CN104062190A - 一种新旧路面联结层材料的抗剪性能检测方法 - Google Patents

一种新旧路面联结层材料的抗剪性能检测方法 Download PDF

Info

Publication number
CN104062190A
CN104062190A CN201410159703.9A CN201410159703A CN104062190A CN 104062190 A CN104062190 A CN 104062190A CN 201410159703 A CN201410159703 A CN 201410159703A CN 104062190 A CN104062190 A CN 104062190A
Authority
CN
China
Prior art keywords
new
binder course
old pavement
composite samples
old
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410159703.9A
Other languages
English (en)
Other versions
CN104062190B (zh
Inventor
刘宁
徐占慧
刘强
杜海丽
蔺亚敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qinghai transportation planning and Design Institute Co., Ltd
Original Assignee
Highway Scientific Research Surveying And Designing Institute Of Qinghai Province
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Highway Scientific Research Surveying And Designing Institute Of Qinghai Province filed Critical Highway Scientific Research Surveying And Designing Institute Of Qinghai Province
Priority to CN201410159703.9A priority Critical patent/CN104062190B/zh
Publication of CN104062190A publication Critical patent/CN104062190A/zh
Application granted granted Critical
Publication of CN104062190B publication Critical patent/CN104062190B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Repair (AREA)
  • Road Paving Structures (AREA)

Abstract

一种新旧路面联结层材料抗剪性能检测方法,其涉及公路工程施工领域,其步骤为:第一步取芯样;第二步芯样清洗;第三步制备新旧路面联结层复合试件;第四步新旧路面复合试件保养;第五步准备试验;第六步试验机设置操作;第七步检测;本发明具有如下有益效果:本发明提出了更符合沥青路面整治过程中新旧沥青路面联结层材料的粘结力实际工作状态下的抗剪强度检测方法,利用本方法可以指导现场施工。

Description

一种新旧路面联结层材料的抗剪性能检测方法
一、技术领域
本发明涉及公路工程施工领域,具体涉及一种新旧路面联结层材料的抗剪性能检测方法。
二、技术背景
目前在沥青路面整治工程中,针对新旧路面联结层材料的抗剪性能检测方法没有统一的标准,包括试验检测方法及检测设备,并且应用在新旧沥青路面联结层进行剪切试验很少,现在剪切试验用的比较多的地方都在水泥混凝土桥面铺装中,而且都是采用直剪的方式,即复合试件进行水平剪切试验,其不能模拟实际沥青路面整治过程中新旧沥青路面联结层实际的工作状态,因为当车辆荷载作用在新的沥青路面上,进而会导致新旧沥青路面联结层产生相对剪切变形,而此时的最大剪应力应该是竖向正应力与水平方向应力的合力,而采用目前比较多的直剪试验则默认剪应力是水平方向,这与实际是相悖的。
目前针对沥青路面整治工程中没有新旧路面联结层材料抗剪强度的评定标准,导致室内试验无法指导现场施工。
三、发明内容
为解决上述技术问题,本发明采用如下技术方案:一种新旧路面联结层材料的抗剪性能检测方法,其检测步骤如下:第一步取芯样:利用路面钻芯机在旧沥青路面同一断面处钻取直径为150mm,厚度为50mm芯样四个,用切割机将芯样上层面层切出新鲜面,放置室温条件下24h,室内保持干燥、通风;
第二步芯样清洗:取出第一步中制备的试样,待其表面风干后,用打磨机将旧路面芯样表面灰尘、杂物清理干净,并使其表面石料出现裸露部分;
第三步制备新旧路面联结层复合试件:取第二步中的芯样并排放置在车辙板中,在芯样上部铺设联结层材料,并用碾锤进行碾压3~4遍,放置室内养护48h,然后再试件表面铺设40mm厚度的新沥青路面,并用车辙板试模成型仪成型,养护,制成新旧路面联结层复合试件,并在室温下保持24小时,最后用钻芯机在新旧路面联结层复合试件钻取直径为100mm的圆柱复合试件;车辙板试模尺寸为300mm×300mm×100mm;联结层材料为集料、水泥、乳化沥青和水组成的混合料,其比例相应为:100:2:9:10.5,其中集料为石灰岩,由0~3mm和3~ 5mm两档粒径规格组成,相应比例分别为76:24,联结层铺筑的厚度为6mm;
第四步新旧路面联结层复合试件保养:将风干、干燥的新旧路面联结层复合试件(5)放在恒温箱中,待新旧路面复合试件(5)温度达到恒温箱设定温度;
第五步准备试验:将第四步中新旧路面联结层复合试件(5)放置斜剪试模(2)上,调节复合试件高度,使新旧路面复合试件(5)的层间略高于斜剪试模(2),斜剪试模(2)倾斜角度为45°,盖上压头(4),调整压头(4)使其与斜剪试模(2)形成平行状态;
第六步试验机设置操作:打开沥青混合料材料性能试验机进入操作系统,设置运行速度为50mm/min;
第七步检测:启动沥青混合料材料性能试验机进入加载程序,直至新旧路面联结层复合试件(5)破坏,记录新旧路面联结层复合试件(5)破坏时最大荷载,取新旧路面联结层复合试件(5)破坏的算术平均值作为新旧路面联结层材料的抗剪性能试验结果。
本发明的数据计算及处理方法:
沥青路面整治工程中,新旧沥青路面联结层材料的抗剪强度试验结果计算方法为:R∠45°=P/A (式1)其中,式1中R∠45°为新旧路面联结层抗剪强度,单位为MPa;本试验中,采用斜剪更符合实际工况,应为当车辆行驶在路面上时,会导致新旧沥青路面联结层产生相对剪切变形,而此时的最大剪应力应该是竖向正应力与水平方向应力的合力,所以采取斜剪试验更符合新旧复合路面过车时的实际应力,P为试件达到破坏时的最大压力,单位为N;A为试件的截面积,单位为mm2;A=πD2/4,D为新旧路面联结层复合试件的直径,单位为mm。
取四个复合试件的算术平均值作为联结层材料抗剪性能的试验结果。
数据的处理方法:对于同一断面进行抗剪性能评价是指在同一断面处取3个芯样,测出三个芯样的抗剪强度值,试验结果为保留小数点后两位,三组数据的变异系数要小于20%,最终取平均值,若三组数据的变异系数大于或等于20%,则需要补做试验。
本发明具有如下有益效果:本发明提出了更符合沥青路面整治过程中新旧沥青路面联结层实际工作状态下的抗剪强度检测方法,利用本方法可以指导现场施工。
四、附图说明
图1为本发明局部放大图
图中:1、底座 2、斜剪试模 3、压力柱 4、压头 5、新旧路面复合试件
五、具体实施方式
实施例1:一种新旧路面联结层材料的抗剪性能检测方法,其检测步骤如下:第一步取芯样:利用路面钻芯机在旧沥青路面同一断面处钻取直径为150mm,厚度为50mm芯样四个,用切割机将芯样上层面层切出新鲜面,放置室温条件下24h,室内保持干燥、通风;
第二步芯样清洗:取出第一步中制备的试样,待其表面风干后,用打磨机将旧路面芯样表面灰尘、杂物清理干净,并使其表面石料出现裸露部分;
第三步制备新旧路面联结层复合试件:取第二步中的芯样并排放置在车辙板中,在芯样上部铺设联结层材料,并用碾锤进行碾压4遍,放置室内养护48h,然后再试件表面铺设40mm厚度的新沥青路面,并用车辙板试模成型仪成型,养护,制成新旧路面联结层复合试件,并在室温下保持24小时,最后用钻芯机在新旧路面联结层复合试件钻取直径为100mm的圆柱复合试件;车辙板试模尺寸为300mm×300mm×100mm;联结层材料为集料、水泥、乳化沥青和水组成的混合料,其比例相应为:100:2:9:10.5,其中集料为石灰岩,由3mm和5mm两档粒径规格组成,相应比例分别为76:24,联结层铺筑的厚度为6mm;
第四步新旧路面联结层复合试件保养:将风干、干燥的新旧路面联结层复合试件(5)放在恒温箱中,待新旧路面复合试件(5)温度达到恒温箱设定温度;
第五步准备试验:将第四步中新旧路面联结层复合试件(5)放置斜剪试模(2)上,调节复合试件高度,使新旧路面复合试件(5)的层间略高于斜剪试模(2),斜剪试模(2)倾斜角度为45°,盖上压头(4),调整压头(4)使其与斜剪试模(2)形成平行状态;
第六步试验机设置操作:打开沥青混合料材料性能试验机进入操作系统,设置运行速度为50mm/min;
第七步检测:启动沥青混合料材料性能试验机进入加载程序,直至新旧路面联结层复合试件(5)破坏,记录新旧路面联结层复合试件(5)破坏时最大荷载,取新旧路面联结层复合试件(5)破坏的算术平均值作为新旧路面联结层材料的抗剪性能试验结果。

Claims (1)

1.一种新旧路面联结层材料的抗剪性能检测方法,其试验步骤如下:第一步取芯样:利用路面钻芯机在旧沥青路面同一断面处钻取直径为150mm,厚度为50mm芯样四个,用切割机将芯样上层面层切出新鲜面,放置室温条件下24h,室内保持干燥、通风;
第二步芯样清洗:取出第一步中制备的试样,待其表面风干后,用打磨机将旧路面芯样表面灰尘、杂物清理干净,并使其表面石料出现裸露部分;
第三步制备新旧路面联结层复合试件:取第二步中的芯样并排放置在车辙板中,在芯样上部铺设联结层材料,并用碾锤进行碾压3~4遍,放置室内养护48h,然后再试件表面铺设40mm厚度的新沥青路面,并用车辙板试模成型仪成型,养护,制成新旧路面联结层复合试件,并在室温下保持24小时,最后用钻芯机在新旧路面联结层复合试件钻取直径为100mm的圆柱复合试件;车辙板试模尺寸为300mm×300mm×100mm;联结层材料为集料、水泥、乳化沥青和水组成的混合料,其比例相应为:100:2:9:10.5,其中集料为石灰岩,由0~3mm和3~ 5mm两档粒径规格组成,相应比例分别为76:24,联结层铺筑的厚度为6mm;
第四步新旧路面联结层复合试件保养:将风干、干燥的新旧路面联结层复合试件(5)放在恒温箱中,待新旧路面复合试件(5)温度达到恒温箱设定温度;
第五步准备试验:将第四步中新旧路面联结层复合试件(5)放置斜剪试模(2)上,调节复合试件高度,使新旧路面复合试件(5)的层间略高于斜剪试模(2),斜剪试模(2)倾斜角度为45°,盖上压头(4),调整压头(4)使其与斜剪试模(2)形成平行状态;
第六步试验机设置操作:打开沥青混合料材料性能试验机进入操作系统,设置运行速度为50mm/min;
第七步检测:启动沥青混合料材料性能试验机进入加载程序,直至新旧路面联结层复合试件(5)破坏,记录新旧路面联结层复合试件(5)破坏时最大荷载,取新旧路面联结层复合试件(5)破坏的算术平均值作为新旧路面联结层材料的抗剪性能试验结果。
CN201410159703.9A 2014-04-21 2014-04-21 一种新旧路面联结层材料的抗剪性能检测方法 Active CN104062190B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410159703.9A CN104062190B (zh) 2014-04-21 2014-04-21 一种新旧路面联结层材料的抗剪性能检测方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410159703.9A CN104062190B (zh) 2014-04-21 2014-04-21 一种新旧路面联结层材料的抗剪性能检测方法

Publications (2)

Publication Number Publication Date
CN104062190A true CN104062190A (zh) 2014-09-24
CN104062190B CN104062190B (zh) 2017-02-22

Family

ID=51550005

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410159703.9A Active CN104062190B (zh) 2014-04-21 2014-04-21 一种新旧路面联结层材料的抗剪性能检测方法

Country Status (1)

Country Link
CN (1) CN104062190B (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104237028A (zh) * 2014-09-30 2014-12-24 合肥工业大学 一种路面结构层间剪切强度测试仪
CN104458432A (zh) * 2014-11-21 2015-03-25 长安大学 一种沥青混合料颗粒性区域确定及影响因素评价方法
CN107831070A (zh) * 2017-12-04 2018-03-23 长沙理工大学 一种复合式路面结构强度及疲劳的压剪测试装置
CN108240965A (zh) * 2017-12-06 2018-07-03 江西省高速公路投资集团有限责任公司 一种沥青路面层间粘结强度检测装置及其检测方法
CN109580396A (zh) * 2018-11-28 2019-04-05 南京林业大学 一种沥青路面表面层荷载疲劳损伤程度的测试方法
CN110542618A (zh) * 2019-09-11 2019-12-06 东南大学 乳化沥青表面处治层层间抗剪强度直剪试验方法
CN113075059A (zh) * 2021-02-26 2021-07-06 银川通达工程技术有限公司 一种新旧路面联结层材料的抗剪性能检测方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2330431A1 (en) * 2001-01-08 2002-07-08 Stephen Norman Goodman In situ shear strength test facility
JP2003129414A (ja) * 2001-10-23 2003-05-08 Taiheiyo Cement Corp 交通開放時期の判断方法
CN101598649A (zh) * 2008-12-22 2009-12-09 长沙理工大学 铺面结构层间界面剪切仪
CN101620054A (zh) * 2009-07-03 2010-01-06 张磊 路面结构及桥面铺装粘结界面抗剪特性的测试装置
CN101995357A (zh) * 2010-11-02 2011-03-30 东南大学 层间抗剪应力状态测试方法
CN102507340A (zh) * 2011-10-21 2012-06-20 同济大学 复合式铺装体系层间剪切强度参数测定方法
CN102519808A (zh) * 2011-12-26 2012-06-27 长沙理工大学 一种复合式沥青路面层间剪切疲劳测试的装置及方法
CN103233405A (zh) * 2013-05-17 2013-08-07 江苏省交通科学研究院股份有限公司 一种新旧沥青路面联结层及其应用

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2330431A1 (en) * 2001-01-08 2002-07-08 Stephen Norman Goodman In situ shear strength test facility
JP2003129414A (ja) * 2001-10-23 2003-05-08 Taiheiyo Cement Corp 交通開放時期の判断方法
CN101598649A (zh) * 2008-12-22 2009-12-09 长沙理工大学 铺面结构层间界面剪切仪
CN101620054A (zh) * 2009-07-03 2010-01-06 张磊 路面结构及桥面铺装粘结界面抗剪特性的测试装置
CN101995357A (zh) * 2010-11-02 2011-03-30 东南大学 层间抗剪应力状态测试方法
CN102507340A (zh) * 2011-10-21 2012-06-20 同济大学 复合式铺装体系层间剪切强度参数测定方法
CN102519808A (zh) * 2011-12-26 2012-06-27 长沙理工大学 一种复合式沥青路面层间剪切疲劳测试的装置及方法
CN103233405A (zh) * 2013-05-17 2013-08-07 江苏省交通科学研究院股份有限公司 一种新旧沥青路面联结层及其应用

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
汪水银: "《室内沥青混凝土路面层间抗剪强度试验方法研究》", 《公路》, no. 2, 28 February 2010 (2010-02-28), pages 144 - 147 *
王联芳: "《双层摊铺路面抗剪性能的研究》", 《公路与汽运》, no. 4, 31 July 2010 (2010-07-31), pages 82 - 85 *
郑智能 等: "《应力吸收层力学特性对比试验研究》", 《西华大学学报(自然科学版)》, vol. 29, no. 5, 30 September 2010 (2010-09-30), pages 71 - 74 *
郭扬 等: "《采用纤维沥青混凝土加铺层的路面层间抗剪性能》", 《大连海事大学学报》, vol. 38, no. 3, 31 August 2012 (2012-08-31), pages 117 - 120 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104237028A (zh) * 2014-09-30 2014-12-24 合肥工业大学 一种路面结构层间剪切强度测试仪
CN104458432A (zh) * 2014-11-21 2015-03-25 长安大学 一种沥青混合料颗粒性区域确定及影响因素评价方法
CN104458432B (zh) * 2014-11-21 2017-02-01 长安大学 一种沥青混合料颗粒性区域确定及影响因素评价方法
CN107831070A (zh) * 2017-12-04 2018-03-23 长沙理工大学 一种复合式路面结构强度及疲劳的压剪测试装置
CN107831070B (zh) * 2017-12-04 2024-04-09 长沙理工大学 一种复合式路面结构强度及疲劳的压剪测试装置
CN108240965A (zh) * 2017-12-06 2018-07-03 江西省高速公路投资集团有限责任公司 一种沥青路面层间粘结强度检测装置及其检测方法
CN109580396A (zh) * 2018-11-28 2019-04-05 南京林业大学 一种沥青路面表面层荷载疲劳损伤程度的测试方法
CN110542618A (zh) * 2019-09-11 2019-12-06 东南大学 乳化沥青表面处治层层间抗剪强度直剪试验方法
CN113075059A (zh) * 2021-02-26 2021-07-06 银川通达工程技术有限公司 一种新旧路面联结层材料的抗剪性能检测方法

Also Published As

Publication number Publication date
CN104062190B (zh) 2017-02-22

Similar Documents

Publication Publication Date Title
CN104062190A (zh) 一种新旧路面联结层材料的抗剪性能检测方法
Wang et al. Application of tack coat in pavement engineering
Li et al. Evaluating the rutting resistance of asphalt mixtures using an advanced repeated load permanent deformation test under field conditions
Shafabakhsh et al. Investigation of dynamic behavior of hot mix asphalt containing waste materials; case study: Glass cullet
Zhu et al. Evaluating the rutting resistance of asphalt mixtures using a simplified triaxial repeated load test
Ling et al. A calibrated mechanics-based model for top-down cracking of asphalt pavements
Xu et al. Evaluation of permanent deformation of asphalt mixtures using different laboratory performance tests
Fallah et al. Reinforcing overlay to reduce reflection cracking; an experimental investigation
CN102746822B (zh) 一种高分子沥青基防水粘结材料及其制备工艺、施工工艺
Rajan et al. Rutting resistance evaluation of highly polymer-modified asphalt binder and mixes using different performance parameters
Al-Qadi et al. Best Practices for Implementation of Tack Coat: Part 2, Field Study
Ogundipe Mechanical behaviour of stress absorbing membrane interlayers
Jaskula et al. Optimisation and field assessment of poroelastic wearing course bond quality
Liu et al. Predicting the performance of the induction healing porous asphalt test section
Ahmed Fracture characterization of thin bonded asphalt concrete overlay systems
Tran et al. Effectiveness of heavier tack coat on field performance of open-graded friction course
Swarna et al. Effect of interface bonds on pavement performance
CN104062179A (zh) 一种道路刚柔层间接触面最佳拉毛工艺参数确定方法
Davidson et al. Best practices in cold in-place recycling
Ortiz Cold in-place recycling mix design, in-place density, and long-term performance in Nevada
Chan et al. Exploring sustainable pavement rehabilitation: Cold in-place recycling with expanded asphalt mix
Chen et al. Effects of polymer modified asphalt emulsion (PMAE) on pavement reflective cracking performance
Francesconi et al. Fast falling weight deflectometer as new tool to perform accelerated pavement testing
Neogi et al. A review work on high frequency induction curing of porous asphalt concrete
Artamendi et al. Resurfacing of the queen elizabeth ii bridge: Binder selection and evaluation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 810001 No. 68, 54 Avenue, Chengxi District, Qinghai City, Xining Province

Patentee after: Qinghai transportation planning and Design Institute Co., Ltd

Address before: 810000 No. 68, 54 Avenue, Chengxi District, Qinghai City, Xining Province

Patentee before: HIGHWAY SURVEY AND DESIGN INSTITUTE OF QINGHAI PROVINCE