CN104775403B - A kind of pilot-operated type Hydro-automatic gate structure - Google Patents

A kind of pilot-operated type Hydro-automatic gate structure Download PDF

Info

Publication number
CN104775403B
CN104775403B CN201510153025.XA CN201510153025A CN104775403B CN 104775403 B CN104775403 B CN 104775403B CN 201510153025 A CN201510153025 A CN 201510153025A CN 104775403 B CN104775403 B CN 104775403B
Authority
CN
China
Prior art keywords
buoyancy tank
tank room
gate
water inlet
float
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510153025.XA
Other languages
Chinese (zh)
Other versions
CN104775403A (en
Inventor
李习洪
周超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Shengyu Smart Ecological Environmental Protection Co ltd
Original Assignee
Wuhan Shengyu Drainage Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Shengyu Drainage Systems Co Ltd filed Critical Wuhan Shengyu Drainage Systems Co Ltd
Priority to CN201510153025.XA priority Critical patent/CN104775403B/en
Publication of CN104775403A publication Critical patent/CN104775403A/en
Application granted granted Critical
Publication of CN104775403B publication Critical patent/CN104775403B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/20Movable barrages; Lock or dry-dock gates
    • E02B7/50Floating gates

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Barrages (AREA)

Abstract

The invention discloses a kind of pilot-operated type Hydro-automatic gate structure, be provided with float chamber in aquifer reserve pond, the bottom of float chamber has current via, and current via communicates with aquifer reserve pond;Float chamber is provided with float;The both sides of the edge of gate and bottom margin respectively with both side surface and the bottom fitted seal of flood discharge passage;Have buoyancy tank room water inlet towards the bottom of the sidewall of the buoyancy tank room of water (flow) direction side, the sidewall bottom of the buoyancy tank room of water (flow) direction side has buoyancy tank room apopore dorsad;Water inlet, buoyancy tank room is provided with the plugging device of closure buoyancy tank room water inlet, is connected and has linkage between plugging device with float.Controlling plugging device lifting by the floating of float with declining, when storage pond liquid level is the lowest, buoyancy tank room starts water inlet, and gate is automatically turned on by the effect of buoyancy tank, when storage pond reaches high level, and plugging device closure buoyancy tank room water inlet, gate slowly closing.

Description

A kind of pilot-operated type Hydro-automatic gate structure
Technical field
The present invention relates to drainage system equipment technical field, be specifically related to a kind of pilot-operated type hydraulic automatism lock Door.
Background technology
Municipal administration rainwater or sewage network in the system of natural water (rivers, lake etc.) overflow, Often through gate controlling water level height.Gate needs to carry out flood discharge according to different water levels, needs dynamic Power drives, and consumes the energy more, is also inconvenient to keep in repair, and the height of water level in aquifer reserve pond cannot be controlled System.The most how to design a kind of simple in construction, do not consume the energy, and controllably descend storage pond water The gate structure of position height is current problems faced.
Summary of the invention
The present invention is aiming at above-mentioned technical problem, it is provided that a kind of pilot-operated type Hydro-automatic gate structure, This structure controls the water inlet of buoyancy tank room by the structure of float and balancing weight, by buoyancy tank regulating gate Keying, thus control the height of water level in aquifer reserve pond, whole process is without consuming the energy, real Good by property.
For realizing this purpose, the pilot-operated type Hydro-automatic gate structure designed by the present invention, including arranging Gate in runner side, it is arranged at the buoyancy tank room of runner opposite side and is later than the underground of buoyancy tank room water inlet Storage pond;Described gate is fixed on the side of rotating shaft, and the opposite side of described rotating shaft is fixed with buoyancy tank, institute State buoyancy tank to be arranged in buoyancy tank room;The two ends of described rotating shaft are hingedly connected on the flow path wall of runner both sides, For flood discharge passage between the flow path wall of described buoyancy tank and runner side;It is characterized in that: lower describedly Being provided with float chamber in reservoir, the bottom of described float chamber has current via, described current via and ground Lower storage pond communicates;Described float chamber is provided with float;The both sides of the edge of described gate and bottom margin Respectively with both side surface and the bottom fitted seal of flood discharge passage;Buoyancy tank room towards water (flow) direction side The bottom of sidewall have buoyancy tank room water inlet, the dorsad sidewall bottom of the buoyancy tank room of water (flow) direction side Have buoyancy tank room apopore;Water inlet, described buoyancy tank room is provided with the closure dress of closure buoyancy tank room water inlet Putting, being connected between described plugging device and float has linkage.
Further, the current via of described float chamber bottom is float chamber apopore, described float chamber The top of side sidewall have float chamber water inlet, the water inlet cross section of described float chamber water inlet is more than The water outlet cross section of float chamber apopore.
Further, it is provided with check valve of water drainage at described float chamber apopore.
Further, described plugging device is balancing weight, and described linkage includes lowering with being arranged at The first pulley above reservoir and be arranged at the second pulley above buoyancy tank room, described float and balancing weight Between connect and have steel wire rope, one end of described steel wire rope connects float, the other end through the first pulley, Second pulley connects balancing weight;The quality of described float is more than the quality of balancing weight.
Further, described balancing weight is spheroid balancing weight.
Further, the water inlet cross section of described buoyancy tank room water inlet is cut more than the water outlet of buoyancy tank room apopore Face;
Further, the bottom of described flood discharge passage is fixed with seal receptacle, and the two ends of described seal receptacle are divided It is not fixed on the side sidewall of buoyancy tank room and the side flow path wall of runner;Described seal receptacle and gate Bottom fitted seal, both sides of the edge and the bottom margin of described gate are respectively and fixedly provided with sealing ring.
Further, described buoyancy tank fixed plate is evenly arranged in the top of buoyancy tank along the width of buoyancy tank.
Further, it is fixedly connected with gate between described gate and rotating shaft and fixes bar, on described gate Being disposed with many group gates and fix bar assembly, often group gate is fixed bar assembly and is included two gates acutangulated Fixing bar, described gate is fixed bar assembly and is evenly arranged along the width of gate.
Further, the flow path wall of described runner both sides is symmetrically fixed with rotating shaft location-plate, described Being fixed with bearing in rotating shaft location-plate, the two ends of described rotating shaft are arranged in bearing.
The invention has the beneficial effects as follows: floating and declining the lifting controlling balancing weight by float, when When storage pond liquid level is the lowest, buoyancy tank room starts water inlet, and gate is automatically turned on by the effect of buoyancy tank, works as tune Reservoir reach high level time, balancing weight closure buoyancy tank room water inlet, gate slowly closing, this Bright reasonable in design, gate can realize automatic open close, is not required to rely on external force.
Accompanying drawing explanation
Fig. 1 be the present invention upstream canal in buoyancy tank room and the top view of gate;
Fig. 2 is buoyancy tank room and the front view of gate in middle and upper reaches runner of the present invention;
When Fig. 3 is storage pond low water level state in the present invention, the structural representation that buoyancy tank room is opened;
When Fig. 4 is storage pond high water level state in the present invention, the structural representation that buoyancy tank room is closed;
Fig. 5 is gate and the structural representation of seal receptacle fitted seal in the present invention;
Fig. 6 is structural representation during gate opening in Fig. 5;
Wherein, 1 gate, 2 aquifer reserve ponds, 3 rotating shafts, 4 flow path walls, 5 buoyancy tanks, 6 Buoyancy tank room, 7 buoyancy tank room water inlets, 8 buoyancy tank room apopores, 9 float chambers, 10 float chambers Apopore, 11 floats, 12 balancing weights, 13 first pulleys, 14 second pulleys, 15 is close Envelope seat, 16 sealing rings, 17 rotating shaft location-plates, 18 buoyancy tank fixed plates, 19 gates fix bar, 20 float chamber water inlets, 21 steel wire ropes, 22 foundation bolts, 23 runners, 24 flood discharges are led to Road, 25 check valve of water drainage.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments the present invention done and describes in detail further:
Pilot-operated type Hydro-automatic gate structure as shown in Fig. 14, including being arranged at runner 23 side Gate 1, be arranged at runner 23 opposite side buoyancy tank room 6 and be later than buoyancy tank room 6 water inlet ground lower Reservoir 2;Described gate 1 is fixed on the side of rotating shaft 3, and the opposite side of described rotating shaft 3 is fixed with buoyancy tank 5, described buoyancy tank 5 is arranged in buoyancy tank room 6;The two ends of described rotating shaft 3 are hingedly connected to runner 23 On the flow path wall 4 of both sides, for flood discharge passage between the flow path wall 4 of described buoyancy tank 5 and runner 23 side 24;It is characterized in that: described aquifer reserve pond 2 is provided with float chamber 9, the bottom of described float chamber 9 Having current via, described current via communicates with aquifer reserve pond 2;Described float chamber 9 is provided with Float 11;The both sides of the edge of described gate 1 and bottom margin respectively with the both side surface of flood discharge passage 24 With bottom fitted seal;Buoyancy tank room is had towards the bottom of the sidewall of the buoyancy tank room 6 of water (flow) direction side Water inlet 7, the sidewall bottom of the buoyancy tank room 6 of water (flow) direction side has buoyancy tank room apopore 8 dorsad; Being provided with the plugging device of closure buoyancy tank room water inlet 7 at described buoyancy tank room water inlet 7, described closure fills Put to be connected between float 11 and have linkage.Float 11 is controlled by the water level height in float chamber 9 Lifting, thus control the lifting of plugging device, by the elevating control buoyancy tank room 6 of plugging device Water inlet, buoyancy tank 5, by the buoyancy of water effect in buoyancy tank room 6, drives rotating shaft 3 to rotate, thus controls The keying of check door 1, the opening-closing process of gate 1 is without power, and adjustably descends storage pond 2 Water level in water level and upstream canal, reasonable in design, practical.
Preferably, the current via of described float chamber 9 bottom is float chamber apopore 10, described float The top of the side sidewall of room 9 has float chamber water inlet 20, the water inlet of described float chamber water inlet 20 Cross section is more than the water outlet cross section of float chamber apopore 10.Quickly intake by float chamber water inlet 20, By the slow draining of float chamber apopore 10, it is ensured that it is reliable and stable that water level regulates.When float chamber water outlet Hole 10 is less, and when float chamber apopore 10 is intake, its inflow is little, the water inlet in float chamber 9 Highly not enough so that float 11 rises to design height, plugging device cannot be by buoyancy tank room water inlet 7 dozens Open.
It is further preferred that be provided with check valve of water drainage 25 at described float chamber apopore 10.Pass through draining The structure of check valve 25, it is ensured that 10 drainings of float chamber apopore are not intake, it is ensured that float chamber 9 Enter drainage works quick, reliable and stable.
Preferably, described plugging device is balancing weight 12, and described linkage includes lowering with being arranged at The first pulley 13 above reservoir 2 and be arranged at the second pulley 14 above buoyancy tank room 6, described float Being connected between 11 with balancing weight 12 and have steel wire rope 21, one end of described steel wire rope 21 connects float 11, The other end connects balancing weight 12 through first pulley the 13, second pulley 14;The quality of described float 11 Quality more than balancing weight 12.
Controlled the lifting of float 11 by the water level height in float chamber 9, thus control balancing weight 12 Lifting, by the water inlet of the elevating control buoyancy tank room 6 of balancing weight 12, buoyancy tank 5 is by buoyancy tank room 6 Interior buoyancy of water effect, drives rotating shaft 3 to rotate, thus the keying of regulating gate 1, gate 1 Opening-closing process is without power, and adjustably descends the water level in storage pond 2 water level and upstream canal, Reasonable in design, practical.
In technique scheme, as shown in Fig. 34, described balancing weight 12 is spheroid balancing weight.Ball Body balancing weight 12 is relatively conventional, draws materials conveniently, low cost.
In technique scheme, the water inlet cross section of described buoyancy tank room water inlet 7 is more than buoyancy tank room apopore 8 Water outlet cross section.Buoyancy tank room water inlet 7 ensure that the fast and stable that buoyancy tank room intakes, the water outlet of buoyancy tank room The water outlet cross section in hole 8 is little, it is ensured that the water level in buoyancy tank room 6 slowly declines, so that it is guaranteed that gate 1 can With slowly closing, improve the stability of gate 1 work.
In technique scheme, as shown in Fig. 56, the bottom of described flood discharge passage 24 is fixed with close Envelope seat 15, the two ends of described seal receptacle 15 are individually fixed in side sidewall and the runner 23 of buoyancy tank room 6 Side flow path wall 4 on;Described seal receptacle 15 and the bottom fitted seal of gate 1, described gate 1 Both sides of the edge and bottom margin be respectively and fixedly provided with sealing ring 16.Gate is ensured by the structure of sealing ring 16 The structure of the seal receptacle 15 bottom the sealing of 1, and runner 23 has also been effectively ensured bottom gate 1 Seal.
In technique scheme, as shown in Fig. 12, right on the flow path wall 4 of described upstream canal both sides Claim to be fixed with rotating shaft location-plate 17, described rotating shaft location-plate 17 is fixed with bearing, described rotating shaft 3 Two ends are arranged in bearing.The articulated structure of rotating shaft 3 is simple, it is easy to installing, practicality is good.
In technique scheme, as shown in Fig. 12, solid between top and the rotating shaft 3 of described buoyancy tank 5 Determine connection and have polylith buoyancy tank fixed plate 18.Buoyancy tank 5 and rotating shaft is ensured by the structure of buoyancy tank fixed plate 18 The intensity of the attachment structure between 3, further enhances structural stability.
In technique scheme, described buoyancy tank fixed plate 18 is evenly arranged in along the width of buoyancy tank 5 The top of buoyancy tank 5.The connection of buoyancy tank 5 and rotating shaft 3 is ensured by the structure of polylith buoyancy tank fixed plate 18 Intensity, it is ensured that the uniform force of buoyancy tank 5.
In technique scheme, it is fixedly connected with gate between described gate 1 and rotating shaft 3 and fixes bar 19.
In technique scheme, as shown in Fig. 12 and Fig. 56, described gate 1 is disposed with many Bar assembly fixed by group gate, and often group gate is fixed bar assembly and included that bar 19 fixed by two gates acutangulated.
In technique scheme, described gate is fixed bar assembly and is evenly arranged along the width of gate 1. The structure fixing bar 19 by many group gates ensure that the bonding strength between gate 1 and rotating shaft 3, and The hoisting capacity of gate 1 is bigger, it is ensured that gate 1 is for the rising of water level and being quick on the draw of reduction, energy Reach effect and the purpose of timely flood discharge, further increase the practicality of device.
In the present invention, as it is shown on figure 3, when the liquid level in the aquifer reserve pond 2 in downstream is the lowest, floating Water in seed cell 9 flows out, and float 11 declines, under the action of gravity of float 11, in buoyancy tank room 6 Balancing weight 12 move upward, buoyancy tank room water inlet 7 is opened, buoyancy tank room 6 start water inlet, buoyancy tank room 6 enter full water after buoyancy tank 5 float, drive gate 1 rotarily open, the aquifer reserve pond 2 in downstream start into Water.
When the water level in the aquifer reserve pond 2 in downstream rises to storage pond the highest permission water level, ground is lowered Water in reservoir 2 will enter float chamber 9, and float 11 floats, balancing weight 12 under gravity to Lower motion, closes buoyancy tank room water inlet 7.The water of buoyancy tank room 6 is after buoyancy tank room apopore 8 flows out, floating Case 5 rotates down, and drives gate 1 rotary closing, and the water in aquifer reserve pond 2 is arranged to natural water Put, retentively descend the stable level of storage pond 2.
The above, the only detailed description of the invention of the present invention, but protection scope of the present invention not office Being limited to this, any those of ordinary skill in the art, can be light in the technical scope that disclosed herein The change being readily conceivable that or replacement, all should contain within protection scope of the present invention.Therefore, the present invention Protection domain should be as the criterion with the protection domain that claims are limited.

Claims (10)

1. a pilot-operated type Hydro-automatic gate structure, including the gate being arranged at runner (23) side (1), it is arranged at the buoyancy tank room (6) of runner (23) opposite side and is later than what buoyancy tank room (6) intake Aquifer reserve pond (2);Described gate (1) is fixed on the side of rotating shaft (3), described rotating shaft (3) Opposite side be fixed with buoyancy tank (5), described buoyancy tank (5) is arranged in buoyancy tank room (6);Described turn The two ends of axle (3) are hingedly connected on the flow path wall (4) of runner (23) both sides, described buoyancy tank (5) And for flood discharge passage (24) between the flow path wall (4) of runner (23) side;It is characterized in that: institute Stating and be provided with float chamber (9) in aquifer reserve pond (2), the bottom of described float chamber (9) has current Via, described current via communicates with aquifer reserve pond (2);Described float chamber (9) is provided with floating Son (11);The both sides of the edge of described gate (1) and bottom margin respectively with flood discharge passage (24) Both side surface and bottom fitted seal;The bottom of sidewall towards the buoyancy tank room (6) of water (flow) direction side Having buoyancy tank room water inlet (7), the sidewall bottom of the buoyancy tank room (6) of water (flow) direction side has dorsad Buoyancy tank room apopore (8);Water inlet (7) place, described buoyancy tank room is provided with closure buoyancy tank room water inlet (7) Plugging device, be connected between described plugging device with float (11) and have linkage.
2. a kind of pilot-operated type Hydro-automatic gate structure as claimed in claim 1, it is characterised in that: The current via of described float chamber (9) bottom is float chamber apopore (10), described float chamber (9) The top of side sidewall have float chamber water inlet (20), entering of described float chamber water inlet (20) Water cross section is more than the water outlet cross section of float chamber apopore (10).
3. a kind of pilot-operated type Hydro-automatic gate structure as claimed in claim 2, it is characterised in that: Described float chamber apopore (10) place is provided with check valve of water drainage (25).
4. a kind of pilot-operated type Hydro-automatic gate structure as claimed in claim 1, it is characterised in that: Described plugging device is balancing weight (12), and described linkage includes being arranged at aquifer reserve pond (2) First pulley (13) of top and be arranged at the second pulley (14) above buoyancy tank room (6), described It is connected between float (11) with balancing weight (12) and has steel wire rope (21), described steel wire rope (21) One end connects float (11), and the other end connects join through the first pulley (13), the second pulley (14) Pouring weight (12);The quality of described float (11) is more than the quality of balancing weight (12).
5. a kind of pilot-operated type Hydro-automatic gate structure as claimed in claim 4, it is characterised in that: Described balancing weight (12) is spheroid balancing weight.
6. a kind of pilot-operated type Hydro-automatic gate structure as claimed in claim 1, it is characterised in that: The water inlet cross section of described buoyancy tank room water inlet (7) is more than the water outlet cross section of buoyancy tank room apopore (8).
7. a kind of pilot-operated type Hydro-automatic gate structure as claimed in claim 1, it is characterised in that: The bottom of described flood discharge passage (24) is fixed with seal receptacle (15), the two ends of described seal receptacle (15) It is individually fixed on the side sidewall of buoyancy tank room (6) and the side flow path wall (4) of runner (23); Described seal receptacle (15) and the bottom fitted seal of gate (1), the dual-side of described gate (1) Edge and bottom margin are respectively and fixedly provided with sealing ring (16).
8. a kind of pilot-operated type Hydro-automatic gate structure as claimed in claim 1, it is characterised in that: Described buoyancy tank (5) top has been evenly arranged buoyancy tank fixed plate (18) along its width.
9. a kind of pilot-operated type Hydro-automatic gate structure as claimed in claim 1, it is characterised in that: It is fixedly connected with gate between described gate (1) and rotating shaft (3) and fixes bar (19), described gate (1) On be disposed with many group gates and fix bar assembly, often group gate is fixed bar assembly and is included two locks acutangulated The fixing bar of door (19), described gate is fixed bar assembly and is evenly arranged along the width of gate (1).
10. a kind of pilot-operated type Hydro-automatic gate structure as claimed in claim 1, it is characterised in that: Rotating shaft location-plate (17) it is symmetrically fixed with on the flow path wall (4) of described runner (23) both sides, described Being fixed with bearing in rotating shaft location-plate (17), the two ends of described rotating shaft (3) are arranged in bearing.
CN201510153025.XA 2015-04-02 2015-04-02 A kind of pilot-operated type Hydro-automatic gate structure Active CN104775403B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510153025.XA CN104775403B (en) 2015-04-02 2015-04-02 A kind of pilot-operated type Hydro-automatic gate structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510153025.XA CN104775403B (en) 2015-04-02 2015-04-02 A kind of pilot-operated type Hydro-automatic gate structure

Publications (2)

Publication Number Publication Date
CN104775403A CN104775403A (en) 2015-07-15
CN104775403B true CN104775403B (en) 2017-01-04

Family

ID=53617145

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510153025.XA Active CN104775403B (en) 2015-04-02 2015-04-02 A kind of pilot-operated type Hydro-automatic gate structure

Country Status (1)

Country Link
CN (1) CN104775403B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110244782A (en) * 2019-07-04 2019-09-17 之间万维(北京)水环境技术有限公司 A kind of water quality improvement water level management device and its regulation method
CN113029296B (en) * 2021-03-06 2024-06-18 河南华北水利水电勘察设计有限公司 Reservoir water level automatic regulating system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2463450Y (en) * 2000-09-25 2001-12-05 湖南省韶山灌区工程管理局 Floating pontoon separated hydraulic self-controlling gate
CN2905896Y (en) * 2006-05-24 2007-05-30 江苏润源水务设备有限公司 Float box type automatic gate
CN101012647A (en) * 2007-02-12 2007-08-08 周明泉 Adjustable flotative van batardeau
CN202369971U (en) * 2011-10-26 2012-08-08 肖凯云 Automatic opening and closing gate
CN204608728U (en) * 2015-04-02 2015-09-02 武汉圣禹排水系统有限公司 A kind of pilot-operated type Hydro-automatic gate structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3711502B2 (en) * 2003-01-16 2005-11-02 国土交通省東北地方整備局長 Non-powered automatic standing lodging gate using changes in water level such as weirs

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2463450Y (en) * 2000-09-25 2001-12-05 湖南省韶山灌区工程管理局 Floating pontoon separated hydraulic self-controlling gate
CN2905896Y (en) * 2006-05-24 2007-05-30 江苏润源水务设备有限公司 Float box type automatic gate
CN101012647A (en) * 2007-02-12 2007-08-08 周明泉 Adjustable flotative van batardeau
CN202369971U (en) * 2011-10-26 2012-08-08 肖凯云 Automatic opening and closing gate
CN204608728U (en) * 2015-04-02 2015-09-02 武汉圣禹排水系统有限公司 A kind of pilot-operated type Hydro-automatic gate structure

Also Published As

Publication number Publication date
CN104775403A (en) 2015-07-15

Similar Documents

Publication Publication Date Title
CN104746636B (en) A kind of sense the hydraulic gate structure that water level automatically turns on
CN203200725U (en) Shutter layered semi-automatic gate
CN204608970U (en) A kind of hydraulic gate structure responded to water level and automatically open
CN203755248U (en) Sliding type float blocking device
CN104863253B (en) The axis Hydro-automatic gate that sensing water level automatically turns on
CN105256770B (en) Counterweight-variable and hydraulic power-controllable automatic fixed shaft turning plate gate
CN104775403B (en) A kind of pilot-operated type Hydro-automatic gate structure
CN207715783U (en) The floating control flow regulating valve of one kind
CN104864160B (en) Pilot-operated type axial hydro-automatic gate
CN204664572U (en) Leading type axis Hydro-automatic gate
CN106320284B (en) Double door leaf hydraulic gates that a kind of gravity opens and closes
CN205999861U (en) Double door leaf hydraulic gates that a kind of gravity is opened and closed
CN104878832A (en) Reverse downstream waterpower automatic gate
CN102561273A (en) Self-adjusting water intake device
CN204676690U (en) The axis Hydro-automatic gate that induction water level is opened automatically
CN204608728U (en) A kind of pilot-operated type Hydro-automatic gate structure
CN113882324A (en) A water intake control gate closed by hydraulic automatic control during flood season
CN204491535U (en) Two floating box type upstream controls weir gate device
CN204676691U (en) C type Hydro-automatic gate
CN207348005U (en) A kind of double-screw type water intaking desilting device
CN104863254B (en) C-type Hydro-automatic gate
CN104746637B (en) Intake adjustable for height floating box type upstream controls weir gate
CN104695389B (en) Double floating box type upstreams control weir gate device
CN204608971U (en) Anti counter-flowing Hydro-automatic gate
KR102351926B1 (en) Sluice Gate Apparatus Equipped with Opening/Closing Automatic Gate

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: No. 509 Weihu Road, Shamao Street, Hannan District, Wuhan City, Hubei Province, 430090

Patentee after: Wuhan Shengyu Smart Ecological Environmental Protection Co.,Ltd.

Address before: 430056 zhuanyang science and Technology Industrial Park, Wuhan Economic and Technological Development Zone, Wuhan City, Hubei Province

Patentee before: WUHAN SHENGYU DRAINAGE SYSTEM Co.,Ltd.

CP03 Change of name, title or address