CN104805931A - Integrated assembled house building wall body and assembling method - Google Patents
Integrated assembled house building wall body and assembling method Download PDFInfo
- Publication number
- CN104805931A CN104805931A CN201510218650.8A CN201510218650A CN104805931A CN 104805931 A CN104805931 A CN 104805931A CN 201510218650 A CN201510218650 A CN 201510218650A CN 104805931 A CN104805931 A CN 104805931A
- Authority
- CN
- China
- Prior art keywords
- crossbeam
- wall
- connector
- facade plate
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 26
- 239000004567 concrete Substances 0.000 claims abstract description 14
- 238000009435 building construction Methods 0.000 claims description 21
- 238000009434 installation Methods 0.000 claims description 18
- 239000003292 glue Substances 0.000 claims description 7
- 239000000284 extract Substances 0.000 claims description 6
- 230000010412 perfusion Effects 0.000 claims description 6
- 239000002002 slurry Substances 0.000 claims description 6
- 230000001154 acute effect Effects 0.000 claims description 3
- 238000004826 seaming Methods 0.000 claims description 3
- 238000010276 construction Methods 0.000 description 9
- 210000002435 tendon Anatomy 0.000 description 4
- 229910000831 Steel Inorganic materials 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 230000003100 immobilizing effect Effects 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000011381 foam concrete Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004134 energy conservation Methods 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 230000002262 irrigation Effects 0.000 description 1
- 238000003973 irrigation Methods 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 238000010079 rubber tapping Methods 0.000 description 1
- 230000002459 sustained effect Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Landscapes
- Finishing Walls (AREA)
Abstract
The invention discloses an integrated assembled house building wall body and an assembling method which are applied to site assembling of indoor wall bodies of house buildings. The integrated assembled house building wall body is composed of a top and bottom locating pile, a support, a vertical face plate and filling concrete; the support is in a long-stripe framework shape and is formed by beams and beam connecting parts which are assembled in site; the vertical face plate covers and is fixed to the outer lateral side of the wall body; the vertical face plate is also fixed to the outer sides of fixed faces of face plates of the beams. The wall body can be quickly built in site and is not limited by the sizes of components, and the wall body can be flexibly built even if columns and special inner building structures exist. According to the integrated assembled house building wall body, prefabricated members or prefabricated frameworks are not needed, a wall body framework can be flexibly and quickly assembled through most fundamental stripe-shaped components, the wall body can be poured in site, a building process is not limited by the sizes of the components, only the horizontal support is needed, no vertical support is needed, the wall body is suitable for various structures, the components are convenient to transport, a wall body building processing is quick, the wall body is flexible and convenient to build, and a lot of house building time is saved.
Description
Technical field
The present invention relates to building construction technology, is the integrated assembling body of wall of a kind of building construction and assemble method specifically.
Background technology
Walling unit after the construction wall construction generally adopted at present adopts framework to form is assembled, long construction period.And existing integrated wall has template cast-in-place foamed concrete body of wall and zinc-plated keel shoe cement panel cast-in-place foamed concrete body of wall.Template cast-in-situ wall is owing to being build with the molding of polylith template to form, and its surface finish is wayward, and its body of wall unit weight is very up to the requirement less than lightweight; The assembling of zinc-plated keel shoe cement panel wall body keel frame is loaded down with trivial details is not easy to site operation, and because keel shoe is that iron sheet compacting forms, so easily deformable in the middle of irrigation process, to be unfavorable for ash wall body plate face bonding, and its wall cost is high to be unfavorable for promoting and energy-conservation.
Integrated assembling body of wall is used to face the requirement improving construction flexibility how to greatest extent, transport convenience and convenient and swift property equally.
Summary of the invention
Technical problem to be solved by this invention is to provide the integrated assembling body of wall of a kind of building construction and assemble method, to make body of wall construction flexibly, fast, conveniently, reliably.
The integrated assembling body of wall of described building construction, for the indoor wall Assembling of building construction, is characterized in that: be assemblied to form by top end guide pile, support, facade plate and fill concrete, wherein,
Guide pile at the bottom of described top, for fixing with top or bottom floor, and as the immobilizing foundation of facade plate, be provided with end face binding face or bottom surface binding face, with facade plate binding face, top end guide pile is the component being individually fixed in top and bottom floor in described body of wall, and body of wall top and guide pile at the bottom of the top of bottom are an entirety respectively or are made up of multiple component be separated;
Described support provides location for body of wall and supports, entirety is rectangular frame-like, is horizontally arranged with multiple in described body of wall, is separated independent setting each other, support long limit both ends of the surface are used for fixing with basis and locating, and described support is spliced by crossbeam and crossbeam connector scene;
Described crossbeam is column, is spliced to form successively by one or more snippets beam segments, and the both sides crossbeam of support is arranged in pairs, and for providing fixing basis for facade plate, described support is provided with the panel stationary plane in outside and the crossbeam Plug Division of inner side;
Described crossbeam connector is used for connecting for the beam segments of the relative both sides of support provides and fixing, and is provided with the connector Plug Division at two ends and the connector at middle part, described connector Plug Division and described crossbeam Plug Division part nested encryptions;
Described facade plate is fixed on wall outer side face, with fixing outside the panel stationary plane of crossbeam.
Described connector Plug Division is column, be provided with vertical connections and tilt link two kinds, the center line of described vertical connections connector and the axes normal of described connector Plug Division, the center line of described tilt link and the axis of described connector Plug Division are the acute angle of 25 ° ~ 85 °.
Described connector Plug Division and described crossbeam Plug Division are equipped with the draw-in groove or dop of taking back hook, described dop or draw-in groove go back to the many places that hook is provided with a place or is parallel to each other.
As embodiment, when described crossbeam connector is arranged at the end of crossbeam, for fixing with basis, the connector thickness in the vertical direction of crossbeam connector is 5mm ~ 50mm, and width is in the horizontal direction 5mm ~ 400mm; When described crossbeam connector is arranged at the middle part of crossbeam, connector thickness is in the vertical direction 3mm ~ 50mm, and width is in the horizontal direction 5mm ~ 400mm.
A kind of special case is that at the bottom of described top, the structure of guide pile is identical with described support.
A kind of embodiment of crossbeam is, described panel stationary plane is provided with the convex tendon of horizontally set.
Build the assemble method of integrated assembling body of wall according to premises, it is characterized in that: comprise the step that following order is carried out:
The first step, arrange that planning setting body of wall is in the position of ceiling, floor and basic wall/basic stand column according to body of wall;
Second step, fixed installation top, position end guide pile set by ceiling and floor, and make the facade plate binding face of guide pile at the bottom of top vertically outside; In wall foundation or upright post basic, the differing heights of the position of set body of wall distributes the installation site of support, the crossbeam connector of mounting bracket end on distributed installation site;
The support of the 3rd step, installation differing heights, by proximad far connecting with beam segments successively from the crossbeam connector that wall or the column of respective heights are fixed, the crossbeam of both sides is connected with crossbeam connector at the seam crossing of beam segments, connect the crossbeam of both sides as required with crossbeam connector at the middle part of beam segments, play glue in the junction of crossbeam connector and crossbeam to fix, splicing becomes complete support;
4th step, lay facade plate respectively at two lateral surfaces of support, the facade plate of first piece of facade plate use different in width of base surface is faced in body of wall both sides, the seam of the facade plate of body of wall both sides is staggered mutually, be tightly connected between facade plate or between facade plate and crossbeam, the panel stationary plane that side crossbeam is laid by each block facade plate and institute or the facade plate binding face pushing up end guide pile are fixed, and reserve or process fill orifice at the top of facade plate;
5th step, to insert bottom intrusion pipe to wall cavity from fill orifice, progressively while concrete perfusion slurry, promote intrusion pipe, until it is inner to fill whole body of wall, extracts intrusion pipe out and also seal fill orifice.
The assemble method of the integrated assembling body of wall of another kind of aforementioned building construction, is characterized in that: comprise the step that following order is carried out:
The first step, arrange that planning setting body of wall is in the position of ceiling, floor and basic wall/basic stand column according to body of wall;
Second step, fixed installation top, position end guide pile set by ceiling and floor, and make the facade plate binding face of guide pile at the bottom of top vertically outside; In wall foundation or upright post basic, the differing heights of the position of set body of wall distributes the installation site of support, the crossbeam connector of mounting bracket end on distributed installation site;
3rd step, the support of differing heights is installed from the wall of respective heights or the fixing crossbeam connector of column simultaneously, by proximad far connecting with beam segments successively, with crossbeam connector, the crossbeam of both sides is connected at the middle part of beam segments or end, play glue in the junction of crossbeam connector and crossbeam and fix; When after being connected to crossbeam connector and the width of the length of not laying the crossbeam of facade plate more than one block of facade plate time, facade plate is laid successively respectively at two lateral surfaces of support, and first block of facade plate that base surface uses width inconsistent is faced in body of wall both sides, the facade plate seaming position of body of wall both sides is staggered, be tightly connected between facade plate or between facade plate and crossbeam, the panel stationary plane that side crossbeam is laid by each block facade plate and institute or the facade plate binding face pushing up end guide pile are fixed, and reserve or process fill orifice at the top of facade plate;
4th step, to insert bottom intrusion pipe to wall cavity from fill orifice, progressively while concrete perfusion slurry, promote intrusion pipe, until it is inner to fill whole body of wall, extracts intrusion pipe out and also seal fill orifice.
In the process of connecting cross beam section and crossbeam connector, the beam segments of same support both sides is set up simultaneously, the beam segments seam crossing adjacent at homonymy connects with the connector Plug Division of crossbeam connector one end, the other end of this crossbeam connector and the crossbeam Plug Division nested encryptions of offside crossbeam.All can be connected with crossbeam connector in the crossbeam Plug Division any position of the non-seam crossing of beam segments.
A kind of comparatively firm scheme is, when selecting tilt link in same support, tilt link and vertical connections are used alternatingly.
A kind of situation running into column, at wall part through column, in the contact position of described column and support, the end fixed cross beam connector in advance of crossbeam, through column part, height corresponding to the offside of crossbeam is fixed cross beam section in advance, when column set up by support, intercept the beam segments being applicable to length, the end of the beam segments running into column is connected with the described connector of fixed cross beam in advance, and described on described column, fixed cross beam section is connected and fixed by the crossbeam of crossbeam connector by offside in advance.
The present invention can on-the-spot fast construction body of wall, and can not arrange flexibly by part dimension restriction ground and set up body of wall, runs into structure in column and special building and also can build flexibly.Its outstanding beneficial effect is, without the need to prefabricated component or make framework in advance, use the assembling of the most basic bar-like member can set up wall frame rapidly flexibly and cast-in-site becomes body of wall, process of construction does not limit by part dimension, only need horizontal support and without the need to vertical supports, various structure can be tackled, parts convenient transportation, wall construction process fast, build flexibly, convenient, save and build building time in a large number.
Accompanying drawing explanation
Fig. 1 is perspective view of the present invention (direction, the lower left corner is looked up),
Fig. 2 is supporting structure embodiment stereogram,
Fig. 3 is crossbeam stereochemical structure embodiment one figure,
Fig. 4 is crossbeam stereochemical structure embodiment two figure,
Fig. 5 is section of beam embodiment one structural representation,
Fig. 6 is section of beam embodiment two structural representation,
Fig. 7 is section of beam embodiment three structural representation,
Fig. 8 is section of beam embodiment four structural representation,
Fig. 9 is the top view of Fig. 7,
Figure 10 is the structural front view of intermediate connector embodiment one,
Figure 11 is the structural front view of intermediate connector embodiment two,
Figure 12 is the top view of Fig. 9 embodiment,
Figure 13 is the top view of the another kind of embodiment of Fig. 9,
Figure 14 is the perspective view of intermediate connector embodiment three,
Figure 15 is the perspective view of the intermediate connector of beam-end,
Figure 16 is the supporting structure stereogram using the crossbeam connector tilted,
Figure 17 is the plane structure schematic diagram of body of wall through column
Figure 18 is the structural representation of top end connector embodiment one,
Figure 19 is the structural representation of top end connector embodiment two.
In figure: 1-support, 2-top end guide pile, 3-facade plate, 4-crossbeam connector, 5-crossbeam, 6-cross girder, 7-column, 8-crossbeam Plug Division, 9-return hook, 10-panel stationary plane, 11-convex tendon, 12-connector Plug Division, 13-dop, 14-draw-in groove, 16-connector, 17-end face binding face, 18-bottom surface binding face, 19-facade plate binding face, 20-beam segments.
Detailed description of the invention
Below in conjunction with drawings and Examples, the present invention is further described: as shown in fig. 1, the integrated assembling body of wall of described building construction, for the indoor wall Assembling of building construction, is assemblied to form by top end guide pile 2, support 1, facade plate 3 and fill concrete.Wall body structure stereogram seen by Fig. 1 angle that to be body of wall look up from lower left.
As Figure 18,19, guide pile at the bottom of described top, for fixing with top or bottom floor, and as the immobilizing foundation of facade plate, be provided with end face binding face 17 or bottom surface binding face 18, with facade plate binding face 19, top end guide pile is the component being individually fixed in top and bottom floor in described body of wall, and top and the component of bottom are an entirety respectively or are made up of multiple component be separated.In FIG, top end guide pile is separating member, top is relative both sides independently components separately, concrete and basic contact area can be increased, the component that bottom is integrated for relative both sides, multiple component is fixed with bottom surface respectively, two lateral surfaces can fixedly mount facade plate, also the integrated member be connected as a single entity by conplane each guide pile can be adopted, even support can be placed directly in bottom or top, fixedly serve as with basis and push up end guide pile, but concrete can be affected with the bond strength on basis.
Described support entirety is rectangular frame-like, is horizontally arranged with multiple in described body of wall, is separated independent setting each other, and support long limit both ends of the surface are used for fixing with basis and locating, and as Fig. 2, described support is spliced by crossbeam 5 and crossbeam connector 4 scene; Visible in the wall body structure of Fig. 1, the technical scheme of body of wall only uses horizontal support, and support, as the immobilizing foundation of facade plate, after support and basis are fixed, has namely fixed the frame construction of whole body of wall.
As Fig. 2, described crossbeam 5 is column, is spliced to form successively, arranges in pairs in the bracket by multistage beam segments 20, and for providing fixing basis for facade plate, from Fig. 3-9, crossbeam is provided with the panel stationary plane 10 in outside and the crossbeam Plug Division 8 of inner side.
In the diagram, described panel stationary plane 10 is provided with the convex tendon 11 of horizontally set.Convex tendon is not only conducive to the flexural strength of crossbeam, and may be used for the water proof groove fitly arranging metope.
From the embodiment of Fig. 5-9, crossbeam Plug Division 8 can be the dop 13 protruded, and also can be recessed draw-in groove 14, crossbeam Plug Division be equipped with back hook 9, and returning hook can be single track or multiple tracks.As Fig. 7,8, the tail trimmer of 9, may be used for body of wall through column, replace support to be fixed on basis as connection offside crossbeam on column.
As Fig. 2, described crossbeam connector 4 provides connection for the beam segments 20 of the relative both sides for support and fixes, as Figure 10-17, crossbeam connector 4 is provided with the connector Plug Division 12 at two ends and the connector 16 at middle part, described connector Plug Division 12 for described crossbeam Plug Division 8 part nested encryptions.
As Figure 10,11, described connector Plug Division 12 can be the dop 13 protruded, and also can be recessed draw-in groove 14, be provided with back hook 9, and the hook 9 that returns of described dop 13 or draw-in groove 14 is provided with together or the multiple tracks be parallel to each other.
As Figure 12, connector Plug Division 12 is column, the center line of described connector 16 and the axes normal of described connector Plug Division 12.
As Figure 12, connector Plug Division 12 is column, and consistent with the cross sectional shape on the vertical plane of its axes normal, the center line of described connector 16 and the angle of described connector Plug Division axis are 25 ° ~ 85 °.With under crossbeam connection status, the end face of connector Plug Division is parallel with crossbeam, makes crossbeam connector and crossbeam become face to contact, connects more firm after bonding.
When described crossbeam connector 4 is arranged at the middle part of crossbeam, connector 16 thickness is in the vertical direction 3mm ~ 50mm, and width is in the horizontal direction 5mm ~ 400mm.
If Figure 15 is the structure of crossbeam connector for beam-end.Crossbeam connector for beam-end also needs to fix with basis, needs comparatively wide connector.Connector 16 thickness in the vertical direction of crossbeam connector is 5mm ~ 50mm, and width is in the horizontal direction 5mm ~ 400mm.
As Fig. 1, described facade plate 3 covers and is fixed on wall outer side face, with fixing outside the panel stationary plane 10 of crossbeam.
Build the assemble method of integrated assembling body of wall according to premises, comprise the step that following order is carried out:
The first step, arrange that planning setting body of wall is in the position of ceiling, floor and basic wall/basic stand column according to body of wall, the position set by ceiling and floor is by steel nail fixed installation top end guide pile 2.
Being fixed on top and guide pile at the bottom of the top of bottom is one overall or be made up of multiple component be separated respectively.In FIG, top end guide pile is separating member, top is relative both sides independently components separately, concrete and basic contact area can be increased, the component that bottom is integrated for relative both sides, multiple component is fixed with bottom surface respectively, two lateral surfaces may be used for fixed installation facade plate, also the integrated member be connected as a single entity by conplane each guide pile can be adopted, even support can be placed directly in bottom or top, fixedly serve as with basis and push up end guide pile, but concrete can be affected with the bond strength on basis.
Second step, the differing heights of the position of body of wall set by wall foundation or upright post basic distribute the installation site of support 1, with the crossbeam connector 4 of steel nail mounting bracket end on distributed installation site.Such as, as in Fig. 1, spaced set support height, each support is all horizontally disposed with.Determine the position of a support in sustained height setting-out, first fix the crossbeam connector at two ends.
3rd step, the support of differing heights is installed respectively, each support is independently set up, when setting up, crossbeam connector 4 fixing on the wall of respective heights or column is started by being proximad far connected to become complete support 1 with the crossbeam connector 4 at beam segments 20 and middle part successively, can from two ends be fixed on crossbeam connector on basis respectively or synchronously, set up to centre.
In the process of connecting cross beam section 20 and crossbeam connector 4, the beam segments 20 of same support 1 both sides is set up simultaneously, beam segments 20 seam crossing adjacent at homonymy connects with the connector Plug Division 12 of crossbeam connector 4 one end, the other end of this crossbeam connector and the crossbeam Plug Division nested encryptions of offside crossbeam.Each layer support can synchronously be set up, and after connecting into intact stent, plays glue fix in junction.
A kind of comparatively firm crossbeam connector scheme is, as shown in figure 16, in same support, select the center line of connector 16 and the end face of connector Plug Division 12 to be the crossbeam connector of acute angle, the incline direction of the connector of the crossbeam connector of the adjacent use of same support is contrary.Use the crossbeam connector connecting cross beam of inclination, the structure of support is more stable.
If Figure 17 is a kind of situation running into column, wall part through column 7 time, in the contact position of described column and support 1, the end winding support crossbeam connector 4 of crossbeam, through column part, height corresponding to the offside of crossbeam is fixed cross beam section 20 in advance, Fig. 7 is shown in by the schematic diagram of beam segments, 8, 9, when column set up by support, intercept the beam segments 20 being applicable to length, the end of the beam segments 20 running into column 7 is connected with the described connector of fixed cross beam in advance, described on described column 7, fixed cross beam section is connected and fixed by the crossbeam of crossbeam connector 4 by offside in advance.Play glue in the junction of crossbeam connector and crossbeam after connection to fix.
4th step, lay facade plate 3 respectively at two lateral surfaces of support, make to be tightly connected between facade plate or between facade plate and crossbeam, each block facade plate with lay side crossbeam fix with steel nail or tapping screw, reserve fill orifice at the top of facade plate.During paving facade plate, use the half that the width of one block of facade plate at edge is middle part, other end edge is used in the facade plate of the half-breadth of side, the facade panel edges of the relative both sides half that staggers is laid.More be conducive to the stable of body of wall.
5th step, to insert bottom intrusion pipe to wall cavity from fill orifice, progressively while concrete perfusion slurry, promote intrusion pipe, until it is inner to fill whole body of wall, extracts intrusion pipe out and also seal fill orifice.
The assemble method of the integrated assembling body of wall of another kind of aforementioned building construction, the support of differing heights is installed simultaneously from the crossbeam connector 4 that wall or the column of respective heights are fixed, by proximad far connecting with beam segments 20 successively, with crossbeam connector 4, the crossbeam of both sides is connected at the middle part of beam segments or end, play glue in the junction of crossbeam connector and crossbeam and fix; When after being connected to crossbeam connector and the width of the length of not laying the crossbeam of facade plate more than one block of facade plate time, facade plate is laid successively respectively at two lateral surfaces of support, and first block of facade plate that base surface uses width inconsistent is faced in body of wall both sides, the facade plate seaming position of body of wall both sides is staggered, be tightly connected between facade plate or between facade plate and crossbeam, the crossbeam that each block facade plate lays side with institute is fixed, and reserves or process fill orifice at the top of facade plate.
Afterwards, insert bottom intrusion pipe to wall cavity from fill orifice, progressively while concrete perfusion slurry, promote intrusion pipe, until it is inner to fill whole body of wall, extracts intrusion pipe out and seal fill orifice.
Claims (10)
1. the integrated assembling body of wall of building construction, for the indoor wall Assembling of building construction, be assemblied to form by top end guide pile (2), support (1), facade plate (3) and fill concrete, wherein, guide pile at the bottom of described top, be provided with end face binding face (17) or bottom surface binding face (18), with facade plate binding face (19), body of wall top and guide pile at the bottom of the top of bottom are an entirety respectively or are made up of multiple component be separated; Described support entirety is rectangular frame-like, is horizontally arranged with multiple in described body of wall, is separated independent setting each other; Described facade plate (3) is fixed on wall outer side face, fixing with panel stationary plane (10) outside of crossbeam;
It is characterized in that:
Described support is spliced according to the needs of the quantity of crossbeam length, intensity and crossbeam connector by the crossbeam (5) of both sides and crossbeam connector (4) scene temporarily, described support is provided with the panel stationary plane (10) in outside and the crossbeam Plug Division (8) of inner side, and support both sides crossbeam is used for providing fixing basis for facade plate;
Described crossbeam (5) is column, is spliced successively or cut to form by one or more snippets beam segments (20);
Described crossbeam connector (4) provides for the beam segments (20) that the both sides for support are relative and connects and fix, be provided with the connector Plug Division (12) at two ends and the connector (16) at middle part, described connector Plug Division (12) and described crossbeam Plug Division (8) part nested encryptions.
2. the integrated assembling body of wall of building construction according to claim 1, it is characterized in that: described connector Plug Division (12) is column, be provided with vertical connections and tilt link two kinds, the center line of described vertical connections connector (16) and the axes normal of described connector Plug Division (12), the center line of described tilt link and the axis of described connector Plug Division (12) are the acute angle of 25 ° ~ 85 °.
3. the integrated assembling body of wall of building construction according to claim 1, it is characterized in that: described connector Plug Division (12) and described crossbeam Plug Division (8) are equipped with the draw-in groove (14) or dop (13) of taking back hook (9), described dop (13) or draw-in groove (14) go back to the many places that hook (9) is provided with a place or is parallel to each other.
4. the integrated assembling body of wall of building construction according to claim 1, it is characterized in that: when described crossbeam connector (4) is arranged at the end of crossbeam, for fixing with basis, connector (16) thickness in the vertical direction of crossbeam connector is 5mm ~ 50mm, and width is in the horizontal direction 5mm ~ 400mm; When described crossbeam connector (4) is arranged at the middle part of crossbeam, connector (16) thickness is in the vertical direction 3mm ~ 50mm, and width is in the horizontal direction 5mm ~ 400mm.
5. the integrated assembling body of wall of building construction according to claim 1, is characterized in that: at the bottom of described top, the structure of guide pile (2) is identical with described support (1).
6. according to an assemble method for the integrated assembling body of wall of the described building construction of one of Claims 1 to 5, it is characterized in that: comprise the step that following order is carried out:
The first step, arrange that planning setting body of wall is in the position of ceiling, floor and basic wall/basic stand column according to body of wall;
Second step, fixed installation top, position end guide pile (2) set by ceiling and floor, and make the facade plate binding face (19) of guide pile at the bottom of top (2) vertically outside; In wall foundation or upright post basic, the differing heights of the position of set body of wall distributes the installation site of support (1), the crossbeam connector (4) of mounting bracket end on distributed installation site;
The support of the 3rd step, installation differing heights, by proximad far connecting with beam segments (20) successively from the crossbeam connector (4) that wall or the column of respective heights are fixed, the crossbeam of both sides is connected with crossbeam connector (4) at the seam crossing of beam segments, connect the crossbeam of both sides as required with crossbeam connector (4) at the middle part of beam segments, play glue in the junction of crossbeam connector and crossbeam to fix, splicing becomes complete support (1);
4th step, lay facade plate respectively at two lateral surfaces of support, the facade plate of first piece of facade plate use different in width of base surface is faced in body of wall both sides, the seam of the facade plate of body of wall both sides is staggered mutually, be tightly connected between facade plate or between facade plate and crossbeam, the panel stationary plane (10) of side crossbeam is laid by each block facade plate and institute or to push up the facade plate binding face (19) of end guide pile (2) fixing, reserves or process fill orifice at the top of facade plate;
5th step, to insert bottom intrusion pipe to wall cavity from fill orifice, progressively while concrete perfusion slurry, promote intrusion pipe, until it is inner to fill whole body of wall, extracts intrusion pipe out and also seal fill orifice.
7. according to an assemble method for the integrated assembling body of wall of the described building construction of one of Claims 1 to 5, it is characterized in that: comprise the step that following order is carried out:
The first step, arrange that planning setting body of wall is in the position of ceiling, floor and basic wall/basic stand column according to body of wall;
Second step, fixed installation top, position end guide pile (2) set by ceiling and floor, and make the facade plate binding face (19) of guide pile at the bottom of top (2) vertically outside; In wall foundation or upright post basic, the differing heights of the position of set body of wall distributes the installation site of support (1), the crossbeam connector (4) of mounting bracket end on distributed installation site;
3rd step, the support of differing heights is installed from the wall of respective heights or the fixing crossbeam connector (4) of column simultaneously, by proximad far connecting with beam segments (20) successively, with crossbeam connector (4), the crossbeam of both sides is connected at the middle part of beam segments or end, play glue in the junction of crossbeam connector and crossbeam and fix, when after being connected to crossbeam connector and the width of the length of not laying the crossbeam of facade plate more than one block of facade plate time, facade plate is laid successively respectively at two lateral surfaces of support, and first block of facade plate that base surface uses width inconsistent is faced in body of wall both sides, the facade plate seaming position of body of wall both sides is staggered, be tightly connected between facade plate or between facade plate and crossbeam, the panel stationary plane (10) of side crossbeam is laid by each block facade plate and institute or to push up the facade plate binding face (19) of end guide pile (2) fixing, reserve at the top of facade plate or process fill orifice,
4th step, to insert bottom intrusion pipe to wall cavity from fill orifice, progressively while concrete perfusion slurry, promote intrusion pipe, until it is inner to fill whole body of wall, extracts intrusion pipe out and also seal fill orifice.
8. the integrated assembling wall assembly method of building construction according to claim 7, it is characterized in that: in described 3rd step, in the process of connecting cross beam section (20) and crossbeam connector (4), the beam segments (20) of same support (1) both sides is set up simultaneously, beam segments (20) seam crossing adjacent at homonymy connects with the connector Plug Division (12) of crossbeam connector (4) one end, the other end of this crossbeam connector and the crossbeam Plug Division nested encryptions of offside crossbeam; All can be connected with crossbeam connector (4) in crossbeam Plug Division (8) any position of the non-seam crossing of beam segments (20).
9. the integrated assembling wall assembly method of building construction according to claim 8, it is characterized in that: when selecting tilt link in same support, tilt link and vertical connections are used alternatingly.
10. the integrated assembling wall assembly method of building construction according to claim 7, it is characterized in that: at wall part when column (7), in the contact position of described column and support (1), the end fixed cross beam connector (4) in advance of crossbeam, through column part, height corresponding to the offside of crossbeam is fixed cross beam section (20) in advance, when column set up by support, intercept the beam segments (20) being applicable to length, the end of the beam segments (20) running into column (7) is connected with the described connector of fixed cross beam in advance, the crossbeam of offside is connected and fixed by crossbeam connector (4) by the described section of fixed cross beam in advance on described column (7).
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510218650.8A CN104805931B (en) | 2015-05-04 | 2015-05-04 | A kind of integrated assembling wall of building construction and assemble method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510218650.8A CN104805931B (en) | 2015-05-04 | 2015-05-04 | A kind of integrated assembling wall of building construction and assemble method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN104805931A true CN104805931A (en) | 2015-07-29 |
| CN104805931B CN104805931B (en) | 2017-07-18 |
Family
ID=53691095
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510218650.8A Expired - Fee Related CN104805931B (en) | 2015-05-04 | 2015-05-04 | A kind of integrated assembling wall of building construction and assemble method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104805931B (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106703258A (en) * | 2015-11-12 | 2017-05-24 | 佛山市构想板业有限公司 | Environment-friendly and energy-saving pouring type wall and construction method thereof |
| CN107268778A (en) * | 2017-08-14 | 2017-10-20 | 庞众 | Assemblnig mobile building |
| CN108612197A (en) * | 2018-05-14 | 2018-10-02 | 王吉胜 | A kind of building construction is integrated to assemble wall and assemble method |
| CN108691372A (en) * | 2017-04-05 | 2018-10-23 | 佛山市构想板业有限公司 | A kind of environment friendly wall and its method of construction being efficiently perfused |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6698710B1 (en) * | 2000-12-20 | 2004-03-02 | Portland Cement Association | System for the construction of insulated concrete structures using vertical planks and tie rails |
| CN201007045Y (en) * | 2007-01-12 | 2008-01-16 | 张靖宇 | Novel wall backbone composing structure |
| CN101725181A (en) * | 2009-11-11 | 2010-06-09 | 何泉 | Timberwork building element and installation process thereof |
| CN202596476U (en) * | 2012-04-26 | 2012-12-12 | 上海金粤幕墙有限公司 | Internal aluminum parting stop edge part connector for hollow glass |
| CN203654519U (en) * | 2013-12-31 | 2014-06-18 | 李�学 | Cast-in-place wall member of house building |
| CN204662703U (en) * | 2015-05-04 | 2015-09-23 | 李�学 | The integrated assembling body of wall of a kind of building construction |
-
2015
- 2015-05-04 CN CN201510218650.8A patent/CN104805931B/en not_active Expired - Fee Related
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6698710B1 (en) * | 2000-12-20 | 2004-03-02 | Portland Cement Association | System for the construction of insulated concrete structures using vertical planks and tie rails |
| CN201007045Y (en) * | 2007-01-12 | 2008-01-16 | 张靖宇 | Novel wall backbone composing structure |
| CN101725181A (en) * | 2009-11-11 | 2010-06-09 | 何泉 | Timberwork building element and installation process thereof |
| CN202596476U (en) * | 2012-04-26 | 2012-12-12 | 上海金粤幕墙有限公司 | Internal aluminum parting stop edge part connector for hollow glass |
| CN203654519U (en) * | 2013-12-31 | 2014-06-18 | 李�学 | Cast-in-place wall member of house building |
| CN204662703U (en) * | 2015-05-04 | 2015-09-23 | 李�学 | The integrated assembling body of wall of a kind of building construction |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106703258A (en) * | 2015-11-12 | 2017-05-24 | 佛山市构想板业有限公司 | Environment-friendly and energy-saving pouring type wall and construction method thereof |
| CN108691372A (en) * | 2017-04-05 | 2018-10-23 | 佛山市构想板业有限公司 | A kind of environment friendly wall and its method of construction being efficiently perfused |
| CN107268778A (en) * | 2017-08-14 | 2017-10-20 | 庞众 | Assemblnig mobile building |
| CN108612197A (en) * | 2018-05-14 | 2018-10-02 | 王吉胜 | A kind of building construction is integrated to assemble wall and assemble method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN104805931B (en) | 2017-07-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101654930B (en) | Beam frame structure of combined type house and assembly method thereof | |
| KR101222550B1 (en) | Modular unit with unified double beam and modular structure using the same | |
| CN103603471B (en) | Sawtooth hanging piece upright post encapsulating device and construction method thereof | |
| EA019161B1 (en) | Precast concrete building units | |
| CN110439148B (en) | Construction method of assembled partition wall system suitable for ultra-large space | |
| CN104805931A (en) | Integrated assembled house building wall body and assembling method | |
| GB2287047A (en) | Building construction of composite boards | |
| CN211597210U (en) | Assembled partition wall system | |
| JP6860167B2 (en) | How to build Box Culvert and Box Culvert | |
| CN106284742A (en) | Half column frame antidetonation faced wall and manufacture method | |
| RU2441965C1 (en) | Multi-stored building of the frame-wall structural system from prefabricated and monolithic reinforced concrete | |
| CN204080843U (en) | Movable plank house foundation structure | |
| CN204662703U (en) | The integrated assembling body of wall of a kind of building construction | |
| CN205444453U (en) | Assembled prestressing force double T board frame construction | |
| CN212641724U (en) | Light environment-friendly beam-slab-column structure for green building | |
| KR102177744B1 (en) | Underground parking lot structure with PC wall | |
| CN204571020U (en) | The metope cell structure of the integrated assembling body of wall of building construction | |
| US3805469A (en) | Concrete floor construction | |
| KR101148546B1 (en) | Steel built up beam for longspan structure and steel frame using the same | |
| CN110439151B (en) | Construction method of modular partition board | |
| CN210216748U (en) | Prefabricated part connecting node and supporting structure | |
| CN203603528U (en) | Thin wall cladding structure of cylinder | |
| CN210809987U (en) | Modularized light wall and fixedly-mounted furniture assembly | |
| JP2008223371A (en) | Wall construction structure for existing building | |
| CN101307621A (en) | Upper and lower light steel chute corner support assembled house building method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| EXSB | Decision made by sipo to initiate substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170718 Termination date: 20190504 |