CN104213894B - Selective repeated fracturing process for old well of oil field - Google Patents

Selective repeated fracturing process for old well of oil field Download PDF

Info

Publication number
CN104213894B
CN104213894B CN201310220061.4A CN201310220061A CN104213894B CN 104213894 B CN104213894 B CN 104213894B CN 201310220061 A CN201310220061 A CN 201310220061A CN 104213894 B CN104213894 B CN 104213894B
Authority
CN
China
Prior art keywords
packer
interval
fracturing
tubing string
complete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310220061.4A
Other languages
Chinese (zh)
Other versions
CN104213894A (en
Inventor
冯飞
付钢旦
桂捷
任勇
冯长青
何华
刘明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Petrochina Co Ltd
Original Assignee
Petrochina Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Petrochina Co Ltd filed Critical Petrochina Co Ltd
Priority to CN201310220061.4A priority Critical patent/CN104213894B/en
Publication of CN104213894A publication Critical patent/CN104213894A/en
Application granted granted Critical
Publication of CN104213894B publication Critical patent/CN104213894B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention discloses a selective repeated fracturing process technology for an old well of an oil field, which is designed for effectively solving the problem of repeated transformation of the old well of the oil field. The technology of the invention adopts the technical steps of assembling, putting in a pipe column, dragging the pipe column to complete the perforation operation of the section to be reformed, setting an upper packer and a middle packer, performing fracturing construction of the newly added section at the bottom, deblocking and dragging the pipe column to the second newly added reformed section for construction. The technology of the invention utilizes hydraulic sand blasting perforation to form large-aperture and deep-penetrating pore canals, can effectively reduce the fracture pressure, and utilizes the advantages of a double-seal single-clamp fracturing process to reduce the requirements on well mouth matching and casing steel grade. The technical pipe column has simple structure, flexible construction method, convenient operation and high efficiency, can effectively solve the problem of repeated reconstruction of the old well of the oil field, can complete repeated fracturing of the reconstructed layer section, and can also perform integrated operation of hole repairing and fracturing of the newly added layer section.

Description

Oilfield old well selectivity refracturing technique
Technical field
The present invention relates to a kind of oilfield old well selectivity refracturing technique, belong to oil gas field pressure Split technical field.
Background technology
Conventional hydraulic sandblasting pressure break is that the hydraulic sand blasting fracturing string dragging band underseal is constructed The multilayer of well or multistage pressure break, the packing of its interval that can only ensure lower floor has been constructed.For For old well, newly-designed transformation interval is likely distributed in the centre transforming interval, by routine Tubing string cannot meet packing top and transform the requirement of interval.Double envelope single deck tape-recorder pressure breaks need first to construction All construction intervals of well carry out conventional perforation, the pressure produced when so easily causing nearly well band pore-forming Real infringement, affects oil well productivity.
Summary of the invention
It is an object of the invention to provide a kind of oilfield old well selectivity refracturing technique, its energy Effectively solve the problem that oilfield old well repeats transformation.
The technology of the present invention construction use process pipe string by oil pipe, safety give up, upper packer, Middle packer, hydraulic ejector, lower packet, ball seat, ball-and-seat, eye pipe and plug composition.
The concrete technology step of the technology of the present invention is as follows:
1) according to repeat transformation needs and the interval of design, assembling, under enter this tubing string;
2) repeatedly drag this tubing string, complete the perforating job of required transformation interval;
3) after all perforations that need to transform interval complete, transfer this tubing string and increase newly to orlop The position of transformation interval, then, delivers steel ball from well head and opens the cunning in controlled upper packer Set, starts upper packer and sets, and and then steel ball continues to move down, and opens controlled middle packer Interior sliding sleeve, packer setting in also starting, last steel ball continues traveling downwardly, and falls in ball seat;
4) after upper packer, middle packer and lower packet set, this tubing string just constitutes The structure of double envelope single deck tape-recorder fracturing technology tubing strings, can directly carry out the pressing crack construction of orlop section;
5), after the pressing crack construction until orlop section completes, fracturing unit truck stops pumping, allows three envelopes Unseal every device, then drag tubing string and increase the position transforming interval to second newly, then restart pressure Split truck pumping, again set three packers, complete the pressing crack construction of the second newly-increased transformation interval;
6) the like, repeat step 5, complete the construction of all newly-increased transformation intervals.
The technology of the present invention utilizes hydraulic jet perforation to form large aperture and deep penetrating duct, can have Effect reduces fracture pressure, utilize double envelope single deck tape-recorder fracturing technology advantage low to well head supporting and casing steel The requirement of level.The technology of the present invention tubular column structure is simple, construction method is flexible, easy to operate and effect Rate is high, can effectively solve oilfield old well and repeat the problem of transformation, can complete to have transformed interval Refracturing, also can carry out perforations adding and the pressure break one operation of newly-increased interval.
Accompanying drawing explanation
Fig. 1 is that oilfield old well has transformed interval schematic diagram.
Fig. 2 is that the technology of the present invention tubing string carries out perforation schematic diagram to newly-increased orlop section.
Fig. 3 is that the technology of the present invention tubing string carries out perforation schematic diagram to newly-increased second interval.
Fig. 4 is that the technology of the present invention tubing string carries out pressure break schematic diagram to newly-increased orlop section.
Fig. 5 is that the technology of the present invention tubing string carries out pressure break schematic diagram to newly-increased second interval.
Detailed description of the invention
Embodiment:
Embodiment referring to figs. 1 through 5 pairs of the technology of the present invention further illustrates:
As a example by the old well of a bite oilfield horizontal well, there are two sections to transform interval, now again to mend Hole and newly-increased transformation interval two sections.The process pipe string that this construction uses is given up by oil pipe 1, safety 2, upper packer 3, middle packer 4, hydraulic ejector 5, lower packet 6, ball seat 7, Ball-and-seat 8, eye pipe 9 and plug 10 form.
The concrete technology step of the technology of the present invention is as follows:
1) according to repeat transformation needs and the interval of design, assembling, under enter this tubing string (see Fig. 2);
2) repeatedly drag this tubing string, complete required transformation interval perforating job (see Fig. 2,3);
3) after all perforations that need to transform interval complete, transfer this tubing string and increase newly to orlop The position A of transformation interval, then, delivers steel ball from well head, opens controlled upper packer 3 Interior sliding sleeve, starts upper packer 3 and sets, and and then steel ball continues to move down, and opens controlled Sliding sleeve in middle packer 4, in also starting, packer 4 sets, and last steel ball continues traveling downwardly, Fall in ball seat 7 (see Fig. 4);
4) after upper packer 3, middle packer 4 and lower packet 6 set, this tubing string is just Constituting the structure of double envelope single deck tape-recorder fracturing technology tubing string, the pressure break that can directly carry out orlop section is executed Work (see Fig. 4);
5), after the pressing crack construction until orlop section completes, fracturing unit truck stops pumping, allows three packings Device unseals, and then drags tubing string and increases transformation interval B newly to second, then restarts fracturing unit truck pump Send, again set three packers, complete the second newly-increased transformation interval B pressing crack construction (see Fig. 5);
6) the like, repeat step 5, complete all constructions that need to transform interval.

Claims (1)

1. an oilfield old well selectivity refracturing technique, it is characterised in that:
Use process pipe string by oil pipe (1), safety give up (2), upper packer (3), in Packer (4), hydraulic ejector (5), lower packet (6), ball seat (7), ball-and-seat (8), Eye pipe (9) and plug (10) composition;
Concrete technology step is as follows:
1) according to repeat transformation needs and the interval of design, assembling, under enter this tubing string;
2) repeatedly drag this tubing string, complete the perforating job of required transformation interval;
3) after all perforations that need to transform interval complete, this tubing string is transferred new to orlop Increase the position (A) of interval, then, deliver steel ball from well head and open controlled upper packer (3) Interior sliding sleeve, starts upper packer (3) and sets, and and then steel ball continues to move down, and opening can Sliding sleeve in the middle packer (4) of control, in also starting, packer (4) sets, last steel ball Continue traveling downwardly, fall in ball seat (7);
4) after upper packer (3), middle packer (4) and lower packet (6) set, this pipe Post just constitutes the structure of double envelope single deck tape-recorder fracturing technology tubing string, can directly carry out orlop new Increase the pressing crack construction of section;
5), after the pressing crack construction until orlop section completes, fracturing unit truck stops pumping, allows three Removing seal for packer, then drags tubing string and increases transformation interval (B) newly to second, then restart Fracturing unit truck pumps, and again sets three packers, completes the second newly-increased transformation interval (B) Pressing crack construction;
6) the like, repeat step 5, complete all constructions that need to transform interval.
CN201310220061.4A 2013-06-05 2013-06-05 Selective repeated fracturing process for old well of oil field Active CN104213894B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310220061.4A CN104213894B (en) 2013-06-05 2013-06-05 Selective repeated fracturing process for old well of oil field

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310220061.4A CN104213894B (en) 2013-06-05 2013-06-05 Selective repeated fracturing process for old well of oil field

Publications (2)

Publication Number Publication Date
CN104213894A CN104213894A (en) 2014-12-17
CN104213894B true CN104213894B (en) 2016-09-07

Family

ID=52095763

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310220061.4A Active CN104213894B (en) 2013-06-05 2013-06-05 Selective repeated fracturing process for old well of oil field

Country Status (1)

Country Link
CN (1) CN104213894B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727798B (en) * 2015-03-30 2017-03-08 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 A kind of low permeability gas reservoir turns to refracturing process
CN110206505A (en) * 2019-05-16 2019-09-06 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 Old well reconstruction method for dragging and fracturing coiled tubing by patching and plugging
CN110284865B (en) * 2019-06-27 2021-09-10 大庆油田有限责任公司 Process method for completing repeated fracturing and energy supplement of compact oil horizontal well at one time
CN112177581B (en) * 2019-07-02 2022-06-03 中国石油天然气股份有限公司 Repeated fracturing method for old well
CN111827934A (en) * 2020-08-04 2020-10-27 中国石油天然气股份有限公司 Method for improving gas injection by using old well bore
CN112324416B (en) * 2020-11-05 2022-08-30 中国石油天然气股份有限公司 Multi-packer process pipe column and method for selective and repeated reconstruction of old well
CN113107418B (en) * 2021-03-25 2023-05-05 中煤科工集团西安研究院有限公司 Segmented pressure-maintaining grouting device and method for horizontal drilling of water-bearing layer of coal seam floor

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7516797B2 (en) * 2004-12-20 2009-04-14 Zinoviy Dmitrievich Khomynets Method for operating a well jet device in the conditions of a formation hydraulic fracturing
CN201513162U (en) * 2009-08-20 2010-06-23 中国石油集团川庆钻探工程有限公司工程技术研究院 Multilayer-section fracturing device of releasing tubular column
CN202250014U (en) * 2011-10-08 2012-05-30 华鼎鸿基石油工程技术(北京)有限公司 Dual-packing single-clamping staged fracturing tool
CN102619494A (en) * 2012-04-16 2012-08-01 江苏如通石油机械股份有限公司 Multi-section sliding sleeve type sand jet perforating and fracturing tool
CN102691495A (en) * 2012-05-18 2012-09-26 中国石油天然气股份有限公司 Staged fracturing method for casing cementing well completion high-fracture stratum horizontal well

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7516797B2 (en) * 2004-12-20 2009-04-14 Zinoviy Dmitrievich Khomynets Method for operating a well jet device in the conditions of a formation hydraulic fracturing
CN201513162U (en) * 2009-08-20 2010-06-23 中国石油集团川庆钻探工程有限公司工程技术研究院 Multilayer-section fracturing device of releasing tubular column
CN202250014U (en) * 2011-10-08 2012-05-30 华鼎鸿基石油工程技术(北京)有限公司 Dual-packing single-clamping staged fracturing tool
CN102619494A (en) * 2012-04-16 2012-08-01 江苏如通石油机械股份有限公司 Multi-section sliding sleeve type sand jet perforating and fracturing tool
CN102691495A (en) * 2012-05-18 2012-09-26 中国石油天然气股份有限公司 Staged fracturing method for casing cementing well completion high-fracture stratum horizontal well

Also Published As

Publication number Publication date
CN104213894A (en) 2014-12-17

Similar Documents

Publication Publication Date Title
CN104213894B (en) Selective repeated fracturing process for old well of oil field
EP3505720A3 (en) Managed pressure cementing
CN202108493U (en) Horizontal well hydraulic jet multi-cluster staged fracturing string
CN104213893B (en) Perforation and fracturing integrated tubular column for selectively and repeatedly reforming old well of oil field and working method thereof
CN203321476U (en) Coiled tubing controllable packer process pipe column for old well repeated reconstruction
RU2014132555A (en) ELEMENTS OF CLEANING CEMENT CELL AND METHODS OF TREATMENT OF THE ENVIRONMENT WELL FOR INTENSIFICATION OF FLOW
CN104213891A (en) Coiled tubing controllable packer process pipe column for old well repeated reconstruction
CN103867177A (en) Horizontal well fracturing method
CN203961938U (en) Packer staged fracturing technology tube pillar in a kind of horizontal well tube
MY187059A (en) Gravel pack service tool with enhanced pressure maintenance
MY192204A (en) A method of plugging and abandoning a well
CN103821489B (en) Horizontal well machinery layering is acidified combination process tubing string with hydraulic jetting fracturing
CN203394492U (en) Coiled tubing perforation and mechanical packing fracturing string
CN102817594B (en) Horizontal well water pumping gas production method and device
CN203626787U (en) Hydraulic jet double-sealing single-clamping perforation and fracturing integrated process pipe column
CN204082116U (en) Oil well horizontal well oil jacket is with note formula two envelope single deck tape-recorder volume fracturing tubing string
CN203394491U (en) Perforation and fracturing integrated tubular column for selectively and repeatedly reforming old well of oil field
CN203978409U (en) Tubing string for back-up sand separate stratum fracfturing technique
CN104632167A (en) Hydraulic jet double-sealing single-clamping perforation and fracturing integrated process pipe column
CN203188991U (en) Sliding sleeve type layering eight-stage fracturing string
CN102182439B (en) Balanced-pressure perforation/negative-pressure backflow process
CN102418508B (en) Using method of water jet packing tool
CN104196512B (en) Oil well horizontal well oil jacket is the same as the double envelope single deck tape-recorder volume fracturing tubing strings of note formula and fracturing process
CN204041042U (en) A kind of coiled tubing drag fracturing tubing string
CN203879478U (en) Hydraulic sand blasting volume fracturing string

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant