CN104775631A - Late-added concrete stand column construction method - Google Patents
Late-added concrete stand column construction method Download PDFInfo
- Publication number
- CN104775631A CN104775631A CN201510082474.XA CN201510082474A CN104775631A CN 104775631 A CN104775631 A CN 104775631A CN 201510082474 A CN201510082474 A CN 201510082474A CN 104775631 A CN104775631 A CN 104775631A
- Authority
- CN
- China
- Prior art keywords
- board
- reinforcing bar
- upright post
- stand column
- column construction
- Prior art date
Links
- 238000010276 construction Methods 0.000 title claims abstract description 27
- 230000002787 reinforcement Effects 0.000 claims abstract description 9
- 230000003014 reinforcing Effects 0.000 claims description 31
- 238000007569 slipcasting Methods 0.000 claims description 17
- 230000000875 corresponding Effects 0.000 claims description 7
- 238000000034 method Methods 0.000 claims description 7
- 210000002445 Nipples Anatomy 0.000 claims description 4
- 238000009434 installation Methods 0.000 claims description 4
- 238000002513 implantation Methods 0.000 claims description 3
- 238000003466 welding Methods 0.000 claims description 2
- 210000002356 Skeleton Anatomy 0.000 abstract 1
- 239000011257 shell materials Substances 0.000 description 7
- 230000000694 effects Effects 0.000 description 4
- 238000005516 engineering processes Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000006011 modification reactions Methods 0.000 description 2
- 208000008425 Protein Deficiency Diseases 0.000 description 1
- 239000004568 cements Substances 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injections Substances 0.000 description 1
- 239000000463 materials Substances 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 239000011901 water Substances 0.000 description 1
Abstract
The invention relates to the field of civil engineering, in particular to a late-added concrete stand column construction method. The late-added concrete stand column construction method comprises the following steps: a lower section of reinforcement is implanted in a stand column construction position on a baseplate; an upper section of reinforcement is connected to an opposite position on a top plate; the lower section of reinforcement and the upper section of reinforcement are connected through a thread joint; a reinforcement skeleton is mounted, and a body part of a stand column is cast; after the body part of the stand column reaches the standard strength requirement, the top of the body part of the stand column is polished; the grouting is performed in an area between the top of the body part of the stand column and the top plate to connect the top of the body part of the stand column with the top plate, so that the difficulty of incapability of tightly connecting the top of the stand column with an original structure in late addition of a concrete stand column in a cast structure is preferably solved, and the engineering quality and the late bearing safety are greatly improved.
Description
Technical field
The present invention relates to field of civil engineering, particularly relate to a kind of rear increasing concrete column construction method.
Background technology
At present, in the structure of having constructed, newly-increased concrete column, generally because column top cannot overlay closely knit with concrete structure, is difficult to play the effect of shoring, and becomes the obstacle that structure design and site operation be difficult to break through.
Therefore, for above deficiency, the invention provides a kind of rear increasing concrete column construction method.
Summary of the invention
(1) technical problem that will solve
The object of this invention is to provide a kind of rear concrete column construction method that increases cannot overlay closely knit with concrete structure to solve rear increasing concrete column construction central post top, is difficult to the problem playing the effect of shoring.
(2) technical scheme
In order to solve the problems of the technologies described above, the invention provides a kind of rear increasing concrete column construction method, it comprises the following steps: S1, base plate upper pillar stand construction location carry out hypomere reinforcing bar implantation or at the pre-buried screw shell of base plate upper pillar stand construction location to install hypomere reinforcing bar, position corresponding on top board connects epimere reinforcing bar;
S2, hypomere reinforcing bar are connected by nipple with epimere reinforcing bar;
S3, installation cage of reinforcement, carry out the cast of upright post main part;
After S4, upright post main part reach specification requirement of strength, dabbing process is carried out at column main part top;
Slip casting cast is carried out, to make upright post main atop part and top board seamless link in S5, region between upright post main atop part and top board.
Wherein, in step S1, when top board connects epimere reinforcing bar, adopt the mode of bar planting.
Wherein, in step S1, when top board connects epimere reinforcing bar, pre-buried screw shell on top board, then makes epimere reinforcing bar be connected with screw shell.
Wherein, in step s 2, the mode that hypomere reinforcing bar and epimere reinforcing bar are overlapped by upset straight thread splice, welding or colligation is connected.
Wherein, in step s 5, under before region between upright post main atop part and top board carries out slip casting, on top board, spud in grouting port and exhaust opening in corresponding position.
Wherein, in step s 5, under before region between upright post main atop part and top board carries out slip casting cast, reserved grouting port and exhaust opening on top board.
(3) beneficial effect
Technique scheme tool of the present invention has the following advantages: in rear increasing concrete column construction method provided by the invention, first install cage of reinforcement, carry out the cast of upright post main part; Then, after upright post main part reaches specification requirement of strength, dabbing process is carried out at column main part top; Slip casting cast is carried out in region between upright post main atop part and top board, to make upright post main atop part and top board seamless link, solve when increasing concrete column after in pouring structure preferably, column top cannot be connected a difficult problem closely with original structure, and greatly improving is workmanship and later stage bearing safety.
Accompanying drawing explanation
Fig. 1 is the stereogram increasing concrete column construction method after the embodiment of the present invention.
In figure, 1: top board; 2: base plate; 3: hypomere reinforcing bar; 4: nipple; 5: screw shell; 6: upright post main part; 7: Grouting Pipe; 8: slip casting district, column top.
Detailed description of the invention
Below in conjunction with drawings and Examples, the specific embodiment of the present invention is described in further detail.Following examples for illustration of the present invention, but are not used for limiting the scope of the invention.
In describing the invention, it will be appreciated that, term " on ", D score, "front", "rear", " top ", " end " " interior ", the orientation of the instruction such as " outward " or position relationship be based on orientation shown in the drawings or position relationship, only the present invention for convenience of description and simplified characterization, instead of indicate or imply that the device of indication or element must have specific orientation, with specific azimuth configuration and operation, therefore can not be interpreted as limitation of the present invention.
In describing the invention, it should be noted that, unless otherwise clearly defined and limited, term " installation ", " being connected ", " connection " should be interpreted broadly, and such as, can be fixedly connected with, also can be removably connect, or connect integratedly; Can be mechanical connection, also can be electrical connection; Can be directly be connected, also indirectly can be connected by intermediary, can be the connection of two element internals.For the ordinary skill in the art, concrete condition above-mentioned term concrete meaning in the present invention can be understood.
As shown in Figure 1, rear increasing concrete column construction method provided by the invention comprises the following steps:
S1, on a base plate 2 column construction location carry out hypomere reinforcing bar 3 implantation or at the pre-buried screw shell of base plate upper pillar stand construction location to install hypomere reinforcing bar, position corresponding on top board 1 connects epimere reinforcing bar;
S2, hypomere reinforcing bar 3 are connected by nipple 4 with epimere reinforcing bar;
S3, installation cage of reinforcement, carry out the cast of upright post main part 6, adopt conventional pouring concrete technique during cast;
After S4, upright post main part 6 reach specification requirement of strength, dabbing process is carried out at column main part 6 top;
Slip casting cast is carried out in S5, region (slip casting district, column top 8) between upright post main part 6 top and top board 1, be connected with top board 1 to make upright post main part 6 top, length between upright post main part 6 top and top board 1 is generally preferably 50cm, the effective connection both being realized by slip casting.
In step S1, when top board 1 connects epimere reinforcing bar, adopt the mode of bar planting.
In step S1, when top board 1 connects epimere reinforcing bar, pre-buried screw shell 5 on top board 1, then makes epimere reinforcing bar be connected with screw shell 5.
In step s 2, hypomere reinforcing bar 3 is connected by upset straight thread splice 4 with epimere reinforcing bar.
In step s 5, under before region between upright post main part 6 top and top board 1 carries out slip casting cast, on top board 1, corresponding position water drilling spuds in grouting port and exhaust opening.
In step s 5, under before region between upright post main part 6 top and top board 1 carries out slip casting cast, reserved grouting port and exhaust opening on top board 1, particularly, pre-buried two Grouting Pipe 7 concordant with top board 1 bottom surface in position corresponding with column on top board 1, use as slip casting on the one hand or exhaust use in slip casting process, the grouting port certainly spudded on top board 1 also has the effect of these two aspects.
Before slip casting cast is carried out in region in rear increasing concrete column construction method provided by the invention between upright post main part 6 top and top board 1, first slip casting district 8, column top territory template is installed.Hold out against close bottom die head and top board 1, mortar leakage prevention.Then starched or other same type of material to the inner pressure injection of column and column concrete equality strength micro-expansion cement by grouting port on plate 1, thus the construction of increasing column after completing.Rear increasing column is divided into routine to build the part two sections of part and grouting methol by the inventive method, increase column after realizing well to be connected with original structure, solve when increasing concrete column after in pouring structure preferably, column top cannot be connected a difficult problem closely with original structure, and greatly improving is workmanship and later stage bearing safety.
The above is only the preferred embodiment of the present invention; it should be pointed out that for those skilled in the art, under the prerequisite not departing from the technology of the present invention principle; can also make some improvement and modification, these improve and modification also should be considered as protection scope of the present invention.
Claims (6)
1. increase a concrete column construction method after, it is characterized in that: it comprises the following steps:
S1, base plate upper pillar stand construction location carry out hypomere reinforcing bar implantation or at the pre-buried screw shell of base plate upper pillar stand construction location to install hypomere reinforcing bar, position corresponding on top board connects epimere reinforcing bar;
S2, hypomere reinforcing bar are connected by nipple with epimere reinforcing bar;
S3, installation cage of reinforcement, carry out the cast of upright post main part;
After S4, upright post main part reach specification requirement of strength, dabbing process is carried out at column main part top;
Slip casting cast is carried out, to make upright post main atop part and top board seamless link in S5, region between upright post main atop part and top board.
2. rear increasing concrete column construction method according to claim 1, is characterized in that: in step S1, adopts the mode of bar planting when top board connects epimere reinforcing bar.
3. rear increasing concrete column construction method according to claim 1, is characterized in that: in step S1, and when top board connects epimere reinforcing bar, pre-buried screw shell on top board, then makes epimere reinforcing bar be connected with screw shell.
4. rear increasing concrete column construction method according to claim 1, it is characterized in that: in step s 2, the mode that hypomere reinforcing bar is overlapped by upset straight thread splice, welding or colligation with epimere reinforcing bar is connected.
5. rear increasing concrete column construction method according to claim 1, is characterized in that: in step s 5, and before slip casting is carried out in the region between upright post main atop part and top board, on top board, spud in grouting port and exhaust opening in corresponding position.
6. rear increasing concrete column construction method according to claim 1, is characterized in that: in step s 5, before slip casting cast is carried out in the region between upright post main atop part and top board, and reserved grouting port and exhaust opening on top board.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510082474.XA CN104775631A (en) | 2015-02-16 | 2015-02-16 | Late-added concrete stand column construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510082474.XA CN104775631A (en) | 2015-02-16 | 2015-02-16 | Late-added concrete stand column construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104775631A true CN104775631A (en) | 2015-07-15 |
Family
ID=53617361
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510082474.XA CN104775631A (en) | 2015-02-16 | 2015-02-16 | Late-added concrete stand column construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104775631A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102031876A (en) * | 2009-09-29 | 2011-04-27 | 中冶天工上海十三冶建设有限公司 | Method for newly adding upright column for building |
CN102444142A (en) * | 2011-09-20 | 2012-05-09 | 新世纪建设集团有限公司 | Pile group column replacement expanded basement and construction method of same |
CN102777052A (en) * | 2012-08-13 | 2012-11-14 | 黄智辉 | Reinforced concrete jacket strengthening beam-column core area structure |
CN103046766A (en) * | 2013-01-14 | 2013-04-17 | 北京筑福建设工程有限责任公司 | Method for lengthening columns, adding beams, resisting earthquakes and reinforcing for bottom frame structure |
CN103225422A (en) * | 2013-04-10 | 2013-07-31 | 北京筑福国际工程技术有限责任公司 | Existing masonry structure using light steel structure direct storey-adding technology and construction method of existing masonry structure |
CN203669112U (en) * | 2013-12-30 | 2014-06-25 | 安徽天筑建设(集团)有限公司 | Added-storey steel frame column base joint on top of multilayer concrete frame structure |
CN104213717A (en) * | 2014-07-10 | 2014-12-17 | 上海市建筑科学研究院(集团)有限公司 | Integrated reconstruction method for multi-storey residential |
-
2015
- 2015-02-16 CN CN201510082474.XA patent/CN104775631A/en not_active Application Discontinuation
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102031876A (en) * | 2009-09-29 | 2011-04-27 | 中冶天工上海十三冶建设有限公司 | Method for newly adding upright column for building |
CN102444142A (en) * | 2011-09-20 | 2012-05-09 | 新世纪建设集团有限公司 | Pile group column replacement expanded basement and construction method of same |
CN102777052A (en) * | 2012-08-13 | 2012-11-14 | 黄智辉 | Reinforced concrete jacket strengthening beam-column core area structure |
CN103046766A (en) * | 2013-01-14 | 2013-04-17 | 北京筑福建设工程有限责任公司 | Method for lengthening columns, adding beams, resisting earthquakes and reinforcing for bottom frame structure |
CN103225422A (en) * | 2013-04-10 | 2013-07-31 | 北京筑福国际工程技术有限责任公司 | Existing masonry structure using light steel structure direct storey-adding technology and construction method of existing masonry structure |
CN203669112U (en) * | 2013-12-30 | 2014-06-25 | 安徽天筑建设(集团)有限公司 | Added-storey steel frame column base joint on top of multilayer concrete frame structure |
CN104213717A (en) * | 2014-07-10 | 2014-12-17 | 上海市建筑科学研究院(集团)有限公司 | Integrated reconstruction method for multi-storey residential |
Non-Patent Citations (1)
Title |
---|
赵新文: "使用功能变更后的增柱施工技术", 《山西建筑》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103981898B (en) | A kind of inverse underground engineering construction method done of overall open cut node | |
CN106761810B (en) | A kind of large-deformation tunnel in soft rock supporting structure system and its construction method | |
CN203684398U (en) | Device for positioning embedded parts in reinforced concrete structure | |
CN107299683B (en) | Compound concrete-filled tubular column assembled docks node and connection method | |
CN102828577B (en) | Steel pipe column base connecting structure and mounting method thereof | |
CN102061710B (en) | Diaphragm wall joint and manufacturing method of diaphragm wall | |
CN203334473U (en) | Tooth socket type connecting structure of upper layer interior wall plate and lower layer interior wall plate of assembling type shear wall | |
CN105220874A (en) | The construction method of basement superelevation exterior wall self-supporting single side formwork system | |
CN103590510B (en) | The fixed connection method of embedded bar in fabricated construction and cast-in-place structural | |
CN104652418B (en) | Diaphragm wall underground utilities position construction method | |
CN101749030A (en) | Porous parallel-connected grouting method and device for reinforcing roadway weak surrounding rock | |
CN206090867U (en) | Steel construction wall column base quick connect structure | |
CN101936010B (en) | Construction method of dewatering well in underground concrete structure | |
CN204753844U (en) | Circular steel tube concrete column sleeve connected node | |
CN106193118B (en) | The tall and big side wall unilateral side formwork erection of open trench tunnel agent structure and its construction technology | |
CN104314587A (en) | Targeted domain-control grouting device and grouting process | |
CN209145612U (en) | A kind of anti-floating type section of jurisdiction for shield tunnel | |
CN102134852A (en) | Concrete pouring device and method | |
CN104652495B (en) | Internal support of foundation pit column and base plate node waterproof construction technology | |
CN204040035U (en) | A kind of positioning guiding structure of steel pile casting | |
CN105545323A (en) | Construction method for open cut tunnel lining | |
CN107654082A (en) | Using basic building block it is vertical under to enlarging technique | |
CN106013172A (en) | Double row pile and diagonal brace combined soft soil deep foundation pit supporting structure and construction method | |
CN105605308B (en) | Municipal blow-off line laying construction method | |
CN104895585A (en) | Construction method of reserved grouting pipe of tunnel vault |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20150715 |