CN104795771A - Puncture clamp for ground potential live working of insulated wire line connection - Google Patents
Puncture clamp for ground potential live working of insulated wire line connection Download PDFInfo
- Publication number
- CN104795771A CN104795771A CN201510225712.8A CN201510225712A CN104795771A CN 104795771 A CN104795771 A CN 104795771A CN 201510225712 A CN201510225712 A CN 201510225712A CN 104795771 A CN104795771 A CN 104795771A
- Authority
- CN
- China
- Prior art keywords
- clamp
- wire
- fastening
- puncture
- upper body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
一种绝缘导线线路连接的地电位带电作业用穿刺线夹,包括线夹上本体和与线夹上本体配合的线夹下本体,线夹上本体的正面设有开口朝下的主线卡槽,主线卡槽内设有上穿剌齿,线夹下本体上设有与主线卡槽相对的导线限位槽,导线限位槽内设有下穿剌齿,主线紧固由上本体与下本体的穿刺完成,副线由上本体设置的常规压板紧固完成。利用穿刺实现通流导电保证了绝缘导线绝缘良好的密封性能,实现了安全、快速的地电位带电作业搭接分支线路,解决了绝缘导线剥皮难的问题,降低了作业的劳动强度,解决了长期以来这项作业必须剥皮的陈旧模式,工作效率提高了50%,解决了绝缘导线剥皮带来的防水密封难题。
A puncture clamp for ground potential live work connected with insulated wires, comprising an upper body of the clamp and a lower body of the clamp matched with the upper body of the clamp. There are upper piercing teeth in the main wire slot, and a wire limiting slot opposite to the main wire slot is provided on the lower body of the clamp. The lower piercing teeth are arranged in the wire limiting slot, and the main wire is fastened by the upper body and the lower body. The puncture is completed, and the auxiliary line is fastened by the conventional pressure plate set on the upper body. The use of puncture to realize current flow and conduction ensures the good sealing performance of the insulated wire insulation, realizes safe and fast ground potential live operation to lap the branch line, solves the problem of difficult peeling of the insulated wire, reduces the labor intensity of the operation, and solves the long-term problem. Since the old mode that this operation must be peeled, the work efficiency has been increased by 50%, and the problem of waterproof and sealing caused by the stripping of insulated wires has been solved.
Description
技术领域 technical field
本发明涉及一种电力工程施工工具,特别是一种绝缘导线线路连接的地电位带电作业用穿刺线夹。 The invention relates to a construction tool for electric power engineering, in particular to a puncture clamp for ground potential live work connected with insulated conductor lines.
背景技术 Background technique
随着社会发展,配电线路网络激增,带来的通道危机已经成为电网发展的瓶颈,为了解决线路通道问题,采用绝缘导线有效解决了通道拥挤、安全隐患等问题。实际工程施工过程中,绝缘导线的压接、跳线、分支线路连接等都需要对导线进行绝缘层剥除,10kv绝缘导线绝缘层厚度约4mm、20kv绝缘导线绝缘层厚度约6mm。工程施工中采用常规的剥除工具有旋转类型和常规的手钳类型,操作过程中对绝缘层进行剥除,存在劳动强度大,费力且效率低,精度难以控制,绝缘层剥除后容易出现导线损伤情况,特别是寒冷冬季进行绝缘层剥除操作时,绝缘层硬度增加,剥除难度更大。目前已有的各类剥皮装置都存在操作强度大,精度不高,容易伤及导线等共性问题,地电位剥皮进行带电搭接分支线路,直接造成导线无法良好密封,发生雨水浸入导线中不利于安全运行。 With the development of society, the network of distribution lines has proliferated, and the channel crisis has become the bottleneck of the development of the power grid. In order to solve the problem of line channels, the use of insulated wires effectively solves the problems of channel congestion and potential safety hazards. In the actual engineering construction process, the insulation layer of the wires needs to be stripped for crimping, jumper wires, and branch line connections. The thickness of the insulation layer of the 10kv insulated wire is about 4mm, and the thickness of the insulation layer of the 20kv insulated wire is about 6mm. Conventional stripping tools used in engineering construction include rotary type and conventional hand pliers type. The insulation layer is stripped during the operation, which is labor-intensive, labor-intensive and inefficient, and the accuracy is difficult to control. After the insulation layer is stripped, it is easy to In the case of wire damage, especially when the insulation layer is stripped in cold winter, the hardness of the insulation layer increases and the stripping is more difficult. At present, all kinds of stripping devices have common problems such as high operating intensity, low precision, and easy damage to the wires. The ground potential stripping is used to connect the branch lines with electricity, which directly causes the wires to not be well sealed, and rainwater immersion into the wires is not conducive safe operation.
发明内容 Contents of the invention
本发明要解决的技术问题是针对现有技术的不足,提出了一种安全、快速实现地电位带电搭接分支线路带电操作的用于绝缘导线线路连接的地电位带电作业用穿刺线夹。 The technical problem to be solved in the present invention is to address the deficiencies of the prior art, and propose a puncture clamp for ground potential live work for connecting insulated wire lines to safely and quickly realize the live operation of ground potential live overlapping branch lines.
本发明要解决的技术问题是通过以下技术方案来实现的,一种绝缘导线线路连接的地电位带电作业用穿刺线夹,其特点是:包括线夹上本体和与线夹上本体配合的线夹下本体,线夹上本体的正面设有开口朝下的主线卡槽,主线卡槽内设有上穿剌齿,线夹下本体上设有与主线卡槽相对的导线限位槽,导线限位槽内设有下穿剌齿,在主线卡槽的两侧分别设有第一螺孔和第二螺孔,线夹下本体上设有与第一螺孔和第二螺孔相对应第一紧固孔和第二紧固孔,第一紧固螺栓、第二紧固螺栓分别穿过第一紧固孔、第二紧固孔与第一螺孔、第二螺孔连接,实现线夹上本体和线夹下本体的抱合,通过上穿剌齿和下穿剌齿对主线外皮穿剌实现与主线的金属部分良好接触,在第一紧固螺栓、第二紧固螺栓的末端均设置有扭力螺帽,扭力螺帽中部设有一个横向的旋转用定位杆,在线夹上本体的背面设有副线固定机构。靠近第一螺孔的线夹上本体向下设有防止线夹下本体左右摆的限位板,第二紧固孔与第二紧固螺栓之间设有挂接机构,安装线夹时,第一紧固螺栓将线夹上本体、线夹下本体连接,第二紧固螺栓通过挂接机构与第二紧固孔相接,保证线夹上本体、线夹下本体之间形成主线喂入口。 The technical problem to be solved by the present invention is achieved through the following technical solutions. A puncture clamp for live work at ground potential connected to an insulated wire circuit is characterized in that it includes an upper body of the clamp and a wire that cooperates with the upper body of the clamp. Clamp the lower body, the front of the upper body of the clamp is provided with a main line slot with the opening facing down, and the main line slot is provided with upper piercing teeth, and the lower body of the clamp is provided with a wire limit slot opposite to the main line slot, and the wire There are lower piercing teeth in the limit slot, first screw holes and second screw holes are respectively set on both sides of the main line card slot, and the lower body of the clamp is provided with corresponding first screw holes and second screw holes. The first fastening hole and the second fastening hole, the first fastening bolt and the second fastening bolt respectively pass through the first fastening hole and the second fastening hole to connect with the first screw hole and the second screw hole to realize The cohesion between the upper body of the wire clip and the lower body of the wire clip, through the upper piercing teeth and the lower piercing teeth to pierce the outer skin of the main wire to achieve good contact with the metal part of the main wire, at the ends of the first fastening bolt and the second fastening bolt All are provided with a torque nut, the middle part of the torque nut is provided with a horizontal positioning rod for rotation, and the back of the upper body of the wire clamp is provided with a secondary wire fixing mechanism. The upper body of the wire clamp close to the first screw hole is provided with a limit plate to prevent the lower body of the wire clamp from swinging left and right. There is a hook mechanism between the second fastening hole and the second fastening bolt. When installing the wire clamp, The first fastening bolt connects the upper body of the wire clamp and the lower body of the wire clamp, and the second fastening bolt connects with the second fastening hole through the hook mechanism to ensure that the main wire feeding is formed between the upper body of the wire clamp and the lower body of the wire clamp. Entrance.
本发明要解决的技术问题还可以通过以下技术方案来进一步实现,所述的副线固定机构包括设置在线夹上本体的副线安装固定用的固定板,固定板上设有上下方向的导线凹槽,导线凹槽两侧设有紧固用螺纹孔,与固定板配合实现安装的是副线压板,副线压板中部设有凸出槽,副线压板上设有两个螺栓紧固孔,固定板与副线压板通过两根螺栓配合完成副线的安装固定。 The technical problem to be solved by the present invention can be further realized through the following technical solutions. The auxiliary wire fixing mechanism includes a fixing plate for installing and fixing the auxiliary wire on the upper body of the wire clip. There are threaded holes for fastening on both sides of the wire groove, and the auxiliary line pressing plate is installed in cooperation with the fixing plate. There is a protruding groove in the middle of the auxiliary line pressing plate, and there are two bolt fastening holes on the auxiliary line pressing plate. The fixing plate and the auxiliary line pressing plate cooperate to complete the installation and fixation of the auxiliary line through two bolts.
本发明要解决的技术问题还可以通过以下技术方案来进一步实现,在线夹上本体的顶部设有用于控制操作杆的定位槽。 The technical problem to be solved by the present invention can be further realized by the following technical solution, the top of the upper body of the cable clamp is provided with a positioning groove for controlling the operating rod.
本发明要解决的技术问题还可以通过以下技术方案来进一步实现,在第一紧固螺栓和第二紧固螺栓上均装有防松垫圈。 The technical problem to be solved by the present invention can be further realized through the following technical solutions, in which anti-loosening washers are installed on the first fastening bolt and the second fastening bolt.
本发明要解决的技术问题还可以通过以下技术方案来进一步实现,所述挂接机构为设置在第二紧固孔内与第二紧固螺栓配合的内螺纹。 The technical problem to be solved by the present invention can be further realized by the following technical solutions, the hooking mechanism is an internal thread arranged in the second fastening hole and matched with the second fastening bolt.
本发明与现有技术相比,主线紧固由上本体与下本体的穿刺完成,副线由上本体设置的常规压板紧固完成。操作时首先完成副线的常规安装,然后利用绝缘操作杆端部的固定卡具套入扭力螺栓,然后将线夹上举利用线夹的开口卡入导线,作业人员相互配合旋转操作杆旋紧扭力螺栓,当扭力达到规定值时,扭力螺栓断裂,此时穿刺已经顺利与导线金属紧密接触,实现导电通流目的。利用穿刺实现通流导电保证了绝缘导线绝缘良好的密封性能,实现了安全、快速的地电位带电作业搭接分支线路,解决了绝缘导线剥皮难的问题,降低了作业的劳动强度,解决了长期以来这项作业必须剥皮的陈旧模式,工作效率提高了50%,解决了绝缘导线剥皮带来的防水密封难题。 Compared with the prior art, the present invention is fastening the main line by piercing the upper body and the lower body, and the auxiliary line is fastened by the conventional pressure plate provided on the upper body. When operating, first complete the conventional installation of the auxiliary line, then use the fixing fixture at the end of the insulating operating rod to insert the torsion bolt, and then lift the wire clamp and use the opening of the wire clamp to insert the wire, and the operators cooperate with each other to rotate the operating rod to tighten. Torsion bolt, when the torque reaches the specified value, the torsion bolt breaks, and at this time the puncture has been in close contact with the wire metal to achieve the purpose of electrical conduction. The use of puncture to realize current flow and conduction ensures the good sealing performance of the insulated wire insulation, realizes safe and fast ground potential live work to lap the branch line, solves the problem of difficult peeling of the insulated wire, reduces the labor intensity of the operation, and solves the long-term problem. Since the old mode that this operation must be peeled, the work efficiency has been increased by 50%, and the waterproof and sealing problem caused by the stripping of the insulated wires has been solved.
附图说明 Description of drawings
图1为本发明的结构简图; Fig. 1 is a structural diagram of the present invention;
图2为图1的侧视图。 FIG. 2 is a side view of FIG. 1 .
具体实施方式 Detailed ways
一种绝缘导线线路连接的地电位带电作业用穿刺线夹,包括线夹上本体和与线夹上本体配合的线夹下本体,线夹上本体的正面设有开口朝下的主线卡槽,主线卡槽内设有上穿剌齿,线夹下本体上设有与主线卡槽相对的导线限位槽,导线限位槽内设有下穿剌齿,在主线卡槽的两侧分别设有第一螺孔和第二螺孔,线夹下本体上设有与第一螺孔和第二螺孔相对应第一紧固孔和第二紧固孔,第一紧固螺栓、第二紧固螺栓分别穿过第一紧固孔、第二紧固孔与第一螺孔、第二螺孔连接,实现线夹上本体和线夹下本体的抱合,通过上穿剌齿和下穿剌齿对主线外皮穿剌实现与主线的金属部分良好接触,在第一紧固螺栓、第二紧固螺栓的末端均设置有扭力螺帽,扭力螺帽中部设有一个横向的旋转用定位杆,在线夹上本体的背面设有副线固定机构。靠近第一螺孔的线夹上本体向下设有防止线夹下本体左右摆的限位板,第二紧固孔与第二紧固螺栓之间设有挂接机构,安装线夹时,第一紧固螺栓将线夹上本体、线夹下本体连接,第二紧固螺栓通过挂接机构与第二紧固孔相接,保证线夹上本体、线夹下本体之间形成主线喂入口。 A puncture clamp for ground potential live work connected with insulated wires, comprising an upper body of the clamp and a lower body of the clamp matched with the upper body of the clamp. There are upper piercing teeth in the main wire slot, and wire limit slots opposite to the main wire slot are arranged on the lower body of the wire clip. There are a first screw hole and a second screw hole, the lower body of the clamp is provided with a first fastening hole and a second fastening hole corresponding to the first screw hole and the second screw hole, the first fastening bolt, the second The fastening bolts pass through the first fastening hole and the second fastening hole respectively to connect with the first screw hole and the second screw hole, so as to realize the cohesion between the upper body of the wire clamp and the lower body of the wire clamp. The barbed teeth puncture the outer skin of the main line to achieve good contact with the metal part of the main line. Torsion nuts are installed at the ends of the first fastening bolt and the second fastening bolt, and a horizontal positioning rod for rotation is provided in the middle of the torsion nut. , There is a secondary wire fixing mechanism on the back of the main body of the wire clamp. The upper body of the wire clamp close to the first screw hole is provided with a limit plate to prevent the lower body of the wire clamp from swinging left and right. There is a hook mechanism between the second fastening hole and the second fastening bolt. When installing the wire clamp, The first fastening bolt connects the upper body of the wire clamp and the lower body of the wire clamp, and the second fastening bolt connects with the second fastening hole through the hook mechanism to ensure that the main wire feeding is formed between the upper body of the wire clamp and the lower body of the wire clamp. Entrance.
所述的副线固定机构包括设置在线夹上本体的副线安装固定用的固定板,固定板上设有上下方向的导线凹槽,导线凹槽两侧设有紧固用螺纹孔,与固定板配合实现安装的是副线压板,副线压板中部设有凸出槽,副线压板上设有两个螺栓紧固孔,固定板与副线压板通过两根螺栓配合完成副线的安装固定。 The auxiliary line fixing mechanism includes a fixing plate for installing and fixing the auxiliary line on the main body of the wire clamp. The fixing plate is provided with a wire groove in an up and down direction, and both sides of the wire groove are provided with threaded holes for fastening, which are connected with the fixing plate. The plate is matched to realize the installation of the secondary line pressure plate. There is a protruding groove in the middle of the secondary line pressure plate, and there are two bolt fastening holes on the secondary line pressure plate. The fixing plate and the secondary line pressure plate cooperate to complete the installation and fixing of the secondary line. .
在线夹上本体的顶部设有用于控制操作杆的定位槽。在第一紧固螺栓和第二紧固螺栓上均装有防松垫圈。所述挂接机构为设置在第二紧固孔内与第二紧固螺栓配合的内螺纹。 The top of the upper body of the cable clamp is provided with a positioning groove for controlling the operating rod. Locking washers are installed on the first fastening bolt and the second fastening bolt. The hooking mechanism is an internal thread arranged in the second fastening hole and matched with the second fastening bolt.
如图所示: as the picture shows:
一种用于解决地电位绝缘导线线路连接的带电作业用穿刺线夹,通过主线和副线不同的安装固定方式,简化了施工工艺,降低施工人员的工作强度,降低了安装施工难度,通过穿刺的主线安装,避免了绝缘导线剥皮操作,副线在地电位状态采用徒手事先安装,解决了地电位剥皮困难难题。长期以来,带电作业绝缘车因为地形环境限制无法开展绝缘导线连接安装的难题得到有效解决。 A puncture clamp for live work used to solve the connection of ground potential insulated wires. Through the different installation and fixing methods of the main line and the auxiliary line, the construction process is simplified, the work intensity of the construction personnel is reduced, and the difficulty of installation and construction is reduced. Through the puncture The installation of the main line avoids the stripping operation of the insulated wire, and the auxiliary line is installed in advance with bare hands in the ground potential state, which solves the difficult problem of ground potential stripping. For a long time, the problem that the insulation vehicle for live work cannot be connected and installed with insulated wires due to terrain and environment constraints has been effectively solved.
