CN103924722A - Cast-in-place ecological insulation roof construction method - Google Patents

Cast-in-place ecological insulation roof construction method Download PDF

Info

Publication number
CN103924722A
CN103924722A CN201410138605.7A CN201410138605A CN103924722A CN 103924722 A CN103924722 A CN 103924722A CN 201410138605 A CN201410138605 A CN 201410138605A CN 103924722 A CN103924722 A CN 103924722A
Authority
CN
China
Prior art keywords
cast
construction method
carbon
bamboo
roof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410138605.7A
Other languages
Chinese (zh)
Other versions
CN103924722B (en
Inventor
葛加君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pizhou Binhe Sme Management Service Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410138605.7A priority Critical patent/CN103924722B/en
Publication of CN103924722A publication Critical patent/CN103924722A/en
Application granted granted Critical
Publication of CN103924722B publication Critical patent/CN103924722B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Building Environments (AREA)
  • Panels For Use In Building Construction (AREA)

Abstract

The invention discloses a cast-in-place ecological insulation roof construction method. The method includes the steps of producing carbon, silicon and calcium materials, producing biological glue, producing a bamboo reinforced mesh, setting up roof forms, laying the bamboo reinforced mesh, casting, maintaining, demounting the forms, pasting aluminum-tin-antimony alloy coils and the like. The cast-in-place ecological insulation roof construction method has the advantages that materials can be obtained locally, resources are saved, constructional operations are facilitated, energy saving and thermal insulation are achieved, the construction method has the characteristics of integrated techniques, a production technique of carbon, silicon and calcium materials, a mounting technique of cast-in-place roof forms, a cast-in-place roof concrete technique and a roof insulation construction technique are adopted, and the construction method is applicable to buildings in different areas, buildings of different types and buildings with different uses.

Description

Cast-in-place ecological heat preservation roof construction method
Technical field
The present invention relates to a kind of cast-in-place ecological heat preservation roof construction method.
Background technology
Roof heat insulation is the core of building construction insulation, and roof heat insulation technology, adopt at present loose fill type insulant to comprise expansion scoria both at home and abroad, expanded perlite, blast furnace cinders etc. comprise foamed plastics class sheet material with tabular heat insulating material, cellular concrete coverboard material, expansion scoria sheet material, expanded perlite sheet material, certainly adopts above heat insulating material to carry out roof heat insulation construction and plays certain effect, but material resources is fewer, cost is higher.
Summary of the invention
The object of the present invention is to provide a kind of easy construction, the cast-in-place ecological heat preservation roof construction method of energy-saving heat preserving.
Technical solution of the present invention is:
A cast-in-place ecological heat preservation roof construction method, is characterized in that: comprise the following steps:
(1) carbon silicon calcium material is made
Carbon silicon calcium material is a kind of ecological property material, Stalk silk, wooden carbon dust, cement flour, pulverized limestone, consists of; Length≤the 4mm of Stalk silk, fineness is in 1mm; Wood carbon dust adopts wooden bamboo to be fired into wooden carbon, and wooden carbon is by pulverizing and sieving, fineness≤1mm; Earth powder adopts common loess, sand or clay, after drying or drying, mills and sieves, and fineness is micron order; Lime is by sieving, and fineness is micron order; After above-mentioned raw material disposal processing, by the weight ratio of Stalk Si Fen ︰ wood Tan Fen ︰ earth Fen ︰ pulverized limestone=30 ︰ 10 ︰ 30 ︰ 30, carry out uniform stirring, form carbon silicon calcium material, pack standby;
(2) biogum is made: biogum is comprised of glutinous rice, wheat flour, elm bark powder; First glutinous rice is ground into powder, then by glutinous rice flour: wheat flour: the weight ratio of elm bark powder=50 ︰ 40 ︰ 10 is configured, and adds water after configuration, and every 1kg mixing powder adds 100 kilograms, water, carry out poach, and constantly stir, until boil latter 30 minutes, agglutination, barrelling, seals stand-by;
(3) bamboo reinforcement net is made: bamboo reinforcement net is made 5 years blue or green bamboos of life of material selection, is whittled into bamboo chip, and bamboo chip thickness is 3mm, and width is 10-15mm, adopts cross to wear weave, and mesh specification is 50-60mm;
(4) roofing template is installed: after construction work main body finishes, carry out the installation of roofing template;
(5) bamboo reinforcement net laying is established: bamboo reinforcement net laying is established employing and completely spread method, and lap-joint >=50mm places supporter on soffit formwork when bamboo reinforcement net laying is established, make bamboo reinforcement net in LIFT centre position;
(6) build: build front be 20-30mm by carbon silicon calcium material and particle diameter orthopaedics, biogum and water by carbon silicon calcium material: orthopaedics: biogum: the weight ratio of water=35 ︰ 40 ︰ 10 ︰ 15 is configured, and uniform stirring, then feeds intake and build, and vibration compacting;
(7) maintenance: should maintain after roofing is built, maintenance period is more than 15 days, and overburden is set between defects liability period, should avoid rain evil, freeze injury, solarization to do harm to;
(8) form removal: when eco-concrete roofing is built the expired laggard row form removal of maintenance;
(9) paste aluminium tin pewter coiled material: adopt weld seam method and viscose type to paste aluminium tin pewter coiled material on the ecological heat preservation roofing body of building, plain during laying, not hollowing, sealing < 5mm.
Described aggregate is stone, building waste piece or cinder.
Stalk silk moisture content≤5%.
The present invention not only can gather materials on the spot, and economize on resources, and constructing operation is convenient, again and play energy-saving heat preserving effect; Construction, has integration technical characterstic, has gathered carbon silicon calcium material manufacturing technology and cast-in-site roof template mounting technique, cast-in-site roof concrete technology, roof heat insulation construction technology in cast-in-place ecological heat preservation roofing construction engineering method.The present invention is applicable to zones of different building construction, dissimilar building construction, different purposes building constructions.
Below in conjunction with embodiment, the invention will be further described.
The specific embodiment
A cast-in-place ecological heat preservation roof construction method, comprises the following steps:
(1) carbon silicon calcium material is made
Carbon silicon calcium material is a kind of ecological property material, Stalk silk, wooden carbon dust, cement flour, pulverized limestone, consists of; Length≤the 4mm of Stalk silk, fineness is in 1mm; Wood carbon dust adopts wooden bamboo to be fired into wooden carbon, and wooden carbon is by pulverizing and sieving, fineness≤1mm; Earth powder adopts common loess, sand or clay, after drying or drying, mills and sieves, and fineness is micron order; Lime is by sieving, and fineness is micron order; After above-mentioned raw material disposal processing, by the weight ratio of Stalk Si Fen ︰ wood Tan Fen ︰ earth Fen ︰ pulverized limestone=30 ︰ 10 ︰ 30 ︰ 30, carry out uniform stirring, form carbon silicon calcium material, pack standby;
(2) biogum is made: biogum is comprised of glutinous rice, wheat flour, elm bark powder; First glutinous rice is ground into powder, then by glutinous rice flour: wheat flour: the weight ratio of elm bark powder=50 ︰ 40 ︰ 10 is configured, and adds water after configuration, and every 1kg mixing powder adds 100 kilograms, water, carry out poach, and constantly stir, until boil latter 30 minutes, agglutination, barrelling, seals stand-by;
(3) bamboo reinforcement net is made: bamboo reinforcement net is made 5 years blue or green bamboos of life of material selection, is whittled into bamboo chip, and bamboo chip thickness is 3mm, and width is 10-15mm, adopts cross to wear weave, and mesh specification is 50-60mm;
(4) roofing template is installed: after construction work main body finishes, carry out the installation of roofing template;
(5) bamboo reinforcement net laying is established: bamboo reinforcement net laying is established employing and completely spread method, and lap-joint >=50mm places supporter on soffit formwork when bamboo reinforcement net laying is established, make bamboo reinforcement net in LIFT centre position;
(6) build: build front be 20-30mm by carbon silicon calcium material and particle diameter orthopaedics, biogum and water by carbon silicon calcium material: orthopaedics: biogum: the weight ratio of water=35 ︰ 40 ︰ 10 ︰ 15 is configured, and uniform stirring, then feeds intake and build, and vibration compacting;
(7) maintenance: should maintain after roofing is built, maintenance period is more than 15 days, and overburden is set between defects liability period, should avoid rain evil, freeze injury, solarization to do harm to;
(8) form removal: when eco-concrete roofing is built the expired laggard row form removal of maintenance;
(9) paste aluminium tin pewter coiled material: adopt weld seam method and viscose type to paste aluminium tin pewter coiled material on the ecological heat preservation roofing body of building, plain during laying, not hollowing, sealing < 5mm.
Described aggregate is stone, building waste piece or cinder.
Stalk silk moisture content≤5%.

Claims (3)

1. a cast-in-place ecological heat preservation roof construction method, is characterized in that: comprise the following steps:
(1) carbon silicon calcium material is made
Carbon silicon calcium material is a kind of ecological property material, Stalk silk, wooden carbon dust, cement flour, pulverized limestone, consists of; Length≤the 4mm of Stalk silk, fineness is in 1mm; Wood carbon dust adopts wooden bamboo to be fired into wooden carbon, and wooden carbon is by pulverizing and sieving, fineness≤1mm; Earth powder adopts common loess, sand or clay, after drying or drying, mills and sieves, and fineness is micron order; Lime is by sieving, and fineness is micron order; After above-mentioned raw material disposal processing, by the weight ratio of Stalk Si Fen ︰ wood Tan Fen ︰ earth Fen ︰ pulverized limestone=30 ︰ 10 ︰ 30 ︰ 30, carry out uniform stirring, form carbon silicon calcium material, pack standby;
(2) biogum is made: biogum is comprised of glutinous rice, wheat flour, elm bark powder; First glutinous rice is ground into powder, then by glutinous rice flour: wheat flour: the weight ratio of elm bark powder=50 ︰ 40 ︰ 10 is configured, and adds water after configuration, and every 1kg mixing powder adds 100 kilograms, water, carry out poach, and constantly stir, until boil latter 30 minutes, agglutination, barrelling, seals stand-by;
(3) bamboo reinforcement net is made: bamboo reinforcement net is made 5 years blue or green bamboos of life of material selection, is whittled into bamboo chip, and bamboo chip thickness is 3mm, and width is 10-15mm, adopts cross to wear weave, and mesh specification is 50-60mm;
(4) roofing template is installed: after construction work main body finishes, carry out the installation of roofing template;
(5) bamboo reinforcement net laying is established: bamboo reinforcement net laying is established employing and completely spread method, and lap-joint >=50mm places supporter on soffit formwork when bamboo reinforcement net laying is established, make bamboo reinforcement net in LIFT centre position;
(6) build: build front be 20-30mm by carbon silicon calcium material and particle diameter orthopaedics, biogum and water by carbon silicon calcium material: orthopaedics: biogum: the weight ratio of water=35 ︰ 40 ︰ 10 ︰ 15 is configured, and uniform stirring, then feeds intake and build, and vibration compacting;
(7) maintenance: should maintain after roofing is built, maintenance period is more than 15 days, and overburden is set between defects liability period, should avoid rain evil, freeze injury, solarization to do harm to;
(8) form removal: when eco-concrete roofing is built the expired laggard row form removal of maintenance;
(9) paste aluminium tin pewter coiled material: adopt weld seam method and viscose type to paste aluminium tin pewter coiled material on the ecological heat preservation roofing body of building, plain during laying, not hollowing, sealing < 5mm.
2. cast-in-place ecological heat preservation roof construction method according to claim 1, is characterized in that: described aggregate is stone, building waste piece or cinder.
3. cast-in-place ecological heat preservation roof construction method according to claim 1 and 2, is characterized in that: Stalk silk moisture content≤5%.
CN201410138605.7A 2014-04-09 2014-04-09 Cast-in-place ecological heat preservation roof construction method Active CN103924722B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410138605.7A CN103924722B (en) 2014-04-09 2014-04-09 Cast-in-place ecological heat preservation roof construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410138605.7A CN103924722B (en) 2014-04-09 2014-04-09 Cast-in-place ecological heat preservation roof construction method

Publications (2)

Publication Number Publication Date
CN103924722A true CN103924722A (en) 2014-07-16
CN103924722B CN103924722B (en) 2015-12-30

Family

ID=51143100

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410138605.7A Active CN103924722B (en) 2014-04-09 2014-04-09 Cast-in-place ecological heat preservation roof construction method

Country Status (1)

Country Link
CN (1) CN103924722B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2637987A1 (en) * 1976-08-24 1978-03-02 Andreas Boeck Cover for embankment or roof - with moulded plastic sheets supporting plant roots and sepd. from roof by plastic spacers
CA2237655C (en) * 1995-11-15 2001-07-24 Parviz Soroushian Dispersion of plant pulp in concrete and use thereof
KR20020009249A (en) * 2000-07-25 2002-02-01 조송준 Manufacturing process and composite of inner and outer building materials
CN101864284A (en) * 2010-06-25 2010-10-20 梁开方 Elm bark powder particles, preparation method for elm bark powder particles, elm bark powder vegetable gum and application of elm bark powder vegetable gum
CN102584102A (en) * 2012-03-09 2012-07-18 河海大学 Preparation and use of glutinous rice tabia cementing material

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2637987A1 (en) * 1976-08-24 1978-03-02 Andreas Boeck Cover for embankment or roof - with moulded plastic sheets supporting plant roots and sepd. from roof by plastic spacers
CA2237655C (en) * 1995-11-15 2001-07-24 Parviz Soroushian Dispersion of plant pulp in concrete and use thereof
KR20020009249A (en) * 2000-07-25 2002-02-01 조송준 Manufacturing process and composite of inner and outer building materials
CN101864284A (en) * 2010-06-25 2010-10-20 梁开方 Elm bark powder particles, preparation method for elm bark powder particles, elm bark powder vegetable gum and application of elm bark powder vegetable gum
CN102584102A (en) * 2012-03-09 2012-07-18 河海大学 Preparation and use of glutinous rice tabia cementing material

Also Published As

Publication number Publication date
CN103924722B (en) 2015-12-30

Similar Documents

Publication Publication Date Title
CN102010168B (en) Baking-free hollow thermal insulation blocks and preparation method thereof
CN103922647B (en) Heat insulation house surface construction ecological glue and uses thereof
CN104817303B (en) A preparation method of cement-based plant straw fiber particle wall material
CN103396044B (en) Energy-saving building block compounded with construction waste, straws and foamed concrete
CN104310949B (en) A kind of Boccaro shale hollow brick
CN102491707B (en) Method of preparing baking-free load-bearing bricks through steam curing of semidry desulfurization residues
CN102491723A (en) Slickens baked brick and production method thereof
CN108238811A (en) A kind of preparation method of foamed ceramic plates
CN106380217A (en) Making method for lightweight environment-friendly ceramic plate
CN104310944B (en) A kind of coal gangue sintering hollow brick
CN103043956A (en) Method for preparing energy-saving wall material by utilizing waste foam glass
CN107285801A (en) A kind of air-entrained concrete building block and its manufacture method
CN104291789A (en) Perforated brick with strong water absorption property, and preparation method thereof
CN104724965A (en) Method for preparing raw soil material
CN103924748B (en) A kind of ecological heat preservation roof construction method
CN103924722A (en) Cast-in-place ecological insulation roof construction method
CN107244866A (en) Flyash brick production technology
CN212611791U (en) An artificial bionic edge stone
CN104341171A (en) Self thermal insulation sintered brick and production method thereof
CN103953164B (en) Cast-in-place ecological heat preservation roof panel preparation method
CN103951300B (en) Heat insulation house surface construction carbon silico-calcium ecomaterial and uses thereof
CN101381223A (en) Land waste calcining brick and production method thereof
CN100425562C (en) Making process and product of heat insulating wall material
CN104478366A (en) Rigid thermal insulation composite board and preparation method thereof
CN102093022A (en) Lightweight heat insulation material and production method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191128

Address after: 221000 No.1, Zhangjiagang East Road, Yitang Town, Pizhou City, Xuzhou City, Jiangsu Province

Patentee after: Pizhou Binhe SME Management Service Co., Ltd.

Address before: 226400, Development Building, east side of Taishan Road, digging Town, Rudong County, Jiangsu, Nantong 1002

Patentee before: Ge Jiajun

TR01 Transfer of patent right