CN104555756B - 单桅杆单滑轮组起吊井架及其施工方法 - Google Patents

单桅杆单滑轮组起吊井架及其施工方法 Download PDF

Info

Publication number
CN104555756B
CN104555756B CN201510037616.0A CN201510037616A CN104555756B CN 104555756 B CN104555756 B CN 104555756B CN 201510037616 A CN201510037616 A CN 201510037616A CN 104555756 B CN104555756 B CN 104555756B
Authority
CN
China
Prior art keywords
brace
mast
lifting
derrick
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510037616.0A
Other languages
English (en)
Other versions
CN104555756A (zh
Inventor
邢启风
卢相忠
张宝峰
邢贵坡
孙立仓
李世存
闫闯
阎涛
李树田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KEILUAN BUILDING (GROUP) CO Ltd TANGSHAN
Original Assignee
KEILUAN BUILDING (GROUP) CO Ltd TANGSHAN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KEILUAN BUILDING (GROUP) CO Ltd TANGSHAN filed Critical KEILUAN BUILDING (GROUP) CO Ltd TANGSHAN
Priority to CN201510037616.0A priority Critical patent/CN104555756B/zh
Publication of CN104555756A publication Critical patent/CN104555756A/zh
Application granted granted Critical
Publication of CN104555756B publication Critical patent/CN104555756B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/60Derricks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C2700/00Cranes
    • B66C2700/01General aspects of mobile cranes, overhead travelling cranes, gantry cranes, loading bridges, cranes for building ships on slipways, cranes for foundries or cranes for public works
    • B66C2700/011Cable cranes

Abstract

本发明涉及起吊井架,特别是一种单桅杆单滑轮组起吊井架及其施工方法。包括主斜撑、副斜撑、天轮平台、主斜撑吊点、副斜撑吊点、桅杆,主斜撑吊点焊接在主斜撑天轮平台上,主斜撑的支腿底端铰链固定;桅杆顶部通过一套滑轮组连接在主斜撑吊点上,主斜撑通过主斜撑吊点、滑轮组起吊;主斜撑上焊接有副斜撑的吊点,副斜撑通过主斜撑、连接在主斜撑与副斜撑之间的滑轮组起吊。本发明解决了现有双桅杆双滑轮组起吊井架两套滑轮组合力起吊时起吊力传递不均衡、施工工序繁琐、施工强度大、人力物力投入大、成本高、及现有单桅杆起吊井架在起吊过程中容易导致滑轮出现偏磨、甚至个别滑轮的轮边因受力过大而损坏,给施工安全带来极大地安全隐患的问题。

Description

单桅杆单滑轮组起吊井架及其施工方法
技术领域
[0001]本发明涉及起吊井架,特别是一种单桅杆单滑轮组起吊井架及其施工方法。
背景技术
[0002]近年来,由于煤矿建设的快速发展,矿井建设的规模也在不断扩大,与之配套的井架的施工明显增多,随着井架制造安装速度的加快,采用更为安全高效的施工方案,显得尤为突出和重要。
[0003]对于煤炭行业井架的安装来说,有众多不同的施工方法。现有的起吊井架及施工方法主要有两种:一是双桅杆或单桅杆双滑轮组起吊井架,二是单桅杆单滑轮组起吊井架。现有的双桅杆或单桅杆双滑轮组起吊井架主要存在如下问题:两套滑轮组合力起吊时起吊力的传递不均衡,并且施工工序繁琐、施工强度大、人力物力投入大、成本高;现有的采用单桅杆起吊井架主要存在如下问题:在起吊过程中,容易导致滑轮出现偏磨现象严重,甚至个别滑轮的轮边因受力过大,结果在起吊过程中出现损坏的相当严重的现实情况,给施工的安全带来极大地安全隐患。
发明内容
[0004]本发明的目的就是为了解决现有技术的不足,提供一种单桅杆单滑轮组起吊井架及其施工方法。以解决现有双桅杆双滑轮组起吊井架两套滑轮组合力起吊时起吊力的传递不均衡、并且施工工序繁琐、施工强度大、人力物力投入大、成本高、以及现有单桅杆起吊井架在起吊过程中容易导致滑轮出现偏磨现象严重、甚至个别滑轮的轮边因受力过大而出现损坏给施工的安全带来极大地安全隐患的问题。
[0005]本发明通过下述技术方案得以解决:
[0006] —种单桅杆单滑轮组起吊井架,包括主斜撑、副斜撑、天轮平台、主斜撑吊点、副斜撑吊点、桅杆,主斜撑吊点焊接在主斜撑天轮平台上,主斜撑的支腿底端铰链固定,可实现反转;桅杆顶部通过一套滑轮组连接在主斜撑吊点上,主斜撑通过主斜撑吊点、滑轮组完成主斜撑的起吊,且可实现主斜撑的翻转起吊;主斜撑上焊接有副斜撑的吊点,副斜撑通过主斜撑、连接在主斜撑与副斜撑之间的滑轮组起吊,形成井架。
[0007] —种单桅杆单滑轮组起吊井架的施工方法,按如下步骤进行:
[0008]步骤一:建立井架基础,埋设起吊铰链梁。
[0009 ]步骤二:起吊设备、桅杆的基础浇筑,井架组装。
[0010]步骤三:起重设备布置、配电,井架组装。
[0011 ]步骤四:井架组装,焊接井架起吊点、铰链。
[0012]步骤五:主斜撑组装完成,安装滑轮组、穿起吊绳,组装桅杆。
[0013]步骤六:竖立桅杆并调整桅杆。
[0014] 步骤七:起吊就位主斜撑。
[0015]步骤八:起吊就位副斜撑。
[0016]步骤九:空中组对焊接主斜撑、副斜撑。
[0017]步骤十:验收处理问题,临设拆除,施工完成。
[0018]采用上述技术方案的本发明,与现有技术相比,其有益效果是:
[0019]主斜撑的起吊仅用一个主斜撑吊点,使用一套滑轮组,便可完成主斜撑的起吊,不仅优化简化起吊工艺,而且避免了起吊点的滑轮绳索在起吊过程中转动,出现动载荷冲击问题,更为安全可靠。采用主斜撑设一个起吊点,解决了传统单桅杆或是双桅杆设两个斜撑吊点起吊主斜撑的复杂工艺,使起吊吊点更加简化合理,并克服了传统吊点与桅杆吊点斜向受拉而导致滑轮出现偏磨严重、甚至个别滑轮的轮边因受力过大出现损坏而导致安全隐患,使起吊更为安全可靠。
[0020]采用单套滑轮组起吊力的传递,消除了两套滑轮组起吊时力的不均衡问题,降低了施工准备的繁琐工艺,降低了施工强度,节省了人力物力的投入,使施工更加便捷、安全。
[0021]采用单桅杆起吊替代双桅杆起吊,能简化井架起吊施工工艺,降低成本和施工度,节省时间。
[0022]对于单桅杆底部的固定,采用长绳索替代单桅杆的根部锚粧,有效降低了施工强度,节约了施工成本。
[0023]本发明的优选方案是:
[0024]主斜撑吊点位于主斜撑天轮平台上方,井架形成后,吊点易于拆除,施工更为安全。
[0025]副斜撑顶部焊接有副斜撑吊点,副斜撑吊点为两个,带两个副斜撑吊点的副斜撑外形呈F字形。
[0026]绷绳为两根,两根绷绳分别设在桅杆两侧,两根绷绳在桅杆起吊过程中绷紧或松弛调节桅杆起立到合适位置。
[0027]主斜撑吊点和副斜撑吊点均采用无缝管。
[0028]竖立并调整桅杆步骤包括:在桅杆的30米处设吊车起吊点,要保证吊车能将桅杆抬高到20米以上;当桅杆顶端偏移达到500mm时,调整桅杆两侧的绷绳,使桅杆的偏差度在要求范围内。
[0029]起吊就位主斜撑步骤包括:在井架的地脚螺栓套筒两侧,距套筒10mm处凿好垫铁位置;将主斜撑抬顶高500mm左右时,停止起吊,检查主斜撑的各个部位、吊车及钢丝绳、基础铰链,确认无问题后方可继续起吊。
[0030]起吊就位副斜撑步骤包括:在井架的地脚螺栓套筒两侧,距套筒10mm处凿好垫铁位置;副斜撑上用白色油漆标出提升中心线;副斜撑起吊到与地面成60度角时,用吊车吊起副斜撑柱脚端往前送;副斜撑起吊到合适位置后,使用吊车把副斜撑柱脚放置到基础标线位置上,穿上地脚螺栓;当副斜撑到达要求位置时即可停止起吊,并把各起吊的凿井稳车绳进行保险固定。
[0031]空中组对焊接主斜撑、副斜撑步骤包括:主斜撑、副斜撑合拢后,利用全站仪观测井架上标识的提升中心线进行井架的找正工作,南北方向偏差通过调整起吊主副斜撑的桅杆滑轮组绳进行找正,东西方向偏差通过调整主斜撑、副斜撑柱脚下的垫铁进行找正;井架天轮平台十字中心线与设计位置允许偏差为±7mm,主斜撑、副斜撑架两底脚中心线与井架中心线的重合度允许偏差为30mmo
附图说明
[0032]图1为本发明的单桅杆单滑轮组起吊井架平面布置示意图。
[0033]图2为本发明的井架起立前初始状态示意图。
[0034]图3为本发明的井架起立且桅杆未直立状态示意图。
[0035]图4为本发明的井架起立且桅杆直立后井架未开始起吊前状态示意图。
[0036]图5为本发明的井架起立且桅杆直立后主斜撑起吊、副斜撑未起吊状态示意图。
[0037]图6为本发明的井架起立且桅杆直立后主斜撑起吊已完成、起吊副斜撑状态示意图。
[0038]图7为本发明的井架起吊完成状态示意图。
[0039]图8为本发明的主斜撑起吊受力分析示意图。
[0040] 附图标记说明:
[0041 ] I 一绷绳;2—副斜撑;3—主斜撑;4一天轮平台;5—桅杆;6—滑轮组;7—吊车;8—凿井绞车组;9一主斜撑吊点;10—副斜撑吊点;11一主销粧,吊车起吊绳12。
具体实施方式
[0042]下面结合附图1至附图7对本发明作进一步阐述,但这些实施例不对本发明构成任何限制。
[0043] —种单桅杆单滑轮组起吊井架,参见附图1至附图7,包括主斜撑3、副斜撑2、天轮平台4、主斜撑吊点9、副斜撑10、桅杆5等,主斜撑3的自重做锚粧,利用主斜撑吊点9通过吊车7将桅杆5直立,桅杆5直立后,其后部绷绳I绷紧,凿井绞车组8牵引滑轮组6,主斜撑3底部的铰链翻转起立主斜撑3;后通过主斜撑3上的滑轮组6起吊副斜撑2。
[0044]桅杆5—根,顶端前部通过滑轮组6与主斜撑吊点9相连,左右两侧通过绷绳I固定,顶端后部与主锚粧11连接。
[0045]副斜撑2顶部焊接有副斜撑吊点10。
[0046]副斜撑吊点10为两个,带两个副斜撑吊点10的副斜撑2外形为F字形。
[0047]绷绳I为两根,两根绷绳I分别设在桅杆5两侧,两根绷绳I在桅杆5起吊过程中绷紧或松弛调节桅杆5起立到合适位置。
[0048]主斜斜撑吊点9、副斜撑吊点1采用无缝管。
[0049]井架斜撑吊点的为Φ426Χ 14的无缝管,焊接在主斜撑天轮平台4的顶部,斜撑吊点焊接的角度保证主斜撑3、副斜撑2起吊到位后,斜撑吊点直立且绷绳I不滑脱,斜撑吊点起吊受力的背部焊接斜向拉条增强斜撑吊点强度;在天轮平台4的凹形处设置两根Φ219Χ10的无缝管做连接梁,消除天轮平台4的强度缺陷,保证施工安全。
[0050]桅杆5设置在主斜撑3基础的中心线位置,以桅杆5实际高38m、计算高度37m为例进行分析。主锚粧11距桅杆5中心8 Im处,主斜撑吊点9选择在天轮平台4轴中心标高位置上,主斜撑吊点9距铰链中心的距离为33155mm,主斜撑吊点9的垂直分力为151396.1kg。吊车起吊绳12、绷绳I的受力如附图8所示,其中,绷绳I拉力为f=156650kg,吊车起吊绳12拉力为F =203286kg。
[0051 ]主斜撑3铰链的强度校核分析:
[0052]下铰链预埋钢梁连接圆钢直径的选择:
[0053]井中侧预埋圆钢承担的力矩Ml:
[0054] Ml=0.5X1.1XsXh = 0.5X1.1X 135663X30 = 2238439kg.cm;
[0055]式中:h为下铰链的高度;两铰链的不均匀系数取1.1 ;s为起吊时的水平分力。
[0056] 预埋螺栓承受的拉力N:
[0057] N=M1/L1,式中:LI为预埋螺栓的计算力臂,Ll=98cm,N=22841Kg。
[0058] 选用四条Φ30的预埋螺栓,其拉应力为σ = 22841/4Χ JI X 1.5 X 1.5 = 807kg/cm2o
[0059]远离井中线侧圆钢的选择:该圆钢平衡主斜撑3自重及起吊副斜撑2时的向下的合力。
[0060] P = 0.5 X P+Q1=0.5 X 209115+0.5 X I.I X 66008 = 140862kg,式中:P为主斜撑3 自重;Ql为起吊副斜撑2时对主斜撑3的每一肢形成的附加压力计算值。
[0061 ] 预埋圆钢的拉力为吧=?\19.3/98 = 277411^,选用4根(})30圆钢时,圆钢的拉应力为981kg。
[0062]下铰链主梁的强度校核分析:
[0063] 下铰链主梁的抗弯截面系数Wl为:Wl = ( 19 X 633 —13 X 593)/6 X 63=5505cm3,下铰链的弯曲应力 ol=Ml/Wl=406Kg/cm2o
[0064]桅杆5起吊副斜撑2的分析:
[0065] 起吊副斜撑2时的钢丝绳的选择:
[0066] 起吊副斜撑2的重量为G=71807kg。
[0067] 选用两套60tX6滑车组配合1t凿井稳车进行起吊,每套滑车组承担计算荷载为Gl=G X0.5X1.2 = 71807.33X0.5X1.2=43084kg。
[0068]轮滑组6的绳端拉力为:f3=43084 X (I.0412 X 0.04)/( 1.0412-1) = 4675kg。
[0069] 轮滑组6选用Φ 23-6 X 19-155钢丝绳,钢丝的破断力总合为31200kg。
[0070]安全系数 η = 31200/4675 = 6.6。
[0071]起吊主斜撑3的校核:
[0072]斜撑吊点设在主斜撑3上部天轮平台4的轴承座板上,斜撑吊点中心在天轮平台4梁的3道横向立筋的中间,立筋和纵向整体立筋交点处。斜撑吊点采用Φ 426X14的无缝钢管,焊接固定在井架轴承座底板上。Φ 426 X 14的无缝钢管向后成70°角与轴承座底板焊接固定。Φ 426 X 14的管内加井子形通长立筋,筋板厚度为12mm。在天轮平台4的凹槽处内用I根Φ 325 X 10的无缝钢管在两吊点的下方面紧贴位置支撑连接固定。在吊点的后面通过20mm厚200mm长的两个拉筋拉固,拉筋与底面成45%
[0073] 起吊总拉力为:203268 Kg。
[0074]天轮平台上吊点绳扣的夹角按45Q计算,单绳扣拉力为116600 Kg0
[0075] [T]=125Mpa,F=116600 Kg。
[0076]需剪切的面积 A2F/[T]=9328mm2。
[0077] φ 426 X 14的钢管割坡口焊接面积(Al):
[0078] Al=(426-14) X 3.14 X 14=18111mm2 >9328mm2 安全。
[0079] —种单桅杆单滑轮组起吊井架的施工方法,施工步骤如下:
[0080]步骤一:建立井架基础,埋设起吊铰链梁。[0081 ]步骤二:起吊设备、桅杆5的基础浇筑,井架组装。
[0082]步骤三:起重设备布置、配电,井架组装。
[0083]步骤四:井架组装,焊接井架起吊点、铰链。
[0084]步骤五:主斜撑3组装完成,安装滑轮组、穿起吊绳,组装桅杆5。
[0085] 步骤六:竖立桅杆5并调整桅杆5。
[0086] 步骤七:起吊就位主斜撑3。
[0087]步骤八:起吊就位副斜撑2。
[0088] 步骤九:空中组对焊接主斜撑3、副斜撑2。
[0089]步骤十:验收处理问题,临设拆除,施工完成。
[0090]竖立并调整桅杆5步骤包括:在桅杆5的30米处设吊车7的起吊点,要保证吊车7能将桅杆5抬高到20米以上;当桅杆5顶端偏移达到500mm时,调整桅杆5两侧的绷绳I,使桅杆5的偏差度在要求范围内。
[0091]起吊就位主斜撑3步骤包括:在井架的地脚螺栓套筒两侧,距套筒10mm处凿好垫铁位置;将主斜撑3抬顶高500mm左右时,停止起吊,检查主斜撑3的各个部位、吊车7及钢丝绳、基础铰链,确认无问题后方可继续起吊。
[0092]起吊就位副斜撑2步骤包括:在井架的地脚螺栓套筒两侧,距套筒10mm处凿好垫铁位置;副斜撑2上用白色油漆标出提升中心线;副斜撑2起吊到与地面成60度角时,用吊车7吊起副斜撑2柱脚端往前送;副斜撑2起吊到合适位置后,使用吊车7把副斜撑2柱脚放置到基础标线位置上,穿上地脚螺栓;当副斜撑2到达要求位置时即可停止起吊,并把各起吊的凿井稳车绳进行保险固定。
[0093]空中组对焊接主斜撑3、副斜撑2步骤包括:主斜撑3、副斜撑2合拢后,利用全站仪观测井架上标识的提升中心线进行井架的找正工作,南北方向偏差通过调整起吊主副斜撑的桅杆滑轮组绳进行找正,东西方向偏差通过调整主斜撑3、副斜撑2柱脚下的垫铁进行找正;井架天轮平台4十字中心线与设计位置允许偏差为±7mm,主斜撑3、副斜撑2架两底脚中心线与井架中心线的重合度允许偏差为30mm。
[0094]本领域技术人员不脱离本发明的实质和精神,可以有多种变形方案实现本发明,以上所述仅为本发明较佳可行的实施例而已,并非因此局限本发明的权利范围,凡运用本发明说明书及附图内容所作的等效结构变化,均包含于本发明的权利范围之内。

Claims (1)

1.一种单桅杆单滑轮组起吊井架的施工方法,单桅杆单滑轮组起吊井架包括主斜撑(3)、副斜撑(2)、天轮平台(4)、主斜撑吊点(9)、副斜撑吊点(10)、桅杆(5),主斜撑吊点(9)焊接在主斜撑天轮平台(4)上,主斜撑(3)的支腿底端铰链固定;桅杆(5)顶部通过一套滑轮组(6)连接在主斜撑吊点(9)上,主斜撑(3)通过主斜撑吊点(9)、滑轮组(6)起吊;主斜撑(3)上焊接有副斜撑的吊点(10),副斜撑(2)通过主斜撑(3)、连接在主斜撑(3)与副斜撑(2)之间的滑轮组(6)起吊;主斜撑吊点(9)位于主斜撑天轮平台(4)上方;副斜撑(2)顶部焊接有副斜撑吊点,副斜撑吊点为两个,带两个副斜撑吊点的副斜撑外形呈F字形;绷绳(I)为两根,两根绷绳(I)分别设在桅杆(5)两侧,两根绷绳(I)在桅杆(5)起吊过程中绷紧或松弛调节桅杆(5)起立到合适位置;主斜撑吊点(9)和副斜撑吊点(10)均采用无缝管;其特征在于:单桅杆单滑轮组起吊井架的施工方法,按如下步骤进行: 步骤一:建立井架基础,埋设起吊铰链梁; 步骤二:起吊设备、桅杆的基础浇筑,井架组装; 步骤三:起重设备布置、配电,井架组装; 步骤四:井架组装,焊接井架起吊点、铰链; 步骤五:主斜撑组装完成,安装滑轮组、穿起吊绳,组装桅杆; 步骤六:竖立桅杆并调整桅杆;竖立并调整桅杆步骤包括:在桅杆的30米处设吊车起吊点,要保证吊车能将桅杆抬高到20米以上;当桅杆顶端偏移达到500mm时,调整桅杆两侧的绷绳,使桅杆的偏差度在要求范围内; 步骤七:起吊就位主斜撑;起吊就位主斜撑步骤包括:在井架的地脚螺栓套筒两侧,距套筒10mm处凿好垫铁位置;将主斜撑抬顶高500mm左右时,停止起吊,检查主斜撑的各个部位、吊车及钢丝绳、基础铰链,确认无问题后方可继续起吊; 步骤八:起吊就位副斜撑;起吊就位副斜撑步骤包括:在井架的地脚螺栓套筒两侧,距套筒10mm处凿好垫铁位置;副斜撑上用白色油漆标出提升中心线;副斜撑起吊到与地面成60度角时,用吊车吊起副斜撑柱脚端往前送;副斜撑起吊到合适位置后,使用吊车把副斜撑柱脚放置到基础标线位置上,穿上地脚螺栓;当副斜撑到达要求位置时即停止起吊,并把各起吊的凿井稳车绳进行保险固定; 步骤九:空中组对焊接主斜撑、副斜撑;空中组对焊接主斜撑、副斜撑步骤包括:主斜撑、副斜撑合拢后,利用全站仪观测井架上标识的提升中心线进行井架的找正工作,南北方向偏差通过调整起吊主副斜撑的桅杆滑轮组绳进行找正,东西方向偏差通过调整主斜撑、副斜撑柱脚下的垫铁进行找正;井架天轮平台十字中心线与设计位置允许偏差为±7mm,主斜撑、副斜撑架两底脚中心线与井架中心线的重合度允许偏差为30mm; 步骤十:验收处理问题,临设拆除,施工完成。
CN201510037616.0A 2015-01-26 2015-01-26 单桅杆单滑轮组起吊井架及其施工方法 Active CN104555756B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510037616.0A CN104555756B (zh) 2015-01-26 2015-01-26 单桅杆单滑轮组起吊井架及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510037616.0A CN104555756B (zh) 2015-01-26 2015-01-26 单桅杆单滑轮组起吊井架及其施工方法

Publications (2)

Publication Number Publication Date
CN104555756A CN104555756A (zh) 2015-04-29
CN104555756B true CN104555756B (zh) 2016-08-24

Family

ID=53072979

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510037616.0A Active CN104555756B (zh) 2015-01-26 2015-01-26 单桅杆单滑轮组起吊井架及其施工方法

Country Status (1)

Country Link
CN (1) CN104555756B (zh)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB760186A (en) * 1954-02-03 1956-10-31 Moore Corp Lee C Improvements in or relating to portable oil well derricks
CN101581198A (zh) * 2009-04-25 2009-11-18 中煤第七十一工程处 箱型井架空中吊装对接方法
CN102910532A (zh) * 2012-05-23 2013-02-06 中煤第三建设(集团)有限责任公司 大型箱型井架空中对接起吊方法
CN102923595A (zh) * 2012-10-12 2013-02-13 中国华冶科工集团有限公司 大型井架的起立设备和起立方法
CN103803394A (zh) * 2014-02-20 2014-05-21 中煤第三建设(集团)有限责任公司 混凝土井塔外套装竖立大型箱型钢结构井架的起吊方法
CN204416961U (zh) * 2015-01-26 2015-06-24 唐山开滦建设(集团)有限责任公司 单桅杆单滑轮组起吊井架

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB760186A (en) * 1954-02-03 1956-10-31 Moore Corp Lee C Improvements in or relating to portable oil well derricks
CN101581198A (zh) * 2009-04-25 2009-11-18 中煤第七十一工程处 箱型井架空中吊装对接方法
CN102910532A (zh) * 2012-05-23 2013-02-06 中煤第三建设(集团)有限责任公司 大型箱型井架空中对接起吊方法
CN102923595A (zh) * 2012-10-12 2013-02-13 中国华冶科工集团有限公司 大型井架的起立设备和起立方法
CN103803394A (zh) * 2014-02-20 2014-05-21 中煤第三建设(集团)有限责任公司 混凝土井塔外套装竖立大型箱型钢结构井架的起吊方法
CN204416961U (zh) * 2015-01-26 2015-06-24 唐山开滦建设(集团)有限责任公司 单桅杆单滑轮组起吊井架

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
单抱杆单滑轮组起立井架工艺;宋震;《中国外资》;20110630(第12期);269 *
单桅杆在橹式井架吊装中的应用;付运林;《中州煤炭》;20080331(第3期);89-92 *

Also Published As

Publication number Publication date
CN104555756A (zh) 2015-04-29

Similar Documents

Publication Publication Date Title
CN107191676A (zh) 埋地管道施工方法
CN103883129B (zh) 一种钢结构屋面梁安装方法
CN104989111B (zh) 钢结构高层吊装施工方法
CN104612407B (zh) 一种异型钢筋混凝土预制柱的吊装方法
CN103630416A (zh) 卷扬机构的试验平台
CN103132702A (zh) 一种大跨度管桁架拔杆提升、空中施转就位施工方法
CN101109028A (zh) 转炉炉壳倒装液压提升方法
JP4099491B2 (ja) ヘリコプタによる鉄塔組立工法及び作業用治具
CN204416961U (zh) 单桅杆单滑轮组起吊井架
CN104555756B (zh) 单桅杆单滑轮组起吊井架及其施工方法
CN109110638A (zh) 高炉大修炉壳吊装工具
CN103615198A (zh) 并列式双桅杆半翻转法起吊大型箱式井架施工方法
CN205741942U (zh) 一种大悬臂挑臂墩帽梁装配式支架
CN101016827A (zh) 18米液压起落可伸缩式钻塔
CN211689943U (zh) 装配式墩柱模板翻转缓冲装置
CN204252839U (zh) 一种水平拼接式天车梁
CN105822132A (zh) 一种特高压输电铁塔的单元式组立方法
CN2893124Y (zh) 井架支撑装置
NL2011985C2 (en) Saddle and hook system.
JP3717910B2 (ja) ヘリコプタによる鉄塔組立工法
CN110980507A (zh) 一种薄壁圆管塔架模块吊装用吊耳结构
CN206108724U (zh) 长大直径桩基钢筋笼自制简易安装支架装置
CN110331672A (zh) 桥梁侧位跨墩提梁支架装置及其简易快速施工方法
CN206140435U (zh) 明挖基坑钢支撑拼装台架
CN106320525B (zh) 采光井顶棚大跨度圆钢管桁架旋转滑移施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant