CN104294802B - Down stream formula step plunge pool system - Google Patents

Down stream formula step plunge pool system Download PDF

Info

Publication number
CN104294802B
CN104294802B CN201410461747.7A CN201410461747A CN104294802B CN 104294802 B CN104294802 B CN 104294802B CN 201410461747 A CN201410461747 A CN 201410461747A CN 104294802 B CN104294802 B CN 104294802B
Authority
CN
China
Prior art keywords
pond
elevation
water
water cushion
ponds
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410461747.7A
Other languages
Chinese (zh)
Other versions
CN104294802A (en
Inventor
张建民
何小泷
许唯临
彭勇
刘善均
王韦
邓军
曲景学
田忠
张法星
周茂林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan University
Original Assignee
Sichuan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan University filed Critical Sichuan University
Priority to CN201410461747.7A priority Critical patent/CN104294802B/en
Publication of CN104294802A publication Critical patent/CN104294802A/en
Application granted granted Critical
Publication of CN104294802B publication Critical patent/CN104294802B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B8/00Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
    • E02B8/06Spillways; Devices for dissipation of energy, e.g. for reducing eddies also for lock or dry-dock gates

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

本发明所述跌流式梯级水垫塘消能系统,包括设置在水库坝体侧面山体不同高程处的多级阶梯式布置的水垫塘,将水库中的水引出的上游引水渠,第二高程至最低高程的各级水垫塘对应的水平溢洪道和将最低高程的水垫塘中的水引入下游河道的岸边引水渠,各级水垫塘的下游端位于同一侧,所述下游端边墙上均设置有溢流堰;上游引水渠的出水口位于最高高程水垫塘的上游上方,第二高程水垫塘对应的水平溢洪道与最高高程水垫塘的高程相同并与最高高程水垫塘设置的溢流堰衔接,其出水口位于第二高程水垫塘的上游上方,……。本发明所述消能系统能避免水垫塘破坏,保证下游河道安全,提高消能率。

The falling flow cascaded water cushion pond energy dissipation system of the present invention includes a multi-level stepped cushion pond arranged at different elevations on the side of the reservoir dam body, and an upstream water diversion channel leading out the water in the reservoir. The horizontal spillway corresponding to the water cushion ponds at all levels from the elevation to the lowest elevation and the bank diversion channel that introduces the water in the water cushion ponds at the lowest elevation into the downstream channel. The downstream ends of the water cushion ponds at all levels are located on the same side, and the downstream ends Overflow weirs are set on the side walls; the outlet of the upstream diversion channel is located above the upper reaches of the highest-elevation water cushion pond, and the horizontal spillway corresponding to the second-elevation water cushion pond is at the same elevation as the highest-elevation water cushion pond The overflow weir set in the pad pond is connected, and its water outlet is located above the upstream of the pad pond at the second elevation, ... . The energy dissipation system of the invention can avoid the damage of the pad pond, ensure the safety of the downstream river course, and improve the energy dissipation rate.

Description

跌流式梯级水垫塘消能系统Energy Dissipation System of Falling Flow Cascade Cushion Pond

技术领域technical field

本发明属于水利水电工程中的泄洪消能技术领域,特别涉及一种适用于狭窄河谷、下游河道由窄变宽的小流量高水头水利工程的水垫塘与跌流消能结合的消能系统。The invention belongs to the technical field of flood discharge and energy dissipation in water conservancy and hydropower projects, and in particular relates to an energy dissipation system suitable for combining water cushion ponds and falling flow energy dissipation in narrow valleys and downstream rivers changing from narrow to wide in small flow and high head water conservancy projects .

背景技术Background technique

高水头电站建设中,为保证水利工程在运行中的安全性,需要采用一系列泄洪消能措施。传统的消能措施包括传统的底流消能,挑流消能和面流消能,新型消能设施包括竖井旋流消能,宽尾墩,阶梯消能,洞塞孔板消能等。但对于狭窄河谷,两岸山体垂直,下游河道迅速由窄变宽,岸坡岩体地质条件复杂的工程,由于地质条件造成的障碍,难以按现有技术中的模式布置水垫塘以及大单宽流量的泄洪隧洞,或采用现有技术的消能设施布置方式,工程耗费较高,工期增长。In the construction of high water head power stations, in order to ensure the safety of hydraulic projects in operation, a series of flood discharge and energy dissipation measures are required. Traditional energy dissipation measures include traditional underflow energy dissipation, deflected flow energy dissipation and surface flow energy dissipation. New energy dissipation facilities include vertical shaft swirl energy dissipation, wide end pier, ladder energy dissipation, hole plug orifice energy dissipation, etc. However, for projects with narrow river valleys, vertical mountains on both sides, rapid changes in downstream channels from narrow to wide, and complex geological conditions on the bank slope, it is difficult to arrange water cushion ponds and large single-width projects according to the existing technology due to obstacles caused by geological conditions. The flood discharge tunnel with large flow rate, or the arrangement of energy-dissipating facilities in the prior art, the project cost is high and the construction period is increased.

发明内容Contents of the invention

本发明的目的在于针对现技术的不足,提供一种适用于狭窄河谷,下游河道由窄变宽的小流量高水头水利工程的跌流式梯级水垫塘消能系统,以提高消能率及工程安全性和经济性,减小枢纽布置的困难程度。The purpose of the present invention is to address the deficiencies of the existing technology, and provide a cascading cascaded pad pond energy dissipation system suitable for narrow valleys and downstream rivers that change from narrow to wide and low-flow and high-head water conservancy projects, so as to improve the energy dissipation rate and project efficiency. Safety and economy, reducing the difficulty of hub layout.

本发明所述跌流式梯级水垫塘消能系统,包括设置在水库坝体侧面山体不同高程处的多级阶梯式布置的水垫塘,将水库中的水引出的上游引水渠,第二高程至最低高程的各级水垫塘对应的水平溢洪道和将最低高程的水垫塘中的水引入下游河道的岸边引水渠,各级水垫塘的下游端位于同一侧,各级水垫塘下游端边墙上均设置有溢流堰;上游引水渠的出水口位于最高高程水垫塘的上游上方,第二高程水垫塘对应的水平溢洪道与最高高程水垫塘的高程相同并与最高高程水垫塘设置的溢流堰衔接,其出水口位于第二高程水垫塘的上游上方,第三高程水垫塘对应的水平溢洪道与第二高程水垫塘的高程相同并与第二高程水垫塘的溢流堰衔接,其出水口位于第三高程水垫塘的上游上方,……,最低高程水垫塘对应的水平溢洪道与次低高程水垫塘的高程相同并与次低高程水垫塘的溢流堰衔接,其出水口位于最低高程水垫塘的上游上方,所述岸边引水渠的进水端与最低高程水垫塘下游端边墙设置的溢流堰衔接,其末端与下游河道相连,从而将水库中的水经上游引水渠跌落至最高高程水垫塘,再经第二高程至最低高程的各级水垫塘对应的水平溢洪道从高至低依次跌落至各级水垫塘中,并经岸边引水渠流入下游河道。在这个过程中,利用跌流使水流碰撞,发生强烈的撞击、紊动、混掺及剪切,消除部分能量,达到提高消能率,避免工程破坏的目的。The falling flow cascaded water cushion pond energy dissipation system of the present invention includes a multi-level stepped cushion pond arranged at different elevations on the side of the reservoir dam body, and an upstream water diversion channel leading out the water in the reservoir. The horizontal spillway corresponding to the water cushion ponds at all levels from the elevation to the lowest elevation and the bank diversion channel that introduces the water in the water cushion ponds at the lowest elevation to the downstream channel. Overflow weirs are set on the side walls of the downstream end of the pond; the outlet of the upstream diversion channel is located above the upper reaches of the highest elevation pond, and the horizontal spillway corresponding to the second elevation pond is at the same elevation as the highest elevation pond The overflow weir set in the highest elevation pond is connected, and its outlet is located above the upstream of the second elevation pond, and the horizontal spillway corresponding to the third elevation pond is at the same elevation as the second elevation pond and is the same as the second elevation pond. The overflow weir of the elevation paddle pond is connected, and its outlet is located above the upper reaches of the third elevation paddle pond, ..., the horizontal spillway corresponding to the lowest elevation paddle pond is the same as the elevation of the next lowest elevation paddle pond and is the same as the second lowest elevation paddle pond The overflow weir of the elevation pad pond is connected, and its water outlet is located above the upper reaches of the lowest elevation pad pond, and the water inlet end of the bank diversion channel is connected with the overflow weir provided on the downstream side wall of the lowest elevation pad pond, Its end is connected with the downstream channel, so that the water in the reservoir drops to the highest elevation cushion pond through the upstream diversion channel, and then drops through the horizontal spillways corresponding to the water cushion ponds at all levels from the second elevation to the lowest elevation from high to low. In the water cushion ponds at all levels, and flow into the downstream channel through the diversion channel on the bank. In this process, the falling flow is used to cause the water flow to collide, resulting in strong impact, turbulence, mixing and shearing, to eliminate part of the energy, so as to improve the energy dissipation rate and avoid engineering damage.

上述跌流式梯级水垫塘消能系统,水垫塘轴线选择开挖量最小的方式进行布置,各级水垫塘的轴线相互平行,或各级水垫塘的轴线相交,或各级水垫塘的轴线部分平行、部分相交,若水垫塘的轴线相交,相交的角度为锐角。For the energy dissipation system of the above-mentioned falling-flow cascaded water cushion ponds, the axis of the water cushion ponds shall be arranged in the way with the least excavation amount. The axes of the pad ponds are partially parallel and partially intersected. If the axes of the pad ponds intersect, the intersection angle is an acute angle.

上述跌流式梯级水垫塘消能系统,相邻两级水垫塘之间的高程差△x=30~45m,防止跌落流速过大破坏水垫塘,且保证工程量最小。各级水垫塘之间的高程差根据地质条件进行选择,可以相等,也可以不等。For the energy dissipation system of the above-mentioned cascaded water cushion ponds with falling flow, the elevation difference between two adjacent water cushion ponds is △x=30-45m, so as to prevent the water cushion ponds from being damaged by excessive falling velocity and ensure the minimum engineering quantity. The elevation difference between pad ponds at all levels is selected according to geological conditions, and can be equal or unequal.

上述跌流式梯级水垫塘消能系统,所述水垫塘的长度l=20~40m、宽度b1=15~30m、深度h1=最大水位高度+波动高度+安全超高。所述最大水位高度为最大泄流量对应的水垫塘中的水位高度,所述波动高度为水流剧烈翻滚引起的水位变化,所述安全超高为保证水流不会翻出水垫塘所需高度。为避免水垫塘发生破坏,应避免水垫塘中混凝土产生拉应力,水垫塘应修建在挖方中,尽量避免填方,且水垫塘应当做好防渗措施,避免渗漏引起消能系统的破坏。同时各级水垫塘内应保证一定水深,防止泄洪时最大流量跌落水流直接冲击水垫塘底板引发水垫塘破坏,进而冲刷山体导致不可修复的破坏,危及枢纽运行安全。For the energy dissipation system of the above-mentioned falling flow cascaded water cushion pond, the length of the water cushion pond is l=20-40m, the width b 1 =15-30m, and the depth h 1 =maximum water level height+fluctuation height+safe superelevation. The maximum water level height is the water level height in the pad pond corresponding to the maximum discharge flow, the fluctuation height is the water level change caused by the violent tumbling of the water flow, and the safe superelevation is the height required to ensure that the water flow will not turn out of the pad pond . In order to avoid the damage of the water cushion pond, the tensile stress of the concrete in the water cushion pond should be avoided. The water cushion pond should be built in the excavation to avoid filling as much as possible, and the water cushion pond should take anti-seepage measures to avoid energy dissipation caused by leakage System disruption. At the same time, a certain water depth should be guaranteed in the water cushion ponds at all levels to prevent the maximum flow of falling water from directly impacting the water cushion pond floor during flood discharge, causing damage to the water cushion ponds, and then scouring the mountains, causing irreparable damage and endangering the operation safety of the hub.

上述跌流式梯级水垫塘消能系统,所述溢流堰的宽度b2≤b1,式中b1为水垫塘的宽度。第二高程至最低高程的各级水垫塘对应的水平溢洪道入水口宽度=上一级水垫塘的溢流堰宽度,因而连接于于两级水垫塘之间的水平溢洪道从上游到下游可以是等宽的,也可以是渐扩的。In the falling flow cascaded water cushion pond energy dissipation system, the width of the overflow weir b 2 ≤ b 1 , where b 1 is the width of the water cushion pond. The width of the inlet of the horizontal spillway corresponding to the water cushion ponds at all levels from the second elevation to the lowest elevation = the overflow weir width of the water cushion pond of the previous level, so the horizontal spillway connected between the two-level water cushion ponds runs from upstream to downstream Can be constant width or progressive.

上述跌流式梯级水垫塘消能系统,所述岸边引水渠末端的水流方向与下游河道的水流方向相交的角度为锐角,以保证水流平顺进入河道,防止出现冲刷。In the falling flow cascaded cushion pond energy dissipation system, the angle between the water flow direction at the end of the bank diversion channel and the water flow direction of the downstream channel is an acute angle, so as to ensure that the water flow smoothly enters the river channel and prevent scour.

与现有技术相比,本发明具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:

1、本发明所述消能系统结合跌流消能和水垫塘分段进行消能,相对于地表陡槽溢洪道(i>1)增大了消能率,由于其布置在坝体侧山体上,避免了在狭窄河谷中修建水垫塘,小流量高水头水流对水垫塘可能发生的破坏,或采用挑流消能时对下游河道的冲刷,因而可保证枢纽的安全性,特别适合下游河道迅速由窄变宽的小流量高水头水利工程,解决了采用现有消能方式布置的场地条件限制、地形地质条件限制的问题。1. The energy dissipation system of the present invention combines the energy dissipation of the falling flow and the water cushion pond for energy dissipation in sections, which increases the energy dissipation rate compared with the surface steep groove spillway (i>1), because it is arranged on the mountain side of the dam body , to avoid the construction of cushion ponds in narrow river valleys, the possible damage to the cushion ponds caused by low-flow and high-head water flow, or the erosion of downstream rivers when deflecting flow is used to dissipate energy, thus ensuring the safety of the hub, especially suitable for downstream The water conservancy project with small flow and high head that the river channel quickly changes from narrow to wide solves the problems of site conditions and topographic and geological conditions that are arranged in the existing energy dissipation method.

2、本发明所述消能系统配合枢纽所在坝址的工程地质条件和地貌条件进行修建,通过调整各级水垫塘轴线及水垫塘大小,使得挖填方数量达到最小,避免了在狭窄河谷修建溢洪道时为减小溢洪道坡度而通常需要的大量填挖方量,提高了工程经济效益。2. The energy dissipation system of the present invention is built in accordance with the engineering geological conditions and geomorphic conditions of the dam site where the hub is located. By adjusting the axes of the water cushion ponds and the size of the water cushion ponds at all levels, the amount of excavation and filling can be minimized, avoiding the need to When the spillway is built in the valley, a large amount of filling and excavation is usually required to reduce the slope of the spillway, which improves the economic benefits of the project.

3、本发明所述消能系统配合枢纽所在坝址的工程地质条件和地貌条件进行修建,根据地形地貌条件灵活设计相邻两级水垫塘之间的高程差,布置灵活,因而能避开不利地质条件,大大降低了枢纽布置难度。3. The energy dissipation system of the present invention is built in accordance with the engineering geological conditions and topographical conditions of the dam site where the hub is located, and the elevation difference between adjacent two-stage pad ponds is flexibly designed according to the topographical and topographical conditions, and the layout is flexible, so it can avoid Unfavorable geological conditions greatly reduce the difficulty of hub layout.

附图说明Description of drawings

图1为发明所述跌流式梯级水垫塘消能系统的第一种总体布置俯视图。Fig. 1 is a top view of the first overall arrangement of the energy dissipation system of the falling flow cascaded cushion pond of the invention.

图2为发明所述跌流式梯级水垫塘消能系统的第二种总体布置俯视图。Fig. 2 is a top view of the second overall layout of the energy dissipation system of the falling-flow cascaded cushion pond described in the invention.

图3为发明所述跌流式梯级水垫塘消能系统的第三种总体布置俯视图。Fig. 3 is a top view of the third overall arrangement of the energy dissipation system of the falling flow cascaded cushion pond according to the invention.

图4为发明所述跌流式梯级水垫塘消能系统的第四种总体布置俯视图。Fig. 4 is a top view of the fourth general arrangement of the energy dissipation system of the falling-flow cascaded cushion pond according to the invention.

图5为发明所述跌流式梯级水垫塘消能系统的第五种总体布置俯视图。Fig. 5 is a top view of the fifth overall arrangement of the energy dissipation system of the falling-flow cascaded cushion pond according to the invention.

图6为图1的A-A剖视图。FIG. 6 is a cross-sectional view along line A-A of FIG. 1 .

图7为在单个水垫塘及与其衔接的水平溢洪道的结构示意图。Fig. 7 is a structural schematic diagram of a single cushion pond and the horizontal spillway connected thereto.

图8为图7的B-B剖视图。Fig. 8 is a B-B sectional view of Fig. 7 .

图9为图7的C-C剖视图。FIG. 9 is a C-C sectional view of FIG. 7 .

图中,1——上游引水渠,2——水垫塘,3——溢流堰,4——水平溢洪道,5——岸边引水渠,6——下游河道,7——山体,8——原地面线,9——水面线,10——大坝,11——上游水库,h1——水垫塘深度,h2——溢流堰高度,Δx—相邻水垫塘之间的高程差,l——水垫塘长度,b1——水垫塘宽度,b2——溢流堰宽度。In the figure, 1—upstream diversion channel, 2—water cushion pond, 3—overflow weir, 4—horizontal spillway, 5—bank diversion channel, 6—downstream channel, 7—mountain, 8 ——original ground line, 9—water surface line, 10—dam, 11—upstream reservoir, h 1 —depth of water cushion, h 2 —height of overflow weir, Δx—distance between adjacent water cushions The elevation difference between them, l—the length of the water cushion pond, b 1 ——the width of the water cushion pond, b 2 ——the width of the overflow weir.

具体实施方式detailed description

下面通过实施例对本发明所述跌流式梯级水垫塘消能系统作进一步说明。The energy dissipation system of the falling flow cascaded cushion pond of the present invention will be further described through the examples below.

实施例1和对比例1的工程概况如下:The engineering overview of embodiment 1 and comparative example 1 is as follows:

某电站修建在狭窄河谷之中,两岸山体陡峭,下游河道迅速由窄变宽,水库上游水位高程为621.00m和下游水位高程为531.00,落差为90m,泄流流量为300m3/s。针对上述工程,采用实施例1和对比例1两种消能系统进行水工模型试验。A power station is built in a narrow river valley, with steep mountains on both sides, and the downstream channel quickly changes from narrow to wide. The upstream water level elevation of the reservoir is 621.00m and the downstream water level elevation is 531.00m, the drop is 90m, and the discharge flow rate is 300m 3 /s. Aiming at the above projects, two energy dissipation systems of Example 1 and Comparative Example 1 were used to carry out hydraulic model tests.

实施例1Example 1

本实施采用跌流式梯级水垫塘消能系统消能,包括设置在水库坝体侧面山体不同高程处的三级阶梯式布置的水垫塘2,将水库中的水引出的上游引水渠1,第二高程和最低高程的各级水垫塘对应的水平溢洪道4和将最低高程的水垫塘中的水引入下游河道6的岸边引水渠5,各级水垫塘的下游端位于同一侧,各级水垫塘下游端边墙上均设置有溢流堰3;上述设施的布置方式如图3所示,各级水垫塘的轴线相互平行,上游引水渠1的出水口位于最高高程水垫塘的上游上方,第二高程水垫塘对应的水平溢洪道与最高高程水垫塘的高程相同并与最高高程水垫塘设置的溢流堰衔接,其出水口位于第二高程水垫塘的上游上方,最低高程水垫塘对应的水平溢洪道与第二高程水垫塘的高程相同并与第二高程水垫塘的溢流堰衔接,其出水口位于最低高程水垫塘的上游上方,所述岸边引水渠5的进水端与最低高程水垫塘下游端边墙设置的溢流堰3衔接,其末端与下游河道6相连,岸边引水渠5末端的水流方向与下游河道6的水流方向相交的角度为27.1°。This implementation adopts the energy dissipation system of cascaded water cushion ponds of falling flow, including the water cushion ponds 2 arranged in three steps at different elevations on the side of the reservoir dam body, and the upstream diversion channel 1 that draws the water out of the reservoir. , the horizontal spillway 4 corresponding to the water cushion ponds at all levels of the second elevation and the lowest elevation and the bank diversion channel 5 that introduces the water in the water cushion ponds at the lowest elevation into the downstream channel 6, and the downstream ends of the water cushion ponds at all levels are located at the same On the side, overflow weirs 3 are set on the downstream end walls of the water cushion ponds at all levels; Above the upper reaches of the high-elevation pad, the horizontal spillway corresponding to the second-elevation pad is at the same elevation as the highest-elevation pad and connected to the overflow weir set in the highest-elevation pad, and its outlet is located at the second-elevation pad Above the upstream of the pond, the horizontal spillway corresponding to the lowest elevation pond has the same elevation as the second elevation pond and connects with the overflow weir of the second elevation pond, and its outlet is located above the upstream of the lowest elevation pond , the water inlet end of the bank diversion canal 5 is connected with the overflow weir 3 arranged on the side wall at the downstream end of the lowest elevation pad pond, and its end is connected with the downstream river channel 6, and the water flow direction at the bank diversion channel 5 end is in line with the downstream channel The angle at which the water flow directions of 6 intersect is 27.1°.

水垫塘的结构如图7、图8、图9所示。三级水垫塘的尺寸相同,它们的长度l=20m、宽度b1=15m、深度h1=10m,它们的溢流堰高度h2=5m、宽度b2=b1,式中b1为水垫塘的宽度,最高高程水垫塘与第二高程水垫塘之间的高程差=第二高程水垫塘与最低高程水垫塘之间的高程差=30m,第二高程水垫塘对应的水平溢洪道入水口宽度与最高高程水垫塘的溢流堰宽度相等,最低高程水垫塘对应的水平溢洪道入水口宽度与第二高程水垫塘的溢流堰宽度相等,各水平溢洪道的出水口宽度与对应的水垫塘宽度相同(见图3)。The structure of the water cushion pond is shown in Figure 7, Figure 8, and Figure 9. The dimensions of the three-stage cushion ponds are the same, their length l=20m, width b 1 =15m, depth h 1 =10m, their overflow weir height h 2 =5m, width b 2 =b 1 , where b 1 is the width of the pad, the elevation difference between the highest elevation pad and the second elevation pad = the elevation difference between the second elevation pad and the lowest elevation pad = 30m, and the second elevation pad The width of the inlet of the horizontal spillway corresponding to the pond is equal to the width of the overflow weir of the highest elevation pad pond, and the width of the inlet of the horizontal spillway corresponding to the lowest elevation pad pond is equal to the width of the overflow weir of the second elevation pad pond. The width of the water outlet is the same as that of the corresponding pad pond (see Figure 3).

试验结果:泄流量为300m3/s时,水流平稳进入下游河道,测得岸边引水渠内水流平均流速为6.5m/s,该梯级水垫塘消能系统消能率达到95%;工程挖填方量为1.7万m3Test results: When the discharge rate is 300m 3 /s, the water flow enters the downstream channel smoothly. The average velocity of the water flow in the diversion channel on the bank is measured to be 6.5m/s, and the energy dissipation rate of the cascade pond energy dissipation system reaches 95%. The fill volume is 17,000 m 3 .

对比例1Comparative example 1

采用陡槽溢洪道加水垫塘布置消能系统,陡槽溢洪道坡度为0.8。The energy dissipation system is arranged with steep trough spillway and water cushion pond, and the slope of the steep trough spillway is 0.8.

试验结果:泄流量为300m3/s时,测得水垫塘尾部平均流速为13.18m/s,水垫塘内最大流速达到25.69m/s,该工程挖填方量达到4.6万m3,工程经济效益和消能效果较实施例1低。Test results: when the discharge rate is 300m 3 /s, the measured average flow velocity at the end of the pad pond is 13.18m/s, and the maximum flow velocity in the pad pond reaches 25.69m /s. The economic benefit and energy dissipation effect are lower than that of Example 1.

实施例2和对比例2的工程概况如下:The engineering overview of embodiment 2 and comparative example 2 is as follows:

某电站修建在狭窄河谷之中,两岸山体陡峭,下游河道迅速由窄变宽,水库入口高程为2126.00m,出口高程为2011.00m,落差为115m,泄洪流量为600m3/s。针对上述工程,采用实施例2和对比例2两种消能系统进行水工模型试验。A power station is built in a narrow river valley, with steep mountains on both sides, and the downstream channel rapidly changes from narrow to wide. The elevation of the reservoir entrance is 2126.00m, the elevation of the exit is 2011.00m, the drop is 115m, and the discharge flow is 600m 3 /s. Aiming at the above projects, two energy dissipation systems of Example 2 and Comparative Example 2 were used to carry out hydraulic model tests.

实施例2Example 2

本实施采用跌流式梯级水垫塘消能系统消能,包括设置在水库坝体侧面山体不同高程处的三级阶梯式布置的水垫塘2,将水库中的水引出的上游引水渠1,第二高程和最低高程的各级水垫塘对应的水平溢洪道4和将最低高程的水垫塘中的水引入下游河道6的岸边引水渠5,各级水垫塘的下游端位于同一侧,各级水垫塘下游端边墙上均设置有溢流堰3;上述设施的布置方式类似于图4,最高高程水垫塘与第二高程水垫塘的轴线相互平行,第二高程水垫塘与最低高程水垫塘的轴线相交成18.4°角;上游引水渠1的出水口位于最高高程水垫塘的上游上方,第二高程水垫塘对应的水平溢洪道与最高高程水垫塘的高程相同并与最高高程水垫塘设置的溢流堰衔接,其出水口位于第二高程水垫塘的上游上方,最低高程水垫塘对应的水平溢洪道与第二高程水垫塘的高程相同并与第二高程水垫塘的溢流堰衔接,其出水口位于最低高程水垫塘的上游上方,所述岸边引水渠5的进水端与最低高程水垫塘下游端边墙设置的溢流堰3衔接,其末端与下游河道6相连,岸边引水渠5末端的水流方向与下游河道6的水流方向相交的角度为26.7°。This implementation adopts the energy dissipation system of cascaded water cushion ponds of falling flow, including the water cushion ponds 2 arranged in three steps at different elevations on the side of the reservoir dam body, and the upstream diversion channel 1 that draws the water out of the reservoir. , the horizontal spillway 4 corresponding to the water cushion ponds at all levels of the second elevation and the lowest elevation and the bank diversion channel 5 that introduces the water in the water cushion ponds at the lowest elevation into the downstream channel 6, and the downstream ends of the water cushion ponds at all levels are located at the same On the other side, overflow weirs 3 are set on the downstream end walls of the pad ponds at all levels; the layout of the above-mentioned facilities is similar to that shown in Figure 4. The axis of the paddy pond intersects with the axis of the lowest elevation paddy pond to form an angle of 18.4°; the outlet of the upstream diversion channel 1 is located above the upstream of the highest elevation paddy pond, and the horizontal spillway corresponding to the second elevation paddle pond and the highest elevation paddy pond The same elevation and connected with the overflow weir set in the highest elevation pond, its outlet is located above the upstream of the second elevation pond, and the horizontal spillway corresponding to the lowest elevation pond is at the same elevation as the second elevation pond And it is connected with the overflow weir of the second elevation pad pond, and its water outlet is located above the upstream of the lowest elevation pad pond, and the water inlet end of the bank diversion channel 5 is set with the bottom side wall of the lowest elevation pad pond. The overflow weir 3 is connected, and its end is connected with the downstream channel 6, and the angle at which the flow direction at the end of the bank diversion channel 5 intersects with the flow direction of the downstream channel 6 is 26.7°.

水垫塘的结构如图7、图8、图9所示。最高高程水垫塘与第二高程水垫塘的尺寸相同,它们的长度l=30m、宽度b1=25m、深度h1=15m,溢流堰3的高度h2=5m、宽度b2=20m<b1,式中b1为水垫塘的宽度,最高高程水垫塘与第二高程水垫塘之间的高程差=45m。最低高程水垫塘长度l=40m、宽度b1=30m、深度h1=15m,溢流堰的高度h2=5m、宽度b2=20m<b1,式中b1为水垫塘的宽度,最低高程水垫塘与第二高程水垫塘之间的高程差=35m。第二高程水垫塘对应的水平溢洪道入水口宽度与最高高程水垫塘的溢流堰宽度相等,最低高程水垫塘对应的水平溢洪道入水口宽度与第二高程水垫塘的溢流堰宽度相等,各水平溢洪道的出水口宽度与对应的水垫塘宽度相同(类似于图2)。The structure of the water cushion pond is shown in Figure 7, Figure 8, and Figure 9. The highest elevation water cushion pond has the same size as the second elevation water cushion pond, their length l=30m, width b 1 =25m, depth h 1 =15m, and the height h 2 of the overflow weir 3 =5m, width b 2 = 20m<b 1 , where b 1 is the width of the pad, and the elevation difference between the pad at the highest elevation and the pad at the second elevation = 45m. The lowest elevation water cushion pond has length l=40m, width b 1 =30m, depth h 1 =15m, height of overflow weir h 2 =5m, width b 2 =20m<b 1 , where b 1 is the water cushion pond Width, the difference in elevation between the lowest elevation pool and the second elevation pool = 35m. The width of the inlet of the horizontal spillway corresponding to the second elevation pad pond is equal to the width of the overflow weir of the highest elevation pad pond, and the width of the inlet of the horizontal spillway corresponding to the lowest elevation pad pond is equal to the width of the overflow weir of the second elevation pad pond Equal, the width of the outlet of each horizontal spillway is the same as the width of the corresponding pad (similar to Figure 2).

试验结果:泄流量为600m3/s时,水流平顺进入河道,对下游岸坡及河流底部无明显冲刷,测得岸边引水渠出口流速为8.3m/s,该消能系统的消能率为96.5%。Test results: When the discharge rate is 600m 3 /s, the water flow enters the river smoothly, and there is no obvious erosion on the downstream bank slope and the bottom of the river. The measured flow velocity at the outlet of the bank diversion channel is 8.3m/s. 96.5%.

对比例2Comparative example 2

采用上游泄洪洞,下部接挑坎直接挑入下游河道的消能系统。The upstream flood discharge tunnel is adopted, and the lower part is directly connected to the energy dissipation system of the downstream river channel.

试验结果:泄流量为600m3/s时,挑流落点距河道对岸仅4.2m,且冲坑深度达到32.12m,威胁到下游河道边坡的安全和工程的正常运行。Test results: When the discharge rate is 600m 3 /s, the drop point of the deflector is only 4.2m away from the opposite bank of the river, and the scour depth reaches 32.12m, which threatens the safety of the downstream river slope and the normal operation of the project.

实施例3和对比例3的工程概况如下:The engineering overview of embodiment 3 and comparative example 3 is as follows:

某电站修建在狭窄河谷之中,两岸山体陡峭,下游河道迅速由窄变宽,水库入口高程为1426.00m,出口高程为1321.00m,落差为105m,泄洪流量为1200m3/s。针对上述工程,采用实施例3和对比例3两种消能系统进行水工模型试验。A power station is built in a narrow river valley, with steep mountains on both sides, and the downstream channel quickly changes from narrow to wide. The elevation of the reservoir entrance is 1426.00m, the elevation of the exit is 1321.00m, the drop is 105m, and the discharge flow is 1200m 3 /s. Aiming at the above projects, two energy dissipation systems of Example 3 and Comparative Example 3 were used to carry out hydraulic model tests.

实施例3Example 3

本实施采用跌流式梯级水垫塘消能系统消能,包括设置在水库坝体侧面山体不同高程处的三级阶梯式布置的水垫塘2,将水库中的水引出的上游引水渠1,第二高程和最低高程的各级水垫塘对应的水平溢洪道4和将最低高程的水垫塘中的水引入下游河道6的岸边引水渠5,各级水垫塘的下游端位于同一侧,各级水垫塘下游端边墙上均设置有溢流堰3;上述设施的布置方式类似于图4,最高高程水垫塘与第二高程水垫塘的轴线相互平行,第二高程水垫塘与最低高程水垫塘的轴线相交成39.5°角;上游引水渠1的出水口位于最高高程水垫塘的上游上方,第二高程水垫塘对应的水平溢洪道与最高高程水垫塘的高程相同并与最高高程水垫塘设置的溢流堰衔接,其出水口位于第二高程水垫塘的上游上方,最低高程水垫塘对应的水平溢洪道与第二高程水垫塘的高程相同并与第二高程水垫塘的溢流堰衔接,其出水口位于最低高程水垫塘的上游上方,所述岸边引水渠5的进水端与最低高程水垫塘下游端边墙设置的溢流堰3衔接,其末端与下游河道6相连,岸边引水渠5末端的水流方向与下游河道6的水流方向相交的角度为32°。This implementation adopts the energy dissipation system of cascaded water cushion ponds of falling flow, including the water cushion ponds 2 arranged in three steps at different elevations on the side of the reservoir dam body, and the upstream diversion channel 1 that draws the water out of the reservoir. , the horizontal spillway 4 corresponding to the water cushion ponds at all levels of the second elevation and the lowest elevation and the bank diversion channel 5 that introduces the water in the water cushion ponds at the lowest elevation into the downstream channel 6, and the downstream ends of the water cushion ponds at all levels are located at the same On the other side, overflow weirs 3 are set on the downstream end walls of the pad ponds at all levels; the layout of the above-mentioned facilities is similar to that shown in Figure 4. The axis of the paddy pond intersects with the axis of the lowest elevation paddle pond to form an angle of 39.5°; the outlet of the upstream diversion channel 1 is located above the upper reaches of the highest elevation paddy pond, and the horizontal spillway corresponding to the second elevation paddle pond and the highest elevation paddle pond The same elevation and connected with the overflow weir set in the highest elevation pond, its outlet is located above the upstream of the second elevation pond, and the horizontal spillway corresponding to the lowest elevation pond is at the same elevation as the second elevation pond And it is connected with the overflow weir of the second elevation pad pond, and its water outlet is located above the upstream of the lowest elevation pad pond, and the water inlet end of the bank diversion channel 5 is set with the bottom side wall of the lowest elevation pad pond. The overflow weir 3 is connected, and its end is connected with the downstream channel 6, and the angle at which the flow direction at the end of the bank diversion channel 5 intersects with the flow direction of the downstream channel 6 is 32°.

水垫塘的结构如图7、图8、图9所示。三级水垫塘的尺寸相同,它们的长度l=30m、宽度b1=25m、深度h1=12m,它们的溢流堰高度h2=5m、宽度b2=18m<b1,式中b1为水垫塘的宽度,最高高程水垫塘与第二高程水垫塘之间的高程差=第二高程水垫塘与最低高程水垫塘之间的高程差=35m,第二高程水垫塘对应的水平溢洪道入水口宽度与最高高程水垫塘的溢流堰宽度相等,最低高程水垫塘对应的水平溢洪道入水口宽度与第二高程水垫塘的溢流堰宽度相等,各水平溢洪道的出水口宽度与入水口等宽(见图4)。The structure of the water cushion pond is shown in Figure 7, Figure 8, and Figure 9. The dimensions of the three-stage cushion ponds are the same, their length l=30m, width b 1 =25m, depth h 1 =12m, their overflow weir height h 2 =5m, width b 2 =18m<b 1 , where b 1 is the width of the paddy pond, the elevation difference between the highest elevation paddle pond and the second elevation paddle pond = the elevation difference between the second elevation paddle pond and the lowest elevation paddle pond = 35m, the second elevation The width of the water inlet of the horizontal spillway corresponding to the water cushion pond is equal to the width of the overflow weir of the water cushion pond at the highest elevation, and the width of the water inlet of the horizontal spillway corresponding to the water cushion pond at the lowest elevation is equal to the width of the overflow weir of the water cushion pond at the second elevation. The width of the outlet of the horizontal spillway is equal to the width of the inlet (see Figure 4).

试验结果:泄洪流量为1200m3/s时,水流平顺进入河道,对下游岸坡及河流底部无明显冲刷,测得岸边引水渠出口流速为2.3m/s,该消能系统的消能率为97.2%。Test results: When the flood discharge flow rate is 1200m 3 /s, the water flow enters the river smoothly, and there is no obvious erosion on the downstream bank slope and the bottom of the river. 97.2%.

对比例3Comparative example 3

采用上游泄洪洞,下部接挑坎直接挑入下游河道的消能系统。The upstream flood discharge tunnel is adopted, and the lower part is directly connected to the energy dissipation system of the downstream river channel.

试验结果:泄洪流量为1200m3/s时,挑流落点距河道对岸仅10.2m,下游雾化严重,且冲坑深度达到32.12m,威胁到下游河道边坡的安全和工程的正常运行。Test results: When the flood discharge rate is 1200m 3 /s, the drop point of the deflector is only 10.2m away from the opposite bank of the river, and the downstream fogging is serious, and the scour depth reaches 32.12m, which threatens the safety of the downstream river slope and the normal operation of the project.

需要说明的是:上述各实施例中的“第二高程水垫塘”又可称为“次低高程水垫塘”。It should be noted that the "second elevation water cushion pond" in the above embodiments can also be called "second-lowest elevation water cushion pond".

Claims (10)

1.一种跌流式梯级水垫塘消能系统,其特征在于该系统包括设置在水库坝体侧面山体不同高程处的多级阶梯式布置的水垫塘(2),将水库中的水引出的上游引水渠(1),第二高程至最低高程的各级水垫塘对应的水平溢洪道(4)和将最低高程水垫塘中的水引入下游河道(6)的岸边引水渠(5),各级水垫塘的下游端位于同一侧,各级水垫塘下游端边墙上均设置有溢流堰(3);上游引水渠(1)的出水口位于最高高程水垫塘的上游上方,第二高程水垫塘对应的水平溢洪道与最高高程水垫塘的高程相同并与最高高程水垫塘设置的溢流堰衔接,其出水口位于第二高程水垫塘的上游上方,第三高程水垫塘对应的水平溢洪道与第二高程水垫塘的高程相同并与第二高程水垫塘的溢流堰衔接,其出水口位于第三高程水垫塘的上游上方,最低高程水垫塘对应的水平溢洪道与次低高程水垫塘的高程相同并与次低高程水垫塘的溢流堰衔接,其出水口位于最低高程水垫塘的上游上方,所述岸边引水渠(5)的进水端与最低高程水垫塘下游端边墙设置的溢流堰衔接,其末端与下游河道(6)相连,从而将水库中的水经上游引水渠跌落至最高高程水垫塘,再经第二高程至最低高程的各级水垫塘对应的水平溢洪道从高至低依次跌落至各级水垫塘中,并经岸边引水渠(5)流入下游河道。1. A drop-flow type cascaded water cushion pond energy dissipation system is characterized in that the system includes a multi-stage stepped water cushion pond (2) arranged at different elevations on the side of the reservoir dam body, and the water in the reservoir is The upstream aqueduct (1) drawn, the horizontal spillway (4) corresponding to the pad ponds at all levels from the second elevation to the lowest elevation, and the bank aqueduct ( 5), the downstream ends of the water cushion ponds at all levels are located on the same side, and overflow weirs (3) are arranged on the side walls of the downstream ends of the water cushion ponds at all levels; the outlet of the upstream diversion channel (1) is located at the highest elevation of the water cushion ponds The horizontal spillway corresponding to the second elevation pond is at the same elevation as the highest elevation pond and connects with the overflow weir set in the highest elevation pond, and its outlet is located above the upstream of the second elevation pond , the horizontal spillway corresponding to the third elevation pond is at the same elevation as the second elevation pond and connects with the overflow weir of the second elevation pond, and its outlet is located above the upstream of the third elevation pond, the lowest The horizontal spillway corresponding to the elevation pond is at the same elevation as the second-lowest elevation pond and connects with the overflow weir of the second-lowest elevation pond, and its outlet is located above the upper reaches of the lowest elevation pond. The water inlet end of the water channel (5) is connected with the overflow weir provided on the downstream side wall of the lowest elevation pad pond, and its end is connected with the downstream channel (6), so that the water in the reservoir is dropped to the highest elevation water through the upstream diversion channel. Dian ponds, and then through the horizontal spillways corresponding to the pad ponds at all levels from the second elevation to the lowest elevation, drop into the pad ponds at all levels in turn from high to low, and flow into the downstream channel through the bank diversion channel (5). 2.根据权利要求1所述跌流式梯级水垫塘消能系统,其特征在于各级水垫塘的轴线相互平行或相交成锐角。2. According to claim 1, the cascaded cascaded water cushion pond energy dissipation system is characterized in that the axes of the water cushion ponds at all levels are parallel to each other or intersect to form an acute angle. 3.根据权利要求1或2所述跌流式梯级水垫塘消能系统,其特征在于相邻两级水垫塘之间的高程差△x=30~45m。3. According to claim 1 or 2, the cascade cascaded water cushion pond energy dissipation system is characterized in that the elevation difference between two adjacent water cushion ponds is Δx=30-45m. 4.根据权利要求1或2所述跌流式梯级水垫塘消能系统,其特征在于所述水垫塘的长度l=20~40m、宽度b1=15~30m、深度h1=最大水位高度+波动高度+安全超高。4. According to claim 1 or 2, the falling flow cascaded water cushion pond energy dissipation system is characterized in that the length of the water cushion pond is l=20-40m, the width b 1 =15-30m, and the depth h 1 =maximum Water level height + fluctuation height + safety super high. 5.根据权利要求3所述跌流式梯级水垫塘消能系统,其特征在于所述水垫塘的长度l=20~40m、宽度b1=15~30m、深度h1=最大水位高度+波动高度+安全超高。5. According to claim 3, the falling flow cascaded water cushion pond energy dissipation system is characterized in that the length of the water cushion pond is l=20-40m, the width b 1 =15-30m, and the depth h 1 =maximum water level +Swing height+Safe super high. 6.根据权利要求1或2所述跌流式梯级水垫塘消能系统,其特征在于所述溢流堰(3)的宽度b2≤b1,式中b1为水垫塘的宽度。6. According to claim 1 or 2, the cascaded cascaded water cushion pond energy dissipation system is characterized in that the width of the overflow weir (3) b 2 ≤ b 1 , where b 1 is the width of the water cushion pond . 7.根据权利要求3所述跌流式梯级水垫塘消能系统,其特征在于所述溢流堰(3)的宽度b2≤b1,式中,b1为水垫塘的宽度。7. The energy dissipation system of the cascading water cushion pond according to claim 3, characterized in that the width of the overflow weir (3) b 2 ≤ b 1 , where b 1 is the width of the water cushion pond. 8.根据权利要求4所述跌流式梯级水垫塘消能系统,其特征在于所述溢流堰(3)的宽度b2≤b1,式中,b1为水垫塘的宽度。8. The energy dissipation system of the falling flow cascaded water cushion pond according to claim 4, characterized in that the width of the overflow weir (3) b 2 ≤ b 1 , where b 1 is the width of the water cushion pond. 9.根据权利要求5所述跌流式梯级水垫塘消能系统,其特征在于所述溢流堰(3)的宽度b2≤b1,式中,b1为水垫塘的宽度。9. The energy dissipation system of falling flow cascaded water cushion ponds according to claim 5, characterized in that the width of the overflow weir (3) b 2 ≤ b 1 , where b 1 is the width of the water cushion ponds. 10.根据权利要求1或2所述跌流式梯级水垫塘消能系统,其特征在于所述岸边引水渠(5)末端的水流方向与下游河道(6)的水流方向相交的角度为锐角。10. According to claim 1 or 2, the falling flow cascaded water cushion pond energy dissipation system is characterized in that the angle at which the water flow direction at the end of the bank diversion channel (5) intersects with the water flow direction of the downstream channel (6) is acute angle.
CN201410461747.7A 2014-09-11 2014-09-11 Down stream formula step plunge pool system Active CN104294802B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410461747.7A CN104294802B (en) 2014-09-11 2014-09-11 Down stream formula step plunge pool system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410461747.7A CN104294802B (en) 2014-09-11 2014-09-11 Down stream formula step plunge pool system

Publications (2)

Publication Number Publication Date
CN104294802A CN104294802A (en) 2015-01-21
CN104294802B true CN104294802B (en) 2016-04-27

Family

ID=52314732

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410461747.7A Active CN104294802B (en) 2014-09-11 2014-09-11 Down stream formula step plunge pool system

Country Status (1)

Country Link
CN (1) CN104294802B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112900381A (en) * 2021-01-26 2021-06-04 珠江水利委员会珠江水利科学研究院 Rotatory stilling pool formula dissipation structure suitable for shaft
CN116607474B (en) * 2023-04-15 2026-02-17 湖南省水利水电勘测设计规划研究总院有限公司 Side slope scour protection's plunge pool structure

Also Published As

Publication number Publication date
CN104294802A (en) 2015-01-21

Similar Documents

Publication Publication Date Title
CN101349047B (en) Air-entrained curve ladder energy dissipator in the flood discharge tunnel
CN104775393B (en) A kind of special-shaped anti-step rectification energy dissipating method and stiling basin
CN103469772B (en) Shaft type flood spillway for reservoirs
CN101761057A (en) Flood-discharging energy dissipater of hydroelectric project
CN108086260B (en) Differential type High-low Bucket Energy Dissipation Building-height falls bank type stilling pond system and energy dissipating method
CN104264639B (en) Underflow type step absorption basin energy-dissipating system
CN107190712B (en) A kind of toe bank falls bank stiling basin formula underflow energy dissipator and design method
CN203411960U (en) Glory hole spillway of reservoir
CN203530941U (en) Split-level and dislocated type multiple-grooved spillway structure
CN202610774U (en) Deep-hole cyclone shaft type flood drainage tunnel
CN101538840B (en) deflected flow energy dissipator in the stilling basin
CN202626947U (en) Picking flow type flaring pier of overflow dam
CN220789664U (en) Gravity dam spillway
CN103938592B (en) Sediment trapping bank is offered tap hole and carries out the method shunted of damming
CN102704447B (en) V-shaped step energy dissipater with transition section
CN104294802B (en) Down stream formula step plunge pool system
CN204644988U (en) A kind of special-shaped anti-step absorption basin
CN107386220A (en) The dam structure of breach shunting two
CN204139139U (en) Flood discharge absorption basin structure
CN110593221A (en) Fold-line type flip bucket at outlet of bank spillway/flood discharge tunnel
CN211256912U (en) Fold-line type flip bucket at outlet of bank spillway/flood discharge tunnel
CN118422654A (en) Structure for improving water flow characteristics at junction of underground cavern and use method thereof
CN104213545B (en) Hang underflow type step stiling basin energy-dissipating system
CN104294801B (en) Energy Dissipation System for Suspended Falling Water Cushion Pond
CN206220066U (en) Passed the flood period the choosing of the breach flow, down stream energy-dissipating structure for gravity dam bank

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant