CN103911990A - A kind of underwater pouring pipe column with retaining wall and its construction method - Google Patents
A kind of underwater pouring pipe column with retaining wall and its construction method Download PDFInfo
- Publication number
- CN103911990A CN103911990A CN201410172024.5A CN201410172024A CN103911990A CN 103911990 A CN103911990 A CN 103911990A CN 201410172024 A CN201410172024 A CN 201410172024A CN 103911990 A CN103911990 A CN 103911990A
- Authority
- CN
- China
- Prior art keywords
- section
- formwork
- hole
- retaining wall
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
技术领域technical field
本发明涉及土木工程、桥梁房建、水工结构中基础现浇施工方法。The invention relates to a foundation cast-in-place construction method in civil engineering, bridge house construction and hydraulic structures.
背景技术Background technique
现有的沉井及沉管基础施工采用分节预制构件后依靠自重或辅助措施接高下沉然后进行压浆处理的方法进行施工。对于该工艺,除存在施工场预制件运输困难、吊装设备大、预制件下沉困难等问题外,还有以下几点难以控制:下沉后由于底部有残渣易整体倾斜;分节预制,各节接口处拼接施工难度大;压浆工艺复杂,压浆质量难以控制,工期长造价高。预制法施工的以上问题已成为行业内公认的难题。The existing caisson and immersed tube foundation construction adopts the method of segmental prefabricated components, then relying on self-weight or auxiliary measures to connect heights and subsidence, and then carry out grouting treatment. For this process, in addition to the difficulties in transporting prefabricated parts at the construction site, the large hoisting equipment, and the difficulty in sinking the prefabricated parts, there are also the following points that are difficult to control: after sinking, the whole body is easy to tilt due to the residue at the bottom; The splicing construction at joint joints is difficult; the grouting process is complicated, the quality of grouting is difficult to control, and the construction period is long and the cost is high. The above problems of prefabrication construction have become recognized problems in the industry.
发明内容Contents of the invention
本发明是为避免上述现有技术所存在的不足之处,提供一种带有护壁的水下浇筑式管柱及其施工方法,以方便施工、提高施工效率。In order to avoid the disadvantages of the above-mentioned prior art, the present invention provides an underwater pouring pipe column with retaining wall and its construction method, so as to facilitate construction and improve construction efficiency.
本发明为解决技术问题采用如下技术方案:The present invention adopts following technical scheme for solving technical problems:
本发明带有护壁的水下浇筑式管柱的结构特点是:所述管柱是在现浇加筋混凝土管柱与成孔内壁之间采用水下快凝材料浇筑形成有护壁层,所述管柱以现浇混凝土底板形成混凝土封底。The structural feature of the underwater pouring pipe column with retaining wall of the present invention is: the pipe column is formed by pouring underwater quick-setting material between the cast-in-place reinforced concrete pipe column and the inner wall of the hole to form a retaining wall layer, and the said pipe column The column is backed with concrete as a cast-in-place concrete slab.
本发明带有护壁的水下浇筑式管柱的施工方法的特点是按如下步骤进行:The characteristics of the construction method of the underwater pouring type pipe column with retaining wall of the present invention are to carry out according to the following steps:
a、在设定的管柱所在位置处,以钻机施工成孔;a. At the position where the pipe string is set, use a drilling rig to construct a hole;
b、在所述成孔中利用环形滑模装置自下而上沿成孔内壁以水下快凝材料浇筑护壁层,形成护壁孔,向所述护壁孔中下放筒形钢筋笼;b. Utilize an annular sliding form device in the forming hole to pour the retaining wall layer with underwater quick-setting material from bottom to top along the inner wall of the forming hole to form a retaining wall hole, and lower a cylindrical reinforcement cage into the retaining wall hole;
c、在所述钢筋笼的筒中下放底节模板,在所述底节模板上、自下而上逐节组装并通过外挂配重下放各节段预制内模板形成内模,锁定内模后在护壁孔中浇筑底板混凝土形成混凝土封底,底节模板浇筑在管柱孔的混凝土封底中进行定位,使成护壁孔形成为封底的环形筒体;c. Lower the bottom section formwork in the tube of the steel cage, assemble it section by section from bottom to top on the bottom section formwork, and lower the prefabricated inner formwork of each section through the external counterweight to form an inner mold. After locking the inner mold, Bottom plate concrete is poured in the retaining wall hole to form a concrete bottom cover, and the bottom section formwork is poured in the concrete bottom cover of the pipe column hole for positioning, so that the retaining wall hole forms a bottom-sealed annular cylinder;
d、在所述封底的环形筒体中,以所述护壁层为外模,在所述外模和内模之间浇筑管身混凝土,在所述管身混凝土达到强度要求后,解除对内模的锁定,自上而下取出各节段预制内模板,完成带有护壁的水下浇筑式管柱的施工;d. In the annular cylinder with the bottom cover, use the retaining layer as the outer mold, and pour concrete for the pipe body between the outer mold and the inner mold. After the concrete for the pipe body reaches the strength requirement, release the internal Locking of the mold, take out the prefabricated inner formwork of each segment from top to bottom, and complete the construction of the underwater pouring pipe column with retaining wall;
e、在所述带有护壁的水下浇筑式管柱的顶面浇注顶盖完成基础承台的施工。e. A top cover is poured on the top surface of the underwater pouring column with retaining walls to complete the construction of the foundation cap.
本发明施工方法的特点也在于:The feature of construction method of the present invention also is:
设置所述各节段预制内模板为空心浮筒结构,在释放对内模的锁定之后,各节段内模板可依靠浮力上浮实现回收。The prefabricated inner formwork of each section is set as a hollow buoy structure, and after the locking of the inner formwork is released, the inner formwork of each section can be recovered by floating up by relying on buoyancy.
所述底节模板的上段为圆柱形筒体,下段为圆锥形筒体,所述底节模板是以其圆锥形筒底浇筑在管柱孔的混凝土封底中进行定位。The upper section of the bottom section formwork is a cylindrical cylinder, and the lower section is a conical cylinder. The bottom section formwork is positioned by pouring its conical cylinder bottom into the concrete back cover of the pipe column hole.
所述各节段预制内模板是由瓦片模板拼装而成;在所述各节段预制内模板中,呈水平设置的“十”字支撑架在其呈“十”字的四个支撑位上支撑有定位立柱,各瓦片模板与相邻位置上定位立柱相互卡嵌,并能够以所述定位立柱为导向柱竖向滑动;相邻节段的预制内模板之间,对应位置上的定位立柱相互螺纹连接;处在与所述底节模板相邻接位置上的第一节段预制内模板中的定位立柱是螺纹连接在所述底节模板的顶面上,在所述各节段预制内模板之间贯穿用于张拉的锁紧钢铰线;所述锁紧钢铰线在孔顶限位平台上利用千斤顶进行张拉。The prefabricated inner formwork of each section is assembled from tile formwork; in the prefabricated inner formwork of each section, the horizontally arranged "ten" support frame is at the four support positions of "ten". There are positioning columns on the upper support, and each tile formwork is interlocked with the positioning columns on the adjacent positions, and can slide vertically with the positioning columns as the guide column; between the prefabricated inner formworks of adjacent segments, the corresponding position The positioning columns are screwed to each other; the positioning columns in the prefabricated inner formwork of the first section at the position adjacent to the bottom section formwork are screwed on the top surface of the bottom section formwork, and each section A locking steel hinge line for tension runs through the prefabricated inner templates of the sections; the locking steel hinge line is tensioned on the hole top limit platform by a jack.
在各道“十”字支撑架的中心分别设置有钢绞线拴结点,并有回收钢绞线在各钢绞线拴结点之间串联连接并延伸至管柱孔的孔口,用于回收“十”字支撑架。In the center of each "ten" supporting frame, steel strand tie nodes are respectively arranged, and recycled steel strands are connected in series between the steel strand tie nodes and extend to the orifice of the pipe column hole. To recycle the "ten" character support frame.