它包括扭力螺帽7与紧固螺栓5、19的结合,扭力螺帽和紧固螺栓的连接为组合式,有利于生产加工。扭力螺帽中部设有一个横向的旋转操作杆用的定位杆8,用于旋转操作杆的固定限位。 It includes the combination of the torsion nut 7 and the fastening bolts 5, 19, and the connection of the torsion nut and the fastening bolt is combined, which is beneficial to production and processing. The middle part of the torque nut is provided with a horizontal positioning rod 8 for the rotating operating rod, which is used for the fixed limit of the rotating operating rod.
它包括线夹下本体18,线夹下本体18上设有导线限位槽16,该限位槽能够保证导线处于正确的位置,保证穿刺安装质量。导线限位槽16内表面设有下穿刺齿17,线夹下本体两端设有第一紧固孔6和第二紧固孔20,安装时第一紧固螺栓5、第二紧固螺栓19通过该孔与穿刺上本体第一螺孔3、第二螺孔15配合实现紧固,以保证穿刺与导线金属部分形成良好接触。 It includes a lower body 18 of the wire clip, and the lower body 18 of the wire clip is provided with a wire limiting groove 16, which can ensure that the wire is in the correct position and ensure the quality of the puncture installation. The inner surface of the wire limit groove 16 is provided with the lower puncture teeth 17, and the two ends of the lower body of the wire clamp are provided with the first fastening hole 6 and the second fastening hole 20. When installing, the first fastening bolt 5 and the second fastening bolt 19 is fastened by cooperating with the first screw hole 3 and the second screw hole 15 of the puncture upper body through this hole, so as to ensure good contact between the puncture and the metal part of the wire.
所述线夹上本体14的主线卡槽9内设有上穿剌齿4,线夹上本体设有供紧固螺栓紧固用的燕尾夹固槽1,该夹固槽用于和操作杆固定,以实现作业人员将安装完成副线的线夹,用夹固操作杆与燕尾夹固槽配合,实现线夹与主线路导线接触的各种调整和控制需求,保证紧固过程中正确的安装质量。线夹上本体14上设有主线卡槽9,该主线卡槽能够保证导线处于正确的位置,保证穿刺安装质量。主线卡槽内表面设有上穿剌齿4,线夹上本体还设有用于限制线夹下本体18左右摆动的限位板21,安装线夹因为要保证线夹上、下本体之间有开口,所以只有第一紧固螺栓将上、下本体连接,用操作杆操作时会发生线夹下本体18左右摆动现象,限位板21可以实现限制下本体18的左右摆动。安装时第一紧固螺栓5和第二紧固螺栓19通过下本体14两端的第一紧固孔6和第二紧固孔20与线夹上本体螺孔15配合实现紧固。紧固过程中第一、第二螺栓要交叉依次旋紧,以保证穿刺与导线金属部分形成良好接触。 The main thread slot 9 of the upper body 14 of the wire clamp is provided with an upper piercing tooth 4, and the upper body of the wire clamp is provided with a dovetail clamping groove 1 for fastening the fastening bolts, and the clamping groove is used for connecting with the operating lever. Fixed, so that the operator will install the clamp of the auxiliary line, and use the clamping lever to cooperate with the dovetail clamping groove to realize various adjustment and control requirements for the contact between the clamp and the main line conductor, and ensure correct tightening during the fastening process. Installation quality. The upper body 14 of the wire clamp is provided with a main wire draw slot 9, which can ensure that the wire is in the correct position and ensure the quality of the puncture installation. The inner surface of the main line slot is provided with upper piercing teeth 4, and the upper body of the wire clamp is also provided with a limit plate 21 for limiting the swing of the lower body 18 of the wire clamp. Opening, so only the first fastening bolt connects the upper and lower bodies, when operating with the operating lever, the lower body 18 of the wire clip will swing left and right, and the limiting plate 21 can realize the left and right swing of the lower body 18. During installation, the first fastening bolt 5 and the second fastening bolt 19 are fastened by cooperating with the first fastening hole 6 and the second fastening hole 20 at the two ends of the lower body 14 and the upper body screw hole 15 of the clamp. During the fastening process, the first and second bolts should be tightened crosswise and sequentially to ensure good contact between the puncture and the metal part of the wire.
所述线夹上本体14设有副线安装固定用的固定板2,固定板2上设有上下方向的导线凹槽,凹槽两侧设有紧固用螺纹孔。与其配合实现安装的是副线压板12,副线压板12中部设有凸出槽11,配合凹槽保证副线安装质量。副线压板12上设有两个螺栓紧固孔13,固定板2与副线压板12配合完成副线的安装功能。 The upper body 14 of the clamp is provided with a fixed plate 2 for installing and fixing the auxiliary line. The fixed plate 2 is provided with a wire groove in an up and down direction, and both sides of the groove are provided with threaded holes for fastening. What cooperates with it to realize installation is the auxiliary line pressing plate 12, and the middle part of the auxiliary line pressing plate 12 is provided with a protruding groove 11, which cooperates with the groove to ensure the installation quality of the auxiliary line. Two bolt fastening holes 13 are provided on the auxiliary line pressing plate 12, and the fixing plate 2 cooperates with the auxiliary line pressing plate 12 to complete the installation function of the auxiliary line.
通过穿刺的应用解决了带电绝缘导线剥皮困难这个老大难问题,利用穿刺实现通流导电保证了绝缘导线绝缘良好的密封性能,解决了绝缘导线因为剥皮而出现的密封难问题。剥皮工序的取消极大降低了施工劳动强度,规避了在剥皮过程中误伤导线的不良现象,解决了因为地形地貌等作业环境影响造成绝缘车无法实施带电作业的被动局面,通过该新型线夹的应用,进一步减少了用户停电,为企业新建线路的按时运行提高了坚强保证,同时也是带电作业开展的一次创新应用。 Through the application of puncture, the long-standing problem of the difficulty of stripping live insulated wires is solved. The use of puncture to realize current conduction ensures the good sealing performance of the insulation of insulated wires, and solves the problem of difficult sealing of insulated wires due to peeling. The cancellation of the stripping process greatly reduces the labor intensity of construction, avoids the undesired phenomenon of accidentally injuring the wires during the stripping process, and solves the passive situation that the insulation vehicle cannot perform live work due to the influence of the terrain and other operating environments. Through the new type of clamp The application further reduces power outages for users and provides a strong guarantee for the on-time operation of new lines for enterprises. It is also an innovative application for live work.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510225712.8A CN104795771B (en) | 2015-05-06 | 2015-05-06 | Piercing clamps for ground potential live working of insulated conductors |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510225712.8A CN104795771B (en) | 2015-05-06 | 2015-05-06 | Piercing clamps for ground potential live working of insulated conductors |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN104795771A true CN104795771A (en) | 2015-07-22 |
| CN104795771B CN104795771B (en) | 2017-03-08 |
Family
ID=53560392
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510225712.8A Expired - Fee Related CN104795771B (en) | 2015-05-06 | 2015-05-06 | Piercing clamps for ground potential live working of insulated conductors |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104795771B (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106451292A (en) * | 2015-08-10 | 2017-02-22 | 上海兆邦电力器材有限公司 | 0.4kV puncture antiskid cluster insulated tension-resistant wire clamp |
| CN108832330A (en) * | 2018-06-28 | 2018-11-16 | 广东电网有限责任公司 | A kind of hinge wire clamp |
| CN108879120A (en) * | 2018-07-03 | 2018-11-23 | 秉岳电气(上海)有限公司 | A kind of insulation puncture line clamping of extendable functions |
| CN109523903A (en) * | 2018-11-03 | 2019-03-26 | 襄阳先义电力科技有限公司 | Draw hanging warning sign |
| CN112821298A (en) * | 2021-01-31 | 2021-05-18 | 西安江夏电力设备制造有限公司 | Automatic live-line work lifting platform and method |
| CN119009607A (en) * | 2024-10-24 | 2024-11-22 | 国网浙江省电力有限公司丽水供电公司 | Bunched wire wiring device and wiring method thereof |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH10248133A (en) * | 1997-02-28 | 1998-09-14 | Daihatsu Motor Co Ltd | Method of cable joint treatment in vehicle |
| CN2833905Y (en) * | 2005-10-26 | 2006-11-01 | 张永 | Medium-voltage penetrating insulated wire with electric flashing device |
| CN201616510U (en) * | 2010-02-20 | 2010-10-27 | 李越汉 | Insulating piercing connector with electrical protection function |
| CN202616416U (en) * | 2012-01-19 | 2012-12-19 | 辽宁华隆电力科技有限公司 | Limiting-type puncture clamp |
-
2015
- 2015-05-06 CN CN201510225712.8A patent/CN104795771B/en not_active Expired - Fee Related
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH10248133A (en) * | 1997-02-28 | 1998-09-14 | Daihatsu Motor Co Ltd | Method of cable joint treatment in vehicle |
| CN2833905Y (en) * | 2005-10-26 | 2006-11-01 | 张永 | Medium-voltage penetrating insulated wire with electric flashing device |
| CN201616510U (en) * | 2010-02-20 | 2010-10-27 | 李越汉 | Insulating piercing connector with electrical protection function |
| CN202616416U (en) * | 2012-01-19 | 2012-12-19 | 辽宁华隆电力科技有限公司 | Limiting-type puncture clamp |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106451292A (en) * | 2015-08-10 | 2017-02-22 | 上海兆邦电力器材有限公司 | 0.4kV puncture antiskid cluster insulated tension-resistant wire clamp |
| CN108832330A (en) * | 2018-06-28 | 2018-11-16 | 广东电网有限责任公司 | A kind of hinge wire clamp |
| CN108879120A (en) * | 2018-07-03 | 2018-11-23 | 秉岳电气(上海)有限公司 | A kind of insulation puncture line clamping of extendable functions |
| CN109523903A (en) * | 2018-11-03 | 2019-03-26 | 襄阳先义电力科技有限公司 | Draw hanging warning sign |
| CN112821298A (en) * | 2021-01-31 | 2021-05-18 | 西安江夏电力设备制造有限公司 | Automatic live-line work lifting platform and method |
| CN112821298B (en) * | 2021-01-31 | 2022-04-19 | 西安江夏电力设备制造有限公司 | Automatic live-line work lifting platform and method |
| CN119009607A (en) * | 2024-10-24 | 2024-11-22 | 国网浙江省电力有限公司丽水供电公司 | Bunched wire wiring device and wiring method thereof |
| CN119009607B (en) * | 2024-10-24 | 2025-02-07 | 国网浙江省电力有限公司丽水供电公司 | Bunched wire wiring device and wiring method thereof |
Also Published As
| Publication number | Publication date |
|---|---|
| CN104795771B (en) | 2017-03-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104795771B (en) | Piercing clamps for ground potential live working of insulated conductors | |
| CN103022749B (en) | Cable connecting clamp with insulating sheath | |
| CN102227071B (en) | Manipulator clamping linking wire clamp special for high voltage electriferous work | |
| CN204720567U (en) | Tee connector | |
| CN205211982U (en) | Binding post of line ball nose exempts from | |
| CN205148170U (en) | Electrified fastening bolt instrument of transmission line | |
| CN204205093U (en) | Electricity testing grounding ring | |
| CN204558687U (en) | A kind of earth potential live operation penetrating cable clamp for insulated conductor connection | |
| CN104157988A (en) | Piercing connector facilitating connection of cables of different diameters | |
| CN201233972Y (en) | Multifunctional connecting plug | |
| CN103001017B (en) | Multidirectional rotary connection cable clamp | |
| CN202042614U (en) | Insulation piercing clamp | |
| CN209461659U (en) | It can livewire work lightning-protection piercing grounding wire clip | |
| CN106961027A (en) | A kind of T-shaped conduction wire clamp | |
| CN203056127U (en) | Puncture cable clamp | |
| CN203103517U (en) | Wire clamp type rapid connecting connector for emergency power supply vehicle | |
| CN110233445B (en) | Quick repair wire and installation drainage wire combination fitting | |
| CN201994433U (en) | Fixing clamp for terminal block of power cable | |
| CN112186623B (en) | Working method of hot-line connection branch wiring combination tool | |
| CN205159543U (en) | Waterproof terminal box of interval illumination branch of subway | |
| CN204696555U (en) | A kind of novel 35kV insulation lead wire of convenient operation | |
| CN209183787U (en) | A kind of universal wire connection device | |
| CN203103848U (en) | a stringer | |
| CN210053102U (en) | Combined hardware fitting for quickly repairing lead and installing drainage line | |
| CN206865013U (en) | The drainage thread locking disengaging gear of rapid arc extinction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| EXSB | Decision made by sipo to initiate substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170308 |