CN104609250B - A kind of steel wire winding device - Google Patents

A kind of steel wire winding device Download PDF

Info

Publication number
CN104609250B
CN104609250B CN201510046284.2A CN201510046284A CN104609250B CN 104609250 B CN104609250 B CN 104609250B CN 201510046284 A CN201510046284 A CN 201510046284A CN 104609250 B CN104609250 B CN 104609250B
Authority
CN
China
Prior art keywords
wire
steel wire
frame
drive shaft
winding device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510046284.2A
Other languages
Chinese (zh)
Other versions
CN104609250A (en
Inventor
熊怀忠
艾荣荣
吕芳芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Hong Yu Communication Apparatus Co Ltd
Original Assignee
Hebei Hong Yu Communication Apparatus Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Hong Yu Communication Apparatus Co Ltd filed Critical Hebei Hong Yu Communication Apparatus Co Ltd
Priority to CN201510046284.2A priority Critical patent/CN104609250B/en
Publication of CN104609250A publication Critical patent/CN104609250A/en
Application granted granted Critical
Publication of CN104609250B publication Critical patent/CN104609250B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Unwinding Of Filamentary Materials (AREA)

Abstract

本发明涉及一种钢丝缠绕装置,包括依次设置在机架上的盘条架、整丝台、缠绕装置和制动装置构成;所述盘条架包括:插装在机架的立轴、设置在立轴顶部的锥笼以及设置在锥笼底部的水平撑杆;所述整丝台包括:固定设置在机架上的台架、设置在台架上用于整丝的竖直整丝轮组;所述缠绕装置包括:驱动电机、通过减速机与驱动电机连接的驱动轴、套装在驱动轴上的卷轴以及与驱动轴配和使用的滑轴;启动驱动电机,卷轴开始转动牵动钢丝,这样钢丝就可以由盘条捆抽出钢丝,而后经过整丝台对钢丝的调整卷置到卷轴上;并且整丝台还可以使卷轴与整丝台之间的钢丝保持紧绷,保证钢丝缠绕的紧密度;本技术方案可以安全、快速、紧密的完成钢丝的缠绕。

The invention relates to a steel wire winding device, which comprises a wire rod stand, a whole wire platform, a winding device and a braking device sequentially arranged on a frame; the wire rod frame includes: a vertical shaft inserted into the frame, The cone cage at the top of the vertical shaft and the horizontal struts arranged at the bottom of the cone cage; the wire trimming platform includes: a frame fixedly arranged on the frame, a vertical wire trimming wheel group arranged on the frame for trimming; The winding device includes: a drive motor, a drive shaft connected to the drive motor through a reducer, a reel sleeved on the drive shaft, and a sliding shaft matched with the drive shaft; when the drive motor is started, the reel starts to rotate and pulls the steel wire, so that the steel wire The steel wire can be pulled out from the wire rod bundle, and then the steel wire can be adjusted and rolled onto the reel through the wire adjustment table; and the wire adjustment table can also keep the steel wire between the reel and the wire adjustment table tight to ensure the tightness of the steel wire winding ; This technical solution can safely, quickly and tightly complete the winding of the steel wire.

Description

一种钢丝缠绕装置A wire winding device

技术领域technical field

本发明涉及输电线缆生产设备,具体涉及一种钢丝缠绕装置。The invention relates to production equipment for power transmission cables, in particular to a steel wire winding device.

背景技术Background technique

在输变电领域钢绞线使用量庞大,但是在生产过程中需要将钢丝盘条缠绕到特定的线轴上,只有缠绕到特定线轴上才能进入到钢绞线缠绕机上进行缠绕工作,一台钢绞线缠绕机同时使用多个线轴。现在缠绕线轴是人工或半机械操作,生产效率低一般十几人才能与一台钢绞线缠绕机配合生产,劳动强度大,省产效率低,并且缠绕的线轴松散,导致一台钢绞线缠绕机频繁启停来更换线轴,一台七芯钢绞线缠绕机用同时使用六个线轴,必须每个线轴都有钢丝才能正常运转,这个就增加了更换线轴的频率,导致生产效率低下。In the field of power transmission and transformation, the use of steel strands is huge, but in the production process, the steel wire coils need to be wound on specific spools. Only when they are wound on specific spools can they enter the steel strand winding machine for winding work. Strand winding machines use multiple spools at the same time. At present, the winding spool is manually or semi-mechanically operated, and the production efficiency is low. Generally, more than a dozen people can cooperate with a steel strand winding machine for production. The labor intensity is high, the production efficiency is low, and the winding spool is loose, causing a steel strand The winding machine frequently starts and stops to replace the spools. A seven-core steel strand winding machine uses six spools at the same time, and each spool must have steel wires to operate normally. This increases the frequency of spool replacement, resulting in low production efficiency.

半机械缠绕装置在使用时需要多人配合,由于工人直接和钢丝接触因此安全缠绕速度很慢,钢丝的缠绕紧密度还是比较松散。The use of the semi-mechanical winding device requires the cooperation of multiple people. Since the workers are in direct contact with the steel wire, the safe winding speed is very slow, and the winding tightness of the steel wire is still relatively loose.

发明内容Contents of the invention

为了解决上述技术问题,本发明提供一种实用、可靠、生产效率高的盘条钢丝缠绕装置。In order to solve the above technical problems, the present invention provides a practical, reliable and high production efficiency wire rod winding device.

本发明采用如下技术方案:一种钢丝缠绕装置,包括依次设置在机架上的盘条架、整丝台、缠绕装置和制动装置构成;所述盘条架包括:插装在机架上可以自由转动的立轴、设置在立轴顶部的锥笼以及设置在锥笼底部的水平撑杆,所述水平撑杆与立轴固定连接;The present invention adopts the following technical solutions: a steel wire winding device, which consists of a coil frame, a whole wire table, a winding device and a brake device arranged sequentially on the frame; the coil frame includes: inserted on the frame A vertical shaft that can rotate freely, a cone cage arranged on the top of the vertical shaft, and a horizontal strut arranged at the bottom of the cone cage, the horizontal struts are fixedly connected to the vertical shaft;

所述整丝台包括:固定设置在机架上的台架、设置在台架上用于整丝的竖直整丝轮组,所述竖直整丝轮组包括两个竖直设置的导轮以及嵌置在两个导轮之间的压轮;所述缠绕装置包括:驱动电机、通过减速机与驱动电机连接的驱动轴、套装在驱动轴上的卷轴以及与驱动轴配和使用的滑轴;所述制动装置包括:设置在立轴根部的抱刹片、一端与抱刹片自由端固定连接的拉线以及与拉线另一端固定连接的制动杆。The wire straightening platform includes: a stand fixedly arranged on the frame, a vertical straight silk wheel set arranged on the stand for straight silk, and the vertical straight silk wheel set includes two vertically arranged guides wheel and a pressure wheel embedded between the two guide wheels; the winding device includes: a drive motor, a drive shaft connected to the drive motor through a reducer, a reel sleeved on the drive shaft, and a Sliding shaft; the brake device includes: a brake pad arranged at the root of the vertical shaft, a pull wire fixedly connected to the free end of the brake pad at one end, and a brake rod fixedly connected to the other end of the pull wire.

进一步说,所述驱动轴通过轴承座设置在机架上,所述驱动轴一端通过皮带与驱动电机连接,所述驱动轴另一端设置有定位台,所述定位台前端为锥形。Furthermore, the drive shaft is arranged on the frame through a bearing seat, one end of the drive shaft is connected to the drive motor through a belt, and the other end of the drive shaft is provided with a positioning platform, and the front end of the positioning platform is tapered.

进一步说,所述滑轴通过滑套设置在机架上,所述滑轴一端为锥形,另一端插装在滑套内,所述滑套上设置有限制滑轴位置的顶丝。Furthermore, the sliding shaft is arranged on the frame through a sliding sleeve, one end of the sliding shaft is tapered, and the other end is inserted into the sliding sleeve, and a top screw is arranged on the sliding sleeve to limit the position of the sliding shaft.

进一步说,还包括设置于整丝台与缠绕装置之间的排线器,所述排线器的转动轴通过皮带与驱动轴连接。Furthermore, it also includes a wire unwinder arranged between the yarn straightening table and the winding device, the rotating shaft of the wire unwinder is connected with the driving shaft through a belt.

进一步说,所述台架还设置有水平整丝轮组,所述水平整丝轮组包括两个水平设置的水平导轮以及嵌置在两个水平导轮之间的水平压轮。Furthermore, the platform is also provided with a horizontal straightening wheel set, and the horizontal straightening wheel set includes two horizontally arranged horizontal guide wheels and a horizontal pressure wheel embedded between the two horizontal guide wheels.

进一步说,所述台架的盘条架一侧设置有引线圈。Further speaking, a lead coil is provided on one side of the rack of the stand.

进一步说,所述竖直整丝轮组与水平整丝轮组之间设置有定线圈。Furthermore, a fixed coil is arranged between the vertical straightening wheel set and the horizontal straightening wheel set.

进一步说,所述台架的缠绕装置一侧设置有导线圈。Furthermore, a conductive coil is provided on one side of the winding device of the platform.

进一步说,制动装置还包括设置在驱动轴上的线轴抱刹片,所述线轴抱刹片自由端通过轴拉线与减速杆连接。Further speaking, the brake device also includes a bobbin holding brake piece arranged on the drive shaft, and the free end of the bobbin holding brake piece is connected to the deceleration lever through the shaft pull wire.

进一步说,所述抱刹片和线轴抱刹片分别设置有复位簧。Furthermore, the brake holding piece and the bobbin holding brake piece are respectively provided with return springs.

本发明的有益效果:盘条架上可以放置整捆的盘条钢丝,将钢丝的头穿过整线架缠绕在固定在驱动轴上的卷轴,启动驱动电机,卷轴开始转动牵动钢丝,这样钢丝就可以由盘条捆抽出钢丝,而后经过整丝台对钢丝的调整卷置到卷轴上;并且整丝台还可以使卷轴与整丝台之间的钢丝保持紧绷,保证钢丝缠绕的紧密度;钢丝在缠绕过程中会有顿挫,并不连贯的对盘条架施加旋转的力,这样盘条架就会旋转的速度超过钢丝卷曲的速度,形成钢丝过多的拥挤在引线圈前方,形成团造成混乱,这样抱刹片就可以抑制盘条架的转速,使盘条架的转速与钢丝的卷曲速度相一致,保证系统正常运行;本技术方案可以安全、快速、紧密的完成钢丝的缠绕。Beneficial effects of the present invention: a whole bundle of wire rod steel wires can be placed on the wire rod frame, the head of the steel wire is passed through the whole wire frame and wound on the reel fixed on the drive shaft, the drive motor is started, and the reel starts to rotate to affect the steel wire, so that the steel wire The steel wire can be pulled out from the wire rod bundle, and then the steel wire can be adjusted and rolled onto the reel through the wire adjustment table; and the wire adjustment table can also keep the steel wire between the reel and the wire adjustment table tight to ensure the tightness of the steel wire winding ; The steel wire will be frustrated during the winding process, and the force of rotation will be applied to the wire rod frame incoherently, so that the speed of the wire rod frame will rotate faster than the speed of the steel wire curling, forming too much crowding of the steel wire in front of the lead coil, forming In this way, the brake disc can restrain the rotation speed of the wire rod frame, so that the rotation speed of the wire rod frame is consistent with the coiling speed of the steel wire, so as to ensure the normal operation of the system; this technical solution can complete the winding of the steel wire safely, quickly and tightly .

驱动轴设置定位台,在卷轴安装时可以固定卷轴的位置,驱动轴前端是锥形可以方便的将卷轴安装到位,由于卷轴是钢制的比较重,用驱动轴的锥件用力挤压卷轴自然到位不用人工搬运。The drive shaft is equipped with a positioning platform, which can fix the position of the reel when the reel is installed. The front end of the drive shaft is tapered to facilitate the installation of the reel in place. Since the reel is made of steel and is relatively heavy, it is natural to squeeze the reel with the cone of the drive shaft. In place without manual handling.

卷轴需要更换,因此固定卷轴的机构要方便拆装和锁死,在安装时滑轴前端也是锥形,这样将卷轴辊到两锥形轴之间,两锥轴的锥尖与卷轴轴心孔对应,将滑轴向驱动轴方向推,两个锥轴将卷轴抬起,当卷轴进入到定位台就完成了固定,这样既省去人工安装,卷轴又与驱动轴连接,安装到位后将滑轴锁死即可开始生产,在卷轴卷满钢丝后,结算滑轴,将滑轴撤出,卷轴自然掉落,完成拆卸。The reel needs to be replaced, so the mechanism for fixing the reel should be easy to disassemble and lock. When installing, the front end of the slide shaft is also tapered, so that the reel is rolled between the two tapered shafts. Correspondingly, push the sliding shaft in the direction of the drive shaft, and the two tapered shafts will lift the reel, and the reel will be fixed when it enters the positioning table, which saves manual installation, and the reel is connected with the drive shaft. After the shaft is locked, the production can start. After the reel is full of steel wires, the sliding shaft is settled, and the sliding shaft is withdrawn. The reel falls naturally, and the disassembly is completed.

在缠绕装置前端设置排线器,可以使钢丝缠绕的更均匀,更密实。Installing a wire puller at the front end of the winding device can make the wire winding more uniform and denser.

在整丝台上设置水平整丝轮组,可以使钢丝在水平和竖直方向都得到梳理,避免钢丝有死弯,以免影响后续生产。A horizontal wire trimming wheel set is installed on the wire trimming table, so that the steel wire can be combed in both horizontal and vertical directions, avoiding dead bends in the steel wire, so as not to affect subsequent production.

引线圈、定线圈和导线圈是为了稳定钢丝的位置,避免钢丝的颤动引起进出设备时产生错位,增加设备的可靠性。The lead coil, fixed coil and guide coil are used to stabilize the position of the steel wire, avoid the misalignment caused by the vibration of the steel wire when entering and exiting the equipment, and increase the reliability of the equipment.

当系统出现断丝的时候就必须停止所有设备然后进行续接,这时卷轴的惯性很大,需要很久才能停下,这样就浪费时间,不利于生产工作,但是线轴抱刹片可以在需要线轴停止时,迅速使线轴停下,进行维修和更换线轴,提高工作效率,增加操作人员对设备的可控性。When the system breaks, all equipment must be stopped and then connected. At this time, the inertia of the reel is very large, and it takes a long time to stop, which is a waste of time and is not conducive to production work. However, the bobbin holding brake can be used when the bobbin is needed. When stopping, quickly stop the bobbin for maintenance and replacement of the bobbin, improve work efficiency, and increase the operator's controllability of the equipment.

抱刹片和线轴抱刹片设置复位簧可以是制动机构与抱刹轴迅速脱离,避免不能及时复位而阻碍系统工作。The brake pad and the bobbin lock pad are equipped with a return spring, which can make the brake mechanism and the brake shaft quickly disengage, so as to prevent the system from being unable to reset in time and hinder the work of the system.

附图说明Description of drawings

图1为本发明结构示意图;Fig. 1 is a structural representation of the present invention;

图2为本发明俯视结构示意图;Fig. 2 is a schematic view of the top view structure of the present invention;

图3为本发明缠绕装置使用状态结构示意图;Fig. 3 is a schematic structural diagram of the use state of the winding device of the present invention;

图4为本发明缠绕装置未安装卷轴状态结构示意图;Fig. 4 is a schematic view of the structure of the winding device of the present invention without a reel installed;

图5为本发明制动装置拉杆结构示意图;Fig. 5 is a structural schematic diagram of the pull rod of the brake device of the present invention;

在图中:1、机架,2、盘条架,21、立轴,22、锥笼,23、水平撑杆,3、整丝台,31、台架,32、竖直整丝轮组,321、导轮,322、压轮,33、水平整丝轮组,331、水平导轮,332、水平压轮,34、引线圈,35、定线圈,36、导线圈,4、缠绕装置,41、驱动电机,42、驱动轴,421、定位台,43、卷轴,44、滑轴,45、滑套,46、顶丝,6、排线器,7、抱刹片,71、拉线,72、制动杆,8、线轴抱刹片,81、轴拉线,82、减速杆,9、复位簧。In the figure: 1, frame, 2, wire rod frame, 21, vertical shaft, 22, cone cage, 23, horizontal strut, 3, whole wire table, 31, stand, 32, vertical wire whole wheel group, 321, guide wheel, 322, pressure wheel, 33, horizontal whole wire wheel group, 331, horizontal guide wheel, 332, horizontal pressure wheel, 34, lead coil, 35, fixed coil, 36, guide coil, 4, winding device, 41, drive motor, 42, drive shaft, 421, positioning platform, 43, reel, 44, sliding shaft, 45, sliding sleeve, 46, jacking wire, 6, cable arrangement, 7, holding brake plate, 71, pull wire, 72, brake lever, 8, bobbin holds brake sheet, 81, axle backguy, 82, deceleration lever, 9, back-moving spring.

具体实施方式Detailed ways

下面结合附图1-5和具体实施例对发明做进一步详细描述:Below in conjunction with accompanying drawing 1-5 and specific embodiment the invention is described in further detail:

如图1、2所示,一种钢丝缠绕装置,其包括依次设置在机架1上的盘条架2、整丝台3、缠绕装置4和制动装置构成;所述盘条架2包括:插装在机架1上可以自由转动的立轴21、设置在立轴21顶部的锥笼22以及设置在锥笼22底部的水平撑杆23,所述水平撑杆23与立轴21固定连接;所述整丝台3包括:固定设置在机架1上的台架31、设置在台架31上用于整丝的竖直整丝轮组32,所述竖直整丝轮组32包括两个竖直设置的导轮321以及嵌置在两个导轮321之间的压轮322;所述缠绕装置4包括:驱动电机41、通过减速机与驱动电机41连接的驱动轴42、套装在驱动轴42上的卷轴43以及与驱动轴42配和使用的滑轴44;所述制动装置包括:设置在立轴21根部的抱刹片7、一端与抱刹片7自由端固定连接的拉线71以及与拉线71另一端固定连接的制动杆72。盘条架2上可以放置整捆的盘条钢丝,将钢丝的头穿过整线架缠绕在固定在驱动轴上的卷轴,启动驱动电机,卷轴开始转动牵动钢丝,这样钢丝就可以由盘条捆抽出钢丝,而后经过整丝台对钢丝的调整卷置到卷轴上;并且整丝台还可以使卷轴与整丝台之间的钢丝保持紧绷,保证钢丝缠绕的紧密度;钢丝在缠绕过程中会有顿挫,并不连贯的对盘条架2施加旋转的力,这样盘条架2就会旋转的速度超过钢丝卷曲的速度,形成钢丝过多的拥挤在引线圈34前方,形成团造成混乱,这样抱刹片7就可以抑制盘条架2的转速,使盘条架2的转速与钢丝的卷曲速度相一致,保证系统正常运行;本技术方案可以安全、快速、紧密的完成钢丝的缠绕。As shown in Figures 1 and 2, a steel wire winding device comprises a coil frame 2, a whole wire platform 3, a winding device 4 and a braking device arranged in sequence on a frame 1; the coil frame 2 includes : the vertical shaft 21 that is inserted on the frame 1 and can rotate freely, the cone cage 22 that is arranged on the top of the vertical shaft 21 and the horizontal strut 23 that is arranged on the bottom of the cone cage 22, the horizontal strut 23 is fixedly connected with the vertical shaft 21; Said whole silk platform 3 comprises: the stand 31 that is fixedly arranged on the frame 1, is arranged on the stand 31 and is used for the vertical whole silk wheel group 32 of whole silk, and described vertical whole silk wheel group 32 comprises two The vertical guide wheel 321 and the pressure wheel 322 embedded between the two guide wheels 321; the winding device 4 includes: a drive motor 41, a drive shaft 42 connected to the drive motor 41 through a reducer, sleeved on the drive The spool 43 on the shaft 42 and the slide shaft 44 used in conjunction with the drive shaft 42; the braking device includes: a brake pad 7 arranged at the root of the vertical shaft 21, a pull wire 71 fixedly connected at one end to the free end of the brake pad 7 And the brake lever 72 fixedly connected with the other end of the pull wire 71. The whole bundle of wire rods can be placed on the wire rod frame 2, the head of the steel wire is passed through the whole wire frame and wound on the spool fixed on the drive shaft, the drive motor is started, and the spool begins to rotate to affect the steel wire, so that the steel wire can be driven by the wire rod. The steel wire is pulled out from the bundle, and then the steel wire is adjusted and rolled onto the reel through the wire adjustment table; and the wire adjustment table can also keep the steel wire between the reel and the wire table tight to ensure the tightness of the steel wire winding; the steel wire during the winding process There will be setbacks in the middle, and the force of rotation is applied to the wire rod frame 2 incoherently, so that the speed of the wire rod frame 2 will exceed the speed of the coiling of the steel wire, forming too much crowding of the steel wire in front of the lead coil 34, forming a group and causing In this way, the holding brake piece 7 can restrain the rotating speed of the wire rod rack 2, so that the rotating speed of the wire rod rack 2 is consistent with the coiling speed of the steel wire, so as to ensure the normal operation of the system; winding.

驱动轴42通过轴承座设置在机架1上,所述驱动轴42一端通过皮带与驱动电机41连接,所述驱动轴42另一端设置有定位台421,所述定位台421前端为锥形。驱动轴设置定位台,在卷轴安装时可以固定卷轴的位置,驱动轴前端是锥形可以方便的将卷轴安装到位,由于卷轴是钢制的比较重,用驱动轴的锥件用力挤压卷轴自然到位不用人工搬运。The drive shaft 42 is arranged on the frame 1 through a bearing seat, one end of the drive shaft 42 is connected with the drive motor 41 through a belt, and the other end of the drive shaft 42 is provided with a positioning platform 421, and the front end of the positioning platform 421 is tapered. The drive shaft is equipped with a positioning platform, which can fix the position of the reel when the reel is installed. The front end of the drive shaft is tapered to facilitate the installation of the reel in place. Since the reel is made of steel and is relatively heavy, it is natural to squeeze the reel with the cone of the drive shaft. In place without manual handling.

滑轴44通过滑套45设置在机架1上,所述滑轴44一端为锥形,另一端插装在滑套45内,所述滑套45上设置有限制滑轴44位置的顶丝46。卷轴43需要更换,因此固定卷轴43的机构要方便拆装和锁死,在安装时滑轴44前端也是锥形,这样将卷轴43辊到两锥形轴之间,两锥轴的锥尖与卷轴轴心孔对应,将滑轴44向驱动轴方向推,两个锥轴将卷轴43抬起,当卷轴43进入到定位台421就完成了固定,这样既省去人工安装,卷轴43又与驱动轴42连接,安装到位后将滑轴44通过顶丝46锁死即可开始生产,如图3、4所示,在卷轴43卷满钢丝后,解锁滑轴44,将滑轴44撤出,卷轴43自然掉落,完成拆卸。安装卷轴43的地面设计为缓坡,安装时直接滚动孔的卷轴到位即可,定位方便劳动强度小,拆卸卷轴时滑轴推出后,卷轴直接落地顺着缓坡滚落,不用人工移位,使用时直接用电葫芦吊装即可,省时省力。The sliding shaft 44 is arranged on the frame 1 through a sliding sleeve 45. One end of the sliding shaft 44 is tapered, and the other end is inserted in the sliding sleeve 45. The sliding sleeve 45 is provided with a top wire that limits the position of the sliding shaft 44. 46. The spool 43 needs to be replaced, so the mechanism for fixing the spool 43 will be easy to disassemble and lock. When installing, the front end of the slide shaft 44 is also tapered, so that the spool 43 is rolled between the two tapered shafts. Corresponding to the center hole of the reel, push the slide shaft 44 towards the direction of the drive shaft, and the two cone shafts will lift the reel 43, and when the reel 43 enters the positioning table 421, the fixation is completed, which saves manual installation, and the reel 43 and The driving shaft 42 is connected, and after the installation is in place, the sliding shaft 44 can be locked by the top wire 46 to start production, as shown in Figures 3 and 4, after the reel 43 is full of steel wires, unlock the sliding shaft 44 and withdraw the sliding shaft 44 , the reel 43 falls naturally, and the disassembly is completed. The ground where the reel 43 is installed is designed to be a gentle slope. When installing, just roll the reel in the hole directly into place. The positioning is convenient and the labor intensity is small. It can be hoisted directly with an electric hoist, saving time and effort.

还包括设置于整丝台3与缠绕装置4之间的排线器6,所述排线器6的转动轴通过皮带与驱动轴42连接。在缠绕装置4前端设置排线器6,可以使钢丝缠绕的更均匀,更密实。It also includes a wire unwinder 6 arranged between the yarn straightening table 3 and the winding device 4 , the rotating shaft of the wire unwinder 6 is connected with the drive shaft 42 through a belt. A cable guide 6 is arranged at the front end of the winding device 4, so that the steel wire can be wound more evenly and densely.

台架31还设置有水平整丝轮组33,所述水平整丝轮组33包括两个水平设置的水平导轮331以及嵌置在两个水平导轮331之间的水平压轮332。在整丝台3上设置水平整丝轮组33,可以使钢丝在水平和竖直方向都得到梳理,避免钢丝有死弯,以免影响后续生产。The stand 31 is also provided with a horizontal straightening wheel set 33 , and the horizontal straightening wheel set 33 includes two horizontally arranged horizontal guide wheels 331 and a horizontal pressure wheel 332 embedded between the two horizontal guide wheels 331 . The horizontal wire trimming wheel set 33 is set on the wire trimming table 3, so that the steel wire can be combed in both horizontal and vertical directions, so as to avoid dead bends in the steel wire, so as not to affect subsequent production.

台架31的盘条架2一侧设置有引线圈34;竖直整丝轮组32与水平整丝轮组33之间设置有定线圈35;台架31的缠绕装置4一侧设置有导线圈36;引线圈34、定线圈35和导线圈36是为了稳定钢丝的位置,避免钢丝的颤动引起进出设备时产生错位,增加设备的可靠性。One side of the rod frame 2 of the stand 31 is provided with a lead coil 34; a fixed coil 35 is arranged between the vertical straightening wheel group 32 and the horizontal straightening wheel group 33; the winding device 4 side of the stand 31 is provided with a wire Circle 36; lead coil 34, fixed coil 35 and guide coil 36 are in order to stabilize the position of steel wire, avoid the vibration of steel wire to cause dislocation when entering and exiting equipment, and increase the reliability of equipment.

制动装置还包括设置在驱动轴42上的线轴抱刹片8,所述线轴抱刹片8自由端通过轴拉线81与减速杆82连接。当系统出现断丝的时候就必须停止所有设备然后进行续接,这时卷轴的惯性很大,需要很久才能停下,这样就浪费时间,不利于生产工作,但是线轴抱刹片可以在需要线轴停止时,迅速使线轴停下,进行维修和更换线轴,提高工作效率,增加操作人员对设备的可控性。The braking device also includes a bobbin holding brake piece 8 arranged on the drive shaft 42 , and the free end of the bobbin holding brake piece 8 is connected to the deceleration lever 82 through a shaft pull wire 81 . When the system breaks, all equipment must be stopped and then connected. At this time, the inertia of the reel is very large, and it takes a long time to stop, which is a waste of time and is not conducive to production work. However, the bobbin holding brake can be used when the bobbin is needed. When stopping, quickly stop the bobbin for maintenance and replacement of the bobbin, improve work efficiency, and increase the operator's controllability of the equipment.

抱刹片7和线轴抱刹片8分别设置有复位簧9;抱刹片和线轴抱刹片设置复位簧可以是制动机构与抱刹轴迅速脱离,避免不能及时复位而阻碍系统工作。The holding brake sheet 7 and the spool holding brake sheet 8 are respectively provided with a return spring 9; the holding brake sheet and the bobbin holding brake sheet are provided with a return spring, which can make the braking mechanism break away from the holding brake shaft quickly, so as to avoid failure to reset in time and hinder the system work.

使用时,将整捆的盘条吊装到盘条架2上,盘条捆水平搬运,将盘条捆套在锥笼22上,然后将盘条捆放置在水平撑杆23上;找到钢丝的一端穿过引线圈34,经过导轮321、压轮322和导轮321,从竖直整丝轮组32出来后,钢丝经过定线圈35,再进入水平整丝轮组33,经过水平导轮331、水平压轮332和水平导轮331,穿过导线圈36经过排线器6缠绕在固定好的卷轴43上,这样就完成了钢丝固定工作;开启驱动电机41,驱动电机41经过减速机将动力传递到驱动轴42上,驱动轴42带动卷轴43和滑轴44转动,从而钢丝开始卷置到卷轴43上,于此同时驱动轴42带动排线器6的传动轴转动,排线器6也开始工作;钢丝被收紧,因此盘踞在盘条架2上的钢丝开始旋转释放钢丝,这样盘条架2的锥笼22、水平撑杆23连带立轴21在牵引钢丝的作用下开始传动;随着盘条架2被带动,钢丝逐渐释放;钢丝经过整丝台3上竖直整丝轮组32、水平整丝轮组33的整形是钢丝四更加平整顺滑。During use, the whole bundle of wire rods is hoisted on the wire rod frame 2, the wire rod bundle is carried horizontally, the wire rod bundle is placed on the cone cage 22, and then the wire rod bundle is placed on the horizontal support rod 23; One end passes through the lead coil 34, passes through the guide wheel 321, the pressure wheel 322 and the guide wheel 321, and after coming out from the vertical wire trimming wheel group 32, the steel wire passes through the fixed coil 35, then enters the horizontal wire trimming wheel group 33, and passes through the horizontal wire trimming wheel group 331, the horizontal pressure wheel 332 and the horizontal guide wheel 331, pass through the guide coil 36 and wind on the fixed reel 43 through the cable arrangement 6, so that the steel wire fixing work is completed; the drive motor 41 is turned on, and the drive motor 41 passes through the reducer The power is transmitted to the drive shaft 42, and the drive shaft 42 drives the reel 43 and the slide shaft 44 to rotate, so that the steel wire begins to be wound on the reel 43, and at the same time, the drive shaft 42 drives the transmission shaft of the cable puller 6 to rotate, and the cable puller 6 6 also starts to work; the steel wire is tightened, so the steel wire entrenched on the coil rack 2 starts to rotate and release the steel wire, so that the cone cage 22 of the coil rack 2, the horizontal strut 23 and the vertical shaft 21 start to drive under the action of the traction steel wire Along with wire rod frame 2 is driven, steel wire releases gradually; Steel wire is through the shaping of vertical whole wire wheel group 32, horizontal whole wire wheel group 33 on the whole wire platform 3 that steel wire 4 is smoother and smoother.

如附图2、5所示,当盘条架2转速过快时,扳动制动杆72通过拉线71将抱刹片7收紧,抱刹片7抱紧立轴21,从而降低盘条架2的转速,速度达到预定速度时,松开制动杆72,复位簧9将抱刹片7复位使之与盘条架2的立轴21脱离;当需要卷轴43停止转动时,拉动减速杆82,带动轴拉线81收紧线轴抱刹片8,线轴抱刹片8抱紧驱动轴42使之减速,从而使卷轴43减速,达到预期效果后,松开减速杆82而后复位簧9带动线轴抱刹片8松开驱动轴42。As shown in accompanying drawings 2 and 5, when the rotation speed of the wire rod frame 2 is too fast, the brake lever 72 is pulled to tighten the brake pad 7 through the pull wire 71, and the brake pad 7 hugs the vertical shaft 21 tightly, thereby lowering the wire rod frame. 2, when the speed reaches the predetermined speed, release the brake lever 72, and the return spring 9 resets the brake sheet 7 to make it break away from the vertical shaft 21 of the coil frame 2; , drive the shaft pull wire 81 to tighten the bobbin holding brake piece 8, the bobbin holding brake piece 8 hugs the driving shaft 42 to decelerate it, so that the reel 43 decelerates, and after the desired effect is achieved, the deceleration lever 82 is released and the return spring 9 drives the bobbin holding The brake pad 8 unclamps the drive shaft 42 .

排线器6的进线一侧也可以设置稳线孔,避免钢丝震动影响钢丝的缠绕质量。在引线圈34处还可以设置安全网墙,避免钢丝接近尾端时的剧烈甩动伤到工作人员。A wire stabilizing hole can also be provided on the wire inlet side of the cable arrangement 6, so as to prevent the vibration of the steel wire from affecting the winding quality of the steel wire. A safety net wall can also be set at the lead coil 34 place, to prevent the staff from being hurt by violent swinging when the steel wire approaches the tail end.

对所公开的本实施例的上述说明,是本领域专业人员能够实现或使用本发明。对这些实施例的多种修改对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本发明的精神或范围的情况下,在其他实施例中实现。因此,本发明将不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和新颖特点相一致的最宽范围。The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the invention. Therefore, the present invention will not be limited to the embodiments shown herein, but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (6)

  1. A kind of 1. steel wire winding device, it is characterised in that:It includes wire rod frame (2), the whole silk platform being successively set in frame (1) (3), wind (4) and brake apparatus are formed;
    The wire rod frame (2) includes:It is inserted into the vertical shaft (21) that can be freely rotated in frame (1), is arranged on vertical shaft (21) top The cone cage (22) in portion and the triatic stay (23) for being arranged on cone cage (22) bottom, the triatic stay (23) are solid with vertical shaft (21) Fixed connection;
    The whole silk platform (3) includes:The stand (31) that is fixedly installed in frame (1), it is arranged on stand (31) and is used for whole silk Vertical whole silk wheel group (32), the vertical whole silk wheel group (32) includes two guide wheels (321) being vertically arranged and is embedded in Pinch roller (322) between two guide wheels (321);
    The wind (4) includes:Motor (41), the drive shaft being connected by reductor with motor (41) (42) spool (43), being sleeved in drive shaft (42) and the slide-bar (44) matched somebody with somebody and used with drive shaft (42);
    Wire rod frame (2) side of the stand (31) sets leaded circle (34), and the vertical whole silk wheel group (32) and level are whole Alignment circle (35) is provided between silk wheel group (33), wind (4) side of the stand (31) is provided with loop (36);
    The brake apparatus includes:Brake holding piece (7), one end and brake holding piece (7) free end for being arranged on vertical shaft (21) root are fixed The bracing wire (71) of connection and the brake bar (72) being fixedly connected with bracing wire (71) other end, the brake holding piece (7) and bobbin are embraced Brake piece (8) is respectively arranged with return spring (9).
  2. A kind of 2. steel wire winding device according to claim 1, it is characterised in that:The drive shaft (42) passes through bearing block It is arranged in frame (1), described drive shaft (42) one end is connected by belt with motor (41), and the drive shaft (42) is another One end is provided with positioning table (421), and positioning table (421) front end is taper.
  3. A kind of 3. steel wire winding device according to claim 1 or 2, it is characterised in that:The slide-bar (44) passes through sliding sleeve (45) it is arranged in frame (1), described slide-bar (44) one end is taper, and the other end is inserted into sliding sleeve (45), the sliding sleeve (45) jackscrew (46) of restricted slide-bar (44) position is set on.
  4. A kind of 4. steel wire winding device according to claim 3, it is characterised in that:Also include be arranged at whole silk platform (3) with Strand oscillator (6) between wind (4), the rotary shaft of the strand oscillator (6) are connected by belt with drive shaft (42).
  5. A kind of 5. steel wire winding device according to claim 4, it is characterised in that:The stand (31) is additionally provided with level Whole silk wheel group (33), the whole silk wheel group (33) of level include two horizontally disposed horizontal guide wheels (331) and embedded in two Horizontal pinch roller (332) between individual horizontal guide wheel (331).
  6. A kind of 6. steel wire winding device according to claim 1, it is characterised in that:Brake apparatus also includes being arranged on driving Bobbin brake holding piece (8) on axle (42), bobbin brake holding piece (8) free end are connected by axle bracing wire (81) and downshift lever (82) Connect.
CN201510046284.2A 2015-01-29 2015-01-29 A kind of steel wire winding device Active CN104609250B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510046284.2A CN104609250B (en) 2015-01-29 2015-01-29 A kind of steel wire winding device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510046284.2A CN104609250B (en) 2015-01-29 2015-01-29 A kind of steel wire winding device

Publications (2)

Publication Number Publication Date
CN104609250A CN104609250A (en) 2015-05-13
CN104609250B true CN104609250B (en) 2018-04-10

Family

ID=53143955

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510046284.2A Active CN104609250B (en) 2015-01-29 2015-01-29 A kind of steel wire winding device

Country Status (1)

Country Link
CN (1) CN104609250B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105858333A (en) * 2016-05-27 2016-08-17 合肥太通制冷科技有限公司 Self-control anti-disordered plate winding production line
CN107673117A (en) * 2016-08-02 2018-02-09 天津市银鹤金属制品有限公司 A kind of preparation method of steel wire coiler
CN109440276A (en) * 2018-11-08 2019-03-08 南阳宇翔工艺品有限公司 A kind of carpet weaving rapidly and efficiently twines machine processed with fine filling
CN111115377B (en) * 2019-12-06 2021-01-29 温州职业技术学院 Steel wire winding device

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102220714A (en) * 2011-03-09 2011-10-19 徐建坤 Device for producing multifunctional silencing kraft steel wire
CN202296540U (en) * 2011-10-14 2012-07-04 鹤壁煤电股份有限公司第九煤矿 Simple reeling-off vehicle
CN202704693U (en) * 2012-08-27 2013-01-30 安志攀 Uncoiling machine for steel wire
CN104291158A (en) * 2014-09-25 2015-01-21 国家电网公司 Steel wire rope coiling machine and steel wire rope coiling and paying-off device

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000116076A (en) * 1998-09-30 2000-04-21 Nippon Electric Ind Co Ltd Automatic winding machine
JP2005062379A (en) * 2003-08-11 2005-03-10 Denki Kagaku Kogyo Kk Winding of optical fiber cable slot
CN201077696Y (en) * 2007-07-04 2008-06-25 蒋任茂 Digital winding displacement controller used for layer winding machine
CN202638953U (en) * 2012-06-14 2013-01-02 无锡平盛科技有限公司 Coiling machine
CN203461611U (en) * 2013-09-22 2014-03-05 盐城银花金属制品有限公司 Breakage prevention payoff rack for coil overturn of steel wire
CN204433954U (en) * 2015-01-29 2015-07-01 河北鸿宇通信器材有限公司 A kind of steel wire winding device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102220714A (en) * 2011-03-09 2011-10-19 徐建坤 Device for producing multifunctional silencing kraft steel wire
CN202296540U (en) * 2011-10-14 2012-07-04 鹤壁煤电股份有限公司第九煤矿 Simple reeling-off vehicle
CN202704693U (en) * 2012-08-27 2013-01-30 安志攀 Uncoiling machine for steel wire
CN104291158A (en) * 2014-09-25 2015-01-21 国家电网公司 Steel wire rope coiling machine and steel wire rope coiling and paying-off device

Also Published As

Publication number Publication date
CN104609250A (en) 2015-05-13

Similar Documents

Publication Publication Date Title
CN104609250B (en) A kind of steel wire winding device
CN110311306B (en) Intelligent distribution box
CN211077954U (en) Cable removes pay-off
CN119284712A (en) A steam turbine rotor lifting tool
CN204433965U (en) A kind of wire rod steel wire winding device
CN111453530A (en) A hoisting wire rope replacement device and control method thereof
CN204433954U (en) A kind of steel wire winding device
CN112499376A (en) Take-up mechanism for electric power installation
CN106743997B (en) Trunk wire-collecting and spool wire-collecting integrated multifunctional wire-collecting machine
CN115240924A (en) A twisted wire mechanism for power cable processing
CN102343381B (en) Pay off device
JPS62220211A (en) Wire drawing method and device
CN109371729A (en) A winding device and its working method
CN213112041U (en) Automatic winding and unwinding devices of wire rope
CN109554968A (en) The device and its construction method of the carrying rope laying of aerial cableway
CN211283165U (en) Novel steel strand wires unwrapping wire device
CN210333823U (en) Anti-winding reinforcing bar unwinding device
CN221459430U (en) Brake device for wire coil pay-off rack
CN209584712U (en) A kind of wrap-up
CN210176188U (en) Winding equipment
CN209427893U (en) A cable reel take-up and pay-off machine
CN217121324U (en) Steel wire unwinding device that can increase
CN213679193U (en) Motor rotor maintenance wire drawing device
CN217921145U (en) Crane
CN106698109A (en) Waste cable recovery device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A wire winding device

Effective date of registration: 20220919

Granted publication date: 20180410

Pledgee: Bank of China Limited by Share Ltd. Cangzhou branch

Pledgor: HEBEI HONGYU COMMUNICATION EQUIPMENT Co.,Ltd.

Registration number: Y2022130000072

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Granted publication date: 20180410

Pledgee: Bank of China Limited by Share Ltd. Cangzhou branch

Pledgor: HEBEI HONGYU COMMUNICATION EQUIPMENT Co.,Ltd.

Registration number: Y2022130000072