CN104328742B - A kind of construction method of trestle waterborne - Google Patents
A kind of construction method of trestle waterborne Download PDFInfo
- Publication number
- CN104328742B CN104328742B CN201410647127.2A CN201410647127A CN104328742B CN 104328742 B CN104328742 B CN 104328742B CN 201410647127 A CN201410647127 A CN 201410647127A CN 104328742 B CN104328742 B CN 104328742B
- Authority
- CN
- China
- Prior art keywords
- supporting pile
- rear support
- trestle
- support leg
- supporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/06—Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
- E01D21/065—Incremental launching
Abstract
The invention discloses a kind of construction method of trestle waterborne, relate to field of bridge construction, the method comprises the following steps: preset sections passage, be horizontally disposed with mobile platform at the top of sections passage, the infield of specifying at the bottom arranges the first fixing hole, the second fixing hole, the first stake holes, the second stake holes, prism of third order hole and the 4th stake holes; Adjustment mobile platform, adjust the first rear support leg, the second rear support leg, first front leg strut is inserted in the first fixing hole, second front leg strut inserts in the second fixing hole, adjust the first rear support leg, the second rear support leg, use pile driving rig that the 9th supporting pile is squeezed into the first stake holes, the tenth supporting pile is squeezed into the second stake holes, 11 supporting pile is squeezed into prism of third order hole, and the 4th stake holes is squeezed in twelve earthly branches support stake; Hoisting overhead travelling crane first captures to be treated frame sections and is placed into assigned address.The present invention can shorten the duration of construction, reduces construction cost, completes the construction of large span trestle waterborne.
Description
Technical field
The present invention relates to field of bridge construction, be specifically related to a kind of construction method of trestle waterborne.
Background technology
Along with Chinese large-sized on-water bridge build growing, trestle waterborne construction also gets more and more.Existing trestle construction waterborne adopts halieutics and crane barge construction method usually.
During halieutics construction, the first hole of first construction bridge, then to be constructed basis, next hole and trestle work structure by packaged type full circle swinging loop wheel machine.
In crane barge method work progress, first prepare large-scale floating crane and barge, then other construction equipments are positioned on barge, realize trestle construction by the operation of large-scale floating crane.
There is following defect in existing trestle construction method waterborne:
(1) environment of over-water construction is poor, the situation that the stream that there will be that the wave is high is anxious, and now, adopt halieutics construction, trestle steel pipe pile is accurately located the larger operation easier of existence by packaged type full circle swinging loop wheel machine by staff; When adopting the construction of crane barge method, crane barge and barge are difficult to stable placement, and staff is difficult to trestle steel pipe pile accurately to be located, easily there is relatively large deviation in trestle steel pipe pile location, and need trestle steel pipe pile is pulled up and reorientates, extend the duration of trestle construction, add construction cost.
(2) halieutics construction is carried out mainly through crawler type loop wheel machine, and the cantilever of crawler type loop wheel machine is shorter, and its construction distance is shorter, has been difficult to large span trestle construction waterborne.
Summary of the invention
For the defect existed in prior art, the object of the present invention is to provide a kind of construction method of trestle waterborne, the duration of construction can be shortened, reduce construction cost, complete the construction of large span trestle waterborne.
For reaching above object, the technical scheme that the present invention takes is: a kind of construction method of trestle waterborne, comprises the following steps:
Step one: preset sections passage, described sections passage comprises channel segment, is provided with the first supporting pile, the second supporting pile, the 3rd supporting pile, the 4th supporting pile bottom it, the 5th supporting pile, the 6th supporting pile, the 7th supporting pile and the 8th supporting pile;
Prefabricated mobile platform, the top of mobile platform is provided with packaged type full circle swinging loop wheel machine and pile driving rig, and bottom is provided with supporting leg in supporting leg in first, second, the first rear support leg and the second rear support leg; Described mobile platform transversely center line symmetry has the first installing hole and the second installing hole, is provided with the first front leg strut, is provided with the second front leg strut in the second installing hole in the first installing hole; The bottom of described mobile platform is provided with hoisting overhead travelling crane; The top of described mobile platform is placed with some first and treats that frame supporting pile, some second treats that frame supporting pile, the some 3rd treats that frame supporting pile and the some 4th treats frame supporting pile;
Step 2: will along trestle construction direction, adjacent passages sections treat that erection region is as treating that frame is interval, is treating that the bottom in frame interval arranges the first fixing hole, the second fixing hole, the first stake holes, the second stake holes, prism of third order hole and the 4th stake holes;
Step 3: be horizontally disposed with mobile platform at the top of channel segment, adjusts the top of the first rear support leg to the first supporting pile, adjusts the top of the second rear support leg to the 5th supporting pile; In adjustment first, supporting leg is to the top of the 4th supporting pile, and in adjustment second, supporting leg is to the top of the 8th supporting pile;
Step 4: the first front leg strut is inserted in the first fixing hole, the second front leg strut inserts in the second fixing hole;
Step 5: the top adjusting the first rear support leg to the second supporting pile, adjusts the top of the second rear support leg to the 6th support stake;
Step 6: treat that frame supporting pile squeezes into the first stake holes by first, forms the 9th supporting pile; Treat that frame supporting pile squeezes into the second stake holes by second, form the tenth supporting pile; Treat that frame supporting pile squeezes into prism of third order hole by the 3rd, form the 11 supporting pile, the 4th treats that frame supporting pile squeezes into the 4th stake holes, forms twelve earthly branches support stake;
Step 7: hoisting overhead travelling crane, is moved to the top for the treatment of frame sections at the top that frame sections is positioned over channel segment by existing treating, hoisting overhead travelling crane after frame sections is mentioned, will move to the direction near the first front leg strut; Make to treat the top that one end of frame sections is positioned at the top of the 4th supporting pile, the other end is positioned at the 9th supporting pile, form trestle sections;
Step 8: preset construction access road repeated execution of steps two ~ step 7 along trestle, forms some total lengths and expection trestle and construct the identical trestle sections of length, some trestle sections formation trestles.
On the basis of technique scheme, first supporting pile described in step one, the 5th supporting pile are symmetrical arranged along the cross central line of channel segment, described second supporting pile, the 6th supporting pile are symmetrical arranged along the cross central line of channel segment, described 3rd supporting pile, the 7th supporting pile are symmetrical arranged along the cross central line of channel segment, and described 4th supporting pile, the 8th supporting pile are symmetrical arranged along the cross central line of channel segment.
On the basis of technique scheme, before adjusting the top of the first rear support leg to the first supporting pile described in step 3, further comprising the steps of: the position of adjustment packaged type full circle swinging loop wheel machine, packaged type full circle swinging loop wheel machine is moved near the first front leg strut direction, the distance treating packaged type full circle swinging loop wheel machine and the first front leg strut is 0 ~ 5m, stops mobile packaged type full circle swinging loop wheel machine.
On the basis of technique scheme, before adjusting the top of the first front leg strut to the first fixing hole described in step 4, further comprising the steps of: the position of adjustment packaged type full circle swinging loop wheel machine, packaged type full circle swinging loop wheel machine is moved to the direction near the first rear support leg, when distance between packaged type full circle swinging loop wheel machine and the first rear support leg is 0 ~ 5m, stop mobile packaged type full circle swinging loop wheel machine.
On the basis of technique scheme, before adjusting the top of the first rear support leg to the second supporting pile described in step 5, further comprising the steps of: the position of adjustment packaged type full circle swinging loop wheel machine, packaged type full circle swinging loop wheel machine is moved near the first front leg strut direction, the distance treating packaged type full circle swinging loop wheel machine and the first stake holes is 0 ~ 5m, stops mobile packaged type full circle swinging loop wheel machine.
On the basis of technique scheme, the top of the first rear support leg to the second supporting pile is adjusted described in step 5, adjust the top of the second rear support leg to the 5th supporting pile, comprise the following steps: by first rear support leg retraction 20 ~ 100cm, by second rear support leg retraction 20 ~ 100cm, the top of mobile first rear support leg to the second supporting pile, adjusts the top of the second rear support leg to the 5th supporting pile.
On the basis of technique scheme, hoisting overhead travelling crane is controlled along after sliding rail moves to the top for the treatment of frame sections described in step 7, further comprising the steps of: to control packaged type full circle swinging loop wheel machine and move to the direction near the first rear support leg, when the distance of packaged type full circle swinging loop wheel machine and the first rear support leg is 0 ~ 5m, stop mobile packaged type full circle swinging loop wheel machine.
On the basis of technique scheme, using the channel segment of trestle sections in step one, using first supporting pile of the 3rd supporting pile in step one, second supporting pile of the 4th supporting pile in step one, five supporting pile of the 7th supporting pile in step one, using six supporting pile of the 8th supporting pile in step one; Using three supporting pile of the 9th supporting pile in step one, four supporting pile of the tenth supporting pile in step one, seven supporting pile of the 11 supporting pile in step one, eight supporting pile of twelve earthly branches support stake in step one, construction access road is preset along trestle, repeated execution of steps two ~ step 7, construct the identical trestle sections of length until form some total lengths and expection trestle, some trestle sections formation trestles.
Compared with prior art, the invention has the advantages that:
(1) construction method of the trestle waterborne of the embodiment of the present invention, comprise mobile platform, mobile platform has the first installing hole and the second installing hole along its cross central line symmetry, the first front leg strut is provided with in first installing hole, the second front leg strut is provided with in second installing hole, construction method of the present invention comprises to be inserted in the first fixing hole by the first front leg strut, second front leg strut inserts in the second fixing hole, first fixing hole and the second fixing hole are all positioned at water-bed rock stratum, after first front leg strut and the second front leg strut insert rock stratum, mobile platform is more stable, when the environment of over-water construction is poor, during the anxious situation of the stream that occurs that the wave is high, mobile platform can stablize placement, when constructing with adopting halieutics and crane barge method in prior art, trestle steel pipe pile is difficult to accurately to be located, need trestle steel pipe pile to pull up and reorientate to compare, trestle steel pipe pile can accurately be located by the present invention, effectively can shorten the duration of construction, reduce construction cost.
(2) construction method of the present invention, comprise top mobile platform being positioned over sections passage, captured by hoisting overhead travelling crane and treat frame sections, to treat that frame sections is placed into the top of the 4th supporting pile and the 9th supporting pile, shorter with the cantilever of halieutics crawler type loop wheel machine in prior art, cannot capture and treat that frame sections is compared, can hang preferably to get and treat frame sections, and will treat that frame sections is placed into assigned address exactly, large span trestle construction waterborne can be completed.
(3) construction method of the present invention comprises and repeatedly moves packaged type full circle swinging loop wheel machine, can keep the balance of mobile platform, effectively prevent mobile platform run-off the straight, ensure that the construction safety of staff after mobile packaged type full circle swinging loop wheel machine.
Accompanying drawing explanation
Fig. 1 is the schematic diagram that in the embodiment of the present invention, sections passage and mobile platform coordinate;
Fig. 2 is the schematic diagram of step S5 in the embodiment of the present invention;
Fig. 3 is the schematic diagram of step S6 in the embodiment of the present invention;
Fig. 4 is the schematic diagram of step S7 in the embodiment of the present invention;
Fig. 5 is the schematic diagram of step S8 in the embodiment of the present invention.
Fig. 6 is the schematic diagram of step S9 in the embodiment of the present invention.
Fig. 7 is the schematic diagram of step S10 in the embodiment of the present invention.
In figure: 1-channel segment, 2-first rear support leg, 3-packaged type full circle swinging loop wheel machine, 4-hoisting overhead travelling crane, supporting leg in 5-first, 6-mobile platform, 7-first front leg strut, 8-first supporting pile, 9-second supporting pile, 10-the 3rd supporting pile, 11-the 4th supporting pile, 12-scar, the 13-water surface, 14-treats frame sections, 15-the 9th supporting pile, 16-the tenth supporting pile.
Detailed description of the invention
Below in conjunction with drawings and Examples, the present invention is described in further detail.
Shown in Figure 1, the embodiment of the present invention provides a kind of construction method of trestle waterborne, comprises the following steps:
S1: preset sections passage, sections passage comprises channel segment 1, the first supporting pile 8, second supporting pile 9, the 3rd supporting pile 10, the 4th supporting pile 11 is provided with bottom it, 5th supporting pile, the 6th supporting pile, the 7th supporting pile and the 8th supporting pile, the top of each supporting pile is provided with tie-beam.
First supporting pile 8, the 5th supporting pile are symmetrical arranged along the cross central line of channel segment 1, and the distance between the first supporting pile 8 and the 5th supporting pile is 6 ~ 12m.
Second supporting pile 9, the 6th supporting pile are symmetrical arranged along the cross central line of channel segment 1, and the distance between the second supporting pile 9 and the 6th supporting pile is 6 ~ 12m.
3rd supporting pile 10, the 7th supporting pile are symmetrical arranged along the cross central line of channel segment 1, and the distance between the 3rd supporting pile 10 and the 7th supporting pile is 6 ~ 12m.
4th supporting pile 11, the 8th supporting pile are symmetrical arranged along the cross central line of channel segment 1, and the distance between the 4th supporting pile 11 and the 8th supporting pile is 6 ~ 12m.
Prefabricated mobile platform 6, mobile platform 6 comprises hydraulic system and electrical system, the top of mobile platform 6 is provided with packaged type full circle swinging loop wheel machine 3 and pile driving rig, bottom to be provided with in first supporting leg in supporting leg 5, second, first rear support leg 2 and the second rear support leg, in first, in supporting leg 5, second, supporting leg is symmetrical arranged along the cross central line of mobile platform 6, and the distance in first in supporting leg 5 and second between supporting leg is 6 ~ 12m.
First rear support leg 2, second rear support leg is symmetrical arranged along the cross central line of mobile platform 6, and the distance between the first rear support leg 2 and the second rear support leg is 6 ~ 12m.
Mobile platform 6 has the first installing hole and the second installing hole along its cross central line symmetry, and the distance between the first installing hole and the second installing hole is 6 ~ 12m, is provided with in the first front leg strut 7, second installing hole and is provided with the second front leg strut in the first installing hole.
The bottom of mobile platform 6 is provided with sliding rail, and sliding rail overlaps with the cross central line of mobile platform 6, sliding rail is provided with 4 ~ 8 hoisting overhead travelling cranes 4.Place some first at the top of mobile platform 6 and treat that frame supporting pile, some second treats that frame supporting pile, the some 3rd treats that frame supporting pile, the some 4th treats frame supporting pile.
S2: will along trestle construction direction, adjacent passages sections 1 treat that sections is set up as waiting in erection region, waiting that the bottom of setting up sections arranges the first fixing hole, the second fixing hole, the first stake holes, the second stake holes, prism of third order hole and the 4th stake holes.
S3: be horizontally disposed with mobile platform at the top of channel segment 1.
S4: adjustment packaged type full circle swinging loop wheel machine 3 moves near the first front leg strut 7 direction, treats that the distance of packaged type full circle swinging loop wheel machine 3 and the first front leg strut 7 is 0 ~ 5m, stops mobile packaged type full circle swinging loop wheel machine 3.
Adjust the top of the first rear support leg 2 to the first supporting pile 8, adjust the top of the second rear support leg to the 5th supporting pile.
In adjustment first, supporting leg 5 is to the top of the 4th supporting pile 11, and in adjustment second, supporting leg is to the top of the 8th supporting pile.
S5: shown in Figure 2, makes packaged type full circle swinging loop wheel machine 3 move to the direction near the first rear support leg 2, when the distance between packaged type full circle swinging loop wheel machine 3 and the first rear support leg 2 is 0 ~ 5m, stops mobile packaged type full circle swinging loop wheel machine 3.Adjust the top of the first front leg strut 7 to the first fixing hole, the top of the second front leg strut to the second fixing hole.
S6: shown in Figure 3, inserts in the first fixing hole by the first front leg strut 7, and the second front leg strut inserts in the second fixing hole, and simultaneously mobile platform 6 is preset construction access road along trestle and moved.
The position of adjustment packaged type full circle swinging loop wheel machine 3, when to make control packaged type full circle swinging loop wheel machine 3 move to the distance of the first stake holes be 0 ~ 5m, stops mobile packaged type full circle swinging loop wheel machine 3.
Bounce back the first rear support leg 2 20 ~ 100cm, and after second rear support leg retraction 20 ~ 100cm, the top of mobile first rear support leg 2 to the second supporting pile 9, mobile second rear support leg is to the top of the 6th supporting pile.
S7: shown in Figure 4, uses pile driving rig to treat that frame supporting pile squeezes into the first stake holes by one first, forms the 9th supporting pile 15; Treat that frame supporting pile squeezes into the second stake holes by one second, form the tenth supporting pile 16; Treat that frame supporting pile squeezes into prism of third order hole by one the 3rd, form the 11 supporting pile; Treat that frame supporting pile squeezes into the 4th stake holes by one the 4th, form twelve earthly branches support stake.
S8: shown in Figure 5, will treat that frame sections 14 is positioned over the top of channel segment 1.
S9: shown in Figure 6, makes hoisting overhead travelling crane 4 move to the top for the treatment of frame sections 14 along sliding rail, and hoisting overhead travelling crane 4 first captures and treats frame sections 14 and mentioned, and then slides along sliding rail near the direction of the first front leg strut 7.
Meanwhile, mobile packaged type full circle swinging loop wheel machine 3, makes it move near direction of the first rear support leg 2, when the distance of packaged type full circle swinging loop wheel machine 3 and the first rear support leg 2 is 0 ~ 5m, stops mobile packaged type full circle swinging loop wheel machine 3.
Mobile hoisting overhead travelling crane 4 is to treating that one end of frame sections 14 is positioned at the top of the 4th supporting pile 11, and the other end is positioned at the top of the 9th supporting pile 15.
S10: shown in Figure 7, will treat that frame sections 14 puts down, and will treat that frame sections 14 is arranged at the top of the 4th supporting pile 11, the 9th supporting pile 15.By channel segment 1 with treat that frame sections 14 is fixed, treat that frame sections 14 forms trestle sections.
S11: using trestle sections as the channel segment 1 in S2, using the 3rd supporting pile 10 as the first supporting pile 8 in S2, the 4th supporting pile 11 as the second supporting pile 9 in S2, the 7th supporting pile as the 5th supporting pile in S2, using the 8th supporting pile as the 6th supporting pile in S2; Using the 9th supporting pile 15 as the 3rd supporting pile 10 in S2, the tenth supporting pile 16 as the 4th supporting pile the 11, the 11 supporting pile in S2 as the 7th supporting pile in S2, twelve earthly branches support stake as the 8th supporting pile in S2, construction access road is preset along trestle, repeat S2 ~ S10, construct the identical trestle sections of length until form some total lengths and expection trestle, some trestle sections formation trestles.
The present invention is not limited to above-mentioned embodiment, and for those skilled in the art, under the premise without departing from the principles of the invention, can also make some improvements and modifications, these improvements and modifications are also considered as within protection scope of the present invention.The content be not described in detail in this manual belongs to the known prior art of professional and technical personnel in the field.
Claims (8)
1. a construction method for trestle waterborne, is characterized in that, described construction method comprises the following steps:
Step one: preset sections passage, described sections passage comprises channel segment (1), the first supporting pile (8), the second supporting pile (9), the 3rd supporting pile (10), the 4th supporting pile (11) is provided with, the 5th supporting pile, the 6th supporting pile, the 7th supporting pile and the 8th supporting pile bottom it;
Prefabricated mobile platform (6), the top of mobile platform (6) is provided with packaged type full circle swinging loop wheel machine (3) and pile driving rig, bottom is provided with supporting leg in supporting leg in first (5), second, the first rear support leg (2) and the second rear support leg; Described mobile platform (6) transversely center line symmetry has the first installing hole and the second installing hole, is provided with the first front leg strut (7), is provided with the second front leg strut in the second installing hole in the first installing hole; The bottom of described mobile platform (6) is provided with hoisting overhead travelling crane (4); The top of described mobile platform (6) is placed with some first and treats that frame supporting pile, some second treats that frame supporting pile, the some 3rd treats that frame supporting pile and the some 4th treats frame supporting pile;
Step 2: will along trestle construction direction, adjacent passages sections (1) treat that erection region is as treating that frame is interval, is treating that the bottom in frame interval arranges the first fixing hole, the second fixing hole, the first stake holes, the second stake holes, prism of third order hole and the 4th stake holes;
Step 3: be horizontally disposed with mobile platform (6) at the top of channel segment (1), adjusts the top of the first rear support leg (2) to the first supporting pile (8), adjusts the top of the second rear support leg to the 5th supporting pile; In adjustment first, supporting leg (5) is to the top of the 4th supporting pile (11), and in adjustment second, supporting leg is to the top of the 8th supporting pile;
Step 4: the first front leg strut (7) is inserted in the first fixing hole, the second front leg strut inserts in the second fixing hole;
Step 5: adjust the top of the first rear support leg (2) to the second supporting pile (9), adjusts the top of the second rear support leg to the 6th support stake;
Step 6: treat that frame supporting pile squeezes into the first stake holes by first, forms the 9th supporting pile (15); Treat that frame supporting pile squeezes into the second stake holes by second, form the tenth supporting pile (16); Treat that frame supporting pile squeezes into prism of third order hole by the 3rd, form the 11 supporting pile, the 4th treats that frame supporting pile squeezes into the 4th stake holes, forms twelve earthly branches support stake;
Step 7: treat the top that frame sections (14) is positioned over channel segment (1) by existing, hoisting overhead travelling crane (4) is moved to the top for the treatment of frame sections (14), hoisting overhead travelling crane (4) after frame sections (14) mention, will move to the direction near the first front leg strut (7); Make to treat the top that one end of frame sections (14) is positioned at the top of the 4th supporting pile (11), the other end is positioned at the 9th supporting pile (15), form trestle sections;
Step 8: preset construction access road repeated execution of steps two ~ step 7 along trestle, forms some total lengths and expection trestle and construct the identical trestle sections of length, some trestle sections formation trestles.
2. the construction method of trestle waterborne as claimed in claim 1, it is characterized in that: the first supporting pile described in step one (8), the 5th supporting pile are symmetrical arranged along the cross central line of channel segment (1), described second supporting pile (9), the 6th supporting pile are symmetrical arranged along the cross central line of channel segment (1), described 3rd supporting pile (10), the 7th supporting pile are symmetrical arranged along the cross central line of channel segment (1), and described 4th supporting pile (11), the 8th supporting pile are symmetrical arranged along the cross central line of channel segment (1).
3. the construction method of trestle waterborne as claimed in claim 1, it is characterized in that: adjust described in step 3 the first rear support leg (2) to the first supporting pile (8) top before, further comprising the steps of: the position of adjustment packaged type full circle swinging loop wheel machine (3), packaged type full circle swinging loop wheel machine (3) is moved near the first front leg strut (7) direction, treat that packaged type full circle swinging loop wheel machine (3) is 0 ~ 5m with the distance of the first front leg strut (7), stop mobile packaged type full circle swinging loop wheel machine (3).
4. the construction method of trestle waterborne as claimed in claim 1, it is characterized in that: adjust described in step 4 the first front leg strut (7) to the first fixing hole top before, further comprising the steps of: the position of adjustment packaged type full circle swinging loop wheel machine (3), packaged type full circle swinging loop wheel machine (3) is moved to the direction near the first rear support leg (2), when distance between packaged type full circle swinging loop wheel machine (3) and the first rear support leg (2) is 0 ~ 5m, stop mobile packaged type full circle swinging loop wheel machine (3).
5. the construction method of trestle waterborne as claimed in claim 1, it is characterized in that: adjust described in step 5 the first rear support leg (2) to the second supporting pile (9) top before, further comprising the steps of: the position of adjustment packaged type full circle swinging loop wheel machine (3), packaged type full circle swinging loop wheel machine (3) is moved near the first front leg strut (7) direction, treat that packaged type full circle swinging loop wheel machine (3) is 0 ~ 5m with the distance of the first stake holes, stop mobile packaged type full circle swinging loop wheel machine (3).
6. the construction method of trestle waterborne as claimed in claim 1, it is characterized in that: described in step 5, adjust the top of the first rear support leg (2) to the second supporting pile (9), adjust the top of the second rear support leg to the 5th supporting pile, comprise the following steps: by the first rear support leg (2) retraction 20 ~ 100cm, by second rear support leg retraction 20 ~ 100cm, mobile first rear support leg (2), to the top of the second supporting pile (9), adjusts the top of the second rear support leg to the 5th supporting pile.
7. the construction method of trestle waterborne as claimed in claim 1, it is characterized in that: hoisting overhead travelling crane described in step 7 (4) is along after sliding rail moves to the top for the treatment of frame sections (14), further comprising the steps of: to control packaged type full circle swinging loop wheel machine (3) and move to the direction near the first rear support leg (2), when packaged type full circle swinging loop wheel machine (3) is 0 ~ 5m with the distance of the first rear support leg (2), stop mobile packaged type full circle swinging loop wheel machine (3).
8. the construction method of trestle waterborne as claimed in claim 1, it is characterized in that, step 8 comprises the following steps: using the channel segment of trestle sections in step one (1), using first supporting pile (8) of the 3rd supporting pile (10) in step one, second supporting pile (9) of the 4th supporting pile (11) in step one, five supporting pile of the 7th supporting pile in step one, using six supporting pile of the 8th supporting pile in step one; Using three supporting pile (10) of the 9th supporting pile (15) in step one, four supporting pile (11) of the tenth supporting pile (16) in step one, seven supporting pile of the 11 supporting pile in step one, eight supporting pile of twelve earthly branches support stake in step one, construction access road is preset along trestle, repeated execution of steps two ~ step 7, construct the identical trestle sections of length until form some total lengths and expection trestle, some trestle sections formation trestles.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410647127.2A CN104328742B (en) | 2014-11-14 | 2014-11-14 | A kind of construction method of trestle waterborne |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410647127.2A CN104328742B (en) | 2014-11-14 | 2014-11-14 | A kind of construction method of trestle waterborne |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104328742A CN104328742A (en) | 2015-02-04 |
CN104328742B true CN104328742B (en) | 2016-04-20 |
Family
ID=52403542
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410647127.2A Active CN104328742B (en) | 2014-11-14 | 2014-11-14 | A kind of construction method of trestle waterborne |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104328742B (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105888076B (en) * | 2016-04-19 | 2018-05-29 | 浙江工业大学 | A kind of construction method in corridor waterborne |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3711355B2 (en) * | 1996-12-11 | 2005-11-02 | 東急建設株式会社 | Bridge erection method |
JP4361775B2 (en) * | 2003-11-10 | 2009-11-11 | 株式会社富士ピー・エス | Bridge erection method and bridge erection device |
CN101122115B (en) * | 2007-08-03 | 2011-01-26 | 中铁一局集团有限公司 | Construction method for tower crane shift |
CN102330413B (en) * | 2011-07-18 | 2013-04-17 | 中铁三局集团有限公司 | Construction method for enabling bridge girder erection machine to independently go up and down girder carrier |
CN202509405U (en) * | 2012-04-18 | 2012-10-31 | 中建二局第三建筑工程有限公司 | Trestle assembling platform |
CN102979039B (en) * | 2012-12-13 | 2014-12-03 | 中铁上海工程局集团第二工程有限公司 | Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream |
-
2014
- 2014-11-14 CN CN201410647127.2A patent/CN104328742B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN104328742A (en) | 2015-02-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201010842Y (en) | Tyre type span-variable multifunctional rail laying machine | |
CN103437782B (en) | Hydraulic pressure automatic moving type steel form carrier and construction method thereof | |
CN204782031U (en) | Interior climbing tower hangs entrance to a cave from promoting safety protection platform | |
CN105952474A (en) | Rapid construction method for primary support of confined concrete of large-section tunnel | |
CN106522997A (en) | Construction trolley for lagging jack in tunnel and underground construction and construction method | |
CN103821340A (en) | Installation method for attached lifting multilayer construction platform | |
CN107990051A (en) | It is a kind of to lift auxiliary device in place and method for jacking pipe joints | |
CN204019724U (en) | Make the mold of prefabricated case beam framework of steel reinforcement | |
CN104328742B (en) | A kind of construction method of trestle waterborne | |
CN107386128A (en) | Double-T shaped beam bridge changes beam construction system | |
CN204151699U (en) | A kind of frame plate machine for changing steel truss girder bridge bridge deck | |
CN204298740U (en) | A kind of mobile platform for trestle construction | |
CN103993745B (en) | A kind of conversion beam integral hoisting device for rapid and hanging method thereof | |
CN103806374B (en) | The overall track erection supplying system of assembly type steel bridge on highway and erection push technique | |
CN203462404U (en) | Bridge girder erecting machine | |
CN105113536B (en) | A kind of portable underground structure side wall formwork system and its construction method | |
CN103774554B (en) | A kind of king-tower tractive erection method of self-anchored suspension bridge case beam | |
CN202298467U (en) | Switching platform bridging device for crossing existing rail lines | |
CN204237269U (en) | The bracing or strutting arrangement of setting machine | |
CN107858935A (en) | Two straddle type Bridge Erectors | |
CN203668772U (en) | Hoisting device for base construction formwork of high speed railway ballastless track | |
CN204873491U (en) | Self -supporting does not have crossbeam hoist system | |
CN106498852A (en) | A kind of bridge erection device | |
CN203961415U (en) | Safety moving formula communication base station | |
CN207072757U (en) | The system mounting structure of grid beams in length and breadth of half-through tubular arch |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |