CN104002931B - U型海洋工程安装船及导管架上部模块安装方法 - Google Patents

U型海洋工程安装船及导管架上部模块安装方法 Download PDF

Info

Publication number
CN104002931B
CN104002931B CN201410192495.2A CN201410192495A CN104002931B CN 104002931 B CN104002931 B CN 104002931B CN 201410192495 A CN201410192495 A CN 201410192495A CN 104002931 B CN104002931 B CN 104002931B
Authority
CN
China
Prior art keywords
catheterostat
ship
upper module
ocean engineering
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410192495.2A
Other languages
English (en)
Other versions
CN104002931A (zh
Inventor
唐友刚
刘旭平
张少洋
张若瑜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN201410192495.2A priority Critical patent/CN104002931B/zh
Publication of CN104002931A publication Critical patent/CN104002931A/zh
Application granted granted Critical
Publication of CN104002931B publication Critical patent/CN104002931B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明属于海洋工程技术领域,涉及一种“U”型海洋工程安装船,用于导管架上部模块的安装,所述的安装船的船体(1)包括船尾U型槽部分(2)和船艏船舯部分(3),在船体(1)的甲板上设置贯通船体(1)首尾的滑轨(4),在船尾“U”型槽部分(2)内侧固定有护舷装置(5)。本发明同时涉及一种使用所述的安装船实现的导管架上部模块安装方法。本发明的安装船稳性好,抗风浪能力强,适用于导管架大型组块的外浮拖安装。

Description

U型海洋工程安装船及导管架上部模块安装方法
所属技术领域
本发明属于海洋工程技术领域,涉及一种海洋工程安装船。
背景技术
目前对导管架上部模块的安装有两种方式:浮吊法和内浮拖法。采用浮吊法的起重船起重能力一般在7500吨以下,对于重量超过起重能力的组块需要采用分块吊装的方法进行安装,这大大增加了海上施工的工作量与项目协调的困难;内浮拖法采用“T”型安装船进行组块安装,该方法可以在一定程度上解决起重船起重能力不足的问题,但内浮拖法限制了船宽的尺度,实施内插法的安装船首部宽度变小,以便使船首插入导管架主导管之间进行组块安装,该种船型的主要不足是,抗风浪能力差,尤其遇到长周期涌浪情况,该船运动剧烈运动幅值大,难以实施海上安装,组块安装过程风险大,对可施工的环境条件提出了更高的要求,作业气象窗口选择困难。
发明内容
本发明的目的是为导管架平台大型组块的安装提供一种新型安装船,该船型耐波性能优越,抵抗风、浪、流能力强,可以满足在海洋环境下安装大型导管架组块的需求。本发明同时提供此种安装船的使用方法。本发明的技术方案如下:
一种“U”型海洋工程安装船,用于导管架组件的安装,所述的安装船的船体(1)包括船尾U型槽部分(2)和船艏船舯部分(3),在船体(1)的甲板上设置贯通船体(1)首尾的滑轨(4),在船尾“U”型槽部分(2)内侧固定有护舷装置(5)。
本发明同时给出一种使用权利要求(1)所述的安装船实现的导管架上部模块安装方法,其特征在于,包括步骤:
1)将导管架上部模块(6)通过牵引装置从“U”型海洋工程安装船的船首沿滑轨(4)转移到安装船上,转移过程通过调载系统实时调整船体的浮态,将上部模块(6)转移到船尾U型槽口部分(2)固定。
2)“U”型海洋工程安装船依靠拖轮拖带到指定安装地点,在安装地点使用系泊缆系泊定位,控制“U”型海洋工程安装船的移动,使“U”型海洋工程安装船的船尾U型槽口部分(2)逐渐围住导管架(7),最终在上部模块(6)插尖与导管架(7)的桩腿对齐的时候,完成上部模块(6)的定位,之后压载系统增加压载水,同时配合水位的下降,使上部模块(6)逐渐下降,插尖与桩腿对接,完成上部模块(6)从“U”型海洋工程安装船到导管架(7)的重量转移。
(3)上部模块(6)与导管架(7)桩腿对接完成后,“U”型海洋工程安装船从导管架(7)退出。
本发明的突出优点是:
1、本发明的新型海洋工程安装船,船体尾部开“U”型槽口,船型稳性好,抗风浪能力强,安装过程中“U”型船槽口围住导管架,实现上部模块的安装;
2、“U”型船的船宽不受导管架桩腿间距的限制,这样不仅可以运载更大的组块,而且提高了安装船的耐波性;
3、“U”型开口内侧布置护舷,可以缓冲因偶然因素造成的安装船运动过大对导管架桩腿的碰撞。
附图说明
图1为本发明的“U”型海洋工程安装船的俯视图;
图2为本发明的“U”型海洋工程安装船运载上部模块与导管架对接示意图。
图中:1、“U”型安装船,2、船尾“U”型槽口,3、船艏船舯部分,4、滑轨,5、槽口护舷,6、上部模块,7、导管架。
具体实施方式
下面结合附图和实施例对本发明作进行详细描述。
图1所示为本发明的“U”型海洋工程安装船,“U”型安装船船体1包括船尾U型槽部分2和船艏船舯部分3,在船体1的甲板上设置贯通安装船1首尾的滑轨4,在船尾“U”型槽2内侧安装护舷装置5。
该“U”型海洋工程安装船为大型平台上部组块的安装提供一种新的外浮拖安装形式。参见图2其安装过程如下:
1、平台上部模块6在码头通过牵引装置从“U”型安装船1的船首沿滑轨4转移到安装船上,转移过程通过调载系统实时调整船体的浮态,最终将上部模块6转移到船尾“U”型槽口2部分固定。
2、“U”型安装船1依靠拖轮拖带到指定安装地点,在安装地点使用系泊缆系泊定位。通过安装船1上的锚绞车绞动锚缆控制安装船的小范围移动,使安装船1的船尾“U”型槽口2逐渐夹住导管架7,最终在上部模块6插尖与导管架7的桩腿对齐的时候,完成上部模块6的定位,之后压载系统增加压载水,同时配合潮汐水位的下降,使上部模块6逐渐下降,插尖与桩腿对接,完成上部模块6从安装船1到导管架7的重量转移。
3、上部模块6与导管架7桩腿对接完成后,“U”型安装船1从导管架7退出。
本发明开发的新型安装船,具有如下的技术特点:
1、本发明包括尾部开槽的“U”型船体,“U”型开口内侧护舷装置,甲板滑轨,设有压载水调载系统,调整船舶不同作业工况的浮态;
2、“U”型船开口宽度根据导管架桩腿间距确定,同时考虑桩腿直径、“U”型开口内侧护舷布置,及一定的工作间隙;开口长度根据上部模块的最大长度确定。
3、“U”型开口内侧护舷装置可以用来防止安装船与导管架桩腿碰撞造成的对导管架的损伤;
4、甲板上设置用以转移组块的滑轨,滑轨间距可以根据上部模块的宽度进行调整。
5、“U”型船设压载调载系统,在模块从码头装船的过程中,调载系统可以实时调整船体在模块转移过程中的浮态;在上部模块安装过程中增加压载水,同时配合潮汐水位降落,调整降低船的吃水,上部模块转移到导管架上面,完成由安装船到导管架的重量转移,实现上部模块的安装。
尽管上面结合附图对本发明的优选实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,并不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围情况下,还可以做出很多形式,这些均属于本发明的保护范围之内。

Claims (1)

1.一种U型海洋工程安装船导管架上部模块安装方法,所采用的安装船的船体(1)包括船尾U型槽部分(2)和船艏船舯部分(3),在船体(1)的甲板上设置贯通船体(1)首尾的滑轨(4),在船尾U型槽部分(2)内侧固定有护舷装置(5);船尾U型槽部分(2)开口宽度根据导管架桩腿间距确定,开口长度根据导管架上部模块的最大长度确定;安装方法如下:
1)将导管架上部模块(6)通过牵引装置从U型海洋工程安装船的船首沿滑轨(4)转移到安装船上,转移过程通过调载系统实时调整船体的浮态,将上部模块(6)转移到船尾U型槽口部分(2)固定;
2)U型海洋工程安装船依靠拖轮拖带到指定安装地点,在安装地点使用系泊缆系泊定位,控制U型海洋工程安装船的移动,使U型海洋工程安装船的船尾U型槽口部分(2)逐渐围住导管架(7),最终在上部模块(6)插尖与导管架(7)的桩腿对齐的时候,完成上部模块(6)的定位,之后压载系统增加压载水,同时配合水位的下降,使上部模块(6)逐渐下降,插尖与桩腿对接,完成上部模块(6)从U型海洋工程安装船到导管架(7)的重量转移;
3)上部模块(6)与导管架(7)桩腿对接完成后,U型海洋工程安装船从导管架(7)退出。
CN201410192495.2A 2014-05-08 2014-05-08 U型海洋工程安装船及导管架上部模块安装方法 Expired - Fee Related CN104002931B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410192495.2A CN104002931B (zh) 2014-05-08 2014-05-08 U型海洋工程安装船及导管架上部模块安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410192495.2A CN104002931B (zh) 2014-05-08 2014-05-08 U型海洋工程安装船及导管架上部模块安装方法

Publications (2)

Publication Number Publication Date
CN104002931A CN104002931A (zh) 2014-08-27
CN104002931B true CN104002931B (zh) 2016-06-29

Family

ID=51363896

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410192495.2A Expired - Fee Related CN104002931B (zh) 2014-05-08 2014-05-08 U型海洋工程安装船及导管架上部模块安装方法

Country Status (1)

Country Link
CN (1) CN104002931B (zh)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104743058B (zh) * 2015-03-24 2017-03-29 中国海洋石油总公司 张力腿平台上部组块浮托安装的方法
CN106741609A (zh) * 2016-12-16 2017-05-31 中国海洋石油总公司 大型海洋结构物的组块动力定位浮托安装工艺
CN111762281A (zh) * 2020-05-29 2020-10-13 中远海运特种运输股份有限公司 一种基于半潜式多功能运输拆装船的整体拆除系统及其作业方法
CN112874722B (zh) * 2021-01-06 2023-02-28 海洋石油工程股份有限公司 一种半潜平台船体与组块对接合拢方法

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BRPI0718975A2 (pt) * 2006-11-22 2014-02-04 Technip France Estrutura de transporte, de instalação e de desmantelamento de uma ponte de uma plataforma petrolífera de exploração no mar e processos de transporte e de instalação de uma ponte de uma plataforma petrolífera até um sítio de exploração e de desmantelamento e de transporte de uma ponte de uma plataforma petrolífera de um sítio de exploração até um elemento de transporte por flutuação
CN102213085A (zh) * 2010-04-09 2011-10-12 中国海洋石油总公司 导管架立管的安装方法
CN102206938A (zh) * 2010-10-13 2011-10-05 天津市海王星海上工程技术有限公司 一种新的海上平台上部组块安装方法
CN201999177U (zh) * 2011-01-21 2011-10-05 中国海洋石油总公司 一种超大型浮托安装驳船
CN202007400U (zh) * 2011-03-31 2011-10-12 三一电气有限责任公司 一种用于导管架施工的海上基础施工平台

Also Published As

Publication number Publication date
CN104002931A (zh) 2014-08-27

Similar Documents

Publication Publication Date Title
CN106114762B (zh) 浅水浮式平台系泊装置及方法
CN201406013Y (zh) 一种具有定位调节防撞功能的海上浮体
CN104002931B (zh) U型海洋工程安装船及导管架上部模块安装方法
RU2008150487A (ru) Система для загрузки и разгрузки углеводородов в водах, предрасположенных к образованию льда
CN101793017B (zh) 自适应船舶拦截方法
CN103661801B (zh) 海洋工程水下推进器的安装辅助系统及安装方法
US20200164947A1 (en) Vessel having an improved hull shape
CN104590497A (zh) Fpso船
WO2007097610A1 (en) Semi-submersible vessel, method for operating a semi-submersible vessel and method for manufacturing a semi-submersible vessel
CN102114899A (zh) 一种超大型浮托安装驳船及其设计方法
CN201620377U (zh) 自适应船舶拦截系统
CN201999177U (zh) 一种超大型浮托安装驳船
CN107618626A (zh) 改进的深水半潜式铺管起重船
CN104600652B (zh) 基于锚泊系统和动力定位的浅海海缆敷设工艺
CN107187554A (zh) 用于半潜式钻井平台干拖运输的双体半潜驳船及作业方法
NL2009028C2 (en) Off-shore installation vessel, method of operating an off-shore installation vessel.
CN108583811B (zh) 一种浮运方法
CN103603319A (zh) 一种恒阻力防撞锚链
CN209535406U (zh) 组合型拉锚可调节式水上飞机安全靠泊浮码头
CN105059484A (zh) 一种大型海洋结构物的上下船作业方式
KR20150104734A (ko) 도르래를 이용한 선박 계류장치
CN205891166U (zh) 一种可代替缆绳兼具护舷功能的智能化轻型系靠泊系统
CN104590480A (zh) 超u型水线的三艏侧推低阻船体
CN205737992U (zh) 一种flng船舶的逃生梯
CN203094382U (zh) Fpso码头系泊缆接分布结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160629

Termination date: 20210508