CN104728899B - Hot blast and electric additional hot mixing formula heat exchanger - Google Patents

Hot blast and electric additional hot mixing formula heat exchanger Download PDF

Info

Publication number
CN104728899B
CN104728899B CN201510108057.8A CN201510108057A CN104728899B CN 104728899 B CN104728899 B CN 104728899B CN 201510108057 A CN201510108057 A CN 201510108057A CN 104728899 B CN104728899 B CN 104728899B
Authority
CN
China
Prior art keywords
heat exchange
exchange body
heating
air
electric
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510108057.8A
Other languages
Chinese (zh)
Other versions
CN104728899A (en
Inventor
李安平
赵庆杞
郭振伟
姜立兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
STATE GRID LIAONING ENERGY SAVING SERVICES Co Ltd
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Liaoning Electric Power Co Ltd
Northeastern University China
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510108057.8A priority Critical patent/CN104728899B/en
Publication of CN104728899A publication Critical patent/CN104728899A/en
Application granted granted Critical
Publication of CN104728899B publication Critical patent/CN104728899B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Heat-Pump Type And Storage Water Heaters (AREA)
  • Cleaning Of Streets, Tracks, Or Beaches (AREA)

Abstract

本发明属于供热系统的技术领域,尤其涉及一种热风与电辅加热混合式换热器,具体是由热风与电辅助加热方式组合在一起的流体换热器,是在金属壳体内焊接和组装由热风道、水管路及电加热管等元器件组成的一种换热器。包括高温热风道、风管束组、水内胆与电辅助加热管组。本发明采用由热风与电辅助加热方式组合在一起的流体换热器,可以实现蓄热锅炉当余热量不足时,利用电力进行辅助快速加热的直热方式配合供热,且在连续供热要求的环境下,利用谷时段蓄热炉蓄热的同时,用辅助直热电加热供暖。这种混合式制热方法,有效地解决了电蓄热式锅炉的硬伤缺陷。配套生产这种换热器为电蓄热式锅炉大量推广应用创造有利条件。市场远景良好,经济效益可观。

The invention belongs to the technical field of heating systems, and in particular relates to a hot air and electric auxiliary heating hybrid heat exchanger, specifically a fluid heat exchanger combined with hot air and electric auxiliary heating, which is welded and welded in a metal shell. Assemble a heat exchanger composed of components such as hot air ducts, water pipes, and electric heating pipes. Including high-temperature hot air duct, air duct bundle, water liner and electric auxiliary heating tube group. The present invention adopts a fluid heat exchanger combined with hot air and electric auxiliary heating, which can realize the direct heating method of assisting rapid heating with electric power when the waste heat of the regenerative boiler is insufficient. In an environment where the heat is stored in the regenerative furnace during the off-peak period, the auxiliary direct thermal electric heating is used for heating. This hybrid heating method effectively solves the defects of electric heat storage boilers. The supporting production of this kind of heat exchanger creates favorable conditions for the large-scale popularization and application of electric heat storage boilers. The market prospect is good and the economic benefits are considerable.

Description

热风与电辅加热混合式换热器Hot air and electric auxiliary heating hybrid heat exchanger

技术领域technical field

本发明属于供热系统的技术领域,尤其涉及一种热风与电辅加热混合式换热器,具体是由热风与电辅助加热方式组合在一起的流体换热器,是在金属壳体内焊接和组装由热风道、水管路及电加热管等元器件组成的一种换热器。The invention belongs to the technical field of heating systems, and in particular relates to a hot air and electric auxiliary heating hybrid heat exchanger, specifically a fluid heat exchanger combined with hot air and electric auxiliary heating, which is welded and welded in a metal shell. Assemble a heat exchanger composed of components such as hot air ducts, water pipes, and electric heating pipes.

背景技术Background technique

目前在国内城乡、工厂及企事业单位使用的锅炉房或换热站,基本都是采用燃煤制热蒸汽和水暖锅炉、燃油制热蒸汽和水暖锅炉、电直热水暖锅炉、电蓄热蒸汽和水暖锅炉等几种方式。燃煤、燃油制热污染环境且资源日渐枯竭,中小型锅炉被逐渐取缔。直热式电锅炉耗电量大,制热成本高,一般单位使用不起。At present, the boiler rooms or heat exchange stations used in urban and rural areas, factories, enterprises and institutions in China basically use coal-fired heating steam and water heating boilers, oil heating steam and water heating boilers, electric direct water heating boilers, electric heat storage Several ways such as steam and water heating boilers. Coal-burning and oil-fired heating pollute the environment and resources are increasingly exhausted, and small and medium-sized boilers are gradually banned. The direct heating electric boiler consumes a lot of electricity and has high heating costs, so it cannot be used by ordinary units.

现代新兴的电蓄热式锅炉采用谷时段低价电蓄热,峰或平时段(高价或平价电)放热生产热水、热风、热油或蒸汽。但谷电时间有限,一般在7个小时,所蓄之热能量随放热时间延长(24小时)逐渐减弱,满足不了供热需求,供暖系统温度难以达标,所以推广迟缓,效果不好。Modern emerging electric heat storage boilers use low-priced electricity to store heat during valley hours, and release heat to produce hot water, hot air, hot oil or steam during peak or normal hours (high-priced or cheap electricity). However, the off-peak power time is limited, generally 7 hours, and the stored thermal energy gradually weakens with the extension of the heat release time (24 hours), which cannot meet the heating demand, and the temperature of the heating system is difficult to meet the standard, so the promotion is slow and the effect is not good.

发明内容Contents of the invention

为了解决上述现有技术存在的技术问题,本发明提供一种热风与电辅加热混合式换热器。目的是为了提供一种混合式制热方法,有效地解决电蓄热式锅炉的无法保证连续供热的硬伤缺陷问题。In order to solve the above-mentioned technical problems in the prior art, the present invention provides a hybrid heat exchanger of hot air and electric auxiliary heating. The purpose of the invention is to provide a hybrid heating method, which can effectively solve the flaw problem that the electric heat storage boiler cannot guarantee continuous heating.

本发明实现发明的技术方案如下:The present invention realizes the technical scheme of invention as follows:

热风与电辅加热混合式换热器,包括高温热风道、风管束组、水内胆与电辅助加热管组;在换热体的上部设有进风道箱,换热体的下部设有出风道箱,换热体部连接的伸缩节将换热体分为上下两部分;所述的进风道箱上连接有进风道口和进风道温度传感器;所述的换热体的内部包括:水内胆、风管路束及辅助加热丝组;换热体的一侧连接辅助加热丝组,辅助加热丝组横向穿入在换热体的水内胆中;换热体内连接有风管路束;换热体的上部连接有安全阀和出水管,出水管上连接有出水管温度传感器;换热体下部连接有回水管和排污阀;其中回水管上连接有回水管温度传感器,回水管和回水管温度传感器之间连接回水管流量计。Hot air and electric auxiliary heating hybrid heat exchanger, including high-temperature hot air passage, air pipe bundle group, water liner and electric auxiliary heating pipe group; the upper part of the heat exchange body is equipped with an air inlet box, and the lower part of the heat exchange body is equipped with The expansion joint connected to the air outlet box and the heat exchange body divides the heat exchange body into upper and lower parts; the air inlet box is connected with an air inlet port and an air inlet temperature sensor; the heat exchange body The interior includes: water liner, air duct bundle and auxiliary heating wire group; one side of the heat exchange body is connected to the auxiliary heating wire group, and the auxiliary heating wire group penetrates horizontally into the water liner of the heat exchange body; the heat exchange body is connected There is an air pipe bundle; the upper part of the heat exchange body is connected with a safety valve and an outlet pipe, and the outlet pipe is connected with a temperature sensor of the outlet pipe; the lower part of the heat exchange body is connected with a return pipe and a drain valve; the return pipe is connected with a return pipe temperature sensor. The sensor is connected to the return pipe flow meter between the return pipe and the return pipe temperature sensor.

所述的换热体内侧的上下两端分别设有管焊接板,管焊接板上设有多个孔,两块管焊接板上的孔与风管路束中的金属管两端相密闭连接;风管路束的金属管外侧与两块管焊接板及换热体壳内壁组成密闭水内胆。The upper and lower ends of the inner side of the heat exchange body are respectively provided with tube welding plates, and the tube welding plates are provided with a plurality of holes, and the holes on the two tube welding plates are airtightly connected with the two ends of the metal tubes in the air duct bundle The outer side of the metal tube of the air duct bundle, the two tube welding plates and the inner wall of the heat exchange body shell form a sealed water liner.

所述的水内胆中间穿入辅助加热丝组,辅助加热丝组的接线柱与换热体密闭连接。The middle of the water liner penetrates the auxiliary heating wire group, and the terminal of the auxiliary heating wire group is airtightly connected with the heat exchange body.

所述的换热体和出风道箱通过出风道箱与换热体法兰相连接;出风道箱的底部连接有出风道口,出风道口连接变频风机D;出风道口上还连接有出风道温度传感器。The heat exchange body and the air outlet box are connected to the flange of the heat exchange body through the air outlet box; the bottom of the air outlet box is connected to an air outlet, and the air outlet is connected to the frequency conversion fan D; Connected to the air outlet temperature sensor.

所述的辅助加热丝组设有8组。There are 8 groups of auxiliary heating wire groups.

本发明的优点效果是:Advantageous effect of the present invention is:

采用由热风与电辅助加热方式组合在一起的流体换热器,可以实现蓄热锅炉当余热量不足时,利用电力进行辅助快速加热的直热方式配合供热,且在连续供热要求的环境下,利用谷时段蓄热炉蓄热的同时,用辅助直热电加热供暖。这种混合式制热方法,有效地解决了电蓄热式锅炉的硬伤缺陷。配套生产这种换热器为电蓄热式锅炉大量推广应用创造有利条件。市场远景良好,经济效益可观。是将来电力供热工程必选方案之一。Using a fluid heat exchanger combined with hot air and electric auxiliary heating can realize the direct heating method of using electric power to assist rapid heating when the waste heat of the regenerative boiler is insufficient, and it can be used in an environment that requires continuous heating. Next, while using the regenerative furnace to store heat during the valley period, the auxiliary direct heating electric heating is used for heating. This hybrid heating method effectively solves the defects of electric heat storage boilers. The supporting production of this kind of heat exchanger creates favorable conditions for the large-scale popularization and application of electric heat storage boilers. The market prospect is good and the economic benefits are considerable. It is one of the must-choice schemes for power heating projects in the future.

附图说明Description of drawings

图1是本发明的原理图;Fig. 1 is a schematic diagram of the present invention;

图2是本发明的立体图;Fig. 2 is a perspective view of the present invention;

图3是本发明的结构示意图;Fig. 3 is a structural representation of the present invention;

图4是图3的俯视图;Fig. 4 is the top view of Fig. 3;

图5是图4的剖面示意图;Fig. 5 is a schematic cross-sectional view of Fig. 4;

图6是图3的剖面图;Fig. 6 is the sectional view of Fig. 3;

图7是本发明中辅助电力加热丝结构示意图;Fig. 7 is a schematic diagram of the structure of the auxiliary electric heating wire in the present invention;

图8是图7的左视图;Fig. 8 is the left view of Fig. 7;

图9是图8的剖面图;Fig. 9 is a sectional view of Fig. 8;

图10是图7的右视图;Fig. 10 is the right view of Fig. 7;

图11是图4的剖面图。FIG. 11 is a sectional view of FIG. 4 .

图中:进风道箱1,进风道口2、进风道温度传感器3,法兰4,换热体5,伸缩节6,出风道箱7,出风道箱与换热体法兰8,出风道口9,辅助加热丝组10,出水管11,出水管温度传感器12,回水管流量计13,回水管温度传感器14,出风道温度传感器15,回水管16,安全阀17,排污阀18,风管路束19,水内胆20,管焊接板21;蓄热锅炉蓄热体A,换热器B,变频风机D,上风道热风F1,下风道热风F2,上供暖热水系统循环水S1,下供暖热水系统循环水S2。In the figure: air inlet box 1, air inlet port 2, air inlet temperature sensor 3, flange 4, heat exchange body 5, expansion joint 6, air outlet box 7, air outlet box and heat exchange body flange 8. Air outlet port 9, auxiliary heating wire group 10, outlet pipe 11, outlet pipe temperature sensor 12, return pipe flowmeter 13, return pipe temperature sensor 14, air outlet temperature sensor 15, return pipe 16, safety valve 17, Sewage valve 18, air pipe bundle 19, water liner 20, pipe welding plate 21; regenerative boiler regenerator A, heat exchanger B, frequency conversion fan D, upper air passage hot air F1, lower air passage hot air F2, upper heating heat Circulating water S1 of the water system, circulating water S2 of the heating and hot water system.

具体实施方式detailed description

本发明是一种热风与电辅加热混合式换热器。具体是将高温热风道、风管束组、水内胆与电辅助加热管组四种元器件交互连接设计在一台金属换热器壳体中,如图1-图11所示。The invention is a hot air and electric auxiliary heating hybrid heat exchanger. Specifically, the four components of the high-temperature hot air duct, the air tube bundle, the water liner and the electric auxiliary heating tube group are designed to be interactively connected in a metal heat exchanger shell, as shown in Figures 1-11.

热风进入进风道口2中,进风道口2连接进风道箱1,同时进风道口2还连接进风道温度传感器3。进风道箱1通过法兰4与换热体5上部连接;换热体5中间部分焊接伸缩节6调节换热体受热膨胀量。换热体5的上部连接出水管11,出水管11上连接有出水管温度传感器12。换热体5上部还连接有安全阀17。换热体5下部连接回水管16,回水管16上接有回水管温度传感器14,回水管口和回水管温度传感器14之间连接回水管流量计13。 换热体5下部还连接排污阀18。所述的换热体5包括:水内胆、风管路束及辅助加热丝组。The hot air enters the air inlet opening 2, and the air inlet opening 2 is connected to the air inlet box 1, and meanwhile, the air inlet opening 2 is also connected to the air inlet temperature sensor 3. The air inlet channel box 1 is connected to the upper part of the heat exchange body 5 through the flange 4; the middle part of the heat exchange body 5 is welded with an expansion joint 6 to adjust the thermal expansion of the heat exchange body. The upper part of the heat exchange body 5 is connected with a water outlet pipe 11 , and a water outlet pipe temperature sensor 12 is connected with the water outlet pipe 11 . A safety valve 17 is also connected to the upper part of the heat exchange body 5 . The lower part of the heat exchange body 5 is connected with a return pipe 16 , the return pipe 16 is connected with a return pipe temperature sensor 14 , and a return pipe flowmeter 13 is connected between the return pipe mouth and the return pipe temperature sensor 14 . The lower part of the heat exchange body 5 is also connected to a drain valve 18 . The heat exchange body 5 includes: a water liner, an air duct bundle and an auxiliary heating wire group.

换热体5和出风道箱7通过出风道箱与换热体法兰8相连接;出风道箱7的底部连接有出风道口9,出风道口9连接变频风机D。出风道口9上还连接有出风道温度传感器15。The heat exchange body 5 and the air outlet box 7 are connected with the heat exchange body flange 8 through the air outlet box; An air outlet temperature sensor 15 is also connected to the air outlet opening 9 .

换热体5的一侧连接辅助加热丝组10,辅助加热丝组10横向穿入换热体5的水内胆20中。One side of the heat exchange body 5 is connected with an auxiliary heating wire group 10 , and the auxiliary heating wire group 10 penetrates laterally into the water liner 20 of the heat exchange body 5 .

换热体5内部结构为:换热体5内侧的上下两端分别焊有管焊接板21,管焊接板21面上有300多个孔,两块管焊接板21上的孔与风管道路束19中所有约300余根金属管,两端外沿焊接,需要密闭,承压,不能漏水。风管路束19的金属管内壁通过热风;风管路束19的金属管外侧与两块管焊接板21及换热体5壳内壁组成密闭水内胆20。The internal structure of the heat exchange body 5 is: the upper and lower ends of the inner side of the heat exchange body 5 are respectively welded with tube welding plates 21, and there are more than 300 holes on the surface of the tube welding plates 21, and the holes on the two tube welding plates 21 are connected with the air duct road. All about 300 metal tubes in beam 19 are welded on the outer edges of both ends, and need to be airtight, pressure-bearing, and water-tight. The inner wall of the metal tube of the air duct bundle 19 passes hot air; the outer side of the metal tube of the air duct bundle 19 forms an airtight water liner 20 with two tube welding plates 21 and the inner wall of the heat exchange body 5 shell.

换热体5水内胆20中间留有安装电加热丝组的空间,可以穿入8组辅助加热丝组10,8组辅助加热丝组10接线柱应与换热体5密闭,不能漏水。 热风与辅助电加热同时启用,也可以交替使用。In the middle of the heat exchange body 5 water liner 20, there is a space for installing the electric heating wire group, and 8 groups of auxiliary heating wire groups 10 can be penetrated. Hot air and auxiliary electric heating are enabled at the same time, and can also be used alternately.

本发明的工作原理如下:The working principle of the present invention is as follows:

如图1所示,蓄热锅炉蓄热体A,换热器B,变频风机D,上风道热风F1和下风道热风F2,供暖热水系统循环水S1和供暖热水系统循环水S2。利用谷时段将蓄热锅炉蓄热体A蓄热至500℃以上。此时,在蓄热锅炉蓄热体A蓄热时,用辅助电加热换热器B。在供热时,启动变频风机D在蓄热锅炉蓄热体A与换热器B之间送风,在换热器B内的上风道热风F1和下风道热风F2内的高温热风与供暖热水系统循环水S1和供暖热水系统循环水S2进行热交换,实现供暖。As shown in Figure 1, heat storage boiler heat storage body A, heat exchanger B, frequency conversion fan D, hot air in the upper air passage F1 and hot air in the lower air passage F2, circulating water S1 and S2 of the heating hot water system. Use the off-peak period to store heat in the heat storage body A of the heat storage boiler to above 500°C. At this time, when the heat storage body A of the heat storage boiler is storing heat, the heat exchanger B is heated with auxiliary electricity. When heating, start the frequency conversion fan D to blow air between the heat storage body A of the heat storage boiler and the heat exchanger B. The circulating water S1 of the water system and the circulating water S2 of the heating hot water system perform heat exchange to realize heating.

对于换热器来讲是:通过高温热风把水加热产生热水或蒸汽,是由换热器来实现能量转换的。换热器内胆纵向列排几百根不锈钢管或紫铜管作为风管路束19,用管焊接板连接固定在壳体内,风管路束19外侧与壳体连接密闭形成水内胆。又从换热器中间横向插入8组电加热管即辅助加热丝组10,穿在水胆里作为辅助加热器。首先,从回水管16流入低温水灌满水内胆,从出水管11流出热水进入供暖系统管道。电蓄热锅炉的热量用变频风机在密闭风道循环,产生高温热风送入换热器顶部进风道,进入风管路束19的几百根金属管中,被水内胆20中循环水吸热后带走热量,降温的热风经过底部回风道返回到电蓄热锅炉。并通过调频控制热风量的大小来调节出水温度。For the heat exchanger, it is: the water is heated by high-temperature hot air to generate hot water or steam, and the energy conversion is realized by the heat exchanger. Hundreds of stainless steel tubes or red copper tubes are arranged vertically in the inner tank of the heat exchanger as the air duct bundle 19, which are connected and fixed in the shell with tube welding plates, and the outside of the air duct bundle 19 is connected and sealed with the shell to form a water inner tank. Transversely insert 8 groups of electric heating tubes and auxiliary heating wire groups 10 from the middle of the heat exchanger again, and wear them in the water bladder as auxiliary heaters. First, low-temperature water flows in from the return pipe 16 to fill the water inner tank, and hot water flows out from the water outlet pipe 11 to enter the heating system pipe. The heat of the electric heat storage boiler is circulated in the closed air duct by the frequency conversion fan, and the high-temperature hot air is sent to the air intake duct on the top of the heat exchanger, and enters the hundreds of metal tubes in the air duct bundle 19, and is circulated by the water liner 20. After absorbing heat, it takes away the heat, and the cooled hot air returns to the electric heat storage boiler through the bottom return air duct. And through the frequency modulation to control the size of the hot air volume to adjust the outlet water temperature.

Claims (1)

1.热风与电辅加热混合式换热器,其特征是:包括高温热风道、风管束组、水内胆与电辅助加热管组;1. Hot air and electric auxiliary heating hybrid heat exchanger, which is characterized by: including high temperature hot air duct, air pipe bundle group, water liner and electric auxiliary heating pipe group; 在换热体(5)的上部设有进风道箱(1),换热体(5)的下部设有出风道箱(7),换热体(5)中部连接的伸缩节(6)将换热体(5)分为上下两部分;所述的进风道箱(1)上连接有进风道口(2)和进风道温度传感器(3);The upper part of the heat exchange body (5) is provided with an air inlet channel box (1), the lower part of the heat exchange body (5) is provided with an air outlet channel box (7), and the expansion joint (6) connected to the middle part of the heat exchange body (5) ) dividing the heat exchange body (5) into upper and lower parts; the air inlet box (1) is connected with an air inlet port (2) and an air inlet temperature sensor (3); 所述的换热体(5)的内部包括:水内胆(20)、风管路束(19)及辅助加热丝组(10);换热体(5)的一侧连接辅助加热丝组(10),辅助加热丝组(10)横向穿入在换热体(5)的水内胆(20)中;换热体(5)内连接有风管路束(19);The interior of the heat exchange body (5) includes: a water liner (20), an air duct bundle (19) and an auxiliary heating wire group (10); one side of the heat exchange body (5) is connected to the auxiliary heating wire group (10), the auxiliary heating wire group (10) penetrates laterally into the water liner (20) of the heat exchange body (5); the heat exchange body (5) is connected with an air duct bundle (19); 换热体(5)的上部连接有安全阀(17)和出水管(11),出水管(11)上连接有出水管温度传感器(12);换热体(5)下部连接有回水管(16)和排污阀(18);其中回水管(16)上连接有回水管温度传感器(14),回水管(16)和回水管温度传感器(14)之间连接回水管流量计(13);The upper part of the heat exchange body (5) is connected with a safety valve (17) and an outlet pipe (11), and the outlet pipe (11) is connected with an outlet pipe temperature sensor (12); the lower part of the heat exchange body (5) is connected with a return pipe ( 16) and drain valve (18); wherein the return pipe (16) is connected with a return pipe temperature sensor (14), and the return pipe flowmeter (13) is connected between the return pipe (16) and the return pipe temperature sensor (14); 所述的换热体(5)内侧的上下两端分别设有管焊接板(21),管焊接板(21)上设有多个孔,两块管焊接板(21)上的孔与风管路束(19)中的金属管两端相密闭连接;风管路束(19)的金属管外侧与两块管焊接板(21)及换热体(5)壳内壁组成密闭水内胆(20);The upper and lower ends of the inner side of the heat exchange body (5) are respectively provided with tube welding plates (21), and a plurality of holes are arranged on the tube welding plates (21). The two ends of the metal tubes in the tube bundle (19) are airtightly connected; the outer side of the metal tube of the air tube bundle (19), two tube welding plates (21) and the inner wall of the heat exchange body (5) shell form an airtight water liner (20); 所述的水内胆(20)中间穿入辅助加热丝组(10),辅助加热丝组(10)的接线柱与换热体(5)密闭连接;The auxiliary heating wire group (10) penetrates through the middle of the water liner (20), and the terminal of the auxiliary heating wire group (10) is airtightly connected with the heat exchange body (5); 所述的换热体(5)和出风道箱(7)通过出风道箱与换热体法兰(8)相连接;出风道箱(7)的底部连接有出风道口(9),出风道口(9)连接变频风机D;出风道口(9)上还连接有出风道温度传感器(15);The heat exchange body (5) and the air outlet box (7) are connected with the heat exchange body flange (8) through the air outlet box; the bottom of the air outlet box (7) is connected with an air outlet (9 ), the air outlet port (9) is connected to the frequency conversion fan D; the air outlet port (9) is also connected with an air outlet temperature sensor (15); 所述的辅助加热丝组(10)设有8组。There are 8 groups of auxiliary heating wire groups (10).
CN201510108057.8A 2015-03-12 2015-03-12 Hot blast and electric additional hot mixing formula heat exchanger Expired - Fee Related CN104728899B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510108057.8A CN104728899B (en) 2015-03-12 2015-03-12 Hot blast and electric additional hot mixing formula heat exchanger

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510108057.8A CN104728899B (en) 2015-03-12 2015-03-12 Hot blast and electric additional hot mixing formula heat exchanger

Publications (2)

Publication Number Publication Date
CN104728899A CN104728899A (en) 2015-06-24
CN104728899B true CN104728899B (en) 2017-11-07

Family

ID=53453050

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510108057.8A Expired - Fee Related CN104728899B (en) 2015-03-12 2015-03-12 Hot blast and electric additional hot mixing formula heat exchanger

Country Status (1)

Country Link
CN (1) CN104728899B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106931643A (en) * 2015-12-30 2017-07-07 沈阳兰昊新能源科技有限公司 Portable electricity accumulation of energy hot air boiler
CN106931642A (en) * 2015-12-30 2017-07-07 沈阳兰昊新能源科技有限公司 Biomass fuel heat accumulating type hot air boiler
CN107289622A (en) * 2017-08-11 2017-10-24 安徽科海压缩机制造有限公司 A kind of heated by natural gas device for being capable of temperature control
CN110500782A (en) * 2019-10-08 2019-11-26 沈阳工程学院 Arrangement scheme of electric heating power of solid electric heat storage boiler device
CN111023229A (en) * 2019-11-19 2020-04-17 中科凯瑞新能源有限公司 Complementary type solid electric heat storage unit

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2275701Y (en) * 1996-09-13 1998-03-04 张玉斌 Dual-purpose water heater using solar energy or electric heating
CN202002315U (en) * 2011-03-21 2011-10-05 石家庄华安热能科技有限公司 Self-energy-storage electric boiler
CN202133111U (en) * 2011-07-19 2012-02-01 朱杰 Closed hot-air circulation high-temperature solid heat-accumulation electric water heater unit
GB2500735A (en) * 2012-03-26 2013-10-02 Basic Holdings Hot liquid cylinder having a controller arranged to communicate with a remote operator
CN204574199U (en) * 2015-03-12 2015-08-19 李安平 Hot blast and the additional hot direct contact heat exchanger of electricity

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2275701Y (en) * 1996-09-13 1998-03-04 张玉斌 Dual-purpose water heater using solar energy or electric heating
CN202002315U (en) * 2011-03-21 2011-10-05 石家庄华安热能科技有限公司 Self-energy-storage electric boiler
CN202133111U (en) * 2011-07-19 2012-02-01 朱杰 Closed hot-air circulation high-temperature solid heat-accumulation electric water heater unit
GB2500735A (en) * 2012-03-26 2013-10-02 Basic Holdings Hot liquid cylinder having a controller arranged to communicate with a remote operator
CN204574199U (en) * 2015-03-12 2015-08-19 李安平 Hot blast and the additional hot direct contact heat exchanger of electricity

Also Published As

Publication number Publication date
CN104728899A (en) 2015-06-24

Similar Documents

Publication Publication Date Title
CN104728899B (en) Hot blast and electric additional hot mixing formula heat exchanger
CN101693230B (en) Coating machine heat recovery utilization energy-saving device
CN203757824U (en) Heat supply system capable of reducing return water temperature of primary network
CN107560044B (en) Evaporative cooling air-conditioning system for providing electric energy by using industrial waste heat
CN204806941U (en) Heat exchanger
CN105043138A (en) Flue gas waste heat recovery system
CN205939378U (en) Split type solid heat storage medium electric boiler
CN201973897U (en) Split solar water heater taking gas as working medium
CN203719469U (en) Pressure-bearing smoke waste heat exchanger
CN201903278U (en) Combined-type condensing heat exchanger
CN204574199U (en) Hot blast and the additional hot direct contact heat exchanger of electricity
CN202792923U (en) Spiral heat exchange device for rotary kiln
CN102200398B (en) Double-shell heat exchanger
CN210921355U (en) Steam boiler waste heat recovery device
CN108625915A (en) It is a kind of using boiler blowdown water and flue gas as the organic rankine cycle system of heat source
CN103353107A (en) Device capable of obtaining superheated steam from high-temperature high-pressure gas
CN206695648U (en) Gas waste-heat retracting device
CN202853139U (en) Novel high-efficiency corrosion-resistant split type solar water heater
CN207701210U (en) A kind of jet dynamic control tail gas waste heat utilizing device
CN201757600U (en) Waste heat recovery device for industrial furnace exhaust gas or coal gas
CN202432885U (en) Floating plate type tubular preheater
CN201935401U (en) Fin type vertical water pipe return stroke
CN207019035U (en) Smoke and waste steam boiler
CN107289796B (en) High-efficient heat transfer horizontal conduction oil heat exchanger
CN217504461U (en) Multi-medium energy storage intermediate heat exchanger

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhao Qingqi

Inventor after: Yang Dongsheng

Inventor after: Wen Jin

Inventor after: Yang Baoqu

Inventor after: Pang Yongheng

Inventor after: Li Anping

Inventor after: Yang Yingxuan

Inventor after: Shang Yue

Inventor before: Li Anping

Inventor before: Zhao Qingqi

Inventor before: Guo Zhenwei

Inventor before: Jiang Libing

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20171221

Address after: Heping District, Siping City of Shenyang province Liaoning 110006 Street No. 39-7

Co-patentee after: STATE GRID LIAONING ENERGY SAVING SERVICES CO., LTD.

Patentee after: Electric Power Research Institute of State Grid Liaoning Electric Power Co., Ltd.

Co-patentee after: Northeastern University

Co-patentee after: State Grid Corporation of China

Address before: No. 9-6, Jiahe Road, peace zone, Shenyang, Liaoning, Liaoning, 311

Co-patentee before: Zhao Qingqi

Patentee before: Li Anping

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171107

Termination date: 20180312