CN104538891B - A kind of composite insulator outlet method - Google Patents
A kind of composite insulator outlet method Download PDFInfo
- Publication number
- CN104538891B CN104538891B CN201410775945.0A CN201410775945A CN104538891B CN 104538891 B CN104538891 B CN 104538891B CN 201410775945 A CN201410775945 A CN 201410775945A CN 104538891 B CN104538891 B CN 104538891B
- Authority
- CN
- China
- Prior art keywords
- plate
- hook
- connecting plate
- bridge
- composite insulator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Insulators (AREA)
- Insulating Bodies (AREA)
Abstract
本发明公开了一种合成绝缘子出线方法,提供一种合成绝缘子出线桥,包括有导线侧联板挂钩、绝缘桥板、张紧装置、横担侧联板挂钩,横担侧联板挂钩与张紧装置的一端相连,张紧装置的另一端与绝缘桥板相连,绝缘上桥板的另一端则导线侧联板挂钩相连,本发明的出线方法,使现场作业人员迅速顺利高效地完成了停电检修工作。现场作业人员反映,220kV垂直排列合成绝缘子串出线桥设计合理、重量轻、携带方便;安装、拆除简单,劳动强度小,所需人员少,现场应用效果良好。
The invention discloses a composite insulator outgoing line method, and provides a composite insulator outgoing line bridge, which includes a wire side connecting plate hook, an insulating bridge plate, a tensioning device, a cross-arm side connecting plate hook, a cross-arm side connecting plate hook and a tensioner. One end of the tensioning device is connected, the other end of the tensioning device is connected to the insulating bridge plate, and the other end of the insulating upper bridge plate is connected to the hook of the wire side connecting plate. The method of wire outlet of the present invention enables the field workers to complete the power failure quickly, smoothly and efficiently. Overhaul work. According to the on-site workers, the 220kV vertically arranged composite insulator string outlet bridge is reasonable in design, light in weight, and easy to carry; it is easy to install and dismantle, with low labor intensity and less personnel required, and the on-site application effect is good.
Description
技术领域technical field
本发明涉及一种出线方法,特别是一种合成绝缘子出线方法 。The present invention relates to a wire outlet method, in particular to a composite insulator wire outlet method.
背景技术Background technique
目前采用垂直排列合成绝缘子串的220kV耐张杆塔不断增多,在进行此类线路停电检修作业时,作业人员必须沿着绝缘子串出导线进行线夹、金具等检修或检查。由于绝缘子串禁止踩踏,如没有合适的出线工具就必须使用较为笨重的梯子等代替。由于采用垂直排列的220kV耐张合成绝缘子串,从横担到导线的距离一般会达到4m左右,如果使用类似梯子、管材等直接架设过渡的方法,因为距离较远所用的梯子或管材需考虑到承受作业人员人体荷载后,也需要增大截面,若再考虑使用绝缘材料,整个出线工具的重量将达到20-30kg,现场使用极为不便。由于线路检修点多面广且作业点大都位于高山、高塔之上,这样将大大增加作业人员的劳动强度,急需研制轻便易于携带的出线方法。At present, the number of 220kV tension poles and towers using vertically arranged synthetic insulator strings is increasing. When performing power outage maintenance operations on such lines, operators must follow the insulator strings out of the wires for maintenance or inspection of clamps, fittings, etc. Since the insulator strings are forbidden to be stepped on, if there is no suitable outlet tool, a relatively cumbersome ladder must be used instead. Due to the use of vertically arranged 220kV tensile composite insulator strings, the distance from the cross arm to the conductor will generally reach about 4m. If a method such as a ladder or pipe is used to directly erect the transition, the ladder or pipe used for the long distance needs to be considered. After bearing the human body load of the workers, the cross-section also needs to be enlarged. If the use of insulating materials is considered, the weight of the entire outlet tool will reach 20-30kg, which is extremely inconvenient to use on site. Since the line maintenance points are many and wide and most of the operating points are located on high mountains and high towers, this will greatly increase the labor intensity of the operators, and it is urgent to develop a light and easy-to-carry outlet method.
发明内容Contents of the invention
本发明的目的在于克服现有技术的不足之处,而提供一种便于携带,并可快速安装在绝缘子串前后联板之间的合成绝缘子出线方法。The purpose of the present invention is to overcome the shortcomings of the prior art, and provide a composite insulator outlet method that is easy to carry and can be quickly installed between the front and rear connecting plates of the insulator string.
一种合成绝缘子出线方法,提供一种合成绝缘子出线桥, 包括有导线侧联板挂钩、绝缘桥板、张紧装置、横担侧联板挂钩,所述的导线侧联板为方型,导线侧联板挂钩包括片状的连接板,连接板的一端设置有与绝缘桥板相配合的连接件,连接板与连接件为垂直交叉布置,连接件活动连接的锁于绝缘桥 板上,在连接件的另一端设置有可钩入方形联板的钩槽,在连接件上还设置有与连接件相垂直的支撑腿,支撑腿支撑于双联碗头处,A composite insulator outlet method, providing a composite insulator outlet bridge, including a wire side connecting plate hook, an insulating bridge plate, a tensioning device, a cross arm side connecting plate hook, the wire side connecting plate is square, and the wire The side plate hook includes a sheet-shaped connecting plate. One end of the connecting plate is provided with a connecting piece matched with the insulating bridge plate. The connecting plate and the connecting piece are vertically intersected. The other end of the connector is provided with a hook groove that can be hooked into the square connecting plate, and a support leg perpendicular to the connector is also provided on the connector, and the support leg is supported at the double bowl head.
所述的绝缘桥板为由几段联接而成,几段之间采用可拆卸式的活动联接;The insulating bridge plate is formed by connecting several sections, and a detachable movable connection is adopted between several sections;
所述的张紧装置为丝杆装置;The tensioning device is a screw device;
所述的横担侧联板挂钩包括有片状的支撑板,所述的支撑板的端部设置有一个辅助挂钩,所述的辅助挂钩包括有带螺纹的挂杆,在支撑板的端部设置有连接块,在连接块上设置有供挂杆穿过的螺纹孔,该螺纹孔的轴线与支撑板平行,在螺纹孔上方与下方的挂杆上均设置有定位螺母,支撑板上沿支撑板的长度方向设置有一排的定位孔,还包括有一个可卡入横担侧三角联板的钩槽,该钩槽可根据绝缘子串的长度选择锁在支撑板的任意定位孔处从而适应不同的绝缘子串,The cross-arm side link plate hook includes a sheet-shaped support plate, and an auxiliary hook is provided at the end of the support plate. The auxiliary hook includes a threaded hanging rod, and the end of the support plate A connecting block is provided, and a threaded hole for the hanging rod to pass through is arranged on the connecting block. There is a row of positioning holes in the length direction of the support plate, and a hook slot that can be snapped into the triangular plate on the side of the cross arm. The hook slot can be locked at any positioning hole of the support plate according to the length of the insulator string to adapt to different insulator strings,
横担侧联板挂钩与张紧装置的一端相连,张紧装置的另一端与绝缘桥板相连,绝缘上桥板的另一端则导线侧联板挂钩相连,出线时(1)由停电检修作业人员到达待检修的杆塔位置,先将工具的折叠部件组装成待用状态,The hook of the cross-arm side connecting plate is connected with one end of the tensioning device, the other end of the tensioning device is connected with the insulating bridge plate, and the other end of the insulating upper bridge plate is connected with the wire side connecting plate hook. When personnel arrive at the tower to be overhauled, they first assemble the folded parts of the tool into a ready-to-use state,
(2)作业人员携带一条传递绳登塔至待检修的绝缘子串位置,通过传递绳将合成绝缘子出线桥传递至杆塔上,(2) The operator carries a transfer rope to the tower to the position of the insulator string to be repaired, and transfers the composite insulator outlet bridge to the tower through the transfer rope.
(3)作业人员绑好双控安全带,移位至耐张绝缘子串三角联板处,手持组装好的合成绝缘子出线桥,先将导线侧联板挂钩挂在方型联板上并将支腿支撑到位,然后将横担侧联板挂钩挂在三角联板上挂好辅助钩,(3) The operator fastens the double-control safety belt, moves to the tension insulator series triangular connecting plate, holds the assembled composite insulator outlet bridge, first hangs the wire side connecting plate hook on the square connecting plate and The legs are supported in place, then hang the hook of the cross-arm side plate on the triangular plate and hang the auxiliary hook,
(4)作业人员收紧张紧装置的丝杆,使出线桥处于紧绷状态,(4) The operator tightens the screw rod of the tensioning device so that the outlet bridge is in a tight state,
(5)作业人员将安全带移到合成绝缘子串上,采取蹲式脚踩出线桥手扶着垂直排列的上串绝缘子,由横担侧向导线侧小步移动进行出线,(5) The operator moves the safety belt to the synthetic insulator string, adopts a squatting foot step on the outgoing line bridge and holds the vertically arranged upper string of insulators, and moves from the side of the cross arm to the conductor side in small steps to exit the line.
(6)导线部位检修工作完成后,作业人员沿出线桥返回横担侧,松出张紧装置的丝杆,拆除出线桥转移到另外一相,重复以上动作直至作业完成。(6) After the maintenance work of the wire part is completed, the operator returns to the cross arm side along the outlet bridge, loosens the screw rod of the tensioning device, removes the outlet bridge and transfers to another phase, and repeats the above actions until the work is completed.
所述的支撑腿为伸缩式支撑腿。The supporting legs are telescopic supporting legs.
实现伸缩式支撑腿的结构有很多,其或为由多节管两两铰接在一起,或为由两节管套叠在一起后,在相互的接触面设置螺纹配合。There are many structures for realizing the telescopic supporting legs, which are either hinged together by multi-section tubes in pairs, or after two tubes are nested together, screw fits are provided on the mutual contact surfaces.
所述的丝杆装置为双行程丝杆装置。The screw device is a double-stroke screw device.
所述的绝缘桥板采用酚醛环氧树脂玻璃钢层压板。The insulating bridge board is made of phenolic epoxy resin fiberglass laminated board.
耐张绝缘子串出线桥安装在导线与横担之间,导线上如果存在感应电压,就有可能通过出线桥传导至作业人员身体部位,出现电击危险,同时,还有可能出现作业人员误登杆,误将出线桥安装在带电导线上的情况,这就需要出线桥的桥板,既要有较高的绝缘强度又要有一定的机械强度,因此采用酚醛环氧树脂玻璃钢层压板。The tension insulator series outlet bridge is installed between the wire and the cross arm. If there is an induced voltage on the wire, it may be transmitted to the body of the operator through the outlet bridge, causing electric shock hazards. At the same time, the operator may accidentally step on the pole , Mistakenly install the outlet bridge on the live wire, which requires the bridge plate of the outlet bridge, which must have high insulation strength and certain mechanical strength, so the phenolic epoxy resin FRP laminate is used.
综上所述的,本发明相比现有技术如下优点:In summary, compared with the prior art, the present invention has the following advantages:
本发明的合成绝缘子串出线方法,可以有效解决采用耐张垂直排列合成绝缘子串的220kV输电线路停电检修。创新性地采用了张紧方式安装,将工具的横向荷载转化为纵向的张力,大大减轻了工具的重量,该工具可以单人操作进行安装和拆除。由于出线桥的桥板采用了高强度绝缘材料,还可防止感应触电和误登杆触电。该成套工具由导线侧联板挂钩、绝缘桥板、张紧器、横担侧联板挂钩等部件组成,具有体积小、质量轻,操作简单方便,易于携带等优点,完成一次出线桥安装仅仅需5-10min,极大程度地减轻了作业人员的劳动强度,提高工作效率和作业安全性。The composite insulator string outlet method of the present invention can effectively solve the power outage maintenance of the 220kV power transmission line using the composite insulator string arranged vertically in tension. It innovatively adopts the tensioning method for installation, which converts the lateral load of the tool into longitudinal tension, which greatly reduces the weight of the tool, and the tool can be installed and removed by one person. Because the bridge plate of the outlet bridge adopts high-strength insulating material, it can also prevent electric shock by induction and electric shock by mistakenly boarding the pole. The complete set of tools is composed of wire side connecting plate hooks, insulating bridge plates, tensioners, cross arm side connecting plate hooks and other components. It has the advantages of small size, light weight, simple and convenient operation, and easy to carry. It takes 5-10 minutes, which greatly reduces the labor intensity of operators and improves work efficiency and safety.
本工具研制完成后,在模拟线路上进行了多次试用,在耐张塔的停电检修中进行了应用。采用新研制的合成绝缘子串出线桥,现场作业人员迅速顺利高效地完成了停电检修工作。现场作业人员反映,220kV垂直排列合成绝缘子串出线桥设计合理、重量轻、携带方便;安装、拆除简单,劳动强度小,所需人员少,现场应用效果良好。After the development of this tool is completed, it has been tried many times on the simulated circuit, and it has been applied in the power-off maintenance of the tension tower. Adopting the newly developed composite insulator string outlet bridge, the on-site operators quickly, smoothly and efficiently completed the power outage maintenance work. According to the on-site workers, the 220kV vertically arranged composite insulator string outlet bridge is reasonable in design, light in weight, and easy to carry; it is easy to install and dismantle, with low labor intensity and less personnel required, and the on-site application effect is good.
附图说明Description of drawings
图1为本发明的合成绝缘子串出线桥结构示意图。Fig. 1 is a schematic structural diagram of a composite insulator string bridge of the present invention.
图2是图1的俯视图。FIG. 2 is a top view of FIG. 1 .
标号说明 1导线侧联板挂钩11连接板111连接件1111连接板的钩槽12支撑腿2绝缘桥板3张紧装置4横担侧联板挂钩41支撑板411支撑板上的定位孔42辅助挂钩43挂杆44定位螺母45钩槽46连接块。Reference Signs Explanation 1 wire side connecting plate hook 11 connecting plate 111 connecting piece 1111 hook groove of connecting plate 12 supporting leg 2 insulating bridge plate 3 tensioning device 4 cross arm side connecting plate hook 41 supporting plate 411 positioning hole 42 auxiliary on supporting plate Hook 43 hanging rod 44 positioning nut 45 hook groove 46 connecting block.
具体实施方式detailed description
下面结合实施例对本发明进行更详细的描述。The present invention will be described in more detail below in conjunction with examples.
实施例1Example 1
一种合成绝缘子出线桥, 包括有导线侧联板挂钩1、绝缘桥板2、张紧装置3、横担侧联板挂钩4,所述的导线侧联板为方型,导线侧联板挂钩包括片状的连接板11,连接板的一端设置有与绝缘桥板相配合的连接件111,连接板与连接件为垂直交叉布置,连接件活动连接的锁于绝缘桥 板上,在连接件的另一端设置有可钩入方形联板的钩槽1111,在连接件上还设置有与连接件相垂直的支撑腿12,支撑腿支撑于双联碗头处,A composite insulator outlet bridge, including a wire side connecting plate hook 1, an insulating bridge plate 2, a tensioning device 3, and a cross arm side connecting plate hook 4, the conducting wire side connecting plate is square, and the conducting wire side connecting plate hook It includes a sheet-shaped connecting plate 11. One end of the connecting plate is provided with a connecting piece 111 that matches the insulating bridge plate. The connecting plate and the connecting piece are vertically intersected. The connecting piece is movably connected to the insulating bridge plate. The other end is provided with a hook groove 1111 that can be hooked into the square connecting plate, and a supporting leg 12 perpendicular to the connecting piece is also provided on the connecting piece, and the supporting leg is supported at the double bowl head.
所述的绝缘桥板为由几段联接而成,几段之间采用可拆卸式的活动联接;The insulating bridge plate is formed by connecting several sections, and a detachable movable connection is adopted between several sections;
所述的张紧装置为丝杆装置;The tensioning device is a screw device;
所述的横担侧联板挂钩4包括有片状的支撑板41,所述的支撑板的端部设置有一个辅助挂钩42,所述的辅助挂钩包括有带螺纹的挂杆43,在支撑板的端部设置有连接块46,在连接块上设置有供挂杆穿过的螺纹孔,该螺纹孔的轴线与支撑板平行,在螺纹孔上方与下方的挂杆上均设置有定位螺母44,支撑板上沿支撑板的长度方向设置有一排的定位孔411,还包括有一个可卡入横担侧三角联板的钩槽45,该钩槽可根据绝缘子串的长度选择锁在支撑板的任意定位孔处从而适应不同的绝缘子串,The cross-arm side link plate hook 4 includes a sheet-shaped support plate 41, an auxiliary hook 42 is provided at the end of the support plate, and the auxiliary hook includes a threaded hanging rod 43, which is The end of the plate is provided with a connecting block 46, and a threaded hole for the hanging rod to pass is arranged on the connecting block. 44. There is a row of positioning holes 411 on the support plate along the length direction of the support plate, and a hook groove 45 that can be snapped into the triangular joint plate on the side of the cross arm. The hook groove can be selected and locked on the support according to the length of the insulator string. Any positioning hole of the board to adapt to different insulator strings,
横担侧联板挂钩与张紧装置的一端相连,张紧装置的另一端与绝缘桥板相连,绝缘上桥板的另一端则导线侧联板挂钩相连。所述的支撑腿为伸缩式支撑腿。所述的丝杆装置为双行程丝杆装置。所述的绝缘桥板采用酚醛环氧树脂玻璃钢层压板。The hook of the cross arm side connecting plate is connected with one end of the tensioning device, the other end of the tensioning device is connected with the insulating bridge plate, and the other end of the insulating upper bridge plate is connected with the wire side connecting plate hook. The supporting legs are telescopic supporting legs. The screw device is a double-stroke screw device. The insulating bridge board is made of phenolic epoxy resin fiberglass laminated board.
本实施例未述部分与现有技术相同。The parts not described in this embodiment are the same as the prior art.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410775945.0A CN104538891B (en) | 2014-12-15 | 2014-12-15 | A kind of composite insulator outlet method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410775945.0A CN104538891B (en) | 2014-12-15 | 2014-12-15 | A kind of composite insulator outlet method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN104538891A CN104538891A (en) | 2015-04-22 |
| CN104538891B true CN104538891B (en) | 2017-09-26 |
Family
ID=52854383
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201410775945.0A Active CN104538891B (en) | 2014-12-15 | 2014-12-15 | A kind of composite insulator outlet method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104538891B (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108551141B (en) * | 2018-04-23 | 2021-03-23 | 李宪宝 | Suspension insulator hoisting quick-release clamp and mounting method |
| CN110571704A (en) * | 2019-08-30 | 2019-12-13 | 贵州电网有限责任公司 | Tool and method suitable for disassembling B-phase drainage line insulator of strain tower |
Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN200969494Y (en) * | 2006-11-03 | 2007-10-31 | 福建省福州电业局 | Portable tangent towers, anchor towers outlet tools |
| KR200438937Y1 (en) * | 2007-03-06 | 2008-03-12 | 주식회사 한발 | Work ladder for checking polymer insulators in transmission line |
| CN201298695Y (en) * | 2008-11-05 | 2009-08-26 | 河南省电力公司信阳供电公司 | Wire-outlet rack for a power transmission line to change a tension resistant insulator |
| CN201868790U (en) * | 2010-12-06 | 2011-06-15 | 河南省电力公司濮阳供电公司 | Insulating gap bridge for repairing power lines |
| JP2011171256A (en) * | 2010-02-22 | 2011-09-01 | Chugoku Electric Power Co Inc:The | Device and method for fixing insulator chain |
| CN103227431A (en) * | 2013-03-19 | 2013-07-31 | 国家电网公司 | Method for replacing insulator chains in 220 kV long-span high tower in live working |
| CN203787859U (en) * | 2014-03-28 | 2014-08-20 | 国家电网公司 | Portable derrick applied to transmission line overhauling |
| JP2014183688A (en) * | 2013-03-21 | 2014-09-29 | Chugoku Electric Power Co Inc:The | Load cancellation device for insulator |
| CN203859440U (en) * | 2014-04-22 | 2014-10-01 | 国家电网公司 | 110kV tension double-string composite insulator loss prevention device |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102882157B (en) * | 2012-10-30 | 2015-05-13 | 国家电网公司 | Portable shockproof hammer tool for replacing tension wire in power cut |
-
2014
- 2014-12-15 CN CN201410775945.0A patent/CN104538891B/en active Active
Patent Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN200969494Y (en) * | 2006-11-03 | 2007-10-31 | 福建省福州电业局 | Portable tangent towers, anchor towers outlet tools |
| KR200438937Y1 (en) * | 2007-03-06 | 2008-03-12 | 주식회사 한발 | Work ladder for checking polymer insulators in transmission line |
| CN201298695Y (en) * | 2008-11-05 | 2009-08-26 | 河南省电力公司信阳供电公司 | Wire-outlet rack for a power transmission line to change a tension resistant insulator |
| JP2011171256A (en) * | 2010-02-22 | 2011-09-01 | Chugoku Electric Power Co Inc:The | Device and method for fixing insulator chain |
| CN201868790U (en) * | 2010-12-06 | 2011-06-15 | 河南省电力公司濮阳供电公司 | Insulating gap bridge for repairing power lines |
| CN103227431A (en) * | 2013-03-19 | 2013-07-31 | 国家电网公司 | Method for replacing insulator chains in 220 kV long-span high tower in live working |
| JP2014183688A (en) * | 2013-03-21 | 2014-09-29 | Chugoku Electric Power Co Inc:The | Load cancellation device for insulator |
| CN203787859U (en) * | 2014-03-28 | 2014-08-20 | 国家电网公司 | Portable derrick applied to transmission line overhauling |
| CN203859440U (en) * | 2014-04-22 | 2014-10-01 | 国家电网公司 | 110kV tension double-string composite insulator loss prevention device |
Also Published As
| Publication number | Publication date |
|---|---|
| CN104538891A (en) | 2015-04-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104993421B (en) | A kind of portable pay-off crossing frame | |
| CN105932599A (en) | Tool set capable of replacing insulator chain of ultra-high-voltage transmission line under electrified state and use method for tool set | |
| CN204645808U (en) | Bar stepped on by cement pole cable | |
| CN105606858A (en) | A polycarbonate electric meter box fixing frame | |
| CN205791227U (en) | Charged for replacement UHV transmission line insulator chain tool set | |
| CN104538891B (en) | A kind of composite insulator outlet method | |
| CN203339564U (en) | High-altitude extended wiring pliers | |
| CN204793847U (en) | Frame is strideed across to portable unwrapping wire | |
| CN204947468U (en) | For the operating desk of pole guy end portion treatment | |
| CN204441795U (en) | Synthetic insulator outlet bridge | |
| CN202572183U (en) | Large-current telescopic high-altitude cable connecting clamp | |
| CN202917892U (en) | Replacing tool for supporting insulator of tubular busbar | |
| CN206964913U (en) | The safety belt hanging bracket of Fast Installation | |
| CN104505768B (en) | Composite insulator outlet bridge | |
| CN204809746U (en) | Special flexible hard ladder of special high voltage direct current circuit strain insulator tower of 800kV | |
| CN209822060U (en) | Multifunctional combined training facility for simulation low-voltage distribution line | |
| CN200969494Y (en) | Portable tangent towers, anchor towers outlet tools | |
| CN205178388U (en) | Two cluster insulators of straight line are changed and are connected | |
| CN205400233U (en) | Install cross arm on wire pole | |
| CN203456795U (en) | Conductor-side link plate clamping tool for replacing four-split conductor duplex strain insulator string | |
| CN202258580U (en) | Wire incoming and outgoing rack for 110kV line strain composite insulator string | |
| CN201518397U (en) | 220kV line conductor live replacement linear insulator string tool | |
| CN101771252B (en) | Device and method for electriferous replacement of phase-to-phase insulators of 220 KV compact line | |
| CN105790158A (en) | Special tools for live replacement of 35kV tension insulator strings | |
| CN205029157U (en) | High voltage electricity circuit earth connection action bars |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |