CN103953352B - Rapid station-passing and turning construction method for long-distance shield tunneling machine of closed station - Google Patents

Rapid station-passing and turning construction method for long-distance shield tunneling machine of closed station Download PDF

Info

Publication number
CN103953352B
CN103953352B CN201410159620.XA CN201410159620A CN103953352B CN 103953352 B CN103953352 B CN 103953352B CN 201410159620 A CN201410159620 A CN 201410159620A CN 103953352 B CN103953352 B CN 103953352B
Authority
CN
China
Prior art keywords
stop
shield machine
dolly
misses
shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410159620.XA
Other languages
Chinese (zh)
Other versions
CN103953352A (en
Inventor
李光强
李波
马海强
王国正
王宇
何敏
王超群
罗辉平
袁森
朱自强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Second Engineering Co Ltd of CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Second Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group, Second Engineering Co Ltd of CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201410159620.XA priority Critical patent/CN103953352B/en
Publication of CN103953352A publication Critical patent/CN103953352A/en
Application granted granted Critical
Publication of CN103953352B publication Critical patent/CN103953352B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a quick turning construction method for a shield machine in a long distance of a closed station, which mainly utilizes a turning trolley which can move along a track to be fixedly connected with the shield machine through a jack, then pushes the shield machine to a preset turning position, and then utilizes a hydraulic jack to carry out angle rotation and translation on the shield machine and the turning trolley until turning is finished.

Description

Closed station long-distance shield structure machine misses the stop tune construction method fast
Technical field
The present invention relates to shield machine technical field of construction, particularly a kind of Closed station long-distance shield structure misses the stop tune construction method fast.
Background technology
Along with China's expanding economy, urban rail transit engineering all at construction city track traffic engineering, is built, station many employings cut and cover tunneling in each main cities in city, and the interval shield structure that adopts sends out construction more; City Subway Station is generally all first built complete, for shield structure provides place; In city, subway construction is often owing to limiting by orographic condition, be reduce cost of investment, between two stations, interval generally can adopt a shield machine to complete construction task, just need shield machine AT STATION in carry out translation tune.It is interval that my company is responsible for construction Chengdu subway No. 4 Federation of Literary and Art Circles of line first stage of the project civil engineering 7 bid section province station ~ beautiful two-way station shield structures, left line total length 990.637m, right line total length 1310.134m, wherein Federation of Literary and Art Circles of province station ~ beautiful two-way station shield structure running tunnel 18# shield machine (extra large Rake) shield machine working shaft to the west of beautiful dual station is tunneled by Federation of Literary and Art Circles of left alignment province station after going into the well, arrive and close shaping Federation of Literary and Art Circles of province station stop line, stop line center line need be moved to, and the 254.3m that misses the stop in stop line station, province's connection station, after reverse end for end at Federation of Literary and Art Circles of province station the east head, again move to right line, last being started to direction, beautiful two-way station by right line secondary is tunneled, to the west of the beautiful two-way station of final arrival after shield machine working shaft, move to left line, reserve shield structure hole by left line again to hang out.
Miss the stop tune as adopted conventional " jacking propelling " method for this shield structure, and shield structure haul distance is long, and progress is slow, long in time limit, and costly, shield machine weight is large, and lifting operation security risk is very big, and narrow space, transport of materials inconvenience, personnel labor intensity is large.
Summary of the invention
Goal of the invention of the present invention is the shortcoming in order to overcome above-mentioned background technology, there is provided a kind of security risk low, shield machine need not be disassembled, and guarantees the globality of shield machine, and the Closed station long-distance shield structure making shield structure can complete connection fast misses the stop tune construction method fast.
Technical scheme of the present invention is: a kind of Closed station long-distance shield structure machine misses the stop tune construction method fast, and the method comprises the steps:
The first step: equipment and materials prepares;
1, adopt shaped steel to add section chief 8200mm, wide 3960mm can along the dolly that misses the stop of rail moving;
2, clear up base plate, lay steel plate in base surface, these steel plate length, width and height are respectively 6280*2000*20mm, and steel plate adopts expansion bolt and base plate to fix, and the dolly that will miss the stop is arranged on steel plate along designed lines center line, and firm with Plate Welding;
Second step: shield machine is connected and fixed and position translation with the dolly that misses the stop;
After shield machine is appeared, the jack of shield machine self is utilized to provide counter-force, being pushed into by shield machine misses the stop on the track of dolly, then shield machine slowly moves missing the stop on trolley track, shield machine fltting speed controls at 20mm/s, when whole shield machine is all positioned on the dolly that misses the stop, after its shield machine screw machine is all positioned at station structure, after shield machine and screw machine possess transverse translation condition, shield machine and the dolly that misses the stop are fixed, to be missed the stop dolly and base plate steel plate constraint release simultaneously, adopt two 100t jack, to miss the stop dolly and shield machine overall by the left line translation 1290mm of design to missing the stop on center line,
3rd step: promote shield machine to predetermined tune position;
Along missing the stop track laying 43# rail, track adopts 10# channel-section steel to fix, and adopts rail clamping device grip track at shield machine rear, two 50t jack are utilized to provide counter-force, miss the stop dolly and shield machine of promotion moves forward along track, and translational speed 80m/d, is advanced into predetermined tune position by shield machine;
4th step: shield machine and dolly first time integral-rotation translation of missing the stop;
After shield machine and the dolly that misses the stop arrive precalculated position, utilize hydraulic jack that shield machine and dolly entirety of missing the stop are turned clockwise 30 ° along A point, and then shifted forward 3000mm;
5th step: shield machine and dolly second time integral-rotation translation of missing the stop;
After shield machine and the dolly first step of missing the stop select translation to put in place, 11.5 ° are rotated counterclockwise again to send out right side B point before cutterhead, and then shield machine and the dolly that misses the stop are rotated counterclockwise 48.5 ° with shield tail C point, by shield machine and trolley translation of missing the stop to horizontal path direction;
6th step: shield machine and dolly third time integral-rotation translation of missing the stop;
Again the shield machine and the dolly that misses the stop that rotate translation are rotated counterclockwise 70 ° along cutter head of shield machine left forward side D point, simultaneously shifted forward 550mm; Again shield machine and the dolly that misses the stop are rotated counterclockwise 12.5 ° along E point on the left of cutterhead, shield machine screw machine staggers after the steel pipe column of station, again shield machine and the dolly that misses the stop are rotated counterclockwise 7.5 ° again with F point on the right side of cutterhead, shield machine and the dolly that misses the stop are moved to together on the right line center line of design, and translation makes cutterhead distance portal 620mm.
Need to carry out repetition measurement to station floor level before construction, then adjust shield machine export & import actual elevation.
Described shield machine main body and the dolly that misses the stop utilize wire rope fixed strain respectively before, during and after shield body, the diverse location spot welding simultaneously contacted with the dolly that misses the stop at shield shell is fixed, again miss the stop dolly and base plate steel plate are welded together, to guarantee shield body and the dolly that misses the stop, bottom steel plate relative movement do not occur.
The invention has the beneficial effects as follows: adopt the method can safely, economy, carry out fast, the construction period is short, and cost is low, human users is convenient, compare conventional construction method, the duration is short, and cost is low, operating equipment is few, operating personnel is few, operation intensity is low, and security risk is low, and shield machine need not be disassembled, guarantee the globality of shield machine, make shield structure can complete connection fast.
accompanying drawing illustrates:
Fig. 1 is that the inventive method shield machine is fixedly connected with step one schematic diagram with the dolly that misses the stop;
Fig. 2 is that the inventive method shield machine is fixedly connected with step 2 schematic diagram with the dolly that misses the stop;
Fig. 3 is that the inventive method shield machine is fixedly connected with step 3 schematic diagram with the dolly that misses the stop;
Fig. 4 ~ Figure 12 is the inventive method shield machine in turnabout period step exploded view;
Wherein: 1, shield machine, 2, miss the stop dolly, and 3, steel plate, 4, jack, 5, screw machine, A direction, shield machine reach direction, B direction, shield machine direction of rotation, I, the left line of circuit, II, miss the stop center line, III, the right line of circuit, IV, the interval right line of shield structure starts portal, A, B, C, D, E, F point of rotation.
Detailed description of the invention
The present embodiment is that a kind of Closed station long-distance shield structure misses the stop tune construction method fast, and the method comprises the steps:
The first step: as shown in Figure 1, equipment and materials prepares;
1, adopt shaped steel to add section chief 8200mm, wide 3960mm can along the dolly that misses the stop (2) of rail moving;
2, clear up base plate, lay steel plate (3) in base surface, this steel plate (3) length, width and height are respectively 6280*2000*20mm, steel plate (3) adopts expansion bolt and base plate to fix, and the dolly (2) that will miss the stop is arranged on steel plate along designed lines center line, and with steel plate (3) firm welding;
Second step: as shown in Figure 2, shield machine (1) is connected and fixed and position translation with the dolly (2) that misses the stop;
After shield machine (1) is appeared, the jack of shield machine (1) self is utilized to provide counter-force, being pushed into by shield machine misses the stop on the track of dolly, then shield machine (1) slowly moves on the dolly that misses the stop (2) track, shield machine (1) fltting speed controls at 20mm/s, when whole shield machine (1) is all positioned on the dolly that misses the stop (2), after the screw machine (5) of its shield machine (1) is all positioned at station structure, after shield machine (1) and screw machine (5) possess transverse translation condition, shield machine (1) and the dolly (2) that misses the stop are fixed, to be missed the stop dolly (2) and base plate steel plate (3) constraint release simultaneously, adopt two 100t jack (4), to miss the stop dolly (2) and shield machine (1) overall by the left line translation 1290mm of design to missing the stop on center line,
3rd step: as shown in Figure 3, promotes shield machine (1) to predetermined tune position;
Along missing the stop track laying 43# rail, track adopts 10# channel-section steel to fix, rail clamping device grip track is adopted at shield machine (1) rear, two 50t jack are utilized to provide counter-force, miss the stop dolly (2) and shield machine (1) of promotion moves forward along track, translational speed 80m/d, is advanced into predetermined tune position by shield machine (1);
4th step: as shown in Figure 4, Figure 5, shield machine (1) and the dolly that misses the stop (2) first time integral-rotation translation;
After shield machine (1) and the dolly that misses the stop (2) arrive precalculated position, utilize hydraulic jack that shield machine (1) and the dolly that misses the stop (2) entirety are turned clockwise 30 ° along A point, and then shifted forward 3000mm;
5th step: as shown in Fig. 6, Fig. 7, Fig. 8, shield machine (1) and the translation of the dolly that misses the stop (2) second time integral-rotation;
After shield machine (1) and the dolly that misses the stop (2) first step select translation to put in place, 11.5 ° are rotated counterclockwise again to send out right side B point before cutterhead, and then shield machine (1) and the dolly that misses the stop (2) are rotated counterclockwise 48.5 ° with shield tail C point, shield machine (1) and the dolly that misses the stop (2) are moved to horizontal path direction;
6th step: as shown in Fig. 9, Figure 10, Figure 11, Figure 12, shield machine (1) and the dolly that misses the stop (2) third time integral-rotation translation;
Again the shield machine (1) and the dolly that misses the stop (2) that rotate translation are rotated counterclockwise 70 ° along shield machine (1) cutterhead left forward side D point, simultaneously shifted forward 550mm; Again shield machine (1) and the dolly that misses the stop (2) are rotated counterclockwise 12.5 ° along E point on the left of cutterhead, shield machine screw machine staggers after the steel pipe column of station, again shield machine and the dolly that misses the stop are rotated counterclockwise 7.5 ° again with F point on the right side of cutterhead, shield machine and the dolly that misses the stop are moved to together on the right line center line of design, and translation makes cutterhead distance portal 620mm.
Need to carry out repetition measurement to station floor level before construction, then adjust shield machine export & import actual elevation.
Described shield machine main body and the dolly that misses the stop utilize wire rope fixed strain respectively before, during and after shield body, the diverse location spot welding simultaneously contacted with the dolly that misses the stop at shield shell is fixed, again miss the stop dolly and base plate lower steel plate are welded together, to guarantee shield body and the dolly that misses the stop, bottom steel plate relative movement do not occur.

Claims (3)

1. Closed station long-distance shield structure machine misses the stop a tune construction method fast, it is characterized in that the method comprises the steps:
The first step: equipment and materials prepares;
1), adopt shaped steel to add section chief 8200mm, wide 3960mm can along the dolly that misses the stop of rail moving;
2), clear up base plate, lay steel plate in base surface, its length, width and height of described steel plate are respectively 6280*2000*20mm, and steel plate adopts expansion bolt and base plate to fix, and the dolly that will miss the stop is arranged on steel plate along designed lines center line, and firm with Plate Welding;
Second step: shield machine is connected and fixed and position translation with the dolly that misses the stop;
After shield machine is appeared, the jack of shield machine self is utilized to provide counter-force, being pushed into by shield machine misses the stop on the track of dolly, then shield machine slowly moves missing the stop on trolley track, shield machine fltting speed controls at 20mm/s, when whole shield machine is all positioned on the dolly that misses the stop, after its shield machine screw machine is all positioned at station structure, after shield machine and screw machine possess transverse translation condition, shield machine and the dolly that misses the stop are fixed, to be missed the stop dolly and base plate steel plate constraint release simultaneously, adopt two 100t jack again, to miss the stop dolly and shield machine overall by the left line translation 1290mm of design to missing the stop on center line,
3rd step: promote shield machine to predetermined tune position;
Along missing the stop track laying 43# rail, track adopts 10# channel-section steel to fix, and adopts rail clamping device grip track at shield machine rear, two 50t jack are utilized to provide counter-force, miss the stop dolly and shield machine of promotion moves forward along track, and translational speed 80m/d, is advanced into predetermined tune position by shield machine;
4th step: shield machine and dolly first time integral-rotation translation of missing the stop;
After shield machine and the dolly that misses the stop arrive precalculated position, utilize hydraulic jack that shield machine and dolly entirety of missing the stop are turned clockwise 30 ° along A point, and then shifted forward 3000mm;
5th step: shield machine and dolly second time integral-rotation translation of missing the stop;
After shield machine and the dolly first step of missing the stop select translation to put in place, 11.5 ° are rotated counterclockwise again with cutterhead right forward side B point, and then shield machine and the dolly that misses the stop are rotated counterclockwise 48.5 ° with shield tail C point, by shield machine and trolley translation of missing the stop to horizontal path direction;
6th step: shield machine and dolly third time integral-rotation translation of missing the stop;
Again the shield machine and the dolly that misses the stop that rotate translation are rotated counterclockwise 70 ° along cutter head of shield machine left forward side D point, simultaneously shifted forward 550mm; Again shield machine and the dolly that misses the stop are rotated counterclockwise 12.5 ° along E point on the left of cutterhead, shield machine screw machine staggers after the steel pipe column of station, again shield machine and the dolly that misses the stop are rotated counterclockwise 7.5 ° again with F point on the right side of cutterhead, shield machine and the dolly that misses the stop are moved to together on the right line center line of design, and translation makes cutterhead distance portal 620mm.
2. Closed station long-distance shield structure machine according to claim 1 misses the stop tune construction method fast, it is characterized in that needing to carry out repetition measurement to station floor level before construction, then adjusts shield machine export & import actual elevation.
3. Closed station long-distance shield structure machine according to claim 1 misses the stop tune construction method fast, it is characterized in that described shield machine main body utilizes wire rope fixed strain respectively with the dolly that misses the stop before, during and after shield body, the diverse location spot welding simultaneously contacted with the dolly that misses the stop at shield shell is fixed, then miss the stop dolly and base plate steel plate are welded together.
CN201410159620.XA 2014-04-21 2014-04-21 Rapid station-passing and turning construction method for long-distance shield tunneling machine of closed station Active CN103953352B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410159620.XA CN103953352B (en) 2014-04-21 2014-04-21 Rapid station-passing and turning construction method for long-distance shield tunneling machine of closed station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410159620.XA CN103953352B (en) 2014-04-21 2014-04-21 Rapid station-passing and turning construction method for long-distance shield tunneling machine of closed station

Publications (2)

Publication Number Publication Date
CN103953352A CN103953352A (en) 2014-07-30
CN103953352B true CN103953352B (en) 2016-03-16

Family

ID=51330682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410159620.XA Active CN103953352B (en) 2014-04-21 2014-04-21 Rapid station-passing and turning construction method for long-distance shield tunneling machine of closed station

Country Status (1)

Country Link
CN (1) CN103953352B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106014430A (en) * 2016-07-14 2016-10-12 中铁工程装备集团机电工程有限公司 Self-propelled shield machine station-passing trolley
CN106837346B (en) * 2017-01-10 2018-11-16 重庆交通建设(集团)有限责任公司 A kind of TBM stepping is missed the stop construction process
CN107975377A (en) * 2017-11-26 2018-05-01 上海宝冶集团有限公司 Horizontal displacement methods of the shield machine in active well
CN110645004B (en) * 2019-10-16 2024-02-02 中铁十一局集团城市轨道工程有限公司 Method for turning shield machine trolley in negative two layers of operated station
CN110529131B (en) * 2019-10-18 2023-09-15 中铁第一勘察设计院集团有限公司 Construction structure and method for maximizing tunneling length of single shield in core urban area
CN113279764B (en) * 2021-03-30 2023-01-03 中铁二十局集团第四工程有限公司 Construction method for split translation of complex steel sleeve and shield tunneling machine

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4076187B2 (en) * 2006-04-13 2008-04-16 株式会社熊谷組 How to build a tunnel
CN101173608A (en) * 2006-10-31 2008-05-07 上海市基础工程公司 Hoisting jack pulling method for double-circle shield-driven tunneling
CN102400690A (en) * 2011-12-26 2012-04-04 中铁四局集团有限公司 Shield machine jacking and turning method in shield method construction subway tunnel
CN202417508U (en) * 2011-12-26 2012-09-05 中铁四局集团有限公司 Pushing system for pushing and turning construction of shield tunneling machine in subway tunnel
CN103032072A (en) * 2012-12-08 2013-04-10 中铁十二局集团第二工程有限公司 Method for disassembling, lifting and transferring closed type station shield to transferring line to be hoisted out

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4076187B2 (en) * 2006-04-13 2008-04-16 株式会社熊谷組 How to build a tunnel
CN101173608A (en) * 2006-10-31 2008-05-07 上海市基础工程公司 Hoisting jack pulling method for double-circle shield-driven tunneling
CN102400690A (en) * 2011-12-26 2012-04-04 中铁四局集团有限公司 Shield machine jacking and turning method in shield method construction subway tunnel
CN202417508U (en) * 2011-12-26 2012-09-05 中铁四局集团有限公司 Pushing system for pushing and turning construction of shield tunneling machine in subway tunnel
CN103032072A (en) * 2012-12-08 2013-04-10 中铁十二局集团第二工程有限公司 Method for disassembling, lifting and transferring closed type station shield to transferring line to be hoisted out

Also Published As

Publication number Publication date
CN103953352A (en) 2014-07-30

Similar Documents

Publication Publication Date Title
CN103953352B (en) Rapid station-passing and turning construction method for long-distance shield tunneling machine of closed station
CN103277110A (en) Construction method of overlapped shield tunnel
CN102230381B (en) Hollow needle beam lining trolley
CN102418530A (en) Roller guide rail station-passing construction method of whole shield machine
CN103174382B (en) Multifunctional hydraulic anchor rod drill carriage
CN102877851A (en) Arc-shaped bottom stepping passing method of open-type hard rock heading machine in urban subway construction
CN203213623U (en) Slide guiding and rectifying device
CN105569568A (en) Drilling and ejecting integrated outburst-prevention drilling machine device
CN103277112A (en) Tunnel engineering train type rapid lifting and folding working platform
CN207018012U (en) A kind of tunnel partition wall uses formwork jumbo
CN204754945U (en) Mine method tunnel preliminary bracing lining cutting grid steel support make
CN203270392U (en) Mine rail vehicle translation device
CN203394541U (en) Flat-top steel mould trolley
CN110626733A (en) Special device for transporting ultra-large-diameter pipeline in narrow space
CN204941564U (en) Subway tunnel narrow spacing leaves the right or normal track row gate-type lining cutting bench frame apparatus
CN204283460U (en) Portion of side, convenient stable type adjustable height tunnel anchor cable construction platform
CN110821525B (en) Tunnel preliminary bracing shotcrete work platform
CN208153037U (en) A kind of stand device and the tunnel stand trolley for being loaded with the stand device
CN202832238U (en) All-dimensional moving base seat for steel pylon composite foundation anchoring drill rig
CN203559909U (en) Height-adjustable lining trolley
CN211520736U (en) Special device for transporting ultra-large-diameter pipeline in narrow space
CN109915185B (en) TBM middle plate frame system that crosses station
RU123065U1 (en) MOUNT MOUNT FOR WORK IN WORKS SAVED FOR RE-USE
CN205474623U (en) Sloping between tracks connection device goes up and down
CN203410474U (en) Turning device of rear matching trolley of shield tunneling machine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant