable to the island operation mode;

图7(c)为适用于孤岛运行方式的微网保护配合关系示意图。Fig. 7(c) is a schematic diagram of the microgrid protection coordination relationship applicable to the island operation mode.

具体实施方式:Detailed ways:

下面结合附图与实施例对本发明作进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

本发明介绍了DG过渡时期的先进故障管理系统方案,这一方案基于现有的保护配置及配网自动化系统设备(包括设备自动化和远程可控开关),它能够提供DG并网时所需的保护,同时减少故障持续时间,减少未能供出的DG电能以及由于电能与机械能不平衡造成DG轴扭矩。其包括的内容如下:The present invention introduces an advanced fault management system solution during the transition period of DG. This solution is based on the existing protection configuration and distribution network automation system equipment (including equipment automation and remote controllable switches), which can provide the required energy for DG grid connection. Protection, while reducing the fault duration, reducing the unsupplied DG electric energy and the DG shaft torque caused by the imbalance between electric energy and mechanical energy. It includes the following contents:

1)在DG容量增大到一定程度的情况下,将并网变电站的变压器接地方式进行调整;1) When the DG capacity increases to a certain extent, adjust the grounding method of the transformer in the grid-connected substation;

2)在已有的保护配置条件下,使当地低频低压装置与配电自动化系统相协调,完成事故后负荷转移及孤岛划分;2) Under the existing protection configuration conditions, coordinate the local low-frequency and low-voltage devices with the distribution automation system, and complete the load transfer and island division after the accident;

3)通过“孤岛”运行方式的操作,实现对一级重要负荷故障期间的持续供电,以及岛内相应的微网保护调整。3) Through the operation of the "island" operation mode, the continuous power supply to the first-level important load during the failure period and the corresponding micro-grid protection adjustment in the island are realized.

本发明的目的是通过接地方式及二次保护系统的优化,解决了DG由单纯“负荷”性质向“小电源”性质过渡的复杂性问题,在现有的保护及自动装置不变的情况下,通过相关技术手段,达到基本满足DG接入后地区电网安全运行的目的。The purpose of the present invention is to solve the complex problem of DG transitioning from a simple "load" property to a "small power source" property through the optimization of the grounding method and the secondary protection system. Under the condition that the existing protection and automatic devices remain unchanged , through relevant technical means, to basically meet the purpose of safe operation of the regional power grid after DG access.

该方案通过改变变电站变压器的接地方式、保护装置的配置、定值整定方案及备自投、低频低压解列方式,最大程度减少故障持续时间,防止DG的损坏。1)在DG容量增大到一定程度的情况下,将并网变电站的变压器接地方式进行调整;This scheme minimizes the fault duration and prevents DG damage by changing the grounding mode of the transformer in the substation, the configuration of the protection device, the setting scheme of the fixed value, and the mode of standby self-switching, low-frequency and low-voltage decoupling. 1) When the DG capacity increases to a certain extent, adjust the grounding method of the transformer in the grid-connected substation;

2)在已有的保护配置条件下,使当地低频低压装置与配电自动化系统相协调,完成事故后负荷转移及孤岛划分;2) Under the existing protection configuration conditions, coordinate the local low-frequency and low-voltage devices with the distribution automation system, and complete the load transfer and island division after the accident;

3)通过“孤岛”运行方式的操作,实现对一级重要负荷故障期间的持续供电,以及岛内相应的微网保护调整。3) Through the operation of the "island" operation mode, the continuous power supply to the first-level important load during the failure period and the corresponding micro-grid protection adjustment in the island are realized.

方案包括以下具体步骤:The protocol includes the following specific steps:

1基于DG并网过渡运行方式协调综合保护方案策略的提出1 Proposal of coordinated comprehensive protection scheme strategy based on DG grid-connected transition operation mode

国际大型电力系统委员会(CIGRE)指出,将分布式发电定义为“非经规划的或中央调度型的电力生产方式,通常与配电网连接,一般发电规模在50~100MW之间。因此当本地DG容量不断增大,达到设定的容量值(50MVA)时,DG就不能当作单纯的“负荷”考虑,而应该将其视为与系统相连的、与发电机组性质不同的“分布式电源”。其保护及自动装置需要解决的问题就是两个层面的问题:1.有效的隔离故障;2.最大范围的保证有效供电。为了解决第一个问题,首先要明确DG容量在增长到哪个点时引起保护的不配合,因而需要调整保护定值;其次是由于DG容量较小时的保护及开关配置在DG作为“小电源”考虑时将是不完善的,如果想要在故障发生时有效的隔离故障,这时的故障断开点需要进行相应调整。为了解决第二个问题,即DG容量增大到一定程度时对当地负荷的支持能力,因此,需要考虑在哪个开关断点断开,形成孤岛运行方式,同时,在形成孤岛后,对于岛内微网保护的实现也需要兼顾考虑。同样道理,对于故障隔离后的负荷重新分配,同样也是要在充分考虑负荷重要性及与当地供配平衡关系的前提下,通过解列及低频低压减载装置将负荷损失降至最低。图1给出了本策略调整的逻辑流程图。从图中可以看出,保护方案要同时考虑两个问题,一是DG作为“小电源”对故障点持续提供短路电流时如何确定故障隔离边界,二是故障隔离后孤岛运行方式下边界点的确定。因此,断开点不仅要充当故障隔离断点的职能,同时也是动态划分孤岛运行方式的边界点;同样道理,DG也具有“双重角色”,一是在发生故障时作为“小电源”提供短路电流需要进行充分隔离,二是在故障判断后还要充当当地供电电源的角色,维持孤岛运行方式。The International Committee on Large Power Systems (CIGRE) pointed out that distributed generation is defined as "unplanned or centrally dispatched power production, usually connected to the distribution network, and the general power generation scale is between 50 and 100MW. Therefore, when local The capacity of DG keeps increasing, and when it reaches the set capacity value (50MVA), DG should not be considered as a simple "load", but should be regarded as a "distributed power supply" connected to the system and different in nature from the generator set. ". The problems to be solved by its protection and automatic devices are two-level problems: 1. Effective isolation of faults; 2. Guaranteeing effective power supply in the largest range. In order to solve the first problem, it is first necessary to clarify at which point the DG capacity is increasing. Therefore, it is necessary to adjust the protection setting; secondly, the protection and switch configuration when the DG capacity is small will be incomplete when DG is considered as a "small power supply". If you want to be effective when a fault occurs The isolated fault of the fault, at this time, the fault disconnection point needs to be adjusted accordingly. In order to solve the second problem, that is, the ability to support the local load when the DG capacity increases to a certain extent, it is necessary to consider which switch disconnection point to disconnect , forming an isolated island operation mode. At the same time, after the island is formed, the realization of micro-grid protection in the island also needs to be considered. Similarly, for load redistribution after fault isolation, it is also necessary to fully consider the importance of the load and the relationship with the local Under the premise of supply-distribution balance relationship, the load loss is minimized by decoupling and low-frequency low-voltage load shedding devices. Figure 1 shows the logic flow chart of this strategy adjustment. It can be seen from the figure that the protection scheme should consider both One is how to determine the fault isolation boundary when DG as a "small power supply" continuously provides short-circuit current to the fault point, and the other is the determination of the boundary point under the island operation mode after fault isolation. Therefore, the disconnection point should not only act as a fault isolation break The function of the DG point is also the boundary point for dynamically dividing the island operation mode; in the same way, the DG also has a "dual role". Finally, it will also act as a local power supply to maintain the island operation mode.

在过渡运行方式下,由于开关断开点的分布及可备用电源的不足需要相应的保护及安全自动装置方案作适应性调整。在进行方案确定的时候,首先故障隔离范围的确定需要收集开关断开点所确定的新边界,并且还要综合考虑这一边界点一旦确定而随之产生的系统解列及孤岛运行方式是否可稳定运行。因此,为了实现在精确隔离故障后的重要负荷的可靠运行,需要综合考虑多个因素,因此信息流的交互就会涉及到以下5个方面:In the transitional operation mode, due to the distribution of switch disconnection points and the lack of backup power supply, it is necessary to make adaptive adjustments to the corresponding protection and safety automatic device scheme. When determining the scheme, firstly, the determination of the fault isolation range needs to collect the new boundary determined by the disconnection point of the switch, and it is also necessary to comprehensively consider whether the system disconnection and the island operation mode that will follow once this boundary point is determined are feasible. Stable operation. Therefore, in order to achieve reliable operation of important loads after accurate isolation of faults, multiple factors need to be considered comprehensively, so the interaction of information flow will involve the following five aspects:

·成本与能源信息·Cost and energy information

·管理与环境信息·Management and environmental information

·控制与测量信息· Control and measurement information

·临界状态信息·Critical state information

·负荷用户信息· Load user information

在电源资源相对比较紧张的情况下,需要对网络拓扑结构、潮流分布、开关分布、保护配置及当地DG的负荷平衡能力、当地供电负荷的性质等因素进行综合分析考虑,并适当地考虑一些变量可能带来的参数误差,才能确定适用于当前运行方式下的可靠、经济保护及安全自动装置方案,方案了确定各个开关及保护配置点的配合关系,用来实现以最小隔离范围隔离故障以及以最小的成本来获得最优的负荷转移方案。信息流向及融合方式如图2所示。根据负荷重要性等级及当地负荷平衡能力确定负荷转移方案。由图2可知,方案的提出及解决实质上是基于5种不同性质信息源的分析处理及综合。简言之,即作为第一层面的保护方案的形成,主要是基于开关(故障断开点)及故障状态分析的结果;而为了事故后可以成功的转移负荷,系统解列方式不仅要考虑现有开关断开后形成即孤岛划分方式,还要综合考虑潮流分析、经济分析、负荷性质等几个层面的问题。因此,在整个的数据来源中,要首先提取出问题解决所需的有关信息,然后根据已有的规则及权重设计,最终形成电网安全稳定运行、用户可靠经济运行的高效方案。In the case of relatively tight power resources, it is necessary to comprehensively analyze and consider factors such as network topology, power flow distribution, switch distribution, protection configuration, local DG load balancing capability, and the nature of local power supply loads, and properly consider some variables The possible parameter errors can be used to determine the reliable, economical protection and safety automatic device scheme suitable for the current operation mode. The scheme determines the coordination relationship between each switch and protection configuration points, which is used to isolate faults with the minimum isolation range and the following The minimum cost to obtain the optimal load transfer scheme. The information flow and fusion method are shown in Figure 2. Determine the load transfer scheme according to the load importance level and local load balancing capability. It can be seen from Figure 2 that the proposal and solution of the scheme are essentially based on the analysis, processing and synthesis of five different types of information sources. In short, the formation of the first-level protection scheme is mainly based on the results of the switch (fault disconnection point) and fault state analysis; and in order to successfully transfer the load after the accident, the system unloading method must not only consider the current There is an island division method formed after the switch is disconnected, and several aspects such as power flow analysis, economic analysis, and load nature must be considered comprehensively. Therefore, in the entire data source, it is necessary to first extract the relevant information needed to solve the problem, and then design according to the existing rules and weights, and finally form an efficient solution for the safe and stable operation of the power grid and the reliable and economical operation of users.

3基于DG性质及关断点的保护方案实施3 Implementation of protection scheme based on DG properties and cut-off points

3.1基于一次运方及开关的保护最初保护及解列方案3.1 The initial protection and de-loading scheme based on the primary transport and switch protection

本方案中由于DG性质发生了变化,将并网变压器高压侧接地,对侧系统线路保护由原来的距离、零序I段伸入变压器,改为保线路85%,并借助于本站变压器高压侧的零序保护作为线路主保护,跳高压侧及桥开关,同时联切并网线开关。其新运行方式决定的开关断开点及非完全保护配置如图4所示。In this scheme, due to the change in the nature of DG, the high-voltage side of the grid-connected transformer is grounded, and the line protection of the opposite side system is extended from the original distance, zero-sequence section I into the transformer, and changed to protect 85% of the line. The zero-sequence protection on the side is used as the main protection of the line, tripping the high-voltage side and the bridge switch, and simultaneously disconnecting the grid line switch. The break point of the switch determined by its new operation mode and the non-complete protection configuration are shown in Fig. 4 .

3.2由过渡运行方式决定的开关断点及不充分保护配置方案3.2 Switch breakpoint determined by transitional operation mode and insufficient protection configuration scheme

图3分布式电源接入110kV变电站接线图。其中MV/LV变电站采用的为内桥式接线,其中的01,02为刀闸,其中跳闸联切并网线L1功能,是由03开关跳闸联切功能实现。由于其初始设计规模小的原因,其分布电源并网的变电站视为无小电源并网的末端站,因此,在变电站侧开关(03,04)并不配置保护装置,因此借助于#1、#2变压器高后备保护是首选。一般只要满足保护灵敏度要求,变压器高后备并不会配置距离保护,同时考虑到光伏电源在系统故障时提供短路电流能力差,同时到目前为止不存在可以应用于工程实际的算法,因此需要寻找一个可靠准确反应系统故障的故障源。综合以上两个因素,最直接的解决办法是将分布式电源视为“小电源”,将变电站的110kV侧接地。同时将高后备保护中的零序过流保护视为负荷侧03,04的线路保护,其整定原则也是遵循本侧线路保护配置原则;I段躲本线线末故障;II段保本线全长且保证灵敏度,并与对侧变电站(220kV站)的所有出线相配合。这样在系统发生故障时,由变压器高压侧接地点向故障点提供足够的零序故障电流,使的其变压器高后备保护动作,开关03(或04)跳开。由分析可知,变压器接地点的确定是分布式电源从哪一台变压器并网,这一台的变压器高压侧就接地运行。接地运行只是为了对系统故障提供一个零序电流源,这一零序系统与分布式电源无关。尽管如此,由于分布式电源是在这一台主变并网,本变高压侧开关跳开后,就有效的将分布式电源从电网隔离。Fig. 3 Wiring diagram of distributed power supply connected to 110kV substation. Among them, the MV/LV substation adopts the inner bridge connection, and the 01 and 02 are knife switches, and the function of tripping and cutting the parallel network line L1 is realized by the tripping and cutting function of the 03 switch. Due to the small scale of its initial design, the substation whose distributed power supply is connected to the grid is regarded as a terminal station without small power supply connected to the grid. Therefore, the switches (03, 04) on the substation side are not equipped with protection devices. Therefore, with the help of #1, #2 Transformer high backup protection is preferred. Generally, as long as the protection sensitivity requirements are met, the high backup of the transformer will not be equipped with distance protection. At the same time, considering that the photovoltaic power supply has poor short-circuit current capability when the system fails, and there is no algorithm that can be applied to engineering practice so far, it is necessary to find a Reliably and accurately reflect the fault source of the system fault. Combining the above two factors, the most direct solution is to regard the distributed power supply as a "small power supply" and ground the 110kV side of the substation. At the same time, the zero-sequence overcurrent protection in the high backup protection is regarded as the line protection of the load side 03 and 04, and its setting principle also follows the principle of line protection configuration on the local side; section I hides the end-of-line fault of the main line; section II maintains the full length of the main line And ensure the sensitivity, and cooperate with all outgoing lines of the opposite side substation (220kV station). In this way, when a fault occurs in the system, the grounding point of the high-voltage side of the transformer provides enough zero-sequence fault current to the fault point, so that the high backup protection of the transformer operates, and the switch 03 (or 04) trips. It can be seen from the analysis that the determination of the grounding point of the transformer is which transformer the distributed power supply is connected to the grid, and the high-voltage side of the transformer of this one is grounded. Ground operation is only to provide a zero-sequence current source for system faults, and this zero-sequence system has nothing to do with distributed power. Nevertheless, since the distributed power is connected to the grid at this main transformer, the distributed power is effectively isolated from the grid after the high-voltage side switch of the local transformer is tripped.

3.3故障响应分析3.3 Failure response analysis

按照目前的保护配置,保护动作如下:线路故障时两端断路器跳开不重合,备投动作,联切DG并网线的模式,此时局部区域将进入孤岛运行方式;作为低压侧近后备及低压侧母线主保护的低压侧限时速断保护跳开本侧开关,联切DG并网线,闭锁低压侧分段备投;主变差动及非电量保护动作,不闭锁变电站进线及低压侧分段备投。According to the current protection configuration, the protection action is as follows: when the line is faulty, the circuit breakers at both ends trip and do not overlap, and the backup operation is performed, and the mode of cutting the DG grid-connected line is connected. At this time, the local area will enter the island operation mode; The low-voltage side time-limited quick-break protection of the main protection of the low-voltage side busbar trips the switch on this side, cuts off the DG grid-connected line, and blocks the low-voltage side segmental backup; the main transformer differential and non-electrical protection action does not block the incoming line of the substation and the low-voltage side segment Prepare to vote.

当一台变运行时,系统侧线路发生故障,将由03开关动作,直接切断光伏与系统的联络通道,高压侧母线失压,不会影响备自投的正常动作。但对于两台变同时运行的方式,变压器高压侧开关03动作并不能完全切断分布式电源的通道,因此会影响备自投的成功率,为此高后备保护动作的同时需要联切本站光伏的并网线L1,根据目前的保护配置这一条可以满足。并且由原来的两台变并列运行改由一台变运行后,需要低压侧的低频、低压装置动作,对相应负荷进行均衡,以达到保证供电质量的问题。而经平衡后跳开的负荷可借助于配网的手拉手加以解决。When one substation is running, if the line on the system side fails, the 03 switch will act to directly cut off the communication channel between the photovoltaic system and the system, and the busbar on the high-voltage side will lose pressure, which will not affect the normal operation of the standby automatic switch. However, for the mode of simultaneous operation of two transformers, the action of switch 03 on the high voltage side of the transformer cannot completely cut off the channel of the distributed power supply, so it will affect the success rate of backup and automatic switching. According to the current protection configuration, this line can be satisfied. And after the parallel operation of the original two substations is changed to the operation of one substation, the low-frequency and low-voltage devices on the low-voltage side need to operate to balance the corresponding loads to ensure the quality of power supply. And the load that jumps out after balancing can be solved by means of the hand in hand of the distribution network.

通过高后备零序保护的保护范围可以看出,03开关保护的范围扩大到高压侧母线。由分析可知,当高压侧母线发生故障时,如果没有有效的识别及闭锁措施,就会导致备投再次投于故障,造成对系统的再次冲击。最好的解决方法是选择在分布式电源并网变电站高压侧装设母差保护,当母线发生故障时,由母差保护动作节点输出闭锁备投装置;如果没有配置母差保护,可以通过比较流过03与01开关的故障电流大小来判断是否为母线故障。当I03>I01时,说明为母线故障。因为,只有故障点位于两开关之间时,才会出现03开关感受到的由系统提供的短路电流远大于01开关由分布式电源提供的短路电流。注意,这里零序电流不再是判断依据,而是直接比较两侧电源所提供的短路电流大小。It can be seen from the protection range of the high-backup zero-sequence protection that the protection range of the 03 switch is extended to the high-voltage side bus. It can be seen from the analysis that when the high-voltage side bus fails, if there is no effective identification and blocking measures, it will cause the backup switch to fail again, causing another impact on the system. The best solution is to install bus differential protection on the high-voltage side of the distributed power grid-connected substation. When the bus fails, the bus differential protection action node will output the blocking backup switching device; if the bus differential protection is not configured, you can compare The magnitude of the fault current flowing through the 03 and 01 switches can be used to judge whether it is a bus fault. When I03>I01, it means bus failure. Because, only when the fault point is located between the two switches, the short-circuit current provided by the system felt by the 03 switch is much greater than the short-circuit current provided by the distributed power supply of the 01 switch. Note that the zero-sequence current is no longer the basis for judging here, but directly compares the short-circuit current provided by the power supplies on both sides.

4基于DG性质及关断点的负荷转移及孤岛操作方案实施4 Implementation of load transfer and island operation scheme based on DG properties and shutdown points

如图3所示,变压器低压侧DG并网线及至每个DG发电单元构成一整套保护配合系统。可以看出以并网线为分界点,系统侧应以系统侧提供的短路电流为整定基准,而作为并网开关跳开后孤岛运行方式下的保护系统应以PD2为始点,因此为保证其能适用于微网运行方式,此系统应以DG提供的小的多的短路电流为基准。这样处理的结果,尽管会使基于DG提供短路电流水平相对系统侧保护会非常灵敏,在系统发生故障也会导致其动作进入孤岛运行方式,但是可以通过时间配合解决这一问题,同时可其保护也可以同时适用于并网及“孤岛”下保护的选择性。As shown in Figure 3, the DG grid-connected line on the low-voltage side of the transformer and each DG power generation unit constitute a complete protection coordination system. It can be seen that with the grid-connected line as the demarcation point, the system side should take the short-circuit current provided by the system side as the setting reference, and the protection system under the island operation mode after the grid-connected switch trips should start from PD2, so in order to ensure its performance Applicable to micro-grid operation mode, this system should be based on the much smaller short-circuit current provided by DG. As a result of this treatment, although the short-circuit current level provided by DG will be very sensitive to the system side protection, and it will also cause its action to enter the island operation mode when the system fails, but this problem can be solved through time cooperation, and at the same time it can be protected. It can also be applied to the selectivity of grid-connected and "isolated island" protection.

考虑到系统故障时DG需要作为电源对当地负荷进行有效的支持,我们不希望其在系统故障时,在故障切除过程中及系统负荷平衡未完成时DG停运,因此,与供电质量相关的电压、频率保护及低频、低压减载装置与系统侧的对应配合关系如图7(a)、(b)、(c)所示。Considering that the DG needs to be used as a power supply to effectively support the local load when the system fails, we do not want the DG to shut down during the system failure, during the fault removal process and when the system load balance is not completed. Therefore, the voltage related to the power supply quality , frequency protection and low frequency, low voltage load shedding device and the corresponding cooperation relationship with the system side as shown in Figure 7 (a), (b), (c).

从图7(a)、(b)、(c)中的配合关系可知,在不会导致DG相关设备损害的前提下,DG侧不论是频率还是电压继电器都比系统侧对应保护高出一个配合级差,这也就保证了当系统侧发生故障时,DG不会先于系统侧相对应继电器动作而导致无法实现对系统的有效支持。同时,也可以看出,基于DG孤岛运行方式的考虑,其DG侧保护的定值是以DG额定容量为基准,即PD3a=2.5In-DG;而系统侧保护取的是以本侧额定电流为基准PD3a=2.5In-LV。尽管DG侧定值取值相对低很多,但是由于时间级差上的配合,使的系统侧发生故障后其保护不会误动,同时,在DG进入孤岛运行方式时仍可以保持其保护功能,及时消除岛内发生的故障。From the coordination relationship in Figure 7(a), (b), and (c), it can be seen that under the premise that it will not cause damage to DG-related equipment, both the frequency and voltage relays on the DG side are higher than the corresponding protection on the system side by one coordination This also ensures that when a fault occurs on the system side, the DG will not act before the corresponding relay on the system side, resulting in failure to achieve effective support for the system. At the same time, it can also be seen that based on the consideration of the DG island operation mode, the fixed value of the DG side protection is based on the DG rated capacity, that is, PD 3a = 2.5I n-DG ; while the system side protection is based on the local side The rated current is based on PD 3a =2.5I n-LV . Although the fixed value of the DG side is relatively low, due to the coordination of the time difference, the protection will not malfunction after a fault occurs on the system side. Eliminate malfunctions that occur on the island.

本文介绍了一种基于DG并网过渡运行方式协调综合保护方案策略,当DG容量不断增加,使的其短路电流水平增加,DG性质也由原来的“纯负荷”转换为“小电源”性质,现有的保护及开关断点已经无法满足过渡情况的需要。本方案在已有的保护及开关断点条件下,通过与一次运行方式的不断匹配,方案的不断优化,信息及状态量的不断交流,形成与一次系统相适应的保护控制接口,达到系统安全运行及供电持续的双重目的。首先故障隔离范围的确定需要收集开关断开点所确定的新边界,并且还要综合考虑这一边界点一旦确定而随之产生的系统解列及孤岛运行方式是否可稳定运行。通过改变变压器接地方式,确保系统故障时可以有效发现故障;同时借助于变压器高压侧零序过流及开关实现了对系统故障的有效隔离;通过保护及自动装置的定值配合,保证了在故障隔离后,有效转移负荷;通过DG孤岛运行操作,保持了DG对当地负荷的持续供电,并且其保护也实现了微网保护功能。这一方案对于大量DG不断增长接入当地的情况提供了有效的解决手段。This paper introduces a coordinated comprehensive protection scheme strategy based on the DG grid-connected transition operation mode. When the DG capacity continues to increase, its short-circuit current level increases, and the DG nature is also converted from the original "pure load" to "small power supply". Existing protection and switch breakpoints can no longer meet the needs of transitional situations. Under the existing protection and switch breakpoint conditions, this scheme forms a protection control interface suitable for the primary system through continuous matching with the primary operation mode, continuous optimization of the scheme, and continuous exchange of information and state quantities to achieve system security. The dual purpose of operation and power supply continuity. First of all, the determination of the fault isolation range needs to collect the new boundary determined by the disconnection point of the switch, and also comprehensively consider whether the system disconnection and island operation mode that will occur once this boundary point is determined can operate stably. By changing the grounding mode of the transformer, it is ensured that the fault can be effectively detected when the system fails; at the same time, the effective isolation of the system fault is realized by means of the zero-sequence overcurrent and the switch on the high voltage side of the transformer; After isolation, the load is effectively transferred; through the operation of the DG island, the continuous power supply of the DG to the local load is maintained, and its protection also realizes the micro-grid protection function. This solution provides an effective solution to the situation where a large number of DGs are continuously connected to the local area.

实施例一:如图3所示,变压器低压侧DG并网线及至每个DG发电单元构成一整套保护配合系统。可以看出以并网线为分界点,系统侧应以系统侧提供的短路电流为整定基准,而作为并网开关跳开后孤岛运行方式下的保护系统应以PD2为始点,因此为保证其能适用于微网运行方式,此系统应以DG提供的小的多的短路电流为基准。这样处理的结果,尽管会使基于DG提供短路电流水平相对系统侧保护会非常灵敏,在系统发生故障也会导致其动作进入孤岛运行方式,但是可以通过时间配合解决这一问题,同时可其保护也可以同时适用于并网及“孤岛”下保护的选择性。Embodiment 1: As shown in Figure 3, the DG grid-connected line at the low-voltage side of the transformer and each DG power generation unit constitute a complete protection coordination system. It can be seen that with the grid-connected line as the demarcation point, the system side should take the short-circuit current provided by the system side as the setting reference, and the protection system under the island operation mode after the grid-connected switch trips should start from PD2, so in order to ensure its performance Applicable to micro-grid operation mode, this system should be based on the much smaller short-circuit current provided by DG. As a result of this treatment, although the short-circuit current level provided by DG will be very sensitive to the system side protection, and it will also cause its action to enter the island operation mode when the system fails, but this problem can be solved through time cooperation, and at the same time it can be protected. It can also be applied to the selectivity of grid-connected and "isolated island" protection.

考虑到系统故障时DG需要作为电源对当地负荷进行有效的支持,我们不希望其在系统故障时,在故障切除过程中及系统负荷平衡未完成时DG停运,因此,与供电质量相关的电压、频率保护及低频、低压减载装置与系统侧的对应配合关系如图7(a)、图7(b)、图7(c)所示。Considering that the DG needs to be used as a power supply to effectively support the local load when the system fails, we do not want the DG to shut down during the system failure, during the fault removal process and when the system load balance is not completed. Therefore, the voltage related to the power supply quality , frequency protection, low frequency, low voltage load shedding device and the corresponding cooperation relationship on the system side are shown in Fig. 7(a), Fig. 7(b) and Fig. 7(c).

从图7(a)、图7(b)、图7(c)中的配合关系可知,在不会导致DG相关设备损害的前提下,DG侧不论是频率还是电压继电器都比系统侧对应保护高出一个配合级差,这也就保证了当系统侧发生故障时,DG不会先于系统侧相对应继电器动作而导致无法实现对系统的有效支持。同时,也可以看出,基于DG孤岛运行方式的考虑,其DG侧保护的定值是以DG额定容量为基准,即PD3a=2.5In-DG;而系统侧保护取的是以本侧额定电流为基准PD3a=2.5In-LV。尽管DG侧定值取值相对低很多,但是由于时间级差上的配合,使的系统侧发生故障后其保护不会误动,同时,在DG进入孤岛运行方式时仍可以保持其保护功能,及时消除岛内发生的故障。From the coordination relationship in Figure 7(a), Figure 7(b), and Figure 7(c), it can be seen that, on the premise that it will not cause damage to DG-related equipment, the DG side, whether it is frequency or voltage relay, is better than the system side. It is higher than a coordination level difference, which also ensures that when a fault occurs on the system side, the DG will not act before the corresponding relay on the system side, resulting in failure to achieve effective support for the system. At the same time, it can also be seen that based on the consideration of the DG island operation mode, the fixed value of the DG side protection is based on the DG rated capacity, that is, PD 3a = 2.5I n-DG ; while the system side protection is based on the local side The rated current is based on PD 3a =2.5I n-LV . Although the fixed value of the DG side is relatively low, due to the coordination of the time difference, the protection will not malfunction after a fault occurs on the system side. Eliminate malfunctions that occur on the island.

上述虽然结合附图对本发明的具体实施方式进行了描述,但并非对本发明保护范围的限制,所属领域技术人员应该明白,在本发明的技术方案的基础上,本领域技术人员不需要付出创造性劳动即可做出的各种修改或变形仍在本发明的保护范围以内。Although the specific implementation of the present invention has been described above in conjunction with the accompanying drawings, it does not limit the protection scope of the present invention. Those skilled in the art should understand that on the basis of the technical solution of the present invention, those skilled in the art do not need to pay creative work Various modifications or variations that can be made are still within the protection scope of the present invention.

Claims (10)

1. coordinate a comprehensive method of protection based on the grid-connected transition operational mode of distributed power generation, it is characterized in that: comprise the following steps:
(1) the Fault Isolation border of clear and definite DG capacity, adjusts its protection definite value, determines decoupled mode lower boundary point after Fault Isolation, after DG capacity increases to set point, the transformer grounding mode of grid-connected transformer station adjusted;
(2) under existing relaying configuration condition, local low-frequency and low-voltage device is coordinated mutually with electrical power distribution automatization system, complete the transfer of accident afterload and isolated island division;
(3) according to decoupled mode, formulate relaying configuration scheme, carry out failure response analysis, the continued power between realizing one-level important load age at failure, and the protection of corresponding microgrid adjusts on the island in.
2. as claimed in claim 1 a kind of based on distributed power generation grid-connected transition operational mode coordination comprehensive method of protection; it is characterized in that: in described step (1); when local DG capacity constantly increases; when reaching the capability value of setting; DG is not just used as simple load and considers, and should be regarded as be connected with system, with the distributed power source of generating set different in kind.
3. coordinate a comprehensive method of protection based on the grid-connected transition operational mode of distributed power generation, it is characterized in that: in described step (1), first want clear and definite DG capacity to cause mismatching of protection when which rising to and putting, thus need adjustment protection definite value; Next is less than 50MW protection and switchgear distribution carries out following adjustment at fault cut-off point when DG capacity: jump DG and to surf the Net transforming plant main transformer high-pressure side and bridge switch, grid-connected wiretap cut by connection simultaneously.
4. as claimed in claim 1 a kind of based on distributed power generation grid-connected transition operational mode coordination comprehensive method of protection, it is characterized in that: in described step (1), when DG capacity increases to set point degree, which need to consider at switch breakpoint to disconnect, form decoupled mode, meanwhile, after formation isolated island, take into account and consider for microgrid protection in island; Redistributing for the load after Fault Isolation, is equally also to take into full account load importance and under supplying the prerequisite of balancing relation with locality, load loss to be down to minimum by off-the-line and low-frequency low-voltage load shedding device.
5. as claimed in claim 1 a kind of based on distributed power generation grid-connected transition operational mode coordination comprehensive method of protection, it is characterized in that: in described step (2), under transition operational mode, due to switch cut-off point distribution and can the deficiency of stand-by power supply need corresponding protection and automatic safety device scheme to make accommodation; When carrying out scheme and determining, first the determination of Fault Isolation scope needs to collect the determined new border of switch cut-off point, and this boundary point will be considered once the system splitting determining and produce thereupon and decoupled mode whether Absorbable organic halogens runs.
6. as claimed in claim 1 a kind of based on distributed power generation grid-connected transition operational mode coordination comprehensive method of protection, it is characterized in that: in described step (2), in order to realize the reliability service of the important load after accurate isolated fault, needing considering cost and energy information, manage and environmental information, to control and metrical information, critical condition information and load user profile; When power resources anxiety; need comprehensively to analyze consideration to network topology structure, trend distribution, switch distribution, relaying configuration and the load balancing ability of local DG and the character factor of local supply load; could determine to be applicable to reliable, the economic protection under current operational mode and automatic safety device scheme; scheme determines the matching relationship of each switch and relaying configuration point, is used for realizing originally obtaining optimum load transfer plan scheme with minimum isolation range isolated fault and with minimum one-tenth.
7. as claimed in claim 1 a kind of based on distributed power generation grid-connected transition operational mode coordination comprehensive method of protection; it is characterized in that: in described step (3); because DG character there occurs change; by grid-connected high voltage side of transformer ground connection; the protection of offside system line stretches into transformer by original distance, zero sequence I section, changes into and protects circuit 85%, and by means of the zero-sequenceprotection of our station high voltage side of transformer as power line main protection; jump high-pressure side and bridge switch, grid-connected wiretap cut by connection simultaneously.
8. as claimed in claim 1 a kind of based on distributed power generation grid-connected transition operational mode coordination comprehensive method of protection, it is characterized in that: in described step (3), protection act is as follows: during line fault, two ends circuit breaker tripping does not overlap, standby throwing action, connection cuts DG and the pattern of netting twine, and now regional area will enter decoupled mode; As this side switch of low-pressure side time-limit quick break protection tripping of the nearly standby of low-pressure side and low-pressure side bus main protection, connection cuts DG and netting twine, and the segmentation of locking low-pressure side is standby throws; Main transformer differential and non-ionizing energy loss action, not locking transforming plant lead-in and the standby throwing of low-pressure side segmentation.
9. as claimed in claim 1 a kind of based on distributed power generation grid-connected transition operational mode coordination comprehensive method of protection, it is characterized in that: in described step (3), when becoming operation for one, system side line failure, by standby high voltage side of transformer switch motion of throwing Union Switch Device, the service channel of direct cut-out photovoltaic and system, high-voltage side bus decompression, the regular event of prepared auto restart can not be affected, but become for two the mode simultaneously run, high voltage side of transformer switch motion can not cut off the passage of distributed power source completely, therefore the success rate of prepared auto restart can be affected, need connection to cut the also netting twine of our station photovoltaic while high backup protection action for this reason, and becoming paired running by original two changes by after a change operation, need the low frequency of low-pressure side, low-voltage device action, equilibrium is carried out to corresponding load, to reach the problem ensureing power supply quality.
10. as claimed in claim 1 a kind of based on distributed power generation grid-connected transition operational mode coordination comprehensive method of protection, it is characterized in that: in described step (3), select at distributed power source grid-connected transformer station high-pressure side installing bus differential protection, when bus breaks down, export locking spare power by bus bar differential prptection operation node; If do not configure bus differential protection; busbar fault is determined whether by comparing the fault current size flowing through inlet wire transformer substation side switch and high voltage side of transformer disconnecting link; when the electric current that inlet wire transformer substation side switch flows through is greater than the fault current that transformer high-voltage side tool flows through, be illustrated as busbar fault.
CN201510185147.7A 2015-04-17 2015-04-17 A Coordinated Comprehensive Protection Method Based on Distributed Generation Grid-connected Transition Operation Mode Active CN104836214B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510185147.7A CN104836214B (en) 2015-04-17 2015-04-17 A Coordinated Comprehensive Protection Method Based on Distributed Generation Grid-connected Transition Operation Mode

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510185147.7A CN104836214B (en) 2015-04-17 2015-04-17 A Coordinated Comprehensive Protection Method Based on Distributed Generation Grid-connected Transition Operation Mode

Publications (2)

Publication Number Publication Date
CN104836214A true CN104836214A (en) 2015-08-12
CN104836214B CN104836214B (en) 2016-02-17

Family

ID=53813914

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510185147.7A Active CN104836214B (en) 2015-04-17 2015-04-17 A Coordinated Comprehensive Protection Method Based on Distributed Generation Grid-connected Transition Operation Mode

Country Status (1)

Country Link
CN (1) CN104836214B (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105117797A (en) * 2015-08-13 2015-12-02 浙江工业大学 Micro grid daily ahead economy optimal dispatch method based on islanding partition
CN105162086A (en) * 2015-09-11 2015-12-16 国家电网公司 Protection method for DG grid-connected transformer grounding system
CN105186468A (en) * 2015-08-13 2015-12-23 广东电网有限责任公司佛山供电局 Power distribution network direction over-current protection online setting method and system for access of distributed power supply
CN105207178A (en) * 2015-09-11 2015-12-30 国家电网公司 Distribution network fault location and islanding method based on DG access
CN106099973A (en) * 2016-06-29 2016-11-09 华能重庆两江燃机发电有限责任公司 A kind of Rhizoma Sparganii M701F4 type 3 simultaneous interconnecting implementation methods of unit gas turbine transformer unit
CN106099875A (en) * 2016-07-07 2016-11-09 周丽玲 A kind of based on distributed power generation grid-connected transition method of operation coordination comprehensive method of protection
CN106410766A (en) * 2016-11-11 2017-02-15 国网山东省电力公司枣庄供电公司 DG grid-connected electric system high acceptance protection method
CN110601154A (en) * 2019-08-26 2019-12-20 南京南瑞继保电气有限公司 Relay protection configuration method for alternating current system with power electronic power generation equipment
CN111130218A (en) * 2019-12-25 2020-05-08 深圳供电局有限公司 Unification device for safety and backup bus difference in substation
CN112134311A (en) * 2020-09-15 2020-12-25 广东电网有限责任公司韶关供电局 Control method, device, equipment and storage medium for small hydropower station power grid
CN112165090A (en) * 2020-09-29 2021-01-01 国电南瑞南京控制系统有限公司 Cooperative self-healing system and method
CN112510658A (en) * 2020-11-11 2021-03-16 广西电网有限责任公司电力科学研究院 Multi-power-supply-point 10kV line feeder automation method with high power supply reliability
CN115498699A (en) * 2022-11-21 2022-12-20 广东电网有限责任公司中山供电局 Energy storage converter grid-connected and off-grid switching method, system, equipment and medium

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102882197A (en) * 2012-10-30 2013-01-16 山东电力集团公司烟台供电公司 DG (distributed generation)-containing power distribution network distributed protection and control method
CN103036219A (en) * 2012-12-10 2013-04-10 华北水利水电学院 Low-voltage micro-grid comprehensive protection method
CN103944160A (en) * 2014-04-09 2014-07-23 国家电网公司 Distribution network protection and automatic device cooperating method based on DG characteristics

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102882197A (en) * 2012-10-30 2013-01-16 山东电力集团公司烟台供电公司 DG (distributed generation)-containing power distribution network distributed protection and control method
CN103036219A (en) * 2012-12-10 2013-04-10 华北水利水电学院 Low-voltage micro-grid comprehensive protection method
CN103944160A (en) * 2014-04-09 2014-07-23 国家电网公司 Distribution network protection and automatic device cooperating method based on DG characteristics

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105117797A (en) * 2015-08-13 2015-12-02 浙江工业大学 Micro grid daily ahead economy optimal dispatch method based on islanding partition
CN105186468A (en) * 2015-08-13 2015-12-23 广东电网有限责任公司佛山供电局 Power distribution network direction over-current protection online setting method and system for access of distributed power supply
CN105186468B (en) * 2015-08-13 2018-01-16 广东电网有限责任公司佛山供电局 A kind of power distribution network directional over-current protection on-line tuning method and system of distributed power source access
CN105117797B (en) * 2015-08-13 2019-01-08 浙江工业大学 The microgrid economic optimum dispatching method a few days ago divided based on isolated island
CN105162086A (en) * 2015-09-11 2015-12-16 国家电网公司 Protection method for DG grid-connected transformer grounding system
CN105207178A (en) * 2015-09-11 2015-12-30 国家电网公司 Distribution network fault location and islanding method based on DG access
CN106099973A (en) * 2016-06-29 2016-11-09 华能重庆两江燃机发电有限责任公司 A kind of Rhizoma Sparganii M701F4 type 3 simultaneous interconnecting implementation methods of unit gas turbine transformer unit
CN106099875A (en) * 2016-07-07 2016-11-09 周丽玲 A kind of based on distributed power generation grid-connected transition method of operation coordination comprehensive method of protection
CN106410766A (en) * 2016-11-11 2017-02-15 国网山东省电力公司枣庄供电公司 DG grid-connected electric system high acceptance protection method
CN106410766B (en) * 2016-11-11 2017-10-13 国网山东省电力公司枣庄供电公司 Based on the high containment guard method of DG interconnected electric power systems
CN110601154A (en) * 2019-08-26 2019-12-20 南京南瑞继保电气有限公司 Relay protection configuration method for alternating current system with power electronic power generation equipment
CN110601154B (en) * 2019-08-26 2021-10-01 南京南瑞继保电气有限公司 Relay protection configuration method for alternating current system with power electronic power generation equipment
CN111130218A (en) * 2019-12-25 2020-05-08 深圳供电局有限公司 Unification device for safety and backup bus difference in substation
CN111130218B (en) * 2019-12-25 2022-05-10 深圳供电局有限公司 Transformer substation security bus difference unification device
CN112134311A (en) * 2020-09-15 2020-12-25 广东电网有限责任公司韶关供电局 Control method, device, equipment and storage medium for small hydropower station power grid
CN112134311B (en) * 2020-09-15 2022-06-14 广东电网有限责任公司韶关供电局 Control method, device, equipment and storage medium for small hydropower station power grid
CN112165090A (en) * 2020-09-29 2021-01-01 国电南瑞南京控制系统有限公司 Cooperative self-healing system and method
CN112510658A (en) * 2020-11-11 2021-03-16 广西电网有限责任公司电力科学研究院 Multi-power-supply-point 10kV line feeder automation method with high power supply reliability
CN112510658B (en) * 2020-11-11 2022-11-22 广西电网有限责任公司电力科学研究院 A high power supply reliability automatic method for 10kV line feeder with multiple power points
CN115498699A (en) * 2022-11-21 2022-12-20 广东电网有限责任公司中山供电局 Energy storage converter grid-connected and off-grid switching method, system, equipment and medium
CN115498699B (en) * 2022-11-21 2023-01-20 广东电网有限责任公司中山供电局 Energy storage converter grid-connected and off-grid switching method, system, equipment and medium

Also Published As

Publication number Publication date
CN104836214B (en) 2016-02-17

Similar Documents

Publication Publication Date Title
CN104836214B (en) A Coordinated Comprehensive Protection Method Based on Distributed Generation Grid-connected Transition Operation Mode
Yazdaninejadi et al. Impact of inverter-based DERs integration on protection, control, operation, and planning of electrical distribution grids
Hamanah et al. AC microgrid protection schemes: A comprehensive review
Memon et al. A critical review of AC Microgrid protection issues and available solutions
CN102790383B (en) Automatic rapid protection control method of novel feeder
CN102882197B (en) DG (distributed generation)-containing power distribution network distributed protection and control method
CN109713794B (en) Distributed intelligent self-recovery system and method
CN107394897A (en) A kind of power distribution network intelligence self-healing method and system based on topological diagram
CN112366809B (en) Pilot plant spare power automatic switching device with new forms of energy
Sarathkumar et al. A technical review on self-healing control strategy for smart grid power systems
CN102290799B (en) Small-scale quick recovery method for power supply of power distribution network in open loop running
Zayandehroodi et al. A Comprehensive review of protection coordination methods in power distribution systems in the presence of DG
Jafari et al. Study of smart grid protection challenges with high photovoltaic penetration
CN108321774A (en) A kind of distribution automation controls on the spot and central controlled combined optimization method
CN104836330A (en) Method for quickly detecting bus PT three-phase disconnection of automatic switching device of standby power supply and method for preventing maloperation of bus PT three-phase disconnection of automatic switching device of standby power supply
CN106410766A (en) DG grid-connected electric system high acceptance protection method
Wan et al. Multi-agent application in protection coordination of power system with distributed generations
CN119050968A (en) On-site distributed area protection self-healing method and system for medium-voltage distribution network
CN107910855B (en) A kind of connection applied to intelligent substation cuts small power supply device
Boljevic et al. Fault current level issues for urban distribution network with high penetration of distributed generation
CN113890093B (en) Relay protection system of distributed power supply after being connected with diamond-type power grid
CN105703341B (en) There is the layering point domain isolated island guard method of anti-jump function for large-scale wind power
CN105004944B (en) A kind of power supply reliability computational methods assessed for power distribution network relay protection
Swathika et al. Relay Coordination in Real-Time Microgrid for varying load demands
Oudalov et al. Microgrid protection

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant