CN104278679A - 一种五(六)轴搅拌桩与预制管桩相结合的围护结构及施工方法 - Google Patents
一种五(六)轴搅拌桩与预制管桩相结合的围护结构及施工方法 Download PDFInfo
- Publication number
- CN104278679A CN104278679A CN201310270145.9A CN201310270145A CN104278679A CN 104278679 A CN104278679 A CN 104278679A CN 201310270145 A CN201310270145 A CN 201310270145A CN 104278679 A CN104278679 A CN 104278679A
- Authority
- CN
- China
- Prior art keywords
- pile
- piles
- construction method
- axle
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/12—Restraining of underground water by damming or interrupting the passage of underground water
- E02D19/18—Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
- E02D5/187—Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/50—Piles comprising both precast concrete portions and concrete portions cast in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/26—Placing by using several means simultaneously
Abstract
本发明涉及一种搅拌桩与预制桩相结合的围护结构及施工方法,该搅拌桩为采用五轴或六轴搅拌桩工艺施工的桩型,以下简称FCW工法。与之相结合的预制构件为管桩,该管桩施工采用城地混凝土管桩芯孔内掘土注浆封底工艺,以下简称CLP工法。本发明机械化程度高具有低噪音、成本造价低、工期大幅度缩短等特点。
Description
技术领域
本发明涉及一种五(六)轴搅拌桩与预制构件相结合的围护结构及其施工方法,主要应用于民用及其工业基础设施建设建设中的基坑围护止水及基坑围护。
背景技术
目前一般基坑围护止水和地基加固多采用二轴搅拌桩和SMW工法。
二轴搅拌桩是80年代延用的工法,机架为井字架,走管式行走,稳定性极差,工效很低,劳动强度大,另动力头部分采用37kw的常规电机,起动动力不足。最深桩长只有18m,下部钻杆只有二道叶片,搅拌不均匀,下部成桩质量难以保证,每次成桩1.2米一组,造成桩搭接冷缝多,容易造成漏水等现象。SMW工法不足之处是水泥渗量20%,水灰比为1.5~2.0才能成桩,由于水灰比的增大,为保证水泥的强度,只能增加水泥用量。水泥用量大,有三分之一置换土,土中含有水泥浆,不能做耕植土及绿化土,只能作为渣土处理,既浪费了材料,又给环境造成污染,造价高。二轴、三轴搅拌桩内插H型钢和在内壁用钻孔灌注桩挡土,成本高,浪费材料严重。
而且二轴搅拌桩只能作为止水帷幕,不能起挡土作用;SMW工法虽然具备一定挡土功能,但在施工过程中需要置换出大量泥浆污染环境,插入型钢给施工增加了难度,同时型钢高昂的租赁费用也增加了施工成本。
发明内容
本发明为了解决了现有技术中的施工难题,通过结合了预制构件和一种无置换土的搅拌桩,形成一个无污染,绿色环保、低造价的围护结构。
本发明通过以下技术方案来实现:
一种五(六)轴搅拌桩与预制管桩相结合的围护结构,所述的围护结构包括五(六)轴搅拌桩与预制管桩,所述的五(六)轴搅拌桩采用城地五轴水泥土搅拌墙施工技术(以下简称FCW工法);所述的预制管桩采用城地混凝土管桩芯孔内掘土注浆封底施工技术(以下简称CLP工法)。
所述的两种桩型可以并排排列(类似灌注桩与搅拌桩的排桩支护),也可以是管桩内嵌于搅拌桩内。
所述的一种五轴水泥土搅拌墙的施工方法,其施工方法包括以下步骤:
(1)放样,开沟槽,装置就位,将五轴水泥土搅拌桩装置移动到待施工位置;
(2)起动后台水泥浆搅拌系统,然后把水泥浆送至存浆桶;
(3)开启集成计算机,让计算机来控制预先设置的数据:每米下降速度、每米喷浆量、桩端设计标高、总喷浆量和总搅拌时间;
(4)开启动力头驱动多功能钻头,边搅拌边喷水泥浆,正转下沉喷浆50%~80%到设计墙底标高。
(5)在墙底标高0.5~1米区间内进行复搅。
(6)反转边喷浆边提钻,反转喷浆20%~50%至墙顶标高;
(7)一上一下即可成桩,根据需要形成重力坝;
(8)一组结束,移至第二组继续施工。
所述的一种混凝土管桩芯孔内掘土注浆封底施工方法,其施工方法包括以下步骤:
(1)放样,根据施工图放出实样;
(2)用吊车吊起预制桩和插入桩中心的螺旋形钻杆;
(3)立起桩和钻杆,使动力头下方和螺旋钻杆上方连接;
(4)使螺旋钻杆旋转的同时运转压入装置,一边排土,一边沉桩;
(5)沉入下节桩,连接上下两根螺旋形钻杆,同时焊接下节桩和上节桩;
(6)旋转螺旋钻杆的同时运转压入装置,一边排土,一边把桩压至地面;
(7)连接送桩器,把桩尖端压到持力层后旋转螺旋形钻杆,同时挖掘指定深度;
(8)在到达指定深度后,立即高压喷射水泥浆,封堵底部端口。
与现有的二轴、三轴围护技术相比,在缩短了的施工工期的同时还很好的保护了周围环境,无置换土产生,无泥浆。插入管桩作为围护结构可替代SMW工法桩,降低了施工难度和施工成本。
附图说明
图1为管桩与五(六)轴搅拌桩排桩组合形式;
图2为管桩内嵌于五(六)轴搅拌桩;
图3为以五轴搅拌桩为例的施工序列图;
具体实施方式
下面结合附图和具体实施例对本发明的一种围护形式进行详细说明。本实施例以本发明技术方案为前提进行实施,给出了详细的实施方式和具体的操作过程,但本发明的保护范围不限于下述的实施例。
实施例:
如图3所示,一种采用上述施工方法施工的管桩与搅拌桩相咬合的竖向围护结构,包括多个管桩和搅拌桩,所述的搅拌桩为五轴搅拌桩,采用套打形式,A序桩的具体施工流程如下:
(1)放样;开沟槽;将五轴水泥土搅拌墙机械设备移动到待施工位置。
(2)启动后台自动水泥浆搅拌系统,然后把水泥浆送至存浆桶。
(3)开启集成计算机,由计算机监控成墙关键数据;每米下降速度、提升速度、每米浆量、墙端设计标高、垂直度、总喷浆量和总搅拌时间。有效控制成墙质量。
(4)开启动力头驱动多功能钻头,边搅拌边喷水泥浆,正转下沉喷浆70%到设计墙底标高。
(5)在墙底标高1米区间内进行复搅。
(6)反转边喷浆边提钻,反转喷浆30%至墙顶标高。
(7)一组结束,移到第二组继续施工。
A序桩施工完成后在其初凝前,进行B序桩的施工,即预制管桩的插入,具体施工流程如下:
(1)用吊车吊起混凝土管桩和插入桩中心的螺旋形钻杆。
(2)立起桩和钻杆,使动力头下方和螺旋钻杆上方连接。
(3)使螺旋钻杆旋转的同时运转压入装置,一边排土,一边沉桩。
(4)沉入下节桩,连接上下两根螺旋形钻杆,同时焊接下节桩和上节桩。
(5)旋转螺旋钻杆的同时运转压入装置,一边排土,一边沉桩直至完成所有桩节施工。
(6)连上送桩器,把桩尖端压到持力层后旋转螺旋形钻杆挖掘至加固体底标高。
(7)桩尖达到指定深度,立即高压喷射水泥浆,封堵桩端。(需要喷浆即实施)
(8)一边喷射水泥浆,一边提升钻头至规定喷射区间处,停止喷射,拔起钻杆。(需要喷浆即实施)
Claims (4)
1.一种五(六)轴搅拌桩与预制管桩相结合的围护结构,其特征在于,所述的围护结构包括五(六)轴搅拌桩与预制管桩,所述的五(六)轴搅拌桩采用城地五轴水泥土搅拌墙施工技术(以下简称FCW工法);所述的预制管桩采用城地混凝土管桩芯孔内掘土注浆封底施工技术(以下简称CLP工法)。
2.根据权利要求1所述的一种五(六)轴搅拌桩与预制管桩相结合的围护结构,其特征在于,所述的两种桩型可以并排排列(类似灌注桩与搅拌桩的排桩支护),也可以是管桩内嵌于搅拌桩内。
3.根据权利要求1所述的一种五轴水泥土搅拌墙的施工方法,其特征在于,所述的施工方法包括以下步骤:
(1)放样,开沟槽,装置就位,将五轴水泥土搅拌桩装置移动到待施工位置;
(2)起动后台水泥浆搅拌系统,然后把水泥浆送至存浆桶;
(3)开启集成计算机,让计算机来控制预先设置的数据:每米下降速度、每米喷浆量、桩端设计标高、总喷浆量和总搅拌时间;
(4)开启动力头驱动多功能钻头,边搅拌边喷水泥浆,正转下沉喷浆50%~80%到设计墙底标高。
(5)在墙底标高0.5~1米区间内进行复搅。
(6)反转边喷浆边提钻,反转喷浆20%~50%至墙顶标高;
(7)一上一下即可成桩,根据需要形成重力坝;
(8)一组结束,移至第二组继续施工。
4.根据权利要求1所述的一种混凝土管桩芯孔内掘土注浆封底施工方法,其特征在于,所述的施工方法包括以下步骤:
(1)放样,根据施工图放出实样;
(2)用吊车吊起预制桩和插入桩中心的螺旋形钻杆;
(3)立起桩和钻杆,使动力头下方和螺旋钻杆上方连接;
(4)使螺旋钻杆旋转的同时运转压入装置,一边排土,一边沉桩;
(5)沉入下节桩,连接上下两根螺旋形钻杆,同时焊接下节桩和上节桩;
(6)旋转螺旋钻杆的同时运转压入装置,一边排土,一边把桩压至地面;
(7)连接送桩器,把桩尖端压到持力层后旋转螺旋形钻杆,同时挖掘指定深度;
(8)在到达指定深度后,立即高压喷射水泥浆,封堵底部端口。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310270145.9A CN104278679A (zh) | 2013-07-01 | 2013-07-01 | 一种五(六)轴搅拌桩与预制管桩相结合的围护结构及施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310270145.9A CN104278679A (zh) | 2013-07-01 | 2013-07-01 | 一种五(六)轴搅拌桩与预制管桩相结合的围护结构及施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104278679A true CN104278679A (zh) | 2015-01-14 |
Family
ID=52253987
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310270145.9A Pending CN104278679A (zh) | 2013-07-01 | 2013-07-01 | 一种五(六)轴搅拌桩与预制管桩相结合的围护结构及施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104278679A (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104612165A (zh) * | 2015-02-06 | 2015-05-13 | 上海城地建设股份有限公司 | 非熔焊多节连接的预制钢筋砼构件围护体系及其施工方法 |
CN104863120A (zh) * | 2015-05-13 | 2015-08-26 | 中国建筑第八工程局有限公司 | 咬合桩施工方法及用于该方法的预制咬合桩 |
CN106120812A (zh) * | 2016-08-09 | 2016-11-16 | 上海强劲地基工程股份有限公司 | 一种装配式工作井结构及施工方法 |
CN107165173A (zh) * | 2017-07-18 | 2017-09-15 | 中冶华天南京工程技术有限公司 | 一种基坑支护体系及其施工方法 |
CN107882024A (zh) * | 2016-09-30 | 2018-04-06 | 上海城地建设股份有限公司 | 预应力预制构件螺丝桩 |
CN112942313A (zh) * | 2021-01-26 | 2021-06-11 | 上海兴庚基础工程有限公司 | 一种水泥搅拌土植入预制钢筋砼桩围护墙及其施工方法 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002146774A (ja) * | 2000-11-13 | 2002-05-22 | Tekken Constr Co Ltd | ソイルセメント柱列壁工法 |
CN101240551A (zh) * | 2007-12-07 | 2008-08-13 | 江苏东大特种基础工程有限公司 | 预制预应力管桩复合支护墙结构 |
CN201232185Y (zh) * | 2008-07-30 | 2009-05-06 | 杭州南方土木工程咨询有限公司 | 多功能水泥搅拌土植桩机 |
CN101509254A (zh) * | 2009-03-09 | 2009-08-19 | 天津市建工工程总承包有限公司 | 钢筋混凝土灌注桩与水泥搅拌桩啮合式基坑支护施工方法 |
CN201459737U (zh) * | 2009-06-25 | 2010-05-12 | 南京林业大学 | 一种基坑支护结构 |
CN102373710A (zh) * | 2011-02-23 | 2012-03-14 | 上海城地建设发展有限公司 | 三轴(二轴)水泥土搅拌桩中插预应力离心管桩(方桩)围护方法 |
CN102383431A (zh) * | 2011-04-21 | 2012-03-21 | 上海城地建设发展有限公司 | 中掘预应力离心管桩(方桩)沉桩装置及其新型沉桩法 |
CN102535450A (zh) * | 2012-01-17 | 2012-07-04 | 上海城地建设发展有限公司 | 一种五轴水泥土搅拌桩装置及施工方法 |
-
2013
- 2013-07-01 CN CN201310270145.9A patent/CN104278679A/zh active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002146774A (ja) * | 2000-11-13 | 2002-05-22 | Tekken Constr Co Ltd | ソイルセメント柱列壁工法 |
CN101240551A (zh) * | 2007-12-07 | 2008-08-13 | 江苏东大特种基础工程有限公司 | 预制预应力管桩复合支护墙结构 |
CN201232185Y (zh) * | 2008-07-30 | 2009-05-06 | 杭州南方土木工程咨询有限公司 | 多功能水泥搅拌土植桩机 |
CN101509254A (zh) * | 2009-03-09 | 2009-08-19 | 天津市建工工程总承包有限公司 | 钢筋混凝土灌注桩与水泥搅拌桩啮合式基坑支护施工方法 |
CN201459737U (zh) * | 2009-06-25 | 2010-05-12 | 南京林业大学 | 一种基坑支护结构 |
CN102373710A (zh) * | 2011-02-23 | 2012-03-14 | 上海城地建设发展有限公司 | 三轴(二轴)水泥土搅拌桩中插预应力离心管桩(方桩)围护方法 |
CN102383431A (zh) * | 2011-04-21 | 2012-03-21 | 上海城地建设发展有限公司 | 中掘预应力离心管桩(方桩)沉桩装置及其新型沉桩法 |
CN102535450A (zh) * | 2012-01-17 | 2012-07-04 | 上海城地建设发展有限公司 | 一种五轴水泥土搅拌桩装置及施工方法 |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104612165A (zh) * | 2015-02-06 | 2015-05-13 | 上海城地建设股份有限公司 | 非熔焊多节连接的预制钢筋砼构件围护体系及其施工方法 |
CN104863120A (zh) * | 2015-05-13 | 2015-08-26 | 中国建筑第八工程局有限公司 | 咬合桩施工方法及用于该方法的预制咬合桩 |
CN106120812A (zh) * | 2016-08-09 | 2016-11-16 | 上海强劲地基工程股份有限公司 | 一种装配式工作井结构及施工方法 |
CN107882024A (zh) * | 2016-09-30 | 2018-04-06 | 上海城地建设股份有限公司 | 预应力预制构件螺丝桩 |
CN107165173A (zh) * | 2017-07-18 | 2017-09-15 | 中冶华天南京工程技术有限公司 | 一种基坑支护体系及其施工方法 |
CN112942313A (zh) * | 2021-01-26 | 2021-06-11 | 上海兴庚基础工程有限公司 | 一种水泥搅拌土植入预制钢筋砼桩围护墙及其施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104675403B (zh) | 一种地下空间施工方法及支护结构 | |
CN104131575B (zh) | 一种岩溶高度发育地层坝基的堵漏排水方法 | |
CN104278679A (zh) | 一种五(六)轴搅拌桩与预制管桩相结合的围护结构及施工方法 | |
CN104153352A (zh) | 一种岩溶地质旋挖灌注桩成孔工艺 | |
CN207062940U (zh) | 一种搅拌桩钻孔机 | |
CN105064336A (zh) | 一种三段式扩底桩的成孔施工方法 | |
CN106592605A (zh) | 一种三轴搅拌桩套打钢筋砼灌注桩基坑围护的施工方法 | |
CN1265062C (zh) | 一种成桩的施工方法及工具 | |
CN109162284A (zh) | 一种海岸滩涂地地下构筑物深基坑支护及其施工方法 | |
CN108867673A (zh) | 一种基于抽水帷幕的基坑中地下水治理方法 | |
CN102409972B (zh) | 多钻头回旋冲砸工程开槽机 | |
CN109183790A (zh) | 一种螺纹桩及其施工工具和施工方法 | |
CN203270642U (zh) | 一种铣槽机掘削搅拌机构 | |
CN104988914A (zh) | 一种水域环境下的钻孔灌注桩断桩处理方法 | |
CN102587353A (zh) | 一种搅拌固化机的搅拌头 | |
CN104674797A (zh) | 一种无挤土的五轴水泥土搅拌桩施工工法 | |
CN104563100A (zh) | 水泥土搅拌桩后植压灌桩支护结构及施工方法 | |
CN107700508A (zh) | 一种型钢搅喷水泥土帷幕支护桩的施工方法 | |
CN110984126B (zh) | 一种易坍地层预加固再成孔灌注桩施工方法 | |
CN104278680A (zh) | 一种五(六)轴搅拌桩与压灌桩相结合的围护结构及施工方法 | |
CN107653889A (zh) | 一种型钢压灌水泥土帷幕支护桩的施工方法 | |
CN104831735B (zh) | 一种桩幕合一的止水支护结构及其施工方法和施工设备 | |
CN205296194U (zh) | 一种富水地层暗挖隧道咬合管幕 | |
CN209162815U (zh) | 一种螺纹桩及其施工工具 | |
CN100485132C (zh) | 桩排式地下防水墙的成型方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20150114 |
|
WD01 | Invention patent application deemed withdrawn after publication |