CN104727546A - 采用铝合金模板浇筑混凝土楼板的方法及其传输孔模具 - Google Patents

采用铝合金模板浇筑混凝土楼板的方法及其传输孔模具 Download PDF

Info

Publication number
CN104727546A
CN104727546A CN201310709283.2A CN201310709283A CN104727546A CN 104727546 A CN104727546 A CN 104727546A CN 201310709283 A CN201310709283 A CN 201310709283A CN 104727546 A CN104727546 A CN 104727546A
Authority
CN
China
Prior art keywords
aluminum alloy
transmission hole
mould plate
concrete floor
alloy mould
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310709283.2A
Other languages
English (en)
Other versions
CN104727546B (zh
Inventor
杨广海
吴坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau Third Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau Third Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau Third Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau Third Construction Engineering Co Ltd
Priority to CN201310709283.2A priority Critical patent/CN104727546B/zh
Publication of CN104727546A publication Critical patent/CN104727546A/zh
Application granted granted Critical
Publication of CN104727546B publication Critical patent/CN104727546B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明涉及一种采用铝合金模板浇筑混凝土楼板的方法及其传输孔模具,属于建筑施工领域。在传统的模板体系当中,我们采用搭设悬挑平台,用塔吊等大型机械转运材料的方法来进行生产。但在铝合金模板体系中,所有的模型版块都是由标准铝合金模板拼装而成,且标准铝合金模板自身的体积及重量都较小,人工完全能够满足标准铝合金模板安装和传递工作。根据铝合金模板体系的上述特点,采用本发明所述的方法及其传输孔模具,所有铝合金标准模板仅依靠人工便可往上一层传递,不需要依靠传统转运材料的塔吊机械,因此,采用本发明能有效提高施工效率,节约建设成本。

Description

采用铝合金模板浇筑混凝土楼板的方法及其传输孔模具
技术领域
[0001] 本发明涉及一种采用铝合金模板浇筑混凝土楼板的方法及其传输孔模具,属于建筑施工领域。
背景技术
[0002] 随着建筑业的发展,建设单位对成本控制以及施工质量的要求越来越高,而铝合金模板体系不仅对质量、安全,甚至在成本控制上都能发挥重要的作用,同时,作为一种回收使用率很高的模板体系,它将在今后的建筑业发展中发挥越来越重要的作用。
[0003] 在传统的模板体系当中,我们采用搭设悬挑平台,用塔吊等大型机械转运材料的方法来进行生产。但在铝合金模板体系中,所有的模型版块都是由铝合金模板拼装而成,且铝合金模板自身的体积及重量都较小,人工完全能够满足铝合金模板安装和传递工作,因此,根据在铝合金模板体系的特点,亟需一种能够摆脱传统塔吊转运材料的方法。
发明内容
[0004] 本发明的目的在于,提供一种能有效提高施工效率、节约建设成本的采用铝合金模板浇筑混凝土楼板的方法及其传输孔模具,以克服现有技术的不足。
[0005] 本发明的技术方案为:
一种采用铝合金模板浇筑混凝土楼板的方法,包括采用现有的铝合金模板浇筑混凝土楼板,在采用铝合金模板浇筑混凝土楼板时,预先在铝合金模板的楼板上制作一个预留孔,用于放置传输孔模具;传输孔模具放置好后,便可在该层铝合金模板的楼板上浇筑混凝土,待该层混凝土浇筑工作完成后,且混凝土硬化达到拆模要求时,则可以将传输孔模具和铝合金模板拆除,传输孔便制作完成;拆除后的铝合金模板,便可人工将其穿过传输孔输送到该层混凝土楼板之上,当输送工作完成后,则可将传输孔封堵上,然后再在该层混凝土楼板上拼装传输上来的铝合金模板,用于浇筑上一层混凝土楼板;如此循环,即可完成整个楼房的混凝土楼板烧筑。
[0006] 所述的传输孔为上端大、下端小的方形通孔或圆锥形通孔,其大小必须能保证铝合金模板顺利穿过。
[0007] 根据上述方法构建的本发明的并用于上述方法的本发明的一种传输孔模具为,该传输孔模具是一个由4〜6mm厚的钢板焊接而成,且上端大、下端小的中空梯形壳体结构或中空圆锥形壳体结构。
[0008] 在上述的传输孔模具内,焊接有两根垂直相交的横杆,以用于增加中空梯形壳体结构或中空圆锥形壳体结构的强度。
[0009] 上述的传输孔模具外的四周上分别焊接有四个把手。
附图说明
[0010] 图1是本发明的设有预留孔的铝合金模板的结构示意图; 图2是图1的俯视结构意图;
图3是采用本发明的传输孔模具进行实施时的结构示意图;
图4是图3的俯视结构意图;
图5是本发明的传输孔的结构示意图;
图6是图5的俯视结构意图。
[0011] 附图标记说明:1_传输孔模具、2-把手、3-混凝土楼板、4-铝合金模板、5-横杆、6-预留孔、7-传输孔。
具体实施方式
[0012] 为了使本发明目的、技术方案和优点更加清楚,下面结合附图和实施例对本发明作进一步的详细说明。
[0013] 本发明的一种采用铝合金模板浇筑混凝土楼板的方法,可以在现有的采用铝合金模板浇筑混凝土楼板的施工工艺中进行实施,该方法包括以下步骤:
步骤1、在已安装好的铝合金模板的楼板上,对预留孔6进行施工放样,预留孔6的孔形可根据使用的需要制作成圆形孔或矩形孔,在本实施例中将预留孔6制作成矩形孔;
步骤2、如图1所示,按照放样尺寸,在铝合金模板体系的楼板上制作预留孔6,预留孔6最大尺寸B要大于铝合金模板4最短尺寸A,即保证铝合金模板4能顺利穿过预留孔6 ;步骤3、如图2所示,将事先制作好的传输孔模具I放置在预留孔6上,并浇筑混凝土
3 ;
步骤4、待混凝土 3硬化后,将铝合金模板4及模具I拆除,如图3所示,传输孔7便制作完成;
步骤5、将拆除的铝合金模板4通过传输孔7人工输送到该层混凝土楼板3之上,待所有传递工作完成后,便可将传输孔7封堵上;
步骤6、然后再在该层混凝土楼板3上架设传输上来的铝合金模板4,用于浇筑上一层混凝土楼板,如此循环,即可完成整个楼房的混凝土楼板浇筑。
[0014] 根据上述方法构建的并用于上述方法中的本发明的一种传输孔模具的结构示意图如图3和图4所示,该传输孔模具I是一个上端大、下端小且中空的梯形壳体结构,即D> C,F > E ;该传输孔模具I的高度H为250mm〜300mm即可;该梯形壳体结构由4〜6mm钢板焊接而成,其内部焊接有两根垂直相交的横杆5,用于增加梯形壳体结构的强度,并在梯形壳体结构外的四周上分别焊接有四个把手2,以便于梯形模具I的拆除。

Claims (6)

1.一种采用铝合金模板浇筑混凝土楼板的方法,包括采用现有的铝合金模板浇筑混凝土楼板,其特征在于:在采用铝合金模板(4)浇筑每层混凝土楼板(3)时,预先在铝合金模板(4)上制作一个预留孔(6),用于放置传输孔模具(1),待传输孔模具(I)放置好后,再进行混凝土楼板(3)的浇筑,待该层混凝土楼板(3)浇筑完毕,并将铝合金模板(4)和传输孔模具(I)拆除后,便形成传输孔(7),然后人工将拆除后的铝合金模板(4)通过传输孔(7)输送到该层混凝土楼板(3)之上,当输送工作完成后,则可将传输孔(7)封堵上,然后在该层混凝土楼板(3)上拼装传输上来的铝合金模板(4),用于浇筑上一层混凝土楼板;如此循环,即可完成整个楼房的混凝土楼板浇筑。
2.根据权利要求1所述的采用铝合金模板浇筑混凝土楼板的方法,其特征在于:所述的传输孔(7 )为上端大、下端小的矩形通孔或圆锥形通孔。
3.根据权利要求1所述的采用铝合金模板浇筑混凝土楼板的方法,其特征在于:所述的传输孔(7)的大小必须能保证铝合金模板(4)顺利穿过。
4.一种用于权利要求1〜3任一所述方法的传输孔模具,其特征在于:该传输孔模具(I)是一个由4〜6mm厚的钢板焊接而成的、且上端大、下端小的中空梯形壳体结构或中空圆锥形壳体结构。
5.根据权利要求4所述的传输孔模具,其特征在于:在所述的传输孔模具(I)内,焊接有两根用于增加中空梯形壳体结构或中空圆锥形壳体结构强度的垂直相交的横杆(5)。
6.根据权利要求4所述的传输孔模具,其特征在于:在所述的传输孔模具(I)外的四周上分别焊接有四个把手(2)。
CN201310709283.2A 2013-12-21 2013-12-21 采用铝合金模板浇筑混凝土楼板的方法及其传输孔模具 Active CN104727546B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310709283.2A CN104727546B (zh) 2013-12-21 2013-12-21 采用铝合金模板浇筑混凝土楼板的方法及其传输孔模具

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310709283.2A CN104727546B (zh) 2013-12-21 2013-12-21 采用铝合金模板浇筑混凝土楼板的方法及其传输孔模具

Publications (2)

Publication Number Publication Date
CN104727546A true CN104727546A (zh) 2015-06-24
CN104727546B CN104727546B (zh) 2017-11-28

Family

ID=53451899

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310709283.2A Active CN104727546B (zh) 2013-12-21 2013-12-21 采用铝合金模板浇筑混凝土楼板的方法及其传输孔模具

Country Status (1)

Country Link
CN (1) CN104727546B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106639309A (zh) * 2017-02-10 2017-05-10 中国五冶集团有限公司 铝模板工具式预留孔模具
CN108118896A (zh) * 2018-01-03 2018-06-05 北京城建远东建设投资集团有限公司 现浇剪力墙结构铝合金模板预留管槽定型模具施工工艺

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6044614A (en) * 1996-05-08 2000-04-04 Newtec Concrete Construction Pty Limited Sequential formwork system for concrete buildings
CN201221198Y (zh) * 2008-06-02 2009-04-15 北京中建柏利工程技术发展有限公司 铝合金模板体系
CN201292665Y (zh) * 2008-11-10 2009-08-19 郑州市第一建筑工程集团有限公司 混凝土楼板预留洞装置
CN102425310A (zh) * 2011-12-15 2012-04-25 中国二十二冶集团有限公司 装配式住宅剪力墙结构墙体竖向连接施工方法
CN102561695A (zh) * 2012-01-04 2012-07-11 广东建星建筑工程有限公司 利用铝模板建造建筑物的施工方法
CN102926530A (zh) * 2012-11-15 2013-02-13 福建安厦新型建筑模板制造有限公司 一种钢框模板组件
CN203452379U (zh) * 2013-09-09 2014-02-26 中建八局第三建设有限公司 一种混凝土结构施工楼层轴线控制孔预留及封堵模具

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6044614A (en) * 1996-05-08 2000-04-04 Newtec Concrete Construction Pty Limited Sequential formwork system for concrete buildings
CN201221198Y (zh) * 2008-06-02 2009-04-15 北京中建柏利工程技术发展有限公司 铝合金模板体系
CN201292665Y (zh) * 2008-11-10 2009-08-19 郑州市第一建筑工程集团有限公司 混凝土楼板预留洞装置
CN102425310A (zh) * 2011-12-15 2012-04-25 中国二十二冶集团有限公司 装配式住宅剪力墙结构墙体竖向连接施工方法
CN102561695A (zh) * 2012-01-04 2012-07-11 广东建星建筑工程有限公司 利用铝模板建造建筑物的施工方法
CN102926530A (zh) * 2012-11-15 2013-02-13 福建安厦新型建筑模板制造有限公司 一种钢框模板组件
CN203452379U (zh) * 2013-09-09 2014-02-26 中建八局第三建设有限公司 一种混凝土结构施工楼层轴线控制孔预留及封堵模具

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106639309A (zh) * 2017-02-10 2017-05-10 中国五冶集团有限公司 铝模板工具式预留孔模具
CN108118896A (zh) * 2018-01-03 2018-06-05 北京城建远东建设投资集团有限公司 现浇剪力墙结构铝合金模板预留管槽定型模具施工工艺

Also Published As

Publication number Publication date
CN104727546B (zh) 2017-11-28

Similar Documents

Publication Publication Date Title
CN102561681B (zh) 填充墙构造柱浇筑成型模板及浇筑成型工艺
CN104631706B (zh) 一种免拆模混凝土柱及其施工方法
CN104695979B (zh) 一种利用高大台车整体横移高大模板的方法
CN102677896B (zh) 卫生间降板定型支模及施工方法
CN206267422U (zh) 一种装配式混凝土叠合柱
CN104727546A (zh) 采用铝合金模板浇筑混凝土楼板的方法及其传输孔模具
CN206625553U (zh) 用于同时浇筑高低跨结构的模板支撑系统
CN105569333A (zh) 一种悬挑层外墙预留孔的施工模板及施工方法
CN102912977A (zh) 一种用于浇筑定型楼梯的模具
CN204571289U (zh) 一种悬挑层外墙预留孔的施工模板
CN203626243U (zh) 一种用铝合金模板浇筑混凝土楼板所用的传输孔模具
CN201713970U (zh) 一种轻质密肋板和轻质密肋楼盖结构体系
CN206646542U (zh) 一种模块化承台中立柱预埋筋定位装置
CN104908148A (zh) 电缆槽盖板预制模板及其施工方法
CN205669210U (zh) 钢结构建筑混凝土杯形基础内孔模架
CN204626965U (zh) 用于建筑楼梯间一次浇筑成形的钢楼梯模板
CN204662486U (zh) 可供大小塔吊转换的共用基础
CN103628684A (zh) 一种同时浇筑楼板和剪力墙的施工方法
CN202882411U (zh) 一种造粒塔滑模制造装置
CN201835524U (zh) 一种顶部带有预埋件混凝土梁的浇注装置
CN206016254U (zh) 建筑用预制构造柱免支模u型壳
CN105951870B (zh) 钢结构建筑混凝土杯形基础内孔模架
CN105317056A (zh) 一种加强型的检查井盖板
CN203462753U (zh) 用于双层钢筋混凝土板墙空腔施工的大钢模板
CN104131689B (zh) 一种可提升的工具堆载平台及提升方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: Beijing road 563000 in Guizhou province Zunyi city Honghuagang District No. 57

Patentee after: The Third Construction Co., Ltd. of China Construction Fourth Engineering Bureau

Address before: Beijing road 563003 in Guizhou province Zunyi city Honghuagang District No. 57

Patentee before: THE THIRD CONSTRUCTION & ENGINEERING CO. OF CCFED

CP03 Change of name, title or address