CN103900429A - Concrete hollow pillar blasting method - Google Patents

Concrete hollow pillar blasting method Download PDF

Info

Publication number
CN103900429A
CN103900429A CN201410157420.0A CN201410157420A CN103900429A CN 103900429 A CN103900429 A CN 103900429A CN 201410157420 A CN201410157420 A CN 201410157420A CN 103900429 A CN103900429 A CN 103900429A
Authority
CN
China
Prior art keywords
hollow
concrete
blasting
hollow area
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410157420.0A
Other languages
Chinese (zh)
Other versions
CN103900429B (en
Inventor
谢先启
贾永胜
刘昌邦
王洪刚
姚颖康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WUHAN BLASTING CO Ltd
Original Assignee
WUHAN BLASTING CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUHAN BLASTING CO Ltd filed Critical WUHAN BLASTING CO Ltd
Priority to CN201410157420.0A priority Critical patent/CN103900429B/en
Publication of CN103900429A publication Critical patent/CN103900429A/en
Application granted granted Critical
Publication of CN103900429B publication Critical patent/CN103900429B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Processing Of Stones Or Stones Resemblance Materials (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

本发明公开了一种混凝土空心立柱或的爆破方法,属于爆破技术领域。该方法包括以下步骤:(1)在所述混凝土空心立柱的顶部钻顶孔,所述顶孔至所述混凝土空心立柱的空心区域,向所述空心区域内注水;(2)在所述混凝土空心立柱的底部钻底孔,所述底孔至所述混凝土空心立柱的空心区域,将所述空心区域内的水排出;(3)通过所述顶孔向所述空心区域注入水泥浆,当所述水泥浆到达所述底孔位置时,将所述底孔堵塞,所述水泥浆注满整个所述空心区域;(4)当所述空心区域内的水泥浆固结后,按工程设计要求对所述混凝土空心立柱进行钻孔,实施爆破。本发明方法在混凝土立柱中有空心孔或连续空腔进行爆破时,保证爆破质量的爆破方法。

The invention discloses a blasting method for concrete hollow columns or columns, belonging to the technical field of blasting. The method comprises the following steps: (1) drilling a top hole on the top of the concrete hollow column, the top hole reaches the hollow area of the concrete hollow column, and injecting water into the hollow area; (2) drilling the concrete into the hollow area; Bottom holes are drilled at the bottom of the hollow column, and the bottom hole reaches the hollow area of the concrete hollow column to discharge the water in the hollow area; (3) inject cement slurry into the hollow area through the top hole, when When the cement slurry reaches the position of the bottom hole, the bottom hole is blocked, and the cement slurry fills the entire hollow area; (4) After the cement slurry in the hollow area is solidified, according to the engineering design It is required to drill the concrete hollow column and implement blasting. The method of the invention is a blasting method for ensuring the blasting quality when there are hollow holes or continuous cavities in the concrete column for blasting.

Description

A kind of blasting method of concrete hollow column
Technical field
The invention belongs to blasting technique field, particularly a kind of concrete hollow column or blasting method.
Background technology
In buildings or structures demolition blasting, on concrete column, drillhole blasting is the method generally using.In some engineering, for saving material, the deadweight that alleviates concrete column, accelerates speed of application, is designed with hollow hole or continuous cavity in the column of being everlasting.Carry out drillhole blasting on this column time, because there is hollow parts in concrete column, big gun hole hole quality and cause the leakage of detonation gas while affecting explosion, even breakage while being unfavorable for concrete material drillhole blasting, easily cause fried and not broken or part concrete explosion not destroy, and because the change of burden forms a large amount of explosion flyings, cause demolition accident.
Summary of the invention
The object of the invention is provides a kind of and in concrete column, has hollow hole or when cavity carries out explosion continuously, ensure the blasting method of blasting quality for addressing the above problem.
The technical solution adopted in the present invention is:
A blasting method for concrete hollow column, comprises the following steps:
(1) bore apical pore at the top of described concrete hollow column, described apical pore is to the hollow area of described concrete hollow column, to water filling in described hollow area;
(2) bore bottom outlet in the bottom of described concrete hollow column, described bottom outlet, to the hollow area of described concrete hollow column, is discharged the water in described hollow area;
(3) by described apical pore to described hollow area injected water mud, in the time that described cement mortar arrives described bottom outlet position, described bottom outlet is stopped up, described cement mortar fills whole described hollow area;
(4) after the cement mortar in described hollow area is fixed, by engineering design requirement, described concrete hollow column is holed, implement explosion.
Further, the water in described step (1) can be determined the seal of size and the hollow area of hollow area.
Further, the water in described step (2) can rinse the foreign material in hollow area.
Preferably, the pore diameter size of described apical pore and described bottom outlet is 4~6cm.
Preferably, described cement mortar is the mixture of water and cement.
Further, the bottom outlet in described step (3) stops up with old and useless newspaper.
The present invention has the following advantages:
(1) adopt slip casting to repair hollow column, convenient and swift, reduced the problem of boring big gun hole because of cavity some effects more, therefore save construction cost, saved engineering time, improve efficiency of construction; (2) construction equipment, material are comparatively general, are easy to buy lease and use, and versatility is stronger;
(3) the column Drilling big gun hole hole quality after repairing is good, and the number of the boring hole obviously reduces, and shot hole blasting service efficiency is high; (4) after in concrete column cavity, injected water mud solidifies, better with original concrete material cementability, be beneficial to explosive placement and explosion and concrete column produced evenly broken.
Brief description of the drawings
Structural representation when injected water mud not in the blasting method of a kind of concrete hollow column that Fig. 1 provides for the embodiment of the present invention 1;
Structural representation in the blasting method of a kind of concrete hollow column that Fig. 2 provides for the embodiment of the present invention 1 when injected water mud.
Detailed description of the invention
Below in conjunction with drawings and embodiments, the present invention will be further described in detail.
Embodiment 1
The present embodiment provides a kind of blasting method of concrete hollow column, and the method is used in certain viaduct pier and implements drillhole blasting dismounting.In drilling construction process, find that bridge pier center is hollow and continuous cavity, so adopt blasting method of the present invention, this comprises the following steps:
(1) bore apical pore 3 at the top of concrete hollow column 1, apical pore 3 is to the hollow area 2 of concrete hollow column 1, to the interior water filling of hollow area 2, to determine the seal of size and hollow area 2 of hollow area 2;
(2) bore bottom outlet 4 in the bottom of concrete hollow column 1, bottom outlet 4 is to the hollow area 2 of concrete hollow column 1, and water can rinse the foreign material in hollow area 2, finally the water in hollow area 2 is discharged;
(3) pass through apical pore 3 to hollow area 2 injected water mud 5, cement mortar 3 is the mixture of water and cement.In the time that cement mortar 5 arrives bottom outlet 4 position, bottom outlet 4 is stopped up with old and useless newspaper, cement mortar 5 fills whole hollow area 2.The pore diameter size of apical pore 3 and bottom outlet 4 is 4cm;
(4) after the cement mortar 5 in hollow area 2 is fixed, by engineering design requirement, concrete hollow column 1 is bored to big gun hole 6, implement explosion.
Embodiment 2
As different from Example 1, the pore diameter size of apical pore 3 and bottom outlet 4 is 5cm to the present embodiment.
The present invention adopts slip casting rehabilitating concrete hollow column 1, convenient and swift, has reduced the problem of boring big gun hole because of cavity some effects more, has therefore saved construction cost, has saved engineering time, has improved efficiency of construction; Construction equipment, material are comparatively general, are easy to buy lease and use, and versatility is stronger; Concrete hollow column 1 Drilling big gun hole hole quality after repairing is good, and the number of the boring hole obviously reduces, and shot hole blasting service efficiency is high; After in concrete hollow column 1 cavity, injected water mud 5 solidifies, better with original concrete material cementability, be beneficial to explosive placement and explosion and concrete hollow column 1 produced evenly broken.
It should be noted last that, above embodiment is only unrestricted in order to technical scheme of the present invention to be described, although the present invention is had been described in detail with reference to preferred embodiment, those of ordinary skill in the art is to be understood that, can modify or be equal to replacement technical scheme of the present invention, and not departing from the spirit and scope of technical solution of the present invention, it all should be encompassed in the middle of claim scope of the present invention.

Claims (6)

1.一种混凝土空心立柱的爆破方法,其特征在于,包括以下步骤:1. a blasting method of concrete hollow column, is characterized in that, comprises the following steps: (1)在所述混凝土空心立柱的顶部钻顶孔,所述顶孔至所述混凝土空心立柱的空心区域,向所述空心区域内注水;(1) Drilling a top hole on the top of the concrete hollow column, the top hole reaches the hollow area of the concrete hollow column, and injects water into the hollow area; (2)在所述混凝土空心立柱的底部钻底孔,所述底孔至所述混凝土空心立柱的空心区域,将所述空心区域内的水排出;(2) Bottom holes are drilled at the bottom of the concrete hollow column, and the bottom hole reaches the hollow area of the concrete hollow column, and the water in the hollow area is discharged; (3)通过所述顶孔向所述空心区域注入水泥浆,当所述水泥浆到达所述底孔位置时,将所述底孔堵塞,所述水泥浆注满整个所述空心区域;(3) injecting cement slurry into the hollow area through the top hole, and when the cement slurry reaches the position of the bottom hole, block the bottom hole, and fill the entire hollow area with the cement slurry; (4)当所述空心区域内的水泥浆固结后,按工程设计要求对所述混凝土空心立柱进行钻孔,实施爆破。(4) After the cement slurry in the hollow area is solidified, the concrete hollow column is drilled according to the engineering design requirements, and blasting is carried out. 2.根据权利要求1所述的混凝土空心立柱的爆破方法,其特征在于,所述步骤(1)中的水可以确定空心区域的大小和空心区域的密闭性。2. The blasting method of the concrete hollow column according to claim 1, characterized in that the water in the step (1) can determine the size of the hollow area and the airtightness of the hollow area. 3.根据权利要求1所述的混凝土空心立柱的爆破方法,其特征在于,所述步骤(2)中的水可以将空心区域内的杂物进行冲洗。3. The blasting method of concrete hollow columns according to claim 1, characterized in that the water in the step (2) can wash away the sundries in the hollow area. 4.根据权利要求1所述的混凝土空心立柱的爆破方法,其特征在于,所述顶孔和所述底孔的孔直径大小为4~6cm。4. The method for blasting concrete hollow columns according to claim 1, characterized in that the diameters of the top holes and the bottom holes are 4-6 cm. 5.根据权利要求1所述的混凝土空心立柱的爆破方法,其特征在于,所述水泥浆为水和水泥的混合物。5. The method for blasting concrete hollow columns according to claim 1, wherein the cement slurry is a mixture of water and cement. 6.根据权利要求1所述的混凝土空心立柱的爆破方法,其特征在于,所述步骤(3)中的底孔用废旧报纸进行堵塞。6. The blasting method of concrete hollow columns according to claim 1, characterized in that the bottom holes in the step (3) are blocked with waste newspapers.
CN201410157420.0A 2014-04-18 2014-04-18 A kind of blasting method of concrete hollow column Expired - Fee Related CN103900429B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410157420.0A CN103900429B (en) 2014-04-18 2014-04-18 A kind of blasting method of concrete hollow column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410157420.0A CN103900429B (en) 2014-04-18 2014-04-18 A kind of blasting method of concrete hollow column

Publications (2)

Publication Number Publication Date
CN103900429A true CN103900429A (en) 2014-07-02
CN103900429B CN103900429B (en) 2016-01-06

Family

ID=50991903

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410157420.0A Expired - Fee Related CN103900429B (en) 2014-04-18 2014-04-18 A kind of blasting method of concrete hollow column

Country Status (1)

Country Link
CN (1) CN103900429B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105823384A (en) * 2016-03-28 2016-08-03 贵州新联爆破工程集团有限公司 Regularly polygonal post drilling and blasting method
CN119877884A (en) * 2025-02-21 2025-04-25 中国建筑第八工程局有限公司 Building indoor space expansion device and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1040074A (en) * 1988-07-30 1990-02-28 斯科钦斯基矿业学院 Utilize the method for blast crushing kinds of rock
KR20020073474A (en) * 2002-09-11 2002-09-26 주식회사 코리아카코 Blasting dissolution method of wall
CN102392420A (en) * 2011-10-31 2012-03-28 刘其伟 Vertical crack grouting and reinforcing method of prestressed concrete hollow slab bridge bottom plate
CN103175452A (en) * 2013-03-25 2013-06-26 姬云峰 Symmetrically swinging blasting method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1040074A (en) * 1988-07-30 1990-02-28 斯科钦斯基矿业学院 Utilize the method for blast crushing kinds of rock
KR20020073474A (en) * 2002-09-11 2002-09-26 주식회사 코리아카코 Blasting dissolution method of wall
CN102392420A (en) * 2011-10-31 2012-03-28 刘其伟 Vertical crack grouting and reinforcing method of prestressed concrete hollow slab bridge bottom plate
CN103175452A (en) * 2013-03-25 2013-06-26 姬云峰 Symmetrically swinging blasting method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
曾赞文等: "筒状结构填砂爆破的药量计算探讨", 《工程爆破》, vol. 15, no. 3, 30 September 2009 (2009-09-30), pages 13 - 16 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105823384A (en) * 2016-03-28 2016-08-03 贵州新联爆破工程集团有限公司 Regularly polygonal post drilling and blasting method
CN119877884A (en) * 2025-02-21 2025-04-25 中国建筑第八工程局有限公司 Building indoor space expansion device and construction method
CN119877884B (en) * 2025-02-21 2025-11-04 中国建筑第八工程局有限公司 An indoor space expansion device and construction method for buildings

Also Published As

Publication number Publication date
CN103900429B (en) 2016-01-06

Similar Documents

Publication Publication Date Title
CN100513745C (en) Construction method for mechanical hole reaming of anchor rod
CN110043190B (en) A method of constructing a large-diameter chamber in a vertical well
CN103089276B (en) Deep-shallow hole and high-low pressure coupling grouting technology
CN103912302B (en) A kind of layer-through drilling hydraulic rupture gas pumping method
CN102226375B (en) Method for forming easy-to-collapse drilled hole
CN105200978A (en) Advancing type localized double-liquid grouting device and construction method
CN109322621B (en) Broken layer pipe fixing and grouting method
CN106499412A (en) A kind of anti-rock burst method for protecting support in the tunnel with active support as theory and support system
CN113153396A (en) Hole sealing, grouting and water plugging reinforcing method for anchor cable holes in roadway water spraying area
CN105507939B (en) A kind of slip casting displaced type drilling solidification sealing and method of the gas without pipe extraction
CN104196455A (en) Anchoring hole bottom single-wing hole broadening method
CN102493403A (en) Rock-fill dam deformation control technology
CN115288476A (en) Water jet breaking and dismantling method based on pre-cracked concrete structure
CN104074535A (en) Composite reinforcing method for grotto roof peeling defects of sandstone grotto
CN104763004B (en) Soil base building method for correcting error
CN110130325B (en) Construction method for rock drilling and grouting
CN111577357A (en) Drill-anchor-integrated hollow anchor rod and anchoring method
CN103900429B (en) A kind of blasting method of concrete hollow column
CN103882859B (en) A kind of original state of Shi Hanzhang fetches earth cast-with-pressure concrete pile and construction method thereof
CN206581960U (en) The solid anchoring integral hydraulic expansion anchor pole of mining slip casting
CN204326061U (en) A kind of pile tube be drawn out easily
CN201158819Y (en) Exhaust Self-Anchor Bolt
CN107354939A (en) A kind of minor diameter static mini steel-pipe pile grouting behind shaft or drift lining construction method
CN206246133U (en) A kind of anti-rock burst support system in tunnel and tunnel structure
CN201214788Y (en) Grouting device under pressure for mortar anchor rod

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160106

CF01 Termination of patent right due to non-payment of annual fee