与已有技术相比,本发明有益效果体现在:Compared with the prior art, the beneficial effects of the present invention are reflected in:
1、本发明中护壁层具有较高的强度质量比、刚度质量比和良好的耐腐蚀性能,防渗性能好,以其作为混凝土的保护外壳可以对混凝土结构实施全寿命保护;1. The retaining wall layer in the present invention has higher strength-to-mass ratio, stiffness-to-mass ratio, good corrosion resistance, and good anti-seepage performance. It can be used as a concrete protective shell to protect the concrete structure for a full life;
2、本发明中护壁层可较好地约束管柱的纵向及环向应变,钢筋骨架可按照最小配筋率配置,与普通钢筋混凝土沉管配筋率大为减小,各节段内模板重复使用,从而节省造价,用量也减轻了钢筋骨架吊装重量。2. The retaining wall layer in the present invention can better restrain the longitudinal and circumferential strains of the pipe string, and the reinforcement skeleton can be configured according to the minimum reinforcement ratio, which is greatly reduced compared with ordinary reinforced concrete immersed pipes. The formwork in each section Repeated use saves the cost, and the amount used also reduces the hoisting weight of the steel frame.
3、与混凝土预制沉管相比,本发明中护壁层与内模的配搭实现管柱现浇,解决了场地预制大直径沉管运输困难的问题,可大大提高施工效率,缩短工期;3. Compared with concrete prefabricated immersed pipes, the collocation of retaining wall layer and inner mold in the present invention realizes pipe column cast-in-place, which solves the problem of difficult transportation of prefabricated large-diameter immersed pipes on site, greatly improves construction efficiency and shortens construction period;
4、已有技术中预制件接高在连接处处理困难,质量不易控制,本发明实现管柱基础一次性浇筑完成,基础为完整整体,可有效提高基础力学性能,基础质量可靠;4. In the prior art, it is difficult to handle the joint height of the prefabricated parts, and the quality is not easy to control. The invention realizes the one-time pouring of the pipe column foundation, and the foundation is a complete whole, which can effectively improve the mechanical properties of the foundation and the quality of the foundation is reliable;
5、已有技术中预制下沉工法在预制件下沉完成后需要进行压浆处理,而压浆工艺复杂,特别对于管柱基础底部压浆质量难以控制,造成基础底部周边松散,使得基础承载力降低,本发明实现一次性现浇,不需要压浆处理。且本发明采用钢结构锥形底节模板,可伸入至较深处,然后完成浇筑,由于浇筑的混凝土流动性强可经挤压渗入各个空间,不会出现传统施工方法可能造成的底部周边松散问题。5. In the prefabricated sinking method in the prior art, grouting treatment is required after the prefabricated parts sink, and the grouting process is complicated, especially for the quality of the grouting at the bottom of the pipe column foundation, which is difficult to control, resulting in loosening of the periphery of the bottom of the foundation, making the foundation load-bearing The force is reduced, and the invention realizes one-time cast-in-place without grouting treatment. Moreover, the present invention adopts a steel structure conical bottom section formwork, which can be extended to a relatively deep place, and then the pouring is completed. Because the poured concrete has strong fluidity, it can be squeezed into each space, and there will be no bottom periphery that may be caused by traditional construction methods. loose question.
附图说明Description of drawings
图1为本发明自浮式内模系统立面图;Fig. 1 is the elevation view of self-floating internal mold system of the present invention;
图2为本发明自浮式内模系统平面图;Fig. 2 is a plan view of the self-floating internal mold system of the present invention;
图3为本发明中底节定位模板安装示意图;Fig. 3 is the schematic diagram of the installation of the bottom section positioning formwork of the present invention;
图4为本发明中第二节立柱及十字支撑架安装示意图;Figure 4 is a schematic diagram of the installation of the second section of the column and the cross support frame in the present invention;
图5为本发明中自浮模板与定位立柱连接示意图;Figure 5 is a schematic diagram of the connection between the self-floating formwork and the positioning column in the present invention;
图6为本发明中十字支撑架与定位立柱连接示意图;Fig. 6 is a schematic diagram of the connection between the cross support frame and the positioning column in the present invention;
图7为本发明管柱立面示意图;Fig. 7 is a schematic diagram of the elevation of the column of the present invention;
图8为本发明管柱平面示意图;Fig. 8 is a schematic plan view of the column of the present invention;
图9为本发明管柱浇筑完成后结构示意图。Fig. 9 is a schematic diagram of the structure of the pipe column of the present invention after pouring is completed.
图中标号:1护壁层,2钢筋笼,3内模板,3a加劲板,4底节模板,5为“十”字支撑架,5a锥形销,6定位立柱,6a支撑牛腿,7锁紧钢铰线,8孔顶限位平台,9千斤顶,10钢绞线拴结点,11混凝土封底,12回收用钢绞线,13穿线孔,14管身混凝土。Numbers in the figure: 1 retaining wall layer, 2 reinforcement cage, 3 inner formwork, 3a stiffening plate, 4 bottom section formwork, 5 is "ten" support frame, 5a tapered pin, 6 positioning column, 6a supporting corbel, 7 lock Tight steel hinges, 8 holes top limit platform, 9 jacks, 10 steel strands tie joints, 11 concrete bottom cover, 12 steel strands for recycling, 13 threading holes, 14 pipe body concrete.
具体实施方式Detailed ways
参见图1、图2、图3、图4、图5和图6,本实施例中设置用于施工带有护壁的水下浇筑式管柱的内模系统的结构形式是:Referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5 and Fig. 6, in the present embodiment, the structural form of the internal formwork system for constructing the underwater pouring column with retaining wall is:
如图1所示,包括一钢结构底节模板4,在底节模板4上、自下而上逐节组装各节段预制内模板3;各节段预制内模板3为可在水中获得浮力的全封闭钢结构空心浮筒结构,在释放对内模的锁定之后,各节段内模板3可依靠浮力上浮实现回收;底节模板4浇筑在管柱孔的混凝土封底11中进行定位。As shown in Figure 1, it includes a steel structure bottom section formwork 4, on the bottom section formwork 4, each section prefabricated inner formwork 3 is assembled section by section from bottom to top; each section prefabricated inner formwork 3 can obtain buoyancy in water The fully enclosed steel structure hollow buoy structure, after releasing the locking of the inner formwork, the inner formwork 3 of each segment can be recovered by floating up by buoyancy; the bottom section formwork 4 is poured in the concrete bottom cover 11 of the column hole for positioning.
如图2和图5所示,各节段预制内模板3是由瓦片模板拼装而成;在各节段预制内模板3中,呈水平设置的“十”字支撑架5在其呈“十”字的四个支撑位上支撑有定位立柱6,各瓦片模板与相邻位置上定位立柱6相互卡嵌,并能够以定位立柱6为导向柱竖向滑动;各瓦片模板为空心全封闭浮式模板,其内设置有各道加劲板3a;各节段预制内模板3根据实际施工条件可以为6-15m。As shown in Figure 2 and Figure 5, the prefabricated inner formwork 3 of each section is assembled from tile formwork; in the prefabricated inner formwork 3 of each section, the "ten" character support frame 5 arranged horizontally is in the shape of " Positioning columns 6 are supported on the four supporting positions of the “ten” character, and each tile formwork is interlocked with the positioning columns 6 at adjacent positions, and can slide vertically with the positioning column 6 as a guide column; each tile formwork is hollow The fully enclosed floating formwork is provided with various stiffening plates 3a inside; the prefabricated inner formwork 3 of each segment can be 6-15m according to the actual construction conditions.
如图3、图4和图5所示,相邻节段的预制内模板3之间,对应位置上的定位立柱6相互螺纹连接;处在与底节模板4相邻接位置上的第一节段预制内模板中的定位立柱是螺纹连接在底节模板4的顶面上,在各节段预制内模板3之间通过设置在预制内模板3中的穿线孔13贯穿用于张拉的锁紧钢铰线7;锁紧钢铰线7在孔顶限位平台8上利用千斤顶9进行张拉。As shown in Figure 3, Figure 4 and Figure 5, between the prefabricated inner formwork 3 of adjacent segments, the positioning columns 6 at the corresponding positions are screwed to each other; The positioning column in the segmental prefabricated inner formwork is screwed on the top surface of the bottom section formwork 4, and the prefabricated inner formwork 3 of each segment passes through the threading hole 13 provided in the prefabricated inner formwork 3 for tensioning. Locking the steel hinge line 7; the locking steel hinge line 7 is tensioned by jack 9 on the hole top limit platform 8.
具体实施中,底节模板4的上段为圆柱形筒体,下段为圆锥形筒体,底节模板4是以其圆锥形筒底浇筑在管柱孔的混凝土封底11中进行定位;In specific implementation, the upper section of the bottom section formwork 4 is a cylindrical cylinder, and the lower section is a conical cylinder, and the bottom section formwork 4 is positioned in the concrete bottom cover 11 of the pipe column hole by pouring its conical cylinder bottom;
如图6所示,“十”字支撑架5根据受力情况进行设置,每节定位立柱6至少设置两道“十”字支撑架5,在各道“十”字支撑架5的中心分别设置有钢绞线拴结点10,并有回收用钢绞线12在各钢绞线拴结点10之间串联连接并延伸至孔口,用于回收“十”字支撑架5,在定位立柱6的内侧壁上设置支撑牛腿6a,“十”字支撑架5通过锥形销5a连接在支撑牛腿6a。As shown in Figure 6, the "ten" support frame 5 is set according to the stress situation, and each positioning column 6 is provided with at least two "ten" support frames 5, and the center of each "ten" support frame 5 is respectively Steel strand tie nodes 10 are provided, and steel strand tie wires 12 for recycling are connected in series between each steel strand tie tie nodes 10 and extend to the orifice for recovery of the "ten" support frame 5. A support bracket 6a is arranged on the inner side wall of the column 6, and the "ten" support frame 5 is connected to the support bracket 6a through a tapered pin 5a.
参见图7、图8和图9,本实施例中带有护壁的水下浇筑式管柱的结构形式是在现浇加筋混凝土管柱与成孔内壁之间采用水下快凝材料浇筑形成有护壁层1,管柱以现浇混凝土底板形成混凝土封底11。Referring to Fig. 7, Fig. 8 and Fig. 9, the structural form of the underwater pouring pipe column with retaining wall in this embodiment is formed by pouring underwater quick-setting materials between the cast-in-place reinforced concrete pipe column and the inner wall of the hole. There is a retaining wall layer 1, and the pipe column forms a concrete back cover 11 with a cast-in-place concrete bottom plate.
本实施例中带有护壁的水下浇筑式管柱的施工方法按如下步骤进行:In this embodiment, the construction method of the underwater pouring type pipe string with retaining wall is carried out as follows:
1、在设定的管柱所在位置处,以钻机施工成孔;1. At the position where the pipe string is set, use a drilling rig to construct a hole;
2、在所述成孔中利用环形滑模装置自下而上沿成孔内壁以水下快凝材料浇筑护壁层(1),形成护壁孔,向所述护壁孔中下放筒形钢筋笼(2);2. Utilize the annular sliding form device in the hole forming to pour the retaining wall layer (1) with underwater quick-setting material along the inner wall of the hole from bottom to top to form a retaining wall hole, and lower the cylindrical reinforcement cage into the retaining wall hole ( 2);
3、在所述钢筋笼(2)的筒中下放底节模板(4),在所述底节模板(4)上、自下而上逐节组装并通过外挂配重下放各节段预制内模板(3)形成内模,锁定内模后在护壁孔中浇筑底板混凝土形成混凝土封底(11),底节模板(4)浇筑在管柱孔的混凝土封底(11)中进行定位,使成护壁孔形成为封底的环形筒体;具体实施是在下方底节模板4至其顶面处在孔口位置时,在底节模板4的顶面安装第一节段预制模板中的定位立柱和“十”字支撑架;再次下放至第一节段预制模板中的定位立柱的顶端处在孔口位置时,以螺纹连接上一节段预制模板中的定位立柱和“十”字支撑架;继续下放各节段预内模板中定位立柱和“十”字支撑架,当利用外挂配重将各节段预制模板中各瓦片模板自孔口处依次沿定位立柱6下沉在指定位置上,在孔顶限位平台8上利用千斤顶9张拉贯穿在各节段预制内模板3上穿线孔13中的锁紧钢绞线7进行压实并锁定,完成内模安装。3. Lower the bottom section formwork (4) in the cylinder of the steel cage (2), assemble the bottom section formwork (4) section by section from bottom to top, and lower each section to prefabricate the inner formwork through the external counterweight (3) form the inner formwork, after locking the inner formwork, pour base concrete in the retaining wall hole to form a concrete back cover (11), and the bottom section formwork (4) is poured in the concrete back cover (11) of the pipe column hole for positioning, so as to form a retaining wall hole It is formed as a bottom-covered annular cylinder; the specific implementation is to install the positioning column and the "ten "Word support frame; when the top of the positioning column in the prefabricated formwork of the first section is at the hole position again, connect the positioning column and the "ten" support frame in the prefabricated formwork of the previous section with threads; continue to lower The positioning column and the "ten" support frame in the prefabricated formwork of each segment, when the external counterweight is used to sink each tile formwork in the prefabricated formwork of each segment from the opening to the designated position along the positioning column 6, the The locking steel strand 7 running through the threading hole 13 on the prefabricated inner formwork 3 of each segment is compacted and locked by jacks 9 on the hole top limiting platform 8 to complete the installation of the inner formwork.
4、在封底的环形筒体中,以所述护壁层1为外模,在外模和内模之间浇筑管身混凝土14,在管身混凝土14达到强度要求后,解除对内模的锁定,自上而下取出各节段预制内模板3,完成带有护壁的水下浇筑式管柱的施工;4. In the bottom-covered annular cylinder, use the retaining layer 1 as the outer mold, pour the pipe body concrete 14 between the outer mold and the inner mold, and release the locking of the inner mold after the pipe body concrete 14 reaches the strength requirement, Take out the prefabricated inner formwork 3 of each segment from top to bottom, and complete the construction of the underwater pouring pipe column with retaining wall;
5、在带有护壁的水下浇筑式管柱的顶面浇注顶盖完成基础承台的施工。5. The top cover is poured on the top surface of the underwater pouring column with retaining wall to complete the construction of the foundation cap.
具体实施中,水下快凝材料是以水泥、石膏、HPMC材料及水按1∶1∶0.01∶0.5的质量配合比混合而成,可根据浇筑高度等实际工况进行适当调整,快凝材料凝固时间为1小时,强度为2MPa,浇筑形成的护壁层1的厚度为5到20cm。In the specific implementation, the underwater quick-setting material is mixed with cement, gypsum, HPMC material and water according to the mass ratio of 1:1:0.01:0.5, which can be adjusted appropriately according to the actual working conditions such as pouring height. The quick-setting material The solidification time is 1 hour, the strength is 2 MPa, and the thickness of the protective wall layer 1 formed by pouring is 5 to 20 cm.
环形滑模装置的浇筑过程是在初始位置浇筑材料强度达到允许值后,移动活动模板至下一位置继续浇筑,实现连续浇筑,环形滑模装置中的滑移式活动模板为环形,这一施工工艺目前已经在工程建设中得到广泛使用。The pouring process of the annular sliding form device is to move the movable formwork to the next position to continue pouring after the strength of the pouring material at the initial position reaches the allowable value, so as to realize continuous pouring. The sliding movable formwork in the annular sliding form device is ring-shaped. This construction The process has been widely used in engineering construction.
单节内模板3的长度为6~15米,各节段预制内模板3设置为空心浮筒结构,在释放对内模板的锁定之后,各节段内模板3可依靠浮力上浮实现回收,其重复使用,节省造价,节约工期;以钢结构锥形底节模板4压入成孔底部较深位置,能有效地起到固定和定位内模板的作用。The length of the inner formwork 3 of a single section is 6-15 meters, and the prefabricated inner formwork 3 of each section is set as a hollow buoy structure. After the locking of the inner formwork is released, the inner formwork 3 of each section can be recovered by floating up by buoyancy. Use, save cost, save construction period; the conical bottom section formwork 4 of steel structure is pressed into the deep position at the bottom of the hole, which can effectively fix and position the inner formwork.
本发明管柱直径在3至6m,可广泛用于桥梁房建、水工结构等工程建设领域,可适用于陆上常规基础的施工,如沉井、管柱等;尤其适于水中基础的施工,如桥梁的塔柱基础、水中锚碇基础、群井基础等。也可在该结构的基础上实施增加摩擦力的措施,如顶入根键形成根式基础等。The diameter of the pipe column of the present invention is 3 to 6m, which can be widely used in engineering construction fields such as bridge building construction and hydraulic structure, and can be applied to the construction of conventional foundations on land, such as caissons and pipe strings; it is especially suitable for foundations in water Construction, such as bridge tower foundation, anchorage foundation in water, group well foundation, etc. Measures to increase friction can also be implemented on the basis of this structure, such as pushing into root keys to form a root foundation, etc.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410172024.5A CN103911990B (en) | 2014-04-25 | 2014-04-25 | A kind of underwater pouring pipe column with retaining wall and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410172024.5A CN103911990B (en) | 2014-04-25 | 2014-04-25 | A kind of underwater pouring pipe column with retaining wall and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103911990A true CN103911990A (en) | 2014-07-09 |
CN103911990B CN103911990B (en) | 2015-11-18 |
Family
ID=51037961
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410172024.5A Active CN103911990B (en) | 2014-04-25 | 2014-04-25 | A kind of underwater pouring pipe column with retaining wall and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103911990B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106337421A (en) * | 2016-10-28 | 2017-01-18 | 绍兴文理学院 | Lattice concrete composite retaining pile wall and construction method based on BIM |
CN111733799A (en) * | 2020-06-10 | 2020-10-02 | 合肥工业大学 | A self-protecting wall large-diameter concrete hollow tubular column foundation forming method |
CN111733805A (en) * | 2020-06-10 | 2020-10-02 | 合肥工业大学 | A cast-in-place large-diameter hollow tubular string foundation underwater mandrel system |
CN111733798A (en) * | 2020-06-10 | 2020-10-02 | 合肥工业大学 | A self-protecting wall large diameter concrete hollow tubular column foundation |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2163279C2 (en) * | 1998-12-28 | 2001-02-20 | Новосибирский государственный архитектурно-строительный университет | Method of making cast-in-place piles with root-like members and device for its embodiment |
CN2934352Y (en) * | 2006-07-26 | 2007-08-15 | 安徽省高速公路总公司 | Root key type drilling perfusion stake construction device |
CN101311421A (en) * | 2006-01-26 | 2008-11-26 | 安徽省高速公路总公司 | Radical anchorage and construction method thereof |
CN102359110A (en) * | 2011-08-03 | 2012-02-22 | 安徽省高速公路控股集团有限公司 | Modular cast-in-place construction method for large-diameter root foundation |
CN103205965A (en) * | 2013-04-28 | 2013-07-17 | 何春林 | Root pressure grouting pile and construction method thereof |
CN203782691U (en) * | 2014-04-25 | 2014-08-20 | 安徽省高速公路控股集团有限公司 | Underwater pouring type pipe column provided with retaining wall and internal mold system thereof |
-
2014
- 2014-04-25 CN CN201410172024.5A patent/CN103911990B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2163279C2 (en) * | 1998-12-28 | 2001-02-20 | Новосибирский государственный архитектурно-строительный университет | Method of making cast-in-place piles with root-like members and device for its embodiment |
CN101311421A (en) * | 2006-01-26 | 2008-11-26 | 安徽省高速公路总公司 | Radical anchorage and construction method thereof |
CN2934352Y (en) * | 2006-07-26 | 2007-08-15 | 安徽省高速公路总公司 | Root key type drilling perfusion stake construction device |
CN102359110A (en) * | 2011-08-03 | 2012-02-22 | 安徽省高速公路控股集团有限公司 | Modular cast-in-place construction method for large-diameter root foundation |
CN103205965A (en) * | 2013-04-28 | 2013-07-17 | 何春林 | Root pressure grouting pile and construction method thereof |
CN203782691U (en) * | 2014-04-25 | 2014-08-20 | 安徽省高速公路控股集团有限公司 | Underwater pouring type pipe column provided with retaining wall and internal mold system thereof |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106337421A (en) * | 2016-10-28 | 2017-01-18 | 绍兴文理学院 | Lattice concrete composite retaining pile wall and construction method based on BIM |
CN111733799A (en) * | 2020-06-10 | 2020-10-02 | 合肥工业大学 | A self-protecting wall large-diameter concrete hollow tubular column foundation forming method |
CN111733805A (en) * | 2020-06-10 | 2020-10-02 | 合肥工业大学 | A cast-in-place large-diameter hollow tubular string foundation underwater mandrel system |
CN111733798A (en) * | 2020-06-10 | 2020-10-02 | 合肥工业大学 | A self-protecting wall large diameter concrete hollow tubular column foundation |
Also Published As
Publication number | Publication date |
---|---|
CN103911990B (en) | 2015-11-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103898900B (en) | Band pull bar steel tube-concrete composite structure diaphragm wall and construction method thereof | |
WO2021026971A1 (en) | Lattice composite wellbore structure and construction method therefor | |
CN103850363A (en) | Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall | |
CN103911990B (en) | A kind of underwater pouring pipe column with retaining wall and its construction method | |
CN106836463A (en) | The constructing device and construction method of cushion cap and ground girder construction | |
CN103911989B (en) | A kind of underwater casting base type foundation with retaining wall and construction method thereof | |
CN104652417A (en) | High-performance concrete corrugated sheet pile, forming die and production method for high-performance concrete corrugated sheet pile | |
CN105862602A (en) | Turnover formwork system of hollow inclined concrete pylon and construction method thereof | |
CN103924581A (en) | Underground continuous wall with prefabricated concrete-filled steel tube composite structure and method for constructing underground continuous wall | |
CN104711931B (en) | Temporary underwater pier manufacturing, assembling and disassembling method suitable for bridge erection | |
CN203654196U (en) | Guide apparatus for large and multifunctional over-water construction platform | |
CN203782691U (en) | Underwater pouring type pipe column provided with retaining wall and internal mold system thereof | |
CN106193644A (en) | Basement reconstruction structure with raft foundation building | |
CN102828506A (en) | Ultra-deep large-section square support pile and construction method thereof | |
CN105298147A (en) | Ultra-deep foundation pit spiral descending quick material transportation passage and construction method thereof | |
CN110512776B (en) | Construction method of assembled steel structure multi-cavity steel plate composite shear wall | |
CN108951607A (en) | The hollow continuous underground wall structure of cast-in-place post-tensioned prestressed concrete and its construction method | |
CN103924595B (en) | A kind of hollow pipe column underwater casting self-floating inner formwork system | |
CN203782715U (en) | Self-floating type inner mold system for under water pouring of hollow pipe column | |
CN103061334B (en) | I-section prestressed reinforced concrete support pile by centrifugal pouring | |
CN108035372B (en) | A method of steel lifted trunk is hung using drilling platform gooseneck | |
CN106337421B (en) | A kind of lattice concrete is compound to go along with sb. to guard him piling wall and the construction method based on BIM | |
CN105908738B (en) | Heavy-gauge steel and the hollow friction pile of Combined concrete and its construction method | |
CN103741724B (en) | A kind of prefabricated prestressed underground continuous wall joint | |
CN108468356A (en) | A kind of anti-float anchor rod and preparation method thereof that existing basement bottom board is reinforced |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 230088 Wan Tong Building, 520 Wangjiang West Road, Hefei hi tech Zone, Anhui Applicant after: ANHUI TRANSPORTATION HOLDING GROUP CO., LTD. Address before: 230088 Wan Tong Building, 520 Wangjiang West Road, Hefei hi tech Zone, Anhui Applicant before: Anhui Highway Holding Group Co., Ltd. |
|
COR | Change of bibliographic data | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |