CN104179256A - Rectangular concrete filled steel tube column and steel beam single-side bolt connecting joint and construction method thereof - Google Patents

Rectangular concrete filled steel tube column and steel beam single-side bolt connecting joint and construction method thereof Download PDF

Info

Publication number
CN104179256A
CN104179256A CN201410468001.9A CN201410468001A CN104179256A CN 104179256 A CN104179256 A CN 104179256A CN 201410468001 A CN201410468001 A CN 201410468001A CN 104179256 A CN104179256 A CN 104179256A
Authority
CN
China
Prior art keywords
steel
steel pipe
end plate
pipe column
monolateral
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410468001.9A
Other languages
Chinese (zh)
Inventor
王志滨
李德山
陶忠
韩林海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou University
Original Assignee
Fuzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou University filed Critical Fuzhou University
Priority to CN201410468001.9A priority Critical patent/CN104179256A/en
Publication of CN104179256A publication Critical patent/CN104179256A/en
Pending legal-status Critical Current

Links

Abstract

The invention relates to a rectangular concrete filled steel tube column and steel beam single-side bolt connecting joint and a construction method of the rectangular concrete filled steel tube column and steel beam single-side bolt connecting joint. The connecting joint comprises a rectangular steel tube column and a steel beam, an end plate is welded to the end of the steel beam and fixedly installed on the side wall of the steel tube column through fasteners, and multiple corresponding bolt holes are longitudinally formed in the end plate and the steel beam in a pairwise mode. A reinforcement structure is arranged in the joint core region of the steel tube column. Compared with the prior art, the novel connecting joint has the advantages that the bearing capacity is high, the plasticity and ductility are good, the energy-dissipation capacity is high, and the mechanical property is reliable; compared with a rigid joint where an outer reinforcement ring is adopted, the concrete filled steel tube column and steel beam single-side bolt connecting joint does not need to be welded on site, all the machining processes, except for concrete pouring, are finished in a factory, and therefore machining quality is more reliable; the concrete filled steel tube column and steel beam single-side bolt connecting joint is convenient to install on site and high in construction speed.

Description

The monolateral bolt connection node of rectangular steel-tube concrete column and girder steel and construction method thereof
Technical field
The present invention relates to the frame joint in a class building structure, be specifically related to the monolateral bolt connection node of a kind of rectangular steel-tube concrete column and girder steel and construction method thereof.
Background technology
Strengthening ring type rigid joint is a kind of joint form being most widely used in steel pipe concrete column-steel beam node, this category node has that bearing capacity is high, rigidity is large, the succinct advantage such as clearly of Path of Force Transfer, but the Site Welding workload of this category node is large, weldquality is difficult for guaranteeing, so steel pipe concrete column-steel beam structures with semi-rigid joints with bolts is just causing more and more researchers and engineer's concern.And steel pipe is closed cross-section, plain bolt is difficult to directly apply in tubular structure, and this causes the form of steel pipe concrete column-steel beam structures with semi-rigid joints with bolts less.The appearance of monolateral bolt fastener, can overcome the above problems well, and such bolt has the advantages such as monolaterally tighten, easy construction, stress performance are reliable.But easily there is cripling under the effect of the rectangular steel pipe tube wall point load outside face being directly connected with monolateral bolt, destroy, therefore adopt bearing capacity, rigidity, ductility and the energy dissipation capacity of monolateral bolted steel pipe concrete column-steel beam node all poor.Therefore be necessary to take certain construction measure to improve near the local stability of the rectangular steel pipe tube wall of bolt join domain, thereby improve the mechanical property of this category node, promote applying of this category node.
Summary of the invention
The object of the invention is the defect existing for the monolateral bolted steel pipe concrete column-steel beam node of existing employing, provide that a kind of bearing capacity is high, succinct clear and definite, the simple structure of power transmission, construct rectangular steel-tube concrete column and the monolateral bolt connection node of girder steel and construction method thereof quickly and easily.
The scheme that technical solution problem of the present invention adopts is, the monolateral bolt connection node of a kind of rectangular steel-tube concrete column and girder steel, comprise rectangle steel tubing string and girder steel, described girder steel end is welded with end plate, described end plate is mounted on steel pipe column sidewall by securing member, described end plate with on steel pipe column, longitudinally offer in pairs some corresponding bolts hole, described steel tubular column joints core space is provided with and adds competent structure.
Further, described securing member is monolateral bolt.
Further, described reinforcement is configured to any one in binding bar, external reinforcing plate for car or built-in short H shaped steel.
Further, described external reinforcing plate for car is comprised of two blocks of channel-section steels, described built-in short its breadth of section of H shaped steel and be highly all slightly less than steel pipe column cross section inside wall width and height, its length is slightly larger than girder steel depth of section.
Further, described channel-section steel web place offers some bolts hole that match with girder steel and end plate in pairs.
Further, described steel pipe column section form is rectangle cold-bent pipe or rectangle straight seam welded steel pipe.
A construction method for steel core concrete column and the monolateral bolt connection node of girder steel, comprises the following steps:
(1) by girder steel and end plate firm welding;
(2) in rectangle steel tubing string joint cores, arrange and add competent structure, when strengthening being configured to external reinforcing plate for car, first adopt weld all around to be reliably connected two blocks of channel-section steels and steel pipe column, then in steel pipe column, stiffener and end plate corresponding position, offer bolt hole, for monolateral bolt is installed; When strengthening being configured to built-in short H shaped steel, first short H shaped steel is filled in to joint core place, and with the spot welding of steel pipe column inwall, then in steel pipe column, built-in short H shaped steel and end plate corresponding position, offer bolt hole, for monolateral bolt is installed; When strengthening being configured to binding bar, first on steel pipe column, offer plug welding hole, binding bar is reliably connected with steel pipe column both sides tube wall by plug welding hole at tapping, then at steel pipe column and end plate corresponding position, offers bolt hole, for monolateral bolt is installed;
(3) by the steel beam lifting that has welded end plate to assigned address, use torque wrench to tighten monolateral bolt, steel pipe column is reliably connected with end plate;
(4) concreting in steel pipe column, completes node construction.
Compared with prior art, the present invention has following beneficial effect: such novel joint bearing capacity is high, plasticity ductility is good, energy dissipation capacity is high, mechanical property is reliable; Compare with adopting the rigid joint of outer annular-stiffer, the monolateral bolt connection node of such steel core concrete column and girder steel does not need Site Welding, and manufacturing procedure Jun factories all except concreting complete, so crudy is more reliable; The monolateral bolt connection node of such steel core concrete column and girder steel, has advantages of that scene is easy for installation, speed of application is fast, is conducive to realize engineering construction standardization and produces, remarkable in economical benefits.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, patent of the present invention is further illustrated.
Fig. 1 adds competent structure to adopt external reinforcing plate for car to implement structural representation;
Fig. 2 is the A-A cross-sectional view of Fig. 1;
Fig. 3 adds competent structure to adopt built-in short H shaped steel to implement structural representation;
Fig. 4 is the B-B cross-sectional view of Fig. 3;
Fig. 5 adds competent structure to adopt binding bar to implement structural representation;
Fig. 6 is the C-C cross-sectional view of Fig. 5;
Number in the figure, 1-steel pipe column; 2-concrete; 3-end plate; 4-girder steel; The monolateral bolt of 5-; 6-external reinforcing plate for car; The built-in short H shaped steel of 7-; 8-binding bar.
The specific embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is further described.
As shown in Fig. 1~6, the monolateral bolt connection node of a kind of rectangular steel-tube concrete column and girder steel, comprise rectangle steel tubing string 1 and girder steel 4, described girder steel 4 ends are welded with end plate 3, described end plate 3 is mounted on steel pipe column 1 sidewall by securing member, described end plate 3 with on steel pipe column 1, longitudinally offer in pairs some corresponding bolts hole, described steel pipe column 1 joint cores is provided with and adds competent structure.
In the present embodiment, described securing member is monolateral bolt 5.
In the present embodiment, described reinforcement is configured to any one in external reinforcing plate for car 6, built-in short H shaped steel 7 or binding bar 8.
In the present embodiment, described external reinforcing plate for car 6 is comprised of two blocks of channel-section steels, described built-in short H shaped steel 7 its breadth of section and be highly all slightly less than steel pipe column 1 cross section inside wall width and height, its length is slightly larger than girder steel 4 depth of sections.
In the present embodiment, described channel-section steel web place offers some bolts hole that match with steel pipe column 1 and end plate 3 in pairs.
In the present embodiment, described steel pipe column 1 section form is rectangle cold-bent pipe or rectangle straight seam welded steel pipe.
A construction method for rectangular steel-tube concrete column and the monolateral bolt connection node of girder steel, comprises the following steps:
(1) by girder steel 4 and end plate 3 firm welding;
(2) in rectangle steel tubing string 1 joint cores, arrange and add competent structure, when strengthening being configured to external reinforcing plate for car 6, first adopt weld all around to be reliably connected with steel pipe column 1 in two blocks of channel-section steels, then in steel pipe column 1, external reinforcing plate for car 6 and end plate 3 corresponding positions, offer bolt hole, for monolateral bolt 5 is installed; When strengthening being configured to built-in short H shaped steel 7, first short H shaped steel 7 is filled in to joint core place, and with steel pipe column 1 inwall spot welding, then in steel pipe column 1, built-in short H shaped steel 7 and end plate 3 corresponding positions, offer bolt hole, for monolateral bolt 5 is installed; When strengthening being configured to binding bar 8, first on steel pipe column 1, offer plug welding hole, binding bar 8 is reliably connected with steel pipe column 1 both sides tube wall by plug welding hole at tapping, then at steel pipe column 1 and end plate 3 corresponding positions, offers bolt hole, for monolateral bolt 5 is installed;
(3) girder steel 4 that has welded end plate 3 is lifted to assigned address, use torque wrench to tighten monolateral bolt 5, steel pipe column 1 is reliably connected with end plate 3;
(4) at the interior concreting 2 of steel pipe column 1, complete node construction.
The specific embodiment:
Embodiment 1:
The structure of the present embodiment is as Fig. 1, shown in Fig. 2, external reinforcing plate for car 6 is comprised of two blocks of channel-section steels, every block of channel-section steel is formed by three block plate weldings or is formed by a block plate clod wash, first by girder steel 4 and end plate 3 firm welding, then adopt weld all around to be reliably connected with steel pipe column 1 tube wall in two blocks of channel-section steels, then at steel pipe column 1 wall, bolt hole is opened for monolateral bolt 5 is installed in channel-section steel web and end plate 3 corresponding positions, during site operation, girder steel 4 is lifted to assigned address, adopt torque wrench to tighten monolateral bolt 5, by end plate 3, external reinforcing plate for car 6 is reliably connected with steel pipe column 1 wall three, finally at the interior concreting 2 of steel pipe column 1, complete the construction of node.
Embodiment 2:
The structure of the present embodiment is as Fig. 3, shown in Fig. 4, first make built-in short H shaped steel 7, its breadth of section and be highly all slightly less than steel pipe column 1 cross section inside wall width and height, its length is slightly larger than girder steel 3 depth of sections, then short H shaped steel 7 is filled in to joint cores, and with steel pipe column 1 inwall spot welding, then by girder steel 4 and end plate 3 firm welding, and at steel pipe column 1 wall, bolt hole is opened for monolateral bolt 5 is installed in built-in short H shaped steel 7 and end plate 3 corresponding positions, during site operation, by girder steel 3 lifting assigned addresses, adopt torque wrench to tighten monolateral bolt 4, by end plate 3, the edge of a wing of built-in short H shaped steel 7 is reliably connected with steel pipe column 1 wall three, finally at the interior concreting 2 of steel pipe column 1, complete the construction of node.
Embodiment 3:
The structure of the present embodiment as shown in Figure 5, Figure 6, first at steel pipe column 1 wall, open plug welding hole, binding bar 8 is reliably connected with both sides tube wall by plug weld at tapping, then by girder steel 4 and end plate 3 firm welding, then at steel pipe column 1 wall and end plate 3 corresponding positions, open bolt hole for monolateral bolt 5 is installed, during site operation, girder steel 4 is lifted to assigned address, adopt torque wrench to tighten monolateral bolt 5, end plate 3 is reliably connected with steel pipe column 1 wall, finally, at the interior concreting 2 of steel pipe column 1, complete the construction of node.
Above-listed preferred embodiment; the object, technical solutions and advantages of the present invention are further described; institute is understood that; the foregoing is only preferred embodiment of the present invention; not in order to limit the present invention; within the spirit and principles in the present invention all, any modification of doing, be equal to replacement, improvement etc., within all should being included in protection scope of the present invention.

Claims (7)

1. a rectangular steel-tube concrete column and the monolateral bolt connection node of girder steel, comprise rectangle steel tubing string and girder steel, it is characterized in that: described girder steel end is welded with end plate, described end plate is mounted on steel pipe column sidewall by securing member, described end plate with on steel pipe column, longitudinally offer in pairs some corresponding bolts hole, described steel tubular column joints core space is provided with and adds competent structure.
2. the monolateral bolt connection node of rectangular steel-tube concrete column according to claim 1 and girder steel, is characterized in that: described securing member is monolateral bolt.
3. the monolateral bolt connection node of rectangular steel-tube concrete column according to claim 1 and girder steel, is characterized in that: described reinforcement is configured to any one in binding bar, external reinforcing plate for car or built-in short H shaped steel.
4. the monolateral bolt connection node of rectangular steel-tube concrete column according to claim 3 and girder steel, it is characterized in that: described external reinforcing plate for car is comprised of two blocks of channel-section steels, described built-in short its breadth of section of H shaped steel and be highly all slightly less than steel pipe column cross section inside wall width and height, its length is slightly larger than girder steel depth of section.
5. the monolateral bolt connection node of rectangular steel-tube concrete column according to claim 4 and girder steel, is characterized in that: described channel-section steel web place offers some bolts hole that match with girder steel and end plate in pairs.
6. the monolateral bolt connection node of rectangular steel-tube concrete column according to claim 1 and girder steel, is characterized in that: described steel pipe column section form is rectangle cold-bent pipe or rectangle straight seam welded steel pipe.
7. a construction method for rectangular steel-tube concrete column and the monolateral bolt connection node of girder steel, is characterized in that, comprises the following steps:
(1) by girder steel and end plate firm welding;
(2) in rectangle steel tubing string joint cores, arrange and add competent structure, when strengthening being configured to external reinforcing plate for car, first adopt weld all around to be reliably connected two blocks of channel-section steels and steel pipe column, then in steel pipe column, stiffener and end plate corresponding position, offer bolt hole, for monolateral bolt is installed; When strengthening being configured to built-in short H shaped steel, first short H shaped steel is filled in to joint core place, and with the spot welding of steel pipe column inwall, then in steel pipe column, built-in short H shaped steel and end plate corresponding position, offer bolt hole, for monolateral bolt is installed; When strengthening being configured to binding bar, first on steel pipe column, offer plug welding hole, binding bar is reliably connected with steel pipe column both sides tube wall by plug welding hole at tapping, then at steel pipe column and end plate corresponding position, offers bolt hole, for monolateral bolt is installed;
(3) by the steel beam lifting that has welded end plate to assigned address, use torque wrench to tighten monolateral bolt, steel pipe column is reliably connected with end plate;
(4) concreting in steel pipe column, completes node construction.
CN201410468001.9A 2014-09-16 2014-09-16 Rectangular concrete filled steel tube column and steel beam single-side bolt connecting joint and construction method thereof Pending CN104179256A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410468001.9A CN104179256A (en) 2014-09-16 2014-09-16 Rectangular concrete filled steel tube column and steel beam single-side bolt connecting joint and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410468001.9A CN104179256A (en) 2014-09-16 2014-09-16 Rectangular concrete filled steel tube column and steel beam single-side bolt connecting joint and construction method thereof

Publications (1)

Publication Number Publication Date
CN104179256A true CN104179256A (en) 2014-12-03

Family

ID=51960575

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410468001.9A Pending CN104179256A (en) 2014-09-16 2014-09-16 Rectangular concrete filled steel tube column and steel beam single-side bolt connecting joint and construction method thereof

Country Status (1)

Country Link
CN (1) CN104179256A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895195A (en) * 2015-05-04 2015-09-09 凤阳中都水泥有限公司 High-stability steel beam
CN105569184A (en) * 2016-01-07 2016-05-11 天津大学 One-way bolt connection node between rectangular steel pipe concrete column and H-type girders
CN105649215A (en) * 2015-08-12 2016-06-08 广州大学 Connecting joint for outer sleeve pipe type concrete filled steel tubular column and steel girder end plate
CN108755937A (en) * 2018-08-10 2018-11-06 东华理工大学 A kind of steel core concrete column connect cross abnormity node with box-girder and I-beam
CN108797809A (en) * 2018-08-21 2018-11-13 长安大学 The connecting joint structure and construction method of core space heavier-duty circular steel tube concrete column and girder steel
CN109898544A (en) * 2019-04-03 2019-06-18 北京工业大学 A kind of unilateral bolt connection structure of concrete structure with hollow sandwich shaft tower and basis
CN110080464A (en) * 2019-04-03 2019-08-02 北京工业大学 A kind of simple assembling formula steel tube concrete column feet

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004107992A (en) * 2002-09-18 2004-04-08 Nippon Steel Corp Long-clamping high-strength bolt joint structure of steel-pipe column and joint metal, and long-clamping bolt
CN201535015U (en) * 2009-07-31 2010-07-28 宝山钢铁股份有限公司 Connecting node of outer sleeve-type square and rectangular steel pipe column and H-shaped steel beam
CN201554121U (en) * 2009-07-31 2010-08-18 宝山钢铁股份有限公司 Connection joint of inner sleeve squared rectangular steel pipe column and H-shaped steel beam
CN201738458U (en) * 2010-08-31 2011-02-09 武汉长丰赛博思钢结构工程有限公司 Novel assembly type end-plate connecting node of cold-bending rectangular steel pipe column and H type steel beam
JP4754347B2 (en) * 2005-12-27 2011-08-24 新日本製鐵株式会社 High-strength bolt tension joint structure of concrete filled square steel tube column and beam
CN202466993U (en) * 2012-01-04 2012-10-03 山东科技大学 Compound steel pipe concrete pile with pull rod
CN202831235U (en) * 2012-08-31 2013-03-27 宝钢建筑系统集成有限公司 Assembled pitch joint of rectangular steel pipe column and H-shaped steel girder of internally installed sleeve
CN204059610U (en) * 2014-09-16 2014-12-31 福州大学 Rectangular steel-tube concrete column and the monolateral bolt connection node of girder steel

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004107992A (en) * 2002-09-18 2004-04-08 Nippon Steel Corp Long-clamping high-strength bolt joint structure of steel-pipe column and joint metal, and long-clamping bolt
JP4754347B2 (en) * 2005-12-27 2011-08-24 新日本製鐵株式会社 High-strength bolt tension joint structure of concrete filled square steel tube column and beam
CN201535015U (en) * 2009-07-31 2010-07-28 宝山钢铁股份有限公司 Connecting node of outer sleeve-type square and rectangular steel pipe column and H-shaped steel beam
CN201554121U (en) * 2009-07-31 2010-08-18 宝山钢铁股份有限公司 Connection joint of inner sleeve squared rectangular steel pipe column and H-shaped steel beam
CN201738458U (en) * 2010-08-31 2011-02-09 武汉长丰赛博思钢结构工程有限公司 Novel assembly type end-plate connecting node of cold-bending rectangular steel pipe column and H type steel beam
CN202466993U (en) * 2012-01-04 2012-10-03 山东科技大学 Compound steel pipe concrete pile with pull rod
CN202831235U (en) * 2012-08-31 2013-03-27 宝钢建筑系统集成有限公司 Assembled pitch joint of rectangular steel pipe column and H-shaped steel girder of internally installed sleeve
CN204059610U (en) * 2014-09-16 2014-12-31 福州大学 Rectangular steel-tube concrete column and the monolateral bolt connection node of girder steel

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104895195A (en) * 2015-05-04 2015-09-09 凤阳中都水泥有限公司 High-stability steel beam
CN105649215A (en) * 2015-08-12 2016-06-08 广州大学 Connecting joint for outer sleeve pipe type concrete filled steel tubular column and steel girder end plate
CN105569184A (en) * 2016-01-07 2016-05-11 天津大学 One-way bolt connection node between rectangular steel pipe concrete column and H-type girders
CN108755937A (en) * 2018-08-10 2018-11-06 东华理工大学 A kind of steel core concrete column connect cross abnormity node with box-girder and I-beam
CN108797809A (en) * 2018-08-21 2018-11-13 长安大学 The connecting joint structure and construction method of core space heavier-duty circular steel tube concrete column and girder steel
CN109898544A (en) * 2019-04-03 2019-06-18 北京工业大学 A kind of unilateral bolt connection structure of concrete structure with hollow sandwich shaft tower and basis
CN110080464A (en) * 2019-04-03 2019-08-02 北京工业大学 A kind of simple assembling formula steel tube concrete column feet

Similar Documents

Publication Publication Date Title
CN104179256A (en) Rectangular concrete filled steel tube column and steel beam single-side bolt connecting joint and construction method thereof
CN203080736U (en) Combined profile steel box-shaped steel plate shear wall
CN204059610U (en) Rectangular steel-tube concrete column and the monolateral bolt connection node of girder steel
CN201738458U (en) Novel assembly type end-plate connecting node of cold-bending rectangular steel pipe column and H type steel beam
CN203878780U (en) Connecting joint of cylindrical rib penetrating type steel pipe concrete column and steel beam
CN207277561U (en) Built-in profile steel high-strength concrete stem superposed column-girder steel group frame
CN101914952A (en) Connecting joint between hollow steel tube concrete column and steel girder and construction method thereof
CN208563601U (en) A kind of concrete column-steel beam combined joint
CN103821235B (en) U-shaped steel-concrete composite beam and the node component of rectangular steel-tube concrete column
CN104912196A (en) Connection joint of concrete filled steel tubular column and enclosed U-shaped steel concrete composite beam
CN203569728U (en) Box-shaped steel plate shear wall with internal trusses
CN107558610A (en) Square set justifies Concrete-filled Double Skin Steel Tube Columns and steel beam connecting joint and construction method
CN204491999U (en) The compound Concrete-Filled Square Steel Tube coupled column of New Thin-walled
CN104251038A (en) Encased steel plate-concrete composite coupling beam and construction method thereof
CN103015534A (en) Lateral connection node of concrete-filled rectangular steel tube column and steel beams
CN104294920B (en) The node component of a kind of U-shaped steel-concrete combination beam and special-shaped steel pipe concrete post and preparation method
CN103806593B (en) A kind of precast concrete
CN103821234A (en) Joint construction for steel-reinforced concrete column and reinforced concrete beam
CN206521768U (en) A kind of shear connector in the double-deck box hat concrete combined structure of immersed tube tunnel
CN204551753U (en) Concrete-filled square thin-walled steel tube columns and girder steel assembling type node structure
CN104196261B (en) A kind of existed concrete bridge post and newly-increased steel beam connecting joint
CN203782894U (en) Joint structure of steel-reinforced concrete column and reinforced concrete beam
CN103526950A (en) Concrete-filled square steel tube and steel beam semi-rigid reinforcing joint for preventing progressive collapse
CN204401628U (en) Large-span steel supports multidirectional connector
CN204098241U (en) Trapezoidal steel plate interpolation type rectangular steel-tube concrete column and steel beam connecting joint

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20141203

RJ01 Rejection of invention patent application after publication