CN104071720A - In-tunnel turn-over method of super-large diameter penstock - Google Patents
In-tunnel turn-over method of super-large diameter penstock Download PDFInfo
- Publication number
- CN104071720A CN104071720A CN201410305926.1A CN201410305926A CN104071720A CN 104071720 A CN104071720 A CN 104071720A CN 201410305926 A CN201410305926 A CN 201410305926A CN 104071720 A CN104071720 A CN 104071720A
- Authority
- CN
- China
- Prior art keywords
- penstock
- groups
- anchors
- super
- anchor
- Prior art date
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 54
- 239000010959 steel Substances 0.000 claims abstract description 54
- 238000010276 construction Methods 0.000 claims abstract description 12
- 230000000875 corresponding Effects 0.000 claims abstract description 6
- 238000009434 installation Methods 0.000 claims description 19
- 239000002965 ropes Substances 0.000 claims description 17
- 239000000725 suspensions Substances 0.000 claims description 10
- 230000005540 biological transmission Effects 0.000 claims description 9
- 239000011901 water Substances 0.000 abstract description 3
- 238000009412 basement excavation Methods 0.000 abstract 1
- 238000004642 transportation engineering Methods 0.000 description 4
- 239000011435 rock Substances 0.000 description 3
- 230000001808 coupling Effects 0.000 description 2
- 238000010168 coupling process Methods 0.000 description 2
- 238000005859 coupling reactions Methods 0.000 description 2
- 238000005516 engineering processes Methods 0.000 description 2
- 238000000034 methods Methods 0.000 description 2
- 239000004570 mortar (masonry) Substances 0.000 description 2
- 281000117292 Birds Eye companies 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000000297 inotrophic Effects 0.000 description 1
Abstract
Description
technical field:
The present invention be applicable to super-large diameter penstock hole, power station in turn-over method relevant, special and flat section of penstock, curved segment turn-over method are relevant.
background technology:
At present, in super-large diameter penstock hole, power station, installation generally adopts " vertical " to carry out over-the-road transportation, by steel pipe transmission hole, is transported to the installation of directly unloading behind installation position.But " vertical " transportation exists overturning, collision etc. to cause the larger security risk of tube coupling deformation effect installation quality, separately need have special requirement to the height in steel pipe transmission hole, give the transportation of super-large diameter penstock, install and bring certain difficulty.
If super-large diameter penstock adopts " flat fortune ", general Hydropower Station Construction props up the requirement that hole size all can meet " flat fortune ", but still the problem that exists super-large diameter penstock to lift by crane in hole, stand up.
summary of the invention:
The object of the invention is the problem in order to solve lifting in power station super-large diameter penstock " flat fortune " hole, to stand up, turn-over method in a kind of super-large diameter penstock hole of evading security risk, raising work efficiency is provided.
The object of the present invention is achieved like this:
Turn-over method in super-large diameter penstock of the present invention hole, the method is to determine three groups of hoisting point positions in steel pipe transmission hole and steel pipe water leading cylinder infall, at three groups of hoisting point positions, carrying out part digs, dig height=steel pipe height+sky anchor height+steel rope, assembly pulley height+480~550mm, three groups of sky anchors and assembly pulley are installed, take in penstock to be stood up and connect equilateral triangle opposite position as three groups of sky anchors and assembly pulley installation site, then below three groups of sky anchors, correspondence is installed three groups of earth anchors and winch, each is organized earth anchor and by steel rope, is linked to be integral body with corresponding winch and day anchor and assembly pulley respectively, three groups of sky anchors and assembly pulley lift by crane super-large diameter penstock jointly, wherein two groups of sky anchors and assembly pulley adherence pressure steel pipe height, another group day anchor and assembly pulley are transferred penstock suspension centre height, until steel pipe complete stand up after after vertical state, dismantle another group day anchor suspension centre, complete the construction of standing up of super-large diameter penstock.
Turn-over method in super-large diameter penstock of the present invention hole is tried out in obtained effective enforcement in the pressure steel pipe of hydropower station installation of rock beach, respond well.If flat section steel pipe adopts " vertical " transportation under Yan Tan power station, outside steel pipe transmission hole size cannot be transported, in hole, also cannot carry out steel pipe and unload, lower flat section of penstock installation cannot be carried out; Adopt in hole of the present invention turn-over method to transport hole and diversion tunnel crown digs 1.1 ten thousand yuan of generation expenses, day anchor, earth anchor are installed 0.8 ten thousand yuan, winch, assembly pulley and are installed approximately 5.6 ten thousand yuan, amount to and drop into 7.5 ten thousand yuan.
The inventive method adopts a day anchor suspension centre to coordinate a winch to stand up construction to steel pipe, can efficiently solve without lifting appliance in the hole in or be not easy to the penstock that lifting appliance lifts to lift, stand up construction; Stand up process steadily, safely, efficiently, can improve penstock installation efficiency, reduce labour intensity, simple to operate, can guarantee to greatest extent that penstock stands up in process indeformable, improve installation quality.
accompanying drawing explanation:
Fig. 1 is the inventive method detail of construction.
Fig. 2 is the birds-eye view of Fig. 1.
Fig. 3 is assembly pulley arrangement plan.
Fig. 4 is that penstock stands up site plan.
Fig. 5 is that penstock stands up another location figure.
the specific embodiment:
Referring to Fig. 1~Fig. 5, turn-over method in the present embodiment super-large diameter penstock hole, the method is to determine three groups of hoisting point positions in steel pipe transmission hole 1 and penstock diversion tunnel 2 infalls, at three groups of hoisting point positions, carry out part and dig, dig height=steel pipe height+sky anchor height+steel rope, assembly pulley height+500mm.At three groups of hoisting point positions, 1# days anchors and assembly pulley 3,2# days anchor and assembly pulley 4,3# days anchor and assembly pulleys 5 are installed, take in penstock to be stood up and connect equilateral triangle opposite position as three groups of sky anchors and assembly pulley installation site.Then corresponding 1# earth anchor and leading sheave 6 and 1# winch 7,2# earth anchor and leading sheave 8 and 2# winch 9,3# earth anchor and leading sheave 10 and the 3# winch 11 installed below 1# days anchors, 2# days anchor, 3# days anchor.1# earth anchor and leading sheave connect into integral body by steel rope and 1# winch and 1# days anchors and assembly pulley.2# earth anchor and leading sheave connect into integral body by steel rope and 2# winch and 2# days anchors and assembly pulley.3# earth anchor and leading sheave connect into integral body by steel rope and 3# winch and 3# days anchors and assembly pulley.Three groups of sky anchors and assembly pulley lift by crane super-large diameter penstock jointly, 1# and 2# days anchor adherence pressure steel pipe height wherein, within 3# days, anchor is transferred penstock suspension centre height (Fig. 4), until steel pipe, complete and stand up after vertical state (Fig. 5), dismantle 3# days anchor suspension centres, complete the construction of standing up of super-large diameter penstock.In Fig. 1~Fig. 5, sequence number 12,13 is respectively penstock, part digs line.
Winch is bought off-the-shelf hardware, generally to move (determining) pulley wiring multiplying power, select 3 winchs that meet rated load, guarantee the normal work of elevator function and operation, winch basis needs embedded foundation anchor pole that winch is fixedly secured, and winch is electric meets relevant regulations requirement; 3 winch positions as shown in Figure 1.
It anchor: adopt 3 * Φ 36mm screw-thread steel to enter rock 6m, after day anchor installation, carry out mortar rockfill grouting and loaded test.Main Function is to carry out hoisting construction as assembly pulley hanging point, assembly pulley: buy finished product, main earth anchor steel rope and the steel pipe suspension centre steel rope of connecting, assembly pulley is divided into fixed (moving) pulley, mainly change direction and the laborsaving reduction winch load of inotropic action, day anchor and assembly pulley installation site are as shown in Figure 1, Figure 2, Figure 3 shows.
Earth anchor: adopt 3 * Φ 36mm screw-thread steel to enter rock 3m, after earth anchor installation, carry out mortar rockfill grouting and loaded test.Main work will be passed to a day anchor assembly pulley after steel wire rope of windlass pulling force guiding, and earth anchor installation site as shown in Figure 1 and Figure 2.
Tube coupling heavy 30t, high 2000mm, diameter 12500mm; The construction of unloading, overturn of lower flat section steel pipe transmission hole and diversion tunnel.
Turn-over method step following (referring to Fig. 1~Fig. 5) in the present embodiment super-large diameter penstock hole:
(1) first three groups of hoisting point positions of steel pipe transmission hole and steel pipe water leading cylinder infall are carried out to part and dig, dig height=steel pipe height+sky anchor height+steel rope, assembly pulley height+500mm.At three groups of hoisting point positions, three groups of sky anchors and assembly pulley are installed, take in steel pipe to be stood up and connect equilateral triangle opposite position as anchor installation site, three groups of skies, as shown in Figure 1, then below three groups of sky anchors, correspondence is installed three groups of earth anchors and winch, each is organized earth anchor and by steel rope, is linked to be integral body with corresponding winch and day anchor and assembly pulley respectively, three groups of sky anchors and assembly pulley lift by crane super-large diameter penstock jointly, 1# wherein, 2# days anchors and assembly pulley adherence pressure steel pipe height, 3# days anchors and assembly pulley are transferred steel pipe suspension centre height, until steel pipe complete stand up after after vertical state, dismantle 3# days anchor suspension centres, complete the construction of standing up of super-large diameter penstock.Diversion tunnel crown digs, and a day anchor, earth anchor, winch are installed, then by steel wire rope of windlass by earth anchor by the steel rope on sky anchor by required baudrier wear around.
(2) utilize flat truck by super-large diameter penstock by steel pipe transmission hole be transported to diversion tunnel crossover sites sky anchor under, the assembly pulley and the steel pipe that three groups of sky anchors are connected by steel wire rope of windlass are reliably fixed; Carry out steel pipe and unload and promote 3 groups of steel wire rope of windlass, slowly improve 1#, 2# winch and assembly pulley height, slowly below 3# winch and assembly pulley height, steel pipe is slowly tilted, until steel pipe, after vertical state, dismounting 3# winch and assembly pulley lifting, carry out penstock installation construction.
(3) all after penstock installations, removes 3# days anchors, winch, assembly pulley, reserved 1#, 2# days anchor, winch, assembly pulley gather together and save installation; Gather together after joint installation, successively each parts such as 1#, 2# days anchor, winch, assembly pulley are removed to recycle again.
Above-described embodiment is that foregoing of the present invention is further described, but this should be interpreted as to the scope of the above-mentioned theme of the present invention only limits to above-described embodiment.All technology realizing based on foregoing all belong to scope of the present invention.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410305926.1A CN104071720A (en) | 2014-07-01 | 2014-07-01 | In-tunnel turn-over method of super-large diameter penstock |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410305926.1A CN104071720A (en) | 2014-07-01 | 2014-07-01 | In-tunnel turn-over method of super-large diameter penstock |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104071720A true CN104071720A (en) | 2014-10-01 |
Family
ID=51593388
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410305926.1A CN104071720A (en) | 2014-07-01 | 2014-07-01 | In-tunnel turn-over method of super-large diameter penstock |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104071720A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104627879A (en) * | 2015-01-30 | 2015-05-20 | 中国葛洲坝集团股份有限公司 | Winch overhead anchor pulley hoisting system in underground cavern and simulation method of winch overhead anchor pulley hoisting system |
CN105645294A (en) * | 2015-12-30 | 2016-06-08 | 华北冶建工程建设有限公司 | Hoisting device for T-shaped stage or piston rack of Wiggins gas holder and formation method of T-shaped stage or piston rack of Wiggins gas holder |
CN106957007A (en) * | 2017-04-24 | 2017-07-18 | 中国葛洲坝集团第工程有限公司 | A kind of super-large diameter penstock equipment for supporting patient with burn and turn-over method |
CN107588233A (en) * | 2017-08-09 | 2018-01-16 | 中国水利水电第七工程局有限公司 | A kind of installation method of super large caliber penstock in inclined shaft lower horizontal section |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1601083A1 (en) * | 1988-05-25 | 1990-10-23 | Ленинградская лесотехническая академия им.С.М.Кирова | Hydraulic tackle block |
US7631854B1 (en) * | 2009-02-23 | 2009-12-15 | Andrew Mountain | Horizontal bicycle storage hoist |
CN201785162U (en) * | 2010-09-09 | 2011-04-06 | 中国十五冶金建设有限公司 | Pull pole hoist for arc gird |
CN202542770U (en) * | 2012-04-28 | 2012-11-21 | 中国葛洲坝集团股份有限公司 | Tube joint turning over device of pressure steel tube in hole chamber |
CN103277582A (en) * | 2013-05-15 | 2013-09-04 | 中国葛洲坝集团股份有限公司 | Method for mounting inclined shaft internal pressure steel tube |
CN103574158A (en) * | 2013-11-19 | 2014-02-12 | 葛洲坝集团第二工程有限公司 | Super-large diameter pressure steel tube inclined shaft three-hanging-point installation method |
-
2014
- 2014-07-01 CN CN201410305926.1A patent/CN104071720A/en not_active Application Discontinuation
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1601083A1 (en) * | 1988-05-25 | 1990-10-23 | Ленинградская лесотехническая академия им.С.М.Кирова | Hydraulic tackle block |
US7631854B1 (en) * | 2009-02-23 | 2009-12-15 | Andrew Mountain | Horizontal bicycle storage hoist |
CN201785162U (en) * | 2010-09-09 | 2011-04-06 | 中国十五冶金建设有限公司 | Pull pole hoist for arc gird |
CN202542770U (en) * | 2012-04-28 | 2012-11-21 | 中国葛洲坝集团股份有限公司 | Tube joint turning over device of pressure steel tube in hole chamber |
CN103277582A (en) * | 2013-05-15 | 2013-09-04 | 中国葛洲坝集团股份有限公司 | Method for mounting inclined shaft internal pressure steel tube |
CN103574158A (en) * | 2013-11-19 | 2014-02-12 | 葛洲坝集团第二工程有限公司 | Super-large diameter pressure steel tube inclined shaft three-hanging-point installation method |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104627879A (en) * | 2015-01-30 | 2015-05-20 | 中国葛洲坝集团股份有限公司 | Winch overhead anchor pulley hoisting system in underground cavern and simulation method of winch overhead anchor pulley hoisting system |
CN105645294A (en) * | 2015-12-30 | 2016-06-08 | 华北冶建工程建设有限公司 | Hoisting device for T-shaped stage or piston rack of Wiggins gas holder and formation method of T-shaped stage or piston rack of Wiggins gas holder |
CN106957007A (en) * | 2017-04-24 | 2017-07-18 | 中国葛洲坝集团第工程有限公司 | A kind of super-large diameter penstock equipment for supporting patient with burn and turn-over method |
CN107588233A (en) * | 2017-08-09 | 2018-01-16 | 中国水利水电第七工程局有限公司 | A kind of installation method of super large caliber penstock in inclined shaft lower horizontal section |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8584429B2 (en) | Tower erection system and method | |
CN102856841B (en) | The mechanical laying method of large-cross section aerial cable | |
CN103145051B (en) | Separated hoisting device of offshore wind turbine generator, and installation method | |
MX2010012068A (en) | Erection method for solar receiver and support tower. | |
CN102596790B (en) | Lightweight high-performance pipelayer | |
CN102109067B (en) | Inner punched pipe construction device and construction method of long-distance sleeve | |
CN105421859A (en) | Electricity grid telegraph pole erecting device and construction method | |
CN102464273B (en) | Offshore fan installing platform and fan integral installation rotary holding and lifting mechanism | |
CN102491162B (en) | Hoisting device and hoisting method | |
CN202358849U (en) | Small-size suspension crane | |
CN105019364B (en) | A kind of head tower slides vertical transfer method | |
CN102127899B (en) | System for lifting and sliding large-tonnage steel box girder in land area and shoal area and construction method thereof | |
CN201494438U (en) | Simple and fast installation cableway for maintenance and rush repair of mountain pipeline | |
CN101301981A (en) | Hoisting method | |
CN102561191A (en) | Integral lifting system and construction method for arch bridge ribs | |
CN203128112U (en) | Bi-directional traction stretchable lifting arm | |
CN204000830U (en) | Merogenesis take-over type sand drain machine | |
CN202689024U (en) | Loaded type movable combined steel-made foundation used for tower pole | |
CN105858435A (en) | Technology for hoisting strip-shaped inclined steel structures in place through single crane | |
CN101774511B (en) | Climbing type hoist and using method thereof | |
CN101487233B (en) | Mounting method for temporary pier top beam of large-span steel box girder stayed-cable bridge | |
CN205024717U (en) | Construction equipment of city utility tunnel immersed tube section | |
CN203959659U (en) | A kind of hook assembly and there is its hoisting crane | |
CN207451463U (en) | A kind of gate-type hoisting sling for being used in hard rock mole hole tear machine open | |
CN101670985B (en) | Electric transmission line iron tower erection tower crane with flexible base and flexible adhesion |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
C06 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
C10 | Entry into substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20141001 |
|
RJ01 | Rejection of invention patent application after publication |