CN104164869B - Band supporting leg diaphram wall Computing Method for Vertical Bearing Capacity - Google Patents
Band supporting leg diaphram wall Computing Method for Vertical Bearing Capacity Download PDFInfo
- Publication number
- CN104164869B CN104164869B CN201410174469.7A CN201410174469A CN104164869B CN 104164869 B CN104164869 B CN 104164869B CN 201410174469 A CN201410174469 A CN 201410174469A CN 104164869 B CN104164869 B CN 104164869B
- Authority
- CN
- China
- Prior art keywords
- bearing capacity
- wall
- outriggers
- vertical bearing
- underground diaphragm
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
技术领域 technical field
本发明属于土木工程专业中岩土工程、基坑工程领域,一般用于建(构)筑物地下室或地下结构。 The invention belongs to the field of geotechnical engineering and foundation pit engineering in civil engineering specialty, and is generally used for building (structure) basements or underground structures.
背景技术 Background technique
随城市规模扩大,汽车保有量增加,高层建筑地下室日益加深,各大城市纷纷进行道路向地下发展的探索,地下空间开发和建设如火如荼。在面积和深度不断加大的地下空间建设过程中,深、厚地下连续墙技术得到了广泛应用,但目前还存在以下问题: With the expansion of the city, the number of cars increases, and the basements of high-rise buildings are deepening day by day, major cities are exploring the development of roads underground, and the development and construction of underground space is in full swing. In the process of underground space construction with increasing area and depth, deep and thick underground diaphragm wall technology has been widely used, but there are still the following problems:
1、主要用作地下室外围护墙,不考虑承受主体结构竖向荷载。 1. It is mainly used as the enclosure wall of the basement, and does not consider bearing the vertical load of the main structure.
2、需以基岩为持力层时,地下连续墙入岩时的施工难度和工程造价增加。 2. When the bedrock is required as the bearing layer, the construction difficulty and project cost increase when the underground diaphragm wall enters the rock.
带支腿地下连续墙是根据特定土质条件、特定使用功能而对地下连续墙的创新,是特殊的地下连续墙。地下连续墙底部设置支腿后,因支腿进入下部较好的持力层或基岩,可兼作工程桩,发挥其端承作用,最终使得带支腿地下连续墙可承受主体结构竖向荷载,同时减少地下连续墙入岩的施工难度,减少工程造价。 The underground diaphragm wall with outriggers is an innovation of the underground diaphragm wall according to specific soil conditions and specific use functions. It is a special underground diaphragm wall. After the outriggers are set at the bottom of the underground diaphragm wall, because the outriggers enter the lower better bearing layer or bedrock, they can also be used as engineering piles to exert their end bearing function, and finally make the underground diaphragm wall with outriggers bear the vertical load of the main structure , and at the same time reduce the construction difficulty of the underground diaphragm wall into the rock, and reduce the project cost.
带支腿地下连续墙承担竖向荷载后,可减少工程桩,解决墙体入岩困难和造价高的问题。和普通地下连续墙相比,社会和经济效益显著。 After the underground diaphragm wall with outriggers bears the vertical load, engineering piles can be reduced, and the problems of difficulty in entering the rock and high cost of the wall can be solved. Compared with common underground diaphragm walls, the social and economic benefits are remarkable.
目前国外没有带支腿地下连续墙相关研究和报道,国内仅广东省早在上个世纪末开展了类似带支腿地下连续墙的施工实践,项目规模小,没有对带支腿地下连续墙的受力和变形特性、适用范围等进行系统实践和理论研究。 At present, there are no related studies and reports on underground diaphragm walls with outriggers abroad. In China, only Guangdong Province has carried out construction practices similar to underground diaphragm walls with outriggers as early as the end of the last century. The project scale is small and there is no impact on the underground diaphragm walls with outriggers Conduct systematic practice and theoretical research on force and deformation characteristics, scope of application, etc.
带支腿地下连续墙为新型地下连续墙形式,目前国家标准没有相应的设计方法。现有的桩基公式适用于单一截面的圆桩或方桩,不能反映墙段和支腿所在的持力层不一致,墙段和支腿端承截面不一样的情况。 The underground diaphragm wall with outriggers is a new type of underground diaphragm wall, and there is no corresponding design method in the current national standard. The existing pile foundation formula is suitable for round piles or square piles with a single cross section, and cannot reflect the fact that the bearing layers of the wall section and the outrigger are not consistent, and the end bearing sections of the wall section and the outrigger are not the same.
发明内容 Contents of the invention
为使工程设计人员依据现有的工程勘察资料和数据,确定带支腿地下连续墙的竖向承载力,本发明提供了根据工程勘察报告提供的各层土体摩擦力和承载力特征值,确定带支腿地下连续墙竖向承载力的计算方法,本发明包括: In order to enable engineering designers to determine the vertical bearing capacity of the underground diaphragm wall with outriggers according to the existing engineering survey data and data, the present invention provides the characteristic values of friction and bearing capacity of each layer of soil provided according to the engineering survey report, The calculation method for determining the vertical bearing capacity of an underground diaphragm wall with outriggers, the present invention includes:
步骤1:带支腿地下连续墙承载力组成分析。 Step 1: Compositional analysis of the bearing capacity of the underground diaphragm wall with outriggers.
步骤2:确定支腿的承载力公式,计算支腿竖向承载力。 Step 2: Determine the bearing capacity formula of the outrigger and calculate the vertical bearing capacity of the outrigger.
步骤3:确定墙段的承载力公式,计算墙段竖向承载力。 Step 3: Determine the bearing capacity formula of the wall segment, and calculate the vertical bearing capacity of the wall segment.
步骤4:由步骤2和步骤3,计算带支腿地下连续墙承载力。 Step 4: From Step 2 and Step 3, calculate the bearing capacity of the underground diaphragm wall with outriggers.
步骤5:带支腿地下连续墙竖向承载力验算。 Step 5: Check the vertical bearing capacity of the underground diaphragm wall with outriggers.
步骤6:支腿竖向承载力验算。 Step 6: Check the vertical bearing capacity of the outrigger.
步骤7:经步骤5、步骤6验算后,最终得到带支腿地下连续墙竖向承载力。 Step 7: After checking and calculating in steps 5 and 6, the vertical bearing capacity of the underground diaphragm wall with outriggers is finally obtained.
本发明的有益效果: Beneficial effects of the present invention:
1、能够共同发挥带支腿地下连续墙墙段和支腿的端阻,提高带支腿地下连续墙的竖向承载力。 1. The end resistance of the section of the underground diaphragm wall with outriggers and the outriggers can be exerted together, and the vertical bearing capacity of the underground diaphragm wall with outriggers can be improved.
2、提供和桩基竖向承载力计算类似的带支腿地下连续墙竖向承载力计算公式,方便设计人员应用,简便易行。 2. Provide the calculation formula of the vertical bearing capacity of the underground diaphragm wall with outriggers similar to the calculation of the vertical bearing capacity of the pile foundation, which is convenient for designers to apply, and is simple and easy.
3、将带支腿地下连续墙自身强度条件考虑在内,明确需进行带支腿地下连续墙墙段和支腿的竖向承载力验算,确保带支腿地下连续墙自身强度满足竖向荷载受压的要求。 3. Considering the self-strength conditions of the underground diaphragm wall with outriggers, it is clear that the vertical bearing capacity of the underground diaphragm wall with outriggers and the outriggers must be checked to ensure that the strength of the underground diaphragm wall with outriggers meets the vertical load Pressurized requirements.
4、带支腿地下连续墙虽为异形地下连续墙,但按本计算方法确定其承载力,需要依据的地基承载力特征值数据和现行国家标准规定的数据条件一致,无需进行特殊的岩土工程勘察,可适应工程的大范围应用。 4. Although the underground diaphragm wall with outriggers is a special-shaped underground diaphragm wall, to determine its bearing capacity according to this calculation method, the characteristic value data of the foundation bearing capacity need to be based on the data conditions specified in the current national standards, and no special geotechnical analysis is required. Engineering survey can be adapted to a wide range of engineering applications.
附图说明 Description of drawings
图1a、图1b和图1c分别为带支腿地下连续墙竖向承载力立体图、正视图和侧视图(用作工程桩); Fig. 1a, Fig. 1b and Fig. 1c are the three-dimensional view, the front view and the side view of the vertical bearing capacity of the underground diaphragm wall with outriggers respectively (used as engineering piles);
图2a、图2b和图2c分别为带支腿地下连续墙竖向承载力立体图、正视图和侧视图(用作地下室外墙); Fig. 2a, Fig. 2b and Fig. 2c are the perspective view, front view and side view of the vertical bearing capacity of the underground diaphragm wall with outriggers respectively (used as the outer wall of the basement);
图3a、图3b和图3c分别为带支腿地下连续墙用作地下室外墙、用作工程桩和支腿时承载力验算图。 Figure 3a, Figure 3b and Figure 3c are the bearing capacity checking diagrams when the underground diaphragm wall with outriggers is used as the outer wall of the basement, and when it is used as engineering piles and outriggers.
具体实施方式 detailed description
下面结合附图对本发明的实施例作详细说明:本实施例在以本发明技术方案为前提下进行实施,给出了详细的实施方式和具体的操作过程,但本发明的保护范围不限于下述的实施例。 The embodiments of the present invention are described in detail below in conjunction with the accompanying drawings: this embodiment is implemented on the premise of the technical solution of the present invention, and detailed implementation methods and specific operating procedures are provided, but the protection scope of the present invention is not limited to the following the described embodiment.
带支腿地下连续墙承受上部结构荷载时,相当于基础,其竖向承载力包括两层涵义:带支腿地下连续墙自身承载力、支承带支腿地下连续墙基础的地基土的极限承载力。后者也称作带支腿地下连续墙的竖向承载力。本发明提供了完整的带支腿地下连续墙、支腿的竖向承载力计算方法,带支腿地下连续墙墙段、支腿自身承载力验算公式,从而最终确定带支腿地下连续墙承载力。 When the underground diaphragm wall with outriggers bears the load of the superstructure, it is equivalent to the foundation, and its vertical bearing capacity includes two meanings: the self-bearing capacity of the underground diaphragm wall with outriggers, and the ultimate bearing capacity of the foundation soil supporting the foundation of the underground diaphragm wall with outriggers force. The latter is also referred to as the vertical bearing capacity of the diaphragm wall with legs. The present invention provides a complete calculation method for the vertical bearing capacity of the underground diaphragm wall with outriggers and outriggers, and the checking formula for the bearing capacity of the section of the underground diaphragm wall with outriggers and the self-bearing capacity of the outriggers, so as to finally determine the bearing capacity of the underground diaphragm wall with outriggers. force.
为实现上述目的,本发明采取下述步骤: To achieve the above object, the present invention takes the following steps:
步骤1:带支腿地下连续墙承载力组成分析。和普通地下连续墙相比,带支腿地下连续墙增加了支腿侧阻力、支腿端阻力两部分竖向承载力。即其竖向承载力由墙段竖向承载力(侧摩阻力qsw1、qsw2和端阻力qpw)和支腿竖向承载力组成(侧摩阻力qsl1、qsl2和端阻力qpl)。带支腿地下连续墙作为竖向承重结构时,支腿发挥端承作用。其竖向承载特性类似于摩擦端承桩。为发挥墙段和支腿端部端阻力作用,应使墙段和支腿进入较好持力层。 Step 1: Compositional analysis of the bearing capacity of the underground diaphragm wall with outriggers. Compared with the ordinary underground diaphragm wall, the underground diaphragm wall with outriggers increases the vertical bearing capacity of the side resistance of the outriggers and the end resistance of the outriggers. That is to say, its vertical bearing capacity is composed of the vertical bearing capacity of the wall section (side friction resistance q sw1 , q sw2 and end resistance q pw ) and the vertical bearing capacity of outrigger (side friction resistance q sl1 , q sl2 and end resistance q pl ). When the underground diaphragm wall with outriggers is used as a vertical load-bearing structure, the outriggers play the role of end bearing. Its vertical load-bearing characteristics are similar to friction end-bearing piles. In order to exert the resistance effect of the wall section and the end of the outrigger, the wall section and the outrigger should enter the better bearing layer.
带支腿地下连续墙用作竖向承重结构,分以下两种情况: The underground diaphragm wall with outriggers is used as a vertical load-bearing structure, which can be divided into the following two situations:
(1)用作工程桩,承受高层建筑上部结构的荷载,参见图1a、图1b和图1c。 (1) Used as engineering piles to bear the load of the superstructure of high-rise buildings, see Figure 1a, Figure 1b and Figure 1c.
(2)承受上部结构荷载,用作地下室外墙。因带支腿地下连续墙墙段幅与幅两两相接,墙幅间无竖向位移差可简化为零,墙两端侧摩阻力qsw1为零。地下室施工过程中,基坑开挖卸载,致使基坑底以上迎土侧墙体部位土体横向约束减弱;为偏于安全,地下室范围墙体侧摩阻力qsw2也取为零,参见图2a、图2b和图2c (2) To bear the load of the upper structure and be used as the outer wall of the basement. Because the wall segments of the underground diaphragm wall with outriggers are connected in pairs, there is no vertical displacement difference between the wall widths, which can be simplified to zero, and the lateral frictional resistance q sw1 at both ends of the wall is zero. During the construction of the basement, the foundation pit is excavated and unloaded, which weakens the lateral restraint of the soil on the side wall above the foundation pit bottom; for safety, the side friction resistance q sw2 of the wall in the basement area is also taken as zero, see Figure 2a , Figure 2b and Figure 2c
步骤2:确定支腿竖向承载力Rl公式,为: Step 2: Determine the vertical bearing capacity R l formula of the outrigger, which is:
Rl=(Qsl+Qpl)/K(1a) R l =(Q sl +Q pl )/K(1a)
其中支腿侧阻力:Qsl=n(α·2t∑qsl1ili+2bl∑qsl2ili)(1b) Outrigger side resistance: Q sl = n(α·2t∑q sl1i l i +2b l ∑q sl2i l i )(1b)
支腿端阻力:Qpl=qplAl;Al=nbl·t(1c) Outrigger end resistance: Q pl =q pl A l ; A l =nb l ·t(1c)
式中:α——支腿沿墙长的侧摩阻折减系数,可取0.8~0.9; In the formula: α——the side friction reduction coefficient of the outrigger along the length of the wall, which can be taken as 0.8~0.9;
Al——支腿的投影面积(m2); A l — projected area of the outrigger (m 2 );
li——第i层土的厚度(m); l i —thickness of the i-th layer of soil (m);
bl、t——支腿的宽度和厚度(m); b l , t——width and thickness of outrigger (m);
n——墙段下支腿的数量(m)。 n - the number of outriggers under the wall section (m).
步骤3:确定墙段竖向承载力Rw公式,为: Step 3: Determine the vertical bearing capacity R w formula of the wall segment, which is:
Rw=(Qsw+Qpw)/K(2a) R w =(Q sw +Q pw )/K(2a)
其中,墙侧阻力:Qsw=2t∑qsw1li+2b∑qsw2li(2b) Among them, wall side resistance: Q sw = 2t∑q sw1 l i +2b∑q sw2 l i (2b)
墙端阻力:Qpw=qsp(Aw-Al);Aw=bt(2c) Wall resistance: Q pw = q sp (A w -A l ); A w = bt(2c)
式中:AW——墙段的投影面积(m2); In the formula: A W —— projected area of wall section (m 2 );
b、t——墙段的宽度和厚度(m); b, t - the width and thickness of the wall section (m);
qsp=qpw。 q sp =q pw .
步骤4:确定带支腿地下连续墙承载力R公式,计算带支腿地下连续墙承载力。 Step 4: Determine the bearing capacity R formula of the underground diaphragm wall with outriggers, and calculate the bearing capacity of the underground diaphragm wall with outriggers.
R=Rw+Rl(3) R= Rw + Rl (3)
qsw1、qsw2、qpw、qs1、qsl2和qpl由工程勘察报告提供,当带支腿地下连续墙兼作地下室外墙时,qsw1值取0,且地下室深度范围墙段四周侧摩阻力qsw1、qsw2均为0。式(1)和式(2)中K为安全系数,和国家标准桩基承载力安全要求一致,取K=2。根据带支腿地下连续墙尺寸,由式(3),可计算得到带支腿地下连续墙竖向承载力。 q sw1 , q sw2 , q pw , q s1 , q sl2 and q pl are provided by the engineering investigation report. When the underground diaphragm wall with outriggers doubles as the exterior wall of the basement, the value of q sw1 shall be 0, and the depth range of the basement shall be around the wall section The frictional resistances q sw1 and q sw2 are both zero. In formulas (1) and (2), K is the safety factor, which is consistent with the safety requirements of the national standard pile foundation bearing capacity, and K=2 is taken. According to the size of the underground diaphragm wall with outriggers, the vertical bearing capacity of the underground diaphragm wall with outriggers can be calculated by formula (3).
步骤5:带支腿地下连续墙墙段竖向承载力验算。墙段所受上部结构竖向荷载P需满足下式要求: Step 5: Check the vertical bearing capacity of the section of the underground diaphragm wall with outriggers. The vertical load P of the superstructure on the wall section must meet the requirements of the following formula:
P≤R'=φcfcAw+0.9fy'As'(4) P≤R'=φ c f c A w +0.9f y 'A s '(4)
式中φc——成墙工作条件系数,同钻孔灌注桩,可取0.7~0.8。 In the formula, φ c —coefficient of the working conditions of the wall, which is the same as the bored pile, can be taken as 0.7~0.8.
fc——混凝土轴心抗压强度设计值; fc — design value of concrete axial compressive strength;
fy'——纵向主筋抗压强度设计值; f y '—design value of compressive strength of longitudinal main reinforcement;
As'——纵向主筋截面面积。 A s '——cross-sectional area of longitudinal main reinforcement.
步骤6:带支腿地下连续墙的支腿竖向承载力验算,见图3a、图3b和图c。支腿顶部所受竖向荷载N为: Step 6: Check the vertical bearing capacity of the outriggers of the underground diaphragm wall with outriggers, see Figure 3a, Figure 3b and Figure c. The vertical load N on the top of the outrigger is:
式中G——支腿顶部以上墙段自重以及墙段分担的地下室竖向荷载;当用作工程桩时,即为支腿顶部以上墙段自重。 In the formula, G——the self-weight of the wall section above the top of the outrigger and the vertical load of the basement shared by the wall section; when used as an engineering pile, it is the self-weight of the wall section above the top of the outrigger.
支腿顶部竖向荷载需满足以下要求: The vertical load on the top of the outrigger must meet the following requirements:
N≤φlcfcAl+0.9fy'As'(6) N≤φ lc f c A l +0.9f y 'A s '(6)
式中φlc——支腿成型的工作条件系数,同钻孔灌注桩,可取0.7~0.8。 In the formula, φ lc —— the working condition coefficient of outrigger forming, which is the same as that of bored pile, and it can be taken as 0.7~0.8.
步骤7:经步骤5、步骤6验算后,在满足支腿自身竖向承载力式(6)的条件下,取式(3)R和式(4)R'两者的最小值,该值即为带支腿地下连续墙最终竖向承载力。 Step 7: After checking and calculating in steps 5 and 6, under the condition of satisfying the vertical bearing capacity formula (6) of the outrigger itself, take the minimum value of both formula (3) R and formula (4) R', the value That is, the ultimate vertical bearing capacity of the underground diaphragm wall with outriggers.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410174469.7A CN104164869B (en) | 2014-04-28 | 2014-04-28 | Band supporting leg diaphram wall Computing Method for Vertical Bearing Capacity |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410174469.7A CN104164869B (en) | 2014-04-28 | 2014-04-28 | Band supporting leg diaphram wall Computing Method for Vertical Bearing Capacity |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN104164869A CN104164869A (en) | 2014-11-26 |
| CN104164869B true CN104164869B (en) | 2016-05-18 |
Family
ID=51908842
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201410174469.7A Active CN104164869B (en) | 2014-04-28 | 2014-04-28 | Band supporting leg diaphram wall Computing Method for Vertical Bearing Capacity |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104164869B (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106570323A (en) * | 2016-10-27 | 2017-04-19 | 天津大学 | Calculation method for vertical bearing capacity of major-diameter combined type bucket foundation |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1114376A (en) * | 1994-09-07 | 1996-01-03 | 张国梁 | Underground continuous wall and construction method thereof |
| CN101736757A (en) * | 2009-12-04 | 2010-06-16 | 上海市第二建筑有限公司 | Two-way synchronous construction method of tube structure of high-rise building |
| CN203373774U (en) * | 2013-06-13 | 2014-01-01 | 中铁隧道集团有限公司 | Subsection steel-bar-distribution pre-stressed concrete continuous wall |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| RU2626101C9 (en) * | 2006-12-19 | 2019-03-25 | Лоудтест, Инк. | Method and device for testing of bearing capacity using the annular sensor |
-
2014
- 2014-04-28 CN CN201410174469.7A patent/CN104164869B/en active Active
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1114376A (en) * | 1994-09-07 | 1996-01-03 | 张国梁 | Underground continuous wall and construction method thereof |
| CN101736757A (en) * | 2009-12-04 | 2010-06-16 | 上海市第二建筑有限公司 | Two-way synchronous construction method of tube structure of high-rise building |
| CN203373774U (en) * | 2013-06-13 | 2014-01-01 | 中铁隧道集团有限公司 | Subsection steel-bar-distribution pre-stressed concrete continuous wall |
Also Published As
| Publication number | Publication date |
|---|---|
| CN104164869A (en) | 2014-11-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104652448B (en) | A kind of Pit imbalance support design method | |
| CN102306225B (en) | Method for simulating construction course and tunnel deformation influence value of multiline overlapping tunnel | |
| CN106650118B (en) | Optimization design method for governing parameters of side slope slide-resistant pile | |
| CN110245401A (en) | An evaluation method for the impact of shield tunnel underpass on existing shield tunnels | |
| CN106649931A (en) | Calculation method for post-construction ground surface settlement of rectangular jacking pipe tunnel construction | |
| CN102605750B (en) | Grouting reinforcement and earthquake resisting method for earth and rockfill dam | |
| Zhang et al. | The performance of mechanical characteristics and failure mode for tunnel concrete lining structure in water-rich layer | |
| CN102392658B (en) | Quantification design method for preliminary bracing parameters of unsymmetrical loading tunnel | |
| CN102140918A (en) | Loess tunnel construction method | |
| CN102651042A (en) | Prestressed pull rod foundation design method for large-span space structure | |
| CN102087677A (en) | Method for solving solution of elastic foundation beams and for back analysis of value m | |
| CN104120677A (en) | Method for dike side slope two-dimensional safety and stability analysis taking shield pass-through influences into consideration | |
| CN118051980A (en) | A method for calculating the three-dimensional support pressure of shield excavation face in composite strata with soft upper and hard lower layers | |
| CN106638718B (en) | Overall length caking property soil anchor unsticking length and dynamic anchor force assay method | |
| CN104164869B (en) | Band supporting leg diaphram wall Computing Method for Vertical Bearing Capacity | |
| CN103981855B (en) | Band supporting leg ground diaphragm wall settlement calculation method | |
| Shi et al. | Analysis on Deformation and Stress Characteristics of a Multibraced Pit‐in‐Pit Excavation in a Subway Transfer Station | |
| CN205382942U (en) | Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility | |
| CN116992525A (en) | Calculation method for vertical response of pile foundation considering self-weight, pile top load and excavation action | |
| CN205077499U (en) | Double row pile supporting construction with transverse connection component | |
| CN106021959A (en) | Side friction calculation method suitable for rectangle-like municipal pipe-jacking tunnel under deep burial condition | |
| Tong | Research on application of multi-factor surrounding rock pressure calculation theory in engineering | |
| CN204000856U (en) | The anti-side changeable ridigity pile of inner support grouting formula level base | |
| CN106650144B (en) | A method of deploying micro piles for slope anti-sliding and its anti-sliding stability evaluation | |
| CN115329449B (en) | Method for calculating optimal reserved interval of upper and lower sections of piles by reverse self-balancing pile testing method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |