CN104746399A - 防治桥头跳车施工方法 - Google Patents

防治桥头跳车施工方法 Download PDF

Info

Publication number
CN104746399A
CN104746399A CN201510167380.2A CN201510167380A CN104746399A CN 104746399 A CN104746399 A CN 104746399A CN 201510167380 A CN201510167380 A CN 201510167380A CN 104746399 A CN104746399 A CN 104746399A
Authority
CN
China
Prior art keywords
compaction
roadbed
degree
grid
abutment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510167380.2A
Other languages
English (en)
Inventor
成军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510167380.2A priority Critical patent/CN104746399A/zh
Publication of CN104746399A publication Critical patent/CN104746399A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

本发明公开了一种防治桥头跳车施工方法,包括基底处理、修整台阶、回填、土工格栅摊铺、碾压、检测等步骤。本发明采用透水性材料加土工格栅处理桥梁台背回填,既能避免因雨水渗入而导致的路基沉降,也能优化桥台区域对基底的整体受力,能很好的避免“跳车”现象。

Description

防治桥头跳车施工方法
技术领域
本发明涉及一种防治桥头跳车施工方法。
背景技术
在道路、桥梁工程施工中,桥梁台背回填是一项容易被忽视的工作,但却常常是严重影响道路、桥梁使用性能的原因之一。路面施工完成后桥梁结构物与路基连接处出现“台阶”,车辆通过时容易产生腾空现象,工程界通常称为“跳车”,“跳车”的产生有以下一些主要原因:
1、台背后的地物、地貌与其它路段不同,地形起伏大,地质条件不一,容易产生地基沉降。同时,一般桥梁处路基填筑高度较大,产生的基底应力相对较大,因此,在台后填筑地段,产生地基沉降也较其它路段大。路基与台背衔接处,因两种不同结构基底要求的承载力和沉降量不相同,导致了结构物和路基产生不均匀沉陷。
2、路基本身的压缩沉降一般情况,桥台先行施工,待路基形成后,在台背处留一缺口,当对此缺口填筑施工时,由于作业面狭小而使压实度工作不到位,特别是台背后约50~100cm范围内,达到规定的压实度要求有一定的难度,致使该处路基压实质量下降,通车后,因行车荷载反复作用引起该处路基的压缩沉降。
3、路基与桥梁台背接头处,常会产生细小缩裂缝,雨水渗入缝隙后,导致该处路基发生沉降。
总之,“跳车”产生的原因是复杂的、综合性的,其主要原因是与基底处理、填筑材料及施工工艺有密切关系,要解决桥梁台背的工后沉降问题,就必须对基底进行有效处理,并采取正确的施工措施和施工办法。
发明内容
本发明的目的在于提供一种既能避免因雨水渗入而导致的路基沉降,也能优化桥台区域对基底的整体受力,能很好的避免“跳车”现象的防治桥头跳车施工方法。
本发明的技术解决方案是:
一种防治桥头跳车施工方法,其特征是:包括下列步骤:
(1)基底处理
一般路基基底处理使压实度满足设计及规范要求,后进行台背回填;
对软土或者杂填土地基,先进行路基处理或深层路基处理,经检测达到设计指标后,再进行台背回填;
(2)修整台阶
对台背处已填筑了一定高度的路基,沿路线方向进行人工挖台阶;台阶顶宽不小于3m,高度不大于0.5m,台阶处的填土压实度符合路基填土的压实度标准,清理的松土运离施工现场;若台背处路基尚未开始填筑,则台背填筑可与路基填土同步进行;
(3)回填
回填土方时,桥梁台背区域从台后2.9米处开始填筑,将路基连接处修筑成0.6×2m的台阶,按照规定的压实度逐层碾压;
(4)土工格栅摊铺
每填筑高度为0.6m时,在压实层上摊铺钢塑土工格栅;土工格栅必须经过试验达到设计要求后才能使用;铺设按设计要求分层铺设,摊铺方向是将格栅自台背沿路线纵向展开,并按设计长度截断;土工格栅张拉须均匀用力,保证土工格栅的整体性,其纵向采用搭接法连接,搭接长度不小于0.3m,并用高强度的土工棒连接,横断面方向不需搭接,两幅并拢即可;与桥台连接部分采用紧固件锚固,压板采用6mm厚钢板,板宽15cm,钢板上的螺栓孔距板边净距不小于50mm,螺栓采用六角头螺栓M16×100mm,垫圈为A16mm,螺母为M16mm;若桥台与线路斜交,将格栅靠桥台一端截成与斜交角度相同的角度,保证格栅与线路走向平行;
(5)碾压
回填中粗砂时,作业面较小的边角处,采用电动平板夯进行夯实,且每层松铺厚度不大于15cm,采用水冲和振动碾压,先采用水冲,然后再根据作业宽度采用振动夯夯实或振动压路机碾压;台身上部根据回填宽度采用压路机碾压,先用压路机静压一遍,再振动碾压,然后再由中间向两侧碾压;每次碾压错开1/3轮宽,碾压至无明显轮迹时,检测压实度;压实度合格后再进行下一层施工;
(6)检测
台背回填分层填筑、分层检测,压实度采用灌水法或灌砂法进行检测;检测频率按JTGF10-2006执行,并同时满足每层每侧不少于6点,检测点位一般为:中间1点,左右边距离耳墙1m处各1点,或监理工程师指定的点位;检测点离台背的距离分别为30cm和1.5H;
每填一层,碾压一层,检测一层,检查频率每层左、中、右检验三个点,压实度经监理工程师检测合格方可填筑下一层。
本发明采用透水性材料(主要为中粗砂)加土工格栅处理桥梁台背回填,既能避免因雨水渗入而导致的路基沉降,也能优化桥台区域对基底的整体受力,能很好的避免“跳车”现象。
本发明提高了回填土方的整体性,使接触部位的阶梯式沉降变为连续渐变沉降,缓解了后台土方的局部下沉现象,跳车感觉明显降低。
土工格栅化学稳定性可靠,在地下寿命可达几十年,能在整个道路工程设计年限里充分发挥作用。透水性材料的回填,避免了路基因雨水渗入和水土流失而导致的路基沉降。整体技术过程工艺简单,操作方便、施工速度快,工程造价低,施工投入少。适用于路基处于软土地基,及路基处于高填方区域的台背回填。适用于一般桥梁、涵洞台背区域的回填。
下面结合实施例对本发明作进一步说明。
具体实施方式
一种防治桥头跳车施工方法,包括下列步骤:
(1)基底处理
一般路基基底处理使压实度满足设计及规范要求,后进行台背回填;
对软土或者杂填土地基,先进行路基处理或深层路基处理,经检测达到设计指标后,再进行台背回填;
(2)修整台阶
对台背处已填筑了一定高度的路基,沿路线方向进行人工挖台阶;台阶顶宽不小于3m,高度不大于0.5m,台阶处的填土压实度符合路基填土的压实度标准,清理的松土运离施工现场;若台背处路基尚未开始填筑,则台背填筑可与路基填土同步进行;
(3)回填
回填土方时,桥梁台背区域从台后2.9米处开始填筑,将路基连接处修筑成0.6×2m的台阶,按照规定的压实度逐层碾压;
(4)土工格栅摊铺
每填筑高度为0.6m时,在压实层上摊铺钢塑土工格栅;土工格栅必须经过试验达到设计要求后才能使用;铺设按设计要求分层铺设,摊铺方向是将格栅自台背沿路线纵向展开,并按设计长度截断;土工格栅张拉须均匀用力,保证土工格栅的整体性,其纵向采用搭接法连接,搭接长度不小于0.3m,并用高强度的土工棒连接,横断面方向不需搭接,两幅并拢即可;与桥台连接部分采用紧固件锚固,压板采用6mm厚钢板,板宽15cm,钢板上的螺栓孔距板边净距不小于50mm,螺栓采用六角头螺栓M16×100mm,垫圈为A16mm,螺母为M16mm;若桥台与线路斜交,将格栅靠桥台一端截成与斜交角度相同的角度,保证格栅与线路走向平行;
(5)碾压
回填中粗砂时,作业面较小的边角处,采用电动平板夯进行夯实,且每层松铺厚度不大于15cm,采用水冲和振动碾压,先采用水冲,然后再根据作业宽度采用振动夯夯实或振动压路机碾压;台身上部根据回填宽度采用压路机碾压,先用压路机静压一遍,再振动碾压,然后再由中间向两侧碾压;每次碾压错开1/3轮宽,碾压至无明显轮迹时,检测压实度;压实度合格后再进行下一层施工;
(6)检测
台背回填分层填筑、分层检测,压实度采用灌水法或灌砂法进行检测;检测频率按JTGF10-2006执行,并同时满足每层每侧不少于6点,检测点位一般为:中间1点,左右边距离耳墙1m处各1点,或监理工程师指定的点位;检测点离台背的距离分别为30cm和1.5H;
每填一层,碾压一层,检测一层,检查频率每层左、中、右检验三个点,压实度经监理工程师检测合格方可填筑下一层。

Claims (1)

1.一种防治桥头跳车施工方法,其特征是:包括下列步骤:
(1)基底处理
一般路基基底处理使压实度满足设计及规范要求,后进行台背回填;
对软土或者杂填土地基,先进行路基处理或深层路基处理,经检测达到设计指标后,再进行台背回填;
(2)修整台阶
对台背处已填筑了一定高度的路基,沿路线方向进行人工挖台阶;台阶顶宽不小于3m,高度不大于0.5m,台阶处的填土压实度符合路基填土的压实度标准,清理的松土运离施工现场;若台背处路基尚未开始填筑,则台背填筑可与路基填土同步进行;
(3)回填
回填土方时,桥梁台背区域从台后2.9米处开始填筑,将路基连接处修筑成0.6×2m的台阶,按照规定的压实度逐层碾压;
(4)土工格栅摊铺
每填筑高度为0.6m时,在压实层上摊铺钢塑土工格栅;土工格栅必须经过试验达到设计要求后才能使用;铺设按设计要求分层铺设,摊铺方向是将格栅自台背沿路线纵向展开,并按设计长度截断;土工格栅张拉须均匀用力,保证土工格栅的整体性,其纵向采用搭接法连接,搭接长度不小于0.3m,并用高强度的土工棒连接,横断面方向不需搭接,两幅并拢即可;与桥台连接部分采用紧固件锚固,压板采用6mm厚钢板,板宽15cm,钢板上的螺栓孔距板边净距不小于50mm,螺栓采用六角头螺栓M16×100mm,垫圈为A16mm,螺母为M16mm;若桥台与线路斜交,将格栅靠桥台一端截成与斜交角度相同的角度,保证格栅与线路走向平行;
(5)碾压
回填中粗砂时,作业面较小的边角处,采用电动平板夯进行夯实,且每层松铺厚度不大于15cm,采用水冲和振动碾压,先采用水冲,然后再根据作业宽度采用振动夯夯实或振动压路机碾压;台身上部根据回填宽度采用压路机碾压,先用压路机静压一遍,再振动碾压,然后再由中间向两侧碾压;每次碾压错开1/3轮宽,碾压至无明显轮迹时,检测压实度;压实度合格后再进行下一层施工;
(6)检测
台背回填分层填筑、分层检测,压实度采用灌水法或灌砂法进行检测;检测频率按JTGF10-2006执行,并同时满足每层每侧不少于6点,检测点位一般为:中间1点,左右边距离耳墙1m处各1点,或监理工程师指定的点位;检测点离台背的距离分别为30cm和1.5H;
每填一层,碾压一层,检测一层,检查频率每层左、中、右检验三个点,压实度经监理工程师检测合格方可填筑下一层。
CN201510167380.2A 2015-04-10 2015-04-10 防治桥头跳车施工方法 Pending CN104746399A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510167380.2A CN104746399A (zh) 2015-04-10 2015-04-10 防治桥头跳车施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510167380.2A CN104746399A (zh) 2015-04-10 2015-04-10 防治桥头跳车施工方法

Publications (1)

Publication Number Publication Date
CN104746399A true CN104746399A (zh) 2015-07-01

Family

ID=53586604

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510167380.2A Pending CN104746399A (zh) 2015-04-10 2015-04-10 防治桥头跳车施工方法

Country Status (1)

Country Link
CN (1) CN104746399A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105016770A (zh) * 2015-07-09 2015-11-04 河南华泰建材开发有限公司 一种桥梁减跨的方法及专用桥梁减跨回填材料
CN106087758A (zh) * 2016-08-06 2016-11-09 桂林理工大学 一种用于减缓桥头跳车的路桥连接结构的施工方法
CN107542016A (zh) * 2017-08-09 2018-01-05 中铁四局集团第工程有限公司 一种控制路基差异沉降的填筑方法
CN110792009A (zh) * 2019-10-17 2020-02-14 龙德建设有限公司 一种基于混凝土复合式路面的桥头跳车防治结构及其铺设方法
CN112095468A (zh) * 2020-05-09 2020-12-18 如皋市规划建筑设计院有限公司 一种桥台高填土方法
CN117364799A (zh) * 2023-10-07 2024-01-09 保利长大工程有限公司 台背回填标准化施工工法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003239276A (ja) * 2003-01-23 2003-08-27 Dia Consultant:Kk 道路の構築工法
CN103572679A (zh) * 2013-11-13 2014-02-12 河海大学 一种降低桥头跳车发生率的路堤结构及填筑方法
CN103741595A (zh) * 2014-01-21 2014-04-23 浙江省交通规划设计研究院 一种用于治理桥头跳车的桥头结构

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003239276A (ja) * 2003-01-23 2003-08-27 Dia Consultant:Kk 道路の構築工法
CN103572679A (zh) * 2013-11-13 2014-02-12 河海大学 一种降低桥头跳车发生率的路堤结构及填筑方法
CN103741595A (zh) * 2014-01-21 2014-04-23 浙江省交通规划设计研究院 一种用于治理桥头跳车的桥头结构

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《公路工程施工组织设计实例应用手册》编写委员会: "《公路工程施工组织设计实例应用手册》", 31 October 2011, 中国建筑工业出版社 *
侯晓莉: "特殊地段路基施工分析", 《西部探矿工程》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105016770A (zh) * 2015-07-09 2015-11-04 河南华泰建材开发有限公司 一种桥梁减跨的方法及专用桥梁减跨回填材料
CN106087758A (zh) * 2016-08-06 2016-11-09 桂林理工大学 一种用于减缓桥头跳车的路桥连接结构的施工方法
CN107542016A (zh) * 2017-08-09 2018-01-05 中铁四局集团第工程有限公司 一种控制路基差异沉降的填筑方法
CN110792009A (zh) * 2019-10-17 2020-02-14 龙德建设有限公司 一种基于混凝土复合式路面的桥头跳车防治结构及其铺设方法
CN112095468A (zh) * 2020-05-09 2020-12-18 如皋市规划建筑设计院有限公司 一种桥台高填土方法
CN117364799A (zh) * 2023-10-07 2024-01-09 保利长大工程有限公司 台背回填标准化施工工法

Similar Documents

Publication Publication Date Title
CN104746399A (zh) 防治桥头跳车施工方法
US20140314497A1 (en) Polymer grouting method for constructing gravel pile
CN102359046A (zh) 一种高填方路基拼接方法
CN103711056B (zh) 钢质工具式临时施工道路及其施工方法
CN101311418A (zh) 深基坑、大面积设备基础换填方法
CN203462484U (zh) 一种既有挡土墙补强结构
CN109914173A (zh) 高速公路改扩建工程中泡沫轻质土浇筑台背结构及其施工方法
CN106592608A (zh) 一种地下综合管廊新地基与老路基差异沉降控制方法
CN113802426A (zh) 采用片石挤密加筋垫层法处理新近填土路基的方法
CN104179105A (zh) 一种逆作法刚性桩复合地基施工方法
CN202849895U (zh) 一种城市沥青路面修复结构
CN102817298B (zh) 一种在冻土上的施工方法
CN104695419A (zh) 一种软土土基的施工方法
CN102296591A (zh) 一种软土基的快速排水固结处理方法
CN203960701U (zh) 软土路基新老路基路面衔接处的差异沉降协调结构
CN111576487A (zh) 一种地下工程基础底板结构及其施工方法
CN110792009A (zh) 一种基于混凝土复合式路面的桥头跳车防治结构及其铺设方法
CN102635044B (zh) 一种强夯对路床挖方路基的处理方法
CN100365210C (zh) 定位夯实路基施工方法
CN102817352B (zh) 高含水率可液化土地基冲击碾压施工工法
CN211340257U (zh) 一种涵洞台背路基加固结构
CN110438855B (zh) 一种下穿铁路桥涵道床回填的施工方法
CN111041918A (zh) 一种路堤拓宽方法
CN203144858U (zh) 一种已通车公路路基沉降控制结构
CN207228090U (zh) 软土地区铁路车站站台沉降置换修复结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150701

RJ01 Rejection of invention patent application after publication