CN104201613A - Device for replacing linear single-string insulators by remote operations and application method of device - Google Patents
Device for replacing linear single-string insulators by remote operations and application method of device Download PDFInfo
- Publication number
- CN104201613A CN104201613A CN201410488731.5A CN201410488731A CN104201613A CN 104201613 A CN104201613 A CN 104201613A CN 201410488731 A CN201410488731 A CN 201410488731A CN 104201613 A CN104201613 A CN 104201613A
- Authority
- CN
- China
- Prior art keywords
- pulley
- insulator string
- block
- side bar
- fixed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Electric Cable Installation (AREA)
- Insulators (AREA)
Abstract
本发明公开了一种更换直线单串绝缘子的装置,包括固定架和连接于其下方的滑车,固定架固定于横担上,其杆身端连接有蜗轮蜗杆装置,蜗轮蜗杆装置通过滑轮及绝缘绳带动滑车沿固定架移动,滑车的前端通过滑轮及提升绝缘绳提升至向上倾斜拖住绝缘子串,使其上端与横担的连接载荷转移至滑车的卡板上,绝缘子串下端与导线的连接载荷通过挂钩及滑轮组件转移至固定架上,这样方便快捷的拆卸绝缘子串。本发明还公开了一种利用本装置更换直线绝缘子串的方法,通过杆身作业人员和地面作业人员的相互配合,作业人员均采取地电位间接操作更换绝缘子,使得绝缘子串的更换操作均在杆身端,远离绝缘子串,实现了安全、高效的目的。
The invention discloses a device for replacing linear single-string insulators, which comprises a fixed frame and a pulley connected below it. The fixed frame is fixed on a cross arm, and a worm gear device is connected to the end of the rod body. The worm gear device passes through the pulley and the insulator. The rope drives the trolley to move along the fixed frame, and the front end of the trolley is lifted by the pulley and the hoisting insulating rope to tilt up and drag the insulator string, so that the connection load between the upper end and the cross arm is transferred to the pallet of the trolley, and the connection between the lower end of the insulator string and the wire The load is transferred to the fixed frame through the hook and pulley assembly, so that the insulator string can be disassembled conveniently and quickly. The invention also discloses a method for replacing linear insulator strings by using the device. Through the mutual cooperation of pole operators and ground operators, the operators all use ground potential to indirectly operate and replace insulators, so that the replacement operation of insulator strings can be performed on the pole. body, away from the insulator string, to achieve the purpose of safety and high efficiency.
Description
技术领域 technical field
本发明涉及一种直线单串绝缘子的输电线路,具体涉及一种远端操作更换输电线路上直线单串绝缘子的装置及其应用方法。 The invention relates to a power transmission line of a straight single-string insulator, in particular to a device for remote operation and replacement of a straight single-string insulator on a power transmission line and an application method thereof.
背景技术 Background technique
目前的更换直线单串绝缘子作业,一般是一个作业人员将滑轮组或卡具登杆至导线悬挂点处,另一个作业人员通过平梯或软梯,登至导线,两个作业人员配合安装好工具,转移荷载,更换绝缘子、拆除工具等步骤来完成作业。而现有紧凑型线路、同塔多回输电线路和同塔多回紧凑型线路普遍存在杆塔高、杆塔型式多样、横担间距离和相间净空距离小、导体布置相对复杂等特征,在城市中间的同塔多回输电线路这一特征尤为明显,使之安全距离不能满足带电作业要求,利用现有方法无法开展带电作业。 The current replacement of straight line single-string insulators generally requires one operator to mount the pulley block or fixture to the suspension point of the conductor, and another operator to climb to the conductor through a flat or soft ladder, and the two operators cooperate to install the tool. Transfer loads, replace insulators, remove tools and more to complete the job. However, the existing compact lines, multi-circuit transmission lines on the same tower, and multi-circuit compact lines on the same tower generally have the characteristics of high pole towers, various types of pole towers, small distances between cross-arms and phase-to-phase clearances, and relatively complicated conductor arrangements. This characteristic of the multi-circuit transmission line on the same tower is particularly obvious, so that the safe distance cannot meet the requirements of live work, and the live work cannot be carried out by using the existing methods.
发明内容 Contents of the invention
本发明的目的在于提供一种安全、高效在杆身侧操作更换直线单串绝缘子的装置及利用该装置更换直线单串绝缘子的方法。 The purpose of the present invention is to provide a safe and efficient device for replacing linear single-string insulators on the shaft side and a method for replacing linear single-string insulators using the device.
本发明公开了一种更换直线单串绝缘子的装置,包括固定架和连接于其下方的滑车,固定架的杆身端连接有蜗轮蜗杆装置,蜗轮蜗杆装置带动滑车沿固定架移动。 The invention discloses a device for replacing linear single-string insulators, which comprises a fixed frame and a pulley connected below it. The shaft end of the fixed frame is connected with a worm gear device, and the worm gear device drives the pulley to move along the fixed frame.
所述固定架包括两根平行的边梁和连接于其两端之间的左连接梁和右连接梁;左连接梁位于边梁的杆身端,其上沿长度方向开设有长圆孔,长圆孔内有两根沿竖直方向的调节丝杆穿过,调节丝杆的下端连接有用于夹住横担底边的夹块,调节丝杆通过其上的螺母与左连接梁的顶面和底面定位;右连接梁位于边梁的导线端,其长度方向两端均连接有F型夹具,F型夹具的U型开口夹住右连接梁,其U型开口的对侧上端和下端均外延伸出形成两平行板,上平行板上连接有沿竖直方向的副调节丝杆,其上端通过螺母与该平行板固定、下端连接有夹臂杆,夹臂杆可滑动的穿过下平行板,其末端连接有夹板;边梁为空心环氧玻璃纤维管,其导线端外端面通过支座连接有共轴的双滑轮、其管内的杆身端通过滑轮轴连接有单滑轮,它们的滑槽均沿边梁的宽度方向,管内滑轮对应的管壁上开设有位于其上侧的缺口。 The fixed frame includes two parallel side beams and a left connecting beam and a right connecting beam connected between the two ends; the left connecting beam is located at the shaft end of the side beam, and an oblong hole is opened along the length direction on it, and the oblong There are two vertical adjustment screw rods passing through the hole. The lower end of the adjustment screw rod is connected with a clamp block for clamping the bottom edge of the cross arm. The adjustment screw rod is connected with the top surface of the left connecting beam and the The bottom surface is positioned; the right connecting beam is located at the wire end of the side beam, and both ends of its length direction are connected with F-shaped clamps. Extend to form two parallel plates, the upper parallel plate is connected with a secondary adjustment screw along the vertical direction, the upper end of which is fixed to the parallel plate by a nut, and the lower end is connected with a clamp arm rod, which can slide through the lower parallel plate The end of the plate is connected with a splint; the side beam is a hollow epoxy glass fiber tube, the outer end of the wire end is connected with a coaxial double pulley through the support, and the shaft end of the tube is connected with a single pulley through the pulley shaft. The chute is all along the width direction of the side beam, and the pipe wall corresponding to the pulley in the pipe is provided with a gap located on its upper side. the
所述两F型夹具夹住右连接梁侧的顶面均有连接块,两连接块之间通过横向的主调节螺杆连接为一个整体,连接块上有相应的螺纹孔;所述右连接梁上对应F型夹具的外侧有固定块,主调节螺杆穿过固定块后通过螺母固定。 The two F-type clamps clamp the top surface of the right connecting beam side with a connecting block, and the two connecting blocks are connected as a whole through a horizontal main adjusting screw, and there are corresponding threaded holes on the connecting block; the right connecting beam There is a fixed block on the outside corresponding to the F-shaped fixture, and the main adjusting screw passes through the fixed block and is fixed by a nut.
所述滑车包括矩形卡板、吊杆和滑轮组,吊杆有四根,它们分立于矩形卡板的四个角上,每根吊杆的上端均连接有滑轮组,滑轮组的上、下两个滑轮通过C型架固定,矩形卡板长度方向同侧滑轮组的下滑轮轴之间通过连杆连接为一个整体。 The block includes a rectangular pallet, a boom and a block of pulleys. There are four booms, which are separated from the four corners of the rectangular clip. The upper end of each boom is connected with a block of pulleys. The upper and lower pulleys of the block It is fixed by a C-shaped frame, and the lower pulley shafts of the same-side pulley blocks in the length direction of the rectangular clamping plate are connected as a whole through connecting rods.
所述滑轮组的上、下滑轮分别位于所述边梁的顶面和底面,所述C型架的开口尺寸与边梁的高度尺寸匹配。 The upper and lower pulleys of the pulley block are respectively located on the top surface and the bottom surface of the side beam, and the opening size of the C-shaped frame matches the height dimension of the side beam.
所述蜗轮蜗杆装置的蜗杆两端对应边梁位置处分别连接有单滑轮,蜗杆通过位于单滑轮两侧的连接板与边梁连接。 The two ends of the worm of the worm gear and worm device are respectively connected to single pulleys at positions corresponding to the side beams, and the worm is connected to the side beams through connecting plates located on both sides of the single pulley.
所述蜗杆两端的滑轮分别与相应侧边梁导线端外双滑轮中的一个滑轮之间有同一根滑动绝缘绳绕过,滑动绝缘绳的两端分别固定于所述滑车同侧的内外C型固定架上。 The pulleys at both ends of the worm and one pulley of the outer double pulleys at the corresponding side beam wire ends are respectively bypassed by the same sliding insulating rope. on the stand.
所述边梁内杆身端的单滑轮和该边梁导线端外双滑轮中的另一个滑轮之间有同一根提升绝缘绳绕过,提升绝缘绳的一端固定于所述滑车靠导线侧的吊杆上,另一端依次从边梁导线端外滑轮的上侧和杆身端内单滑轮的下侧绕过后从该处的缺口中导出。 The same lifting insulating rope is bypassed between the single pulley at the inner shaft end of the side beam and the other pulley of the outer double pulley at the wire end of the side beam, and one end of the lifting insulating rope is fixed to the suspension on the wire side of the pulley. On the rod, the other end goes around the upper side of the outer pulley at the side beam wire end and the lower side of the inner single pulley at the shaft end in turn, and then leads out from the gap there.
所述边梁的长度方向外侧对应所述右连接梁处通过支架连接有滑轮,该滑轮的滑槽沿边梁的长度方向,滑轮上连接有绝缘绳,该绝缘绳的下端连接有挂钩。 The outside of the length direction of the side beam corresponds to the right connecting beam and is connected with a pulley by a bracket. The chute of the pulley is along the length direction of the side beam. The pulley is connected with an insulating rope, and the lower end of the insulation rope is connected with a hook.
本发明还公开了一种利用上述装置更换直线单串绝缘子的方法,包括以下步骤: The invention also discloses a method for replacing a linear single-string insulator by using the above-mentioned device, which includes the following steps:
(1)、地面作业人员将本装置的滑车单独组装好、固定架与其它部件及各绝缘绳组装好; (1) The ground operator assembles the pulley of the device separately, and assembles the fixing frame with other components and insulating ropes;
(2)、杆身作业人员将固定架放置于横担上平面的合适位置,使固定架的边梁位于横担的长度方向两侧,通过操纵杆调节固定架导线端两F型夹具之间连接的主调节丝杆及纵向的副调节丝杆,使F型夹具及副调节丝杆下端的夹板夹住该端横担的两侧及底边; (2) The shaft operator places the fixing frame at a suitable position on the upper plane of the cross arm, so that the side beams of the fixing frame are located on both sides of the length direction of the cross arm, and adjust the distance between the two F-shaped clamps at the wire end of the fixing frame through the joystick. Connect the main adjustment screw and the longitudinal auxiliary adjustment screw so that the F-shaped clamp and the splint at the lower end of the auxiliary adjustment screw clamp the two sides and the bottom edge of the cross arm at the end;
(3)、通过操作杆调节固定架杆身端的调节丝杆,使其下端的夹块夹住横担宽度方向底边两侧; (3) Adjust the adjusting screw rod at the end of the fixed frame through the operating rod, so that the clamping block at the lower end clamps both sides of the bottom edge in the width direction of the cross arm;
(4)、将滑车上端的C型架挂接于固定架的边梁上; (4) Hook the C-shaped frame at the upper end of the tackle to the side beam of the fixed frame;
(5)、通过操纵杆将提升绝缘绳的下端固定于滑车近导线端的吊杆上、滑动绝缘绳的两端分别固定于滑车上端同一侧的C型架上; (5) Fix the lower end of the hoisting insulating rope on the boom near the wire end of the tackle through the joystick, and fix the two ends of the sliding insulating rope on the C-frame on the same side of the upper end of the tackle respectively;
(6)、通过操纵杆将固定架导线端的两挂钩分别钩住导线,同时收紧绝缘绳使导线荷载转移至固定架上,通过操纵杆将绝缘子串下端的W销和碗头挂板; (6) Use the joystick to hook the two hooks at the wire end of the fixed frame to the wire respectively, and at the same time tighten the insulating rope to transfer the load of the wire to the fixed frame, and use the joystick to hang the W pin and the bowl head at the lower end of the insulator string;
(7)、启动蜗轮蜗杆装置通过滑动绝缘绳带动滑车靠近绝缘子串; (7) Start the worm gear device to drive the pulley close to the insulator string by sliding the insulating rope;
(8)、地面作业人员将提升绝缘绳收紧,使滑车的U型卡板卡在第二片和第三片绝缘子之间,并将绝缘子串向上提起; (8) The ground operator tightens the hoisting insulating rope so that the U-shaped clamping plate of the tackle is stuck between the second and third insulators, and lifts the insulator string upwards;
(9)、杆身作业人员通过操纵杆拔出绝缘子串上端的W销和球头; (9) The shaft operator pulls out the W pin and the ball head at the upper end of the insulator string through the joystick;
(10)、地面作业人员防松提升绝缘绳,使滑车的U型卡板回位; (10) The ground operator should prevent loosening and lift the insulating rope, so that the U-shaped clamping plate of the tackle can be returned to its position;
(11)、杆身作业人员启动蜗轮蜗杆装置,牵引滑车拖着绝缘子串移动至杆身侧; (11) The shaft operator starts the worm gear device, and the traction block drags the insulator string to move to the side of the shaft;
(12)、通过悬挂在杆塔上的无极绳将绝缘子串取下移至地面; (12) Remove the insulator string and move it to the ground through the endless rope suspended on the tower;
(13)、将新的绝缘子串通过滑车运至合适位置安装。 (13). Transport the new insulator string to a suitable location for installation by means of a pulley.
本发明公开的装置工作原理如下:将固定架置于杆身横担上,使边梁位于横担的两侧,杆身端通过调节丝杆及其下端的夹块与横担固定,导线端通过F型夹具、调节螺杆及丝杆和夹板组件与横担固定。蜗轮蜗杆装置通过绝缘绳及滑轮带动滑车沿边梁移动。通过提升从边梁杆身端内滑轮处导出的绝缘绳使滑车的外端往上倾斜。通过边梁导线端外侧的滑轮及绝缘绳和挂钩将导线提升,使绝缘子串上的载荷转移。 The working principle of the device disclosed in the present invention is as follows: the fixing frame is placed on the cross arm of the shaft, so that the side beams are located on both sides of the cross arm, the end of the shaft is fixed with the cross arm by adjusting the screw rod and the clamp block at the lower end, and the end of the wire is fixed to the cross arm. It is fixed with the cross arm through F-shaped clamps, adjusting screw rods, screw rods and splint components. The worm gear device drives the pulley to move along the side beam through the insulating rope and the pulley. The outer end of the block is tilted upward by lifting the insulating rope leading from the inner pulley at the shaft end of the side beam. The wire is lifted by the pulley outside the wire end of the side beam, the insulating rope and the hook, so that the load on the insulator string is transferred.
本发明公开的利用该装置更换直线单串绝缘子的方法,通过杆身作业人员和地面作业人员的相互配合,作业人员均采取地电位间接操作更换绝缘子,使得绝缘子串的更换操作均在杆身端,远离绝缘子串,实现了安全、高效的目的。 In the method disclosed by the present invention for replacing a straight line single string of insulators, through the mutual cooperation of shaft operators and ground operators, the operators all adopt ground potential indirect operations to replace insulators, so that the replacement operation of the insulator strings is all at the shaft end. , away from the insulator string, to achieve the purpose of safety and high efficiency.
附图说明 Description of drawings
图1为本发明的结构示意图。 Fig. 1 is a structural schematic diagram of the present invention.
图2为图1的俯视示意图。 FIG. 2 is a schematic top view of FIG. 1 .
图3为图1中的滑轮组结构示意图。 Fig. 3 is a schematic structural diagram of the pulley block in Fig. 1 .
图4为图1中的F型夹具结构示意图。 FIG. 4 is a schematic structural diagram of the F-type fixture in FIG. 1 .
具体实施方式 Detailed ways
如图所示,本发明公开了一种更换直线单串绝缘子的装置,包括水平的固定架10和连接于其下方的滑车20,固定架10的杆身端连接有蜗轮蜗杆装置30,蜗轮蜗杆装置30带动滑车20沿固定架10移动。 As shown in the figure, the present invention discloses a device for replacing linear single-string insulators, which includes a horizontal fixed frame 10 and a trolley 20 connected below it. The shaft end of the fixed frame 10 is connected with a worm gear device 30. The device 30 drives the trolley 20 to move along the fixed frame 10 .
固定架10包括两根平行的边梁11和连接于其两端的左连接梁12和右连接梁13。 The fixed frame 10 includes two parallel side beams 11 and a left connecting beam 12 and a right connecting beam 13 connected to two ends thereof.
左连接梁12位于边梁11的杆身端,其上沿长度方向开设有长圆孔,长圆孔内有两根沿竖直方向的调节丝杆14穿过,调节丝杆14的下端连接有用于夹住横担底边的夹块15,调节丝杆14通过其上的螺母与左连接梁12的顶面和底面定位。 The left connecting beam 12 is positioned at the shaft end of the side beam 11, and is provided with an oblong hole along the length direction on it, and two adjusting screw rods 14 along the vertical direction are passed through in the oblong hole, and the lower end of the adjusting screw rod 14 is connected with a Clamp the clamp block 15 on the bottom edge of the cross arm, and adjust the screw mandrel 14 to be positioned with the top surface and the bottom surface of the left connecting beam 12 through the nut on it.
右连接梁13位于边梁11的导线端,其长度方向两端均连接有F型夹具16,F型夹具16的U型开口夹住右连接梁13,其U型开口的对侧上端和下端均外延伸出形成两平行板,上平行板上连接有沿竖直方向的副调节丝杆161,副调节丝杆161的上端通过螺母与该平行板固定、下端连接有夹臂杆162,夹臂杆162可滑动的穿过下平行板,其末端连接有夹板163。 The right connecting beam 13 is located at the wire end of the side beam 11, and both ends of its length direction are connected with F-shaped clamps 16. The U-shaped opening of the F-shaped clamp 16 clamps the right connecting beam 13, and the opposite upper and lower ends of the U-shaped opening Both extend outward to form two parallel plates, the upper parallel plate is connected with a secondary adjustment screw 161 along the vertical direction, the upper end of the auxiliary adjustment screw 161 is fixed with the parallel plate by a nut, and the lower end is connected with a clamping arm rod 162, clamping The arm bar 162 is slidably passed through the lower parallel plate, and the clamping plate 163 is connected to its end.
两F型夹具16夹住右连接梁13侧的顶面均有连接块164,两连接块164之间通过水平的主调节螺杆19连接为一个整体,连接块164上有相应的螺纹孔。右连接梁13上对应F型夹具16的外侧有固定块131,主调节螺杆19穿过固定块131后通过螺母固定。 Two F-type clamps 16 clamp the top surface of the right connecting beam 13 side and all have connecting block 164, are connected as a whole by horizontal main adjustment screw rod 19 between two connecting blocks 164, and corresponding screw holes are arranged on connecting block 164. There is a fixed block 131 on the outside of the corresponding F-shaped clamp 16 on the right connecting beam 13, and the main adjusting screw rod 19 passes through the fixed block 131 and is fixed by a nut.
边梁11为空心管,其导线端外端面通过支座连接有共轴的双滑轮17、其管内的杆身端通过滑轮轴连接有单滑轮18,它们的滑槽均沿边梁的宽度方向,管内单滑轮18对应的管壁上开设有位于其上侧的缺口。 The side beam 11 is a hollow tube, the outer end surface of the wire end is connected with a coaxial double pulley 17 through the support, and the shaft end in the tube is connected with a single pulley 18 through the pulley shaft, and their chutes are all along the width direction of the side beam. The pipe wall corresponding to the single pulley 18 in the pipe is provided with a gap located on its upper side. the
滑车20包括矩形卡板21、吊杆22和滑轮组23,吊杆22有四根,它们分立于矩形卡板21的四个角上,每根吊杆22的上端均连接有滑轮组23,滑轮组23的上、下两个滑轮通过C型架24固定,矩形卡板21长度方向同侧滑轮组23的下滑轮轴之间通过连杆25连接为一个整体。 Tackle 20 comprises rectangular clamp 21, suspender 22 and block pulley 23, and suspender 22 has four, and they are separated on four angles of rectangular clamp 21, and the upper end of every suspender 22 is all connected with pulley block 23, and pulley block 23 The upper and lower pulleys are fixed by the C-shaped frame 24, and the lower pulley shaft of the same side pulley block 23 in the rectangular clamping plate 21 length direction is connected as a whole by a connecting rod 25.
滑轮组23的上、下滑轮分别位于边梁11的顶面和底面,C型架24的开口尺寸与边梁11的高度尺寸匹配。 The upper and lower pulleys of the pulley block 23 are located on the top surface and the bottom surface of the side beam 11 respectively, and the opening size of the C-shaped frame 24 matches the height dimension of the side beam 11 .
蜗轮蜗杆装置3的蜗杆31两端对应边梁11位置处分别连接有单滑轮18,蜗杆31通过位于单滑轮18两侧的连接板与边梁11连接。 The two ends of the worm 31 of the worm gear device 3 are respectively connected with a single pulley 18 at the positions corresponding to the side beam 11 , and the worm 31 is connected with the side beam 11 through connecting plates located on both sides of the single pulley 18 .
蜗杆31两端的单滑轮18分别与相应侧边梁11导线端外双滑轮17中的一个滑轮之间有同一根滑动绝缘绳50绕过,其两端分别固定于滑车20同侧的内、外C型架24上。边梁11内杆身端的单滑轮18和该边梁11导线端外双滑轮17中的另一个滑轮之间有同一根提升绝缘绳60绕过,其一端固定于滑车2靠导线侧的吊杆22上、另一端依次从边梁11导线端外滑轮的上侧和杆身端内滑轮的下侧绕过后从该处的缺口中导出。 The single pulley 18 at the two ends of the worm 31 and one pulley in the outer double pulley 17 at the lead end of the corresponding side beam 11 have the same sliding insulating rope 50 to go around, and its two ends are respectively fixed on the inner and outer pulleys on the same side of the pulley 20. On the C-frame 24. The same lifting insulating rope 60 is passed between the single pulley 18 at the inner shaft end of the side beam 11 and the other pulley in the outer double pulley 17 at the wire end of the side beam 11, and one end of it is fixed on the suspension rod on the wire side of the pulley 2 On 22, the other end is derived from the gap at this place after going around the upper side of the outer pulley of the side beam 11 lead end and the lower side of the shaft end inner pulley successively.
边梁11的长度方向外侧对应右连接梁13处通过支架连接有滑轮40,该滑轮的滑槽沿边梁的长度方向,滑轮40上连接有绝缘吊绳70,其下端连接有挂钩80。 The length direction outside of side beam 11 is connected with pulley 40 by bracket corresponding to right connecting beam 13 places, and the chute of this pulley is along the length direction of side beam, and pulley 40 is connected with insulating suspension rope 70, and its lower end is connected with hook 80.
本发明公开的装置工作原理如下:将固定架置于杆身横担上,使边梁位于横担的两侧,杆身端通过调节丝杆及其下端的夹块与横担固定,导线端通过F型夹具、调节螺杆及丝杆和夹板组件与横担固定。蜗轮蜗杆装置通过绝缘绳及滑轮带动滑车沿边梁移动。通过提升从边梁杆身端内滑轮处导出的绝缘绳使滑车的外端往上倾斜。通过边梁导线端外侧的滑轮及绝缘绳和挂钩将导线提升,使绝缘子串上的载荷转移。 The working principle of the device disclosed in the present invention is as follows: the fixing frame is placed on the cross arm of the shaft, so that the side beams are located on both sides of the cross arm, the end of the shaft is fixed with the cross arm by adjusting the screw rod and the clamp block at the lower end, and the end of the wire is fixed to the cross arm. It is fixed with the cross arm through F-shaped clamps, adjusting screw rods, screw rods and splint components. The worm gear device drives the pulley to move along the side beam through the insulating rope and the pulley. The outer end of the block is tilted upward by lifting the insulating rope leading from the inner pulley at the shaft end of the side beam. The wire is lifted by the pulley outside the wire end of the side beam, the insulating rope and the hook, so that the load on the insulator string is transferred.
本发明还公开了一种本发明还公开了一种利用上述装置更换直线单串绝缘子的方法,包括以下步骤: The invention also discloses a method for replacing a linear single-string insulator by using the above-mentioned device, which includes the following steps:
(1)、地面作业人员将本装置的滑车20单独组装好、固定架10与其它部件及各绝缘绳组装好; (1) The ground operator assembles the tackle 20 of the device separately, and assembles the fixing frame 10 with other components and insulating ropes;
(2)、杆身作业人员将固定架10放置于横担上平面的合适位置,使固定架10的边梁11位于横担的长度方向两侧,通过操纵杆调节固定架11导线端两F型夹具16之间连接的主调节丝杆19及纵向的副调节丝杆161,使F型夹具16及副调节丝杆16下端的夹板163夹住该端横担的两侧及底边; (2) Shaft operators place the fixed frame 10 at a suitable position on the upper plane of the cross arm, so that the side beams 11 of the fixed frame 10 are located on both sides of the length direction of the cross arm, and adjust the two ends of the wire ends of the fixed frame 11 through the joystick. The main adjusting screw mandrel 19 and the longitudinal auxiliary adjusting screw mandrel 161 connected between the type clamps 16 make the clamping plate 163 at the lower end of the F-type clamps 16 and the auxiliary adjusting screw mandrel 16 clamp the both sides and the bottom edge of the end cross arm;
(3)、通过操作杆调节固定架10杆身端的调节丝杆14,使其下端的夹块15夹住横担宽度方向底边两侧; (3) Adjust the adjusting screw rod 14 at the shaft end of the fixed frame 10 through the operating rod, so that the clamping block 15 at the lower end clamps both sides of the bottom edge in the width direction of the cross arm;
(4)、将滑车2上端的C型架24挂接于固定架10的边梁11上; (4), hook the C-shaped frame 24 at the upper end of the tackle 2 to the side beam 11 of the fixed frame 10;
(5)、通过操纵杆将提升绝缘绳60的下端固定于滑车2近导线端的吊杆22上、滑动绝缘绳50的两端分别固定于滑车2上端同一侧的C型架24上; (5), fix the lower end of the hoisting insulating rope 60 on the boom 22 near the lead end of the tackle 2 through the operating lever, and fix the two ends of the sliding insulating rope 50 on the C-frame 24 on the same side of the upper end of the tackle 2 respectively;
(6)、通过操纵杆将固定架10导线端的两挂钩80分别钩住导线,同时收紧绝缘绳70使导线荷载转移至固定架10上,通过操纵杆将绝缘子串下端的W销和碗头挂板; (6) Use the joystick to hook the two hooks 80 at the wire end of the fixed frame 10 to the wires respectively, and at the same time tighten the insulating rope 70 to transfer the load of the wire to the fixed frame 10, and use the joystick to connect the W pin and the bowl head at the lower end of the insulator string hanging board;
(7)、启动蜗轮蜗杆装置30通过滑动绝缘绳50带动滑车2靠近绝缘子串; (7), start the worm gear device 30 to drive the pulley 2 close to the insulator string by sliding the insulating rope 50;
(8)、地面作业人员将提升绝缘绳60收紧,使滑车20的U型卡板21卡在第二片和第三片绝缘子之间,并将绝缘子串向上提起; (8) The ground operator tightens the lifting insulation rope 60, so that the U-shaped clamping plate 21 of the tackle 20 is stuck between the second and third insulators, and lifts the insulator string upwards;
(9)、杆身作业人员通过操纵杆拔出绝缘子串上端的W销和球头; (9) The shaft operator pulls out the W pin and the ball head at the upper end of the insulator string through the joystick;
(10)、地面作业人员防松提升绝缘绳60,使滑车20的U型卡板21回位; (10), the ground operator lifts the insulating rope 60 against loosening, so that the U-shaped clamping plate 21 of the tackle 20 returns to its position;
(11)、杆身作业人员启动蜗轮蜗杆装置30,牵引滑车20拖着绝缘子串移动至杆身侧; (11), the shaft operator starts the worm gear device 30, and the traction block 20 drags the insulator string to move to the side of the shaft;
(12)、通过悬挂在杆塔上的无极绳将绝缘子串取下移至地面; (12) Remove the insulator string and move it to the ground through the endless rope suspended on the tower;
(13)、将新的绝缘子串通过滑车2运至合适位置安装。 (13). Transport the new insulator string to a suitable location for installation via the trolley 2.
作业人员均采取地电位间接操作更换绝缘子串,且操作均在横担的杆身侧进行,具有安全和高效的优势。 Operators use ground potential indirect operations to replace insulator strings, and the operations are all carried out on the side of the pole of the cross arm, which has the advantages of safety and efficiency.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410488731.5A CN104201613B (en) | 2014-09-23 | 2014-09-23 | Far-end operation changes device and the application process thereof of straight line list insulator string |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410488731.5A CN104201613B (en) | 2014-09-23 | 2014-09-23 | Far-end operation changes device and the application process thereof of straight line list insulator string |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN104201613A true CN104201613A (en) | 2014-12-10 |
| CN104201613B CN104201613B (en) | 2016-03-16 |
Family
ID=52086866
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201410488731.5A Active CN104201613B (en) | 2014-09-23 | 2014-09-23 | Far-end operation changes device and the application process thereof of straight line list insulator string |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104201613B (en) |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107069562A (en) * | 2017-06-28 | 2017-08-18 | 云南电网有限责任公司曲靖供电局 | Replacing insulator under electrified method and load transfer device |
| CN107086495A (en) * | 2017-06-28 | 2017-08-22 | 云南电网有限责任公司曲靖供电局 | Load transfer instrument and electric power maintenance equipment |
| CN107086499A (en) * | 2017-06-28 | 2017-08-22 | 云南电网有限责任公司曲靖供电局 | Conductor load transfer tool and replacing insulator string device |
| CN107147034A (en) * | 2017-05-12 | 2017-09-08 | 国家电网公司 | Tension-resistant rod insulator replacement device |
| CN107769088A (en) * | 2017-11-16 | 2018-03-06 | 常州机电职业技术学院 | A power supply pole wire lifter |
| CN108436430A (en) * | 2018-05-02 | 2018-08-24 | 国家电网公司 | A kind of special dress pin device of M pins based on from fly block |
| CN109038365A (en) * | 2018-08-10 | 2018-12-18 | 国网四川省电力公司检修公司 | Charged for replacement 500kV linear insulator chain load tackling system |
| CN115274230A (en) * | 2022-07-20 | 2022-11-01 | 国网安徽省电力有限公司宿州供电公司 | Suspension insulator assisted mounting device and mounting method thereof |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU694925A1 (en) * | 1978-06-12 | 1979-10-30 | Главное Управление Энергетики И Электрификации При Совете Министров Молдавской Сср "Молдглавэнерго" | Device for replacing insulators of overhead high-voltage power transmission lines |
| CN102142661A (en) * | 2010-01-28 | 2011-08-03 | 上海东捷电力高压带电作业有限公司 | Method for replacing 35 kV linear insulator for ground potential |
| US8782885B2 (en) * | 2011-12-19 | 2014-07-22 | Haverfield International Incorporated | Method for replacing an electrical supension insulator on a tower |
| CN204144792U (en) * | 2014-09-23 | 2015-02-04 | 国家电网公司 | Far-end operation changes the device of straight line list insulator string |
-
2014
- 2014-09-23 CN CN201410488731.5A patent/CN104201613B/en active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU694925A1 (en) * | 1978-06-12 | 1979-10-30 | Главное Управление Энергетики И Электрификации При Совете Министров Молдавской Сср "Молдглавэнерго" | Device for replacing insulators of overhead high-voltage power transmission lines |
| CN102142661A (en) * | 2010-01-28 | 2011-08-03 | 上海东捷电力高压带电作业有限公司 | Method for replacing 35 kV linear insulator for ground potential |
| US8782885B2 (en) * | 2011-12-19 | 2014-07-22 | Haverfield International Incorporated | Method for replacing an electrical supension insulator on a tower |
| CN204144792U (en) * | 2014-09-23 | 2015-02-04 | 国家电网公司 | Far-end operation changes the device of straight line list insulator string |
Cited By (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107147034A (en) * | 2017-05-12 | 2017-09-08 | 国家电网公司 | Tension-resistant rod insulator replacement device |
| CN107069562A (en) * | 2017-06-28 | 2017-08-18 | 云南电网有限责任公司曲靖供电局 | Replacing insulator under electrified method and load transfer device |
| CN107086495A (en) * | 2017-06-28 | 2017-08-22 | 云南电网有限责任公司曲靖供电局 | Load transfer instrument and electric power maintenance equipment |
| CN107086499A (en) * | 2017-06-28 | 2017-08-22 | 云南电网有限责任公司曲靖供电局 | Conductor load transfer tool and replacing insulator string device |
| CN107086499B (en) * | 2017-06-28 | 2019-03-08 | 云南电网有限责任公司曲靖供电局 | Conductor load transfer tool and replacing insulator string device |
| CN107086495B (en) * | 2017-06-28 | 2019-05-31 | 云南电网有限责任公司曲靖供电局 | Load transfer tool and electric power maintenance equipment |
| CN107769088A (en) * | 2017-11-16 | 2018-03-06 | 常州机电职业技术学院 | A power supply pole wire lifter |
| CN108436430A (en) * | 2018-05-02 | 2018-08-24 | 国家电网公司 | A kind of special dress pin device of M pins based on from fly block |
| CN108436430B (en) * | 2018-05-02 | 2020-01-07 | 国家电网公司 | A special pin loader for M pins based on automatic pulley |
| CN109038365A (en) * | 2018-08-10 | 2018-12-18 | 国网四川省电力公司检修公司 | Charged for replacement 500kV linear insulator chain load tackling system |
| CN109038365B (en) * | 2018-08-10 | 2019-12-31 | 国网四川省电力公司检修公司 | Lifting system for live replacement of 500kV linear insulator string load |
| CN115274230A (en) * | 2022-07-20 | 2022-11-01 | 国网安徽省电力有限公司宿州供电公司 | Suspension insulator assisted mounting device and mounting method thereof |
Also Published As
| Publication number | Publication date |
|---|---|
| CN104201613B (en) | 2016-03-16 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104201613B (en) | Far-end operation changes device and the application process thereof of straight line list insulator string | |
| CN104167687B (en) | Tool for live-line replacement of suspension insulator and using working method thereof | |
| CN102882153B (en) | Phase replacing insulator string method in charged for replacement circuit many times towers | |
| CN102231492B (en) | Hanging insulator string cross-arm side fittings replacement jig | |
| CN103944107A (en) | Tool for electrified replacement of 500kV strain insulator string | |
| CN103715633A (en) | Clamping device and method for replacing single-hole connecting plate strain insulator string | |
| CN102237654B (en) | Method for replacing jumper string using tool at double angle hanging point | |
| CN104022459A (en) | 10 KV distribution line pole-mounted wire suspension device | |
| CN106129902A (en) | A kind of overhead ground wire lifting device | |
| CN204144792U (en) | Far-end operation changes the device of straight line list insulator string | |
| CN108551009A (en) | A kind of ground wire suspension arrangement | |
| CN104967047B (en) | The special flexible hard ladder of ± 800kV UHVDC Transmission Lines anchor supports and its application method | |
| CN203289011U (en) | Tension cross arm hoisting device | |
| CN105375389B (en) | Wire fixing device | |
| CN202363811U (en) | Cross arm clamping device for replacing insulator of direct-current 500kv straight-line string | |
| CN204349336U (en) | Overhead-groundwire lifter | |
| CN204205395U (en) | Cross-arm bracket | |
| CN102916372A (en) | Wire lifting tool for intermediate phase conductor of 10kV same-pole multi-circuit line | |
| CN205123134U (en) | Lead wire fixing device | |
| CN206442059U (en) | A kind of insulated gin | |
| CN103138204A (en) | Multifunctional installing rack used for replacing tension cross arm | |
| CN104134948A (en) | 500kV overhead line tangent tower lightning conductor lifting working device | |
| CN105398991B (en) | Capacitor lifts utensil | |
| CN203895853U (en) | Multifunctional length-adjustable insulator cradle | |
| CN205275098U (en) | Condenser hoist and mount utensil |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C53 | Correction of patent of invention or patent application | ||
| CB03 | Change of inventor or designer information |
Inventor after: Zou Dehua Inventor after: Xia Zengming Inventor after: Liu Xiaqing Inventor after: Niu Jie Inventor after: Zhou Guandong Inventor after: Liu Tuocheng Inventor after: Wang Zhigang Inventor after: Yang Miao Inventor after: Zhang Jianjun Inventor after: Li Hui Inventor before: Liu Xiaqing Inventor before: Zou Dehua Inventor before: Niu Jie Inventor before: Liu Tuocheng Inventor before: Zhang Jianjun Inventor before: Wu Liuxin Inventor before: Li Hui Inventor before: Lei Dongyun |
|
| COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: LIU XIAQING ZOU DEHUA NIU JIE LIU TUOSHENG ZHANG JIANJUN WU LIUXIN LI HUI LEI DONGYUN TO: ZOU DEHUA LIU XIAQING NIU JIE ZHOU GUANDONG LIU TUOSHENG WANG ZHIGANG YANG MIAO ZHANG JIANJUN LI HUI XIA ZENGMING |
|
| CB03 | Change of inventor or designer information |
Inventor after: Xia Zengming Inventor after: Li Hui Inventor after: Zou Dehua Inventor after: Liu Xiaqing Inventor after: Niu Jie Inventor after: Zhou Guandong Inventor after: Liu Tuocheng Inventor after: Wang Zhigang Inventor after: Zhang Jianjun Inventor after: Chen Long Inventor before: Zou Dehua Inventor before: Xia Zengming Inventor before: Liu Xiaqing Inventor before: Niu Jie Inventor before: Zhou Guandong Inventor before: Liu Tuocheng Inventor before: Wang Zhigang Inventor before: Yang Miao Inventor before: Zhang Jianjun Inventor before: Li Hui |
|
| COR | Change of bibliographic data | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |