CN103898915A - 建筑物小面积深基坑抗浮止水施工方法 - Google Patents

建筑物小面积深基坑抗浮止水施工方法 Download PDF

Info

Publication number
CN103898915A
CN103898915A CN201410156683.XA CN201410156683A CN103898915A CN 103898915 A CN103898915 A CN 103898915A CN 201410156683 A CN201410156683 A CN 201410156683A CN 103898915 A CN103898915 A CN 103898915A
Authority
CN
China
Prior art keywords
floating
foundation pit
small
deep foundation
dewatering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410156683.XA
Other languages
English (en)
Other versions
CN103898915B (zh
Inventor
苑宗双
吕思清
董军伟
雷小通
马建民
孟德伟
杨辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201410156683.XA priority Critical patent/CN103898915B/zh
Publication of CN103898915A publication Critical patent/CN103898915A/zh
Application granted granted Critical
Publication of CN103898915B publication Critical patent/CN103898915B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

本发明涉及一种建筑物小面积深基坑抗浮止水施工方法。其步骤是:在小面积深基坑周围进行井点降水;将地下水位降至筏板下500mm后,开挖小面积深基坑土方;混凝土抗浮保护壳施工;在混凝土抗浮保护壳内部铺设防水卷材,外部回填级配砂石;混凝土抗浮保护壳养护,同时施工其他基坑垫层;停止降水,封降水井,将混凝土保护壳内卷材与其他部位卷材连接为整体;混凝土抗浮保护壳独自承担水压,壳内进行筏板施工。本发明优点是:井点降水直接设在小面积深基坑上口,降水管影响范围集中,降水效果好;设置混凝土抗浮保护壳承担水压,保护筏板在其内部正常进行施工;提前停止降水,防水连续铺设于抗浮壳内部能够与其他基坑防水形成完整的防水体系。

Description

建筑物小面积深基坑抗浮止水施工方法
技术领域
本发明涉及建筑施工方法,尤其是一种建筑物小面积深基坑抗浮止水施工方法。
背景技术
建筑物小面积深基坑开挖前,一般需要进行井点降水,将地下水位降至筏板下500mm方可进行土方开挖,此种方法需要在建筑物外围基坑四周设置井点提前进行降水,存在的问题是:工期长,降水影响范围有限,影响降水效果;也可采取沉井施工技术,但沉井施工存在沉井内部土方只能采取人工开挖,工期长和沉井施工无法保证卷材防水连续性的缺点。
发明内容
本发明的目的是提供一种建筑物小面积深基坑抗浮止水施工方法,解决现有技术存在的上述问题。
本发明解决上述技术问题采用的技术方案是:
一种建筑物小面积深基坑抗浮止水施工方法,按下述步骤进行:
a.在小面积深基坑周围进行井点降水;
b.将地下水位降至筏板下500mm后,开挖小面积深基坑土方;
c.进行混凝土抗浮保护壳施工;
d.在混凝土抗浮保护壳内部铺设防水卷材,外部回填级配砂石;
e.混凝土抗浮保护壳养护,同时施工其他基坑垫层;
f.停止降水,封降水井,将混凝土保护壳内防水卷材与其他部位防水卷材连接为整体;
g.混凝土抗浮保护壳独自承担水压,壳内进行正常筏板施工。
采用上述技术方案的本发明,与现有技术相比,其优点是:
①    井点降水直接设在小面积深基坑上口,降水管影响范围集中,降水效果好;
②井点停止降水,水位恢复后,抗浮保护壳独自承担水压,保护筏板在其内部正常进行施工;
③在大面积防水层铺设之前,提前停止降水,使整个底板防水连续铺设于抗浮保护壳内部,与其他基坑防水形成完整的防水体系。
附图说明
图1为本发明实施例基坑构造平面图。
图2为图1中A-A剖视图。
图中:降水井1,混凝土抗浮保护壳2,筏板3,防水卷材4,级配砂石5,地下水位6。
具体实施方式
下面结合实施例对本发明作进一步说明,目的仅在于更好地理解本发明内容。
参见图1、图2,本实施例所述的建筑物小面积深基坑抗浮止水施工方法,按下述步骤进行:
1.在小面积深基坑周围进行井点降水,打降水井1,真空泵或者潜水泵抽水,降低地下水位6至筏板3下500mm。
2.开挖小面积深基坑土方。
3.根据筏板3排开水的体积计算浮力,设计混凝土抗浮保护壳2,然后施工混凝土抗浮保护壳2。
4.在混凝土抗浮保护壳2内部铺设防水卷材4,外部回填级配砂石5。
5.混凝土抗浮保护壳2养护,同时施工其他基坑垫层。
6.停止降水,封降水井1,将混凝土抗浮保护壳2内防水卷材4与其他部位防水卷材连接为整体。
7.水位恢复后,混凝土抗浮保护壳2独自承担水压,壳内进行正常筏板3施工。

Claims (1)

1.一种建筑物小面积深基坑抗浮止水施工方法,其特征在于,按下述步骤进行:
a.在小面积深基坑周围进行井点降水;
b.将地下水位降至筏板下500mm后,开挖小面积深基坑土方;
c.进行混凝土抗浮保护壳施工;
d.在混凝土抗浮保护壳内部铺设防水卷材,外部回填级配砂石;
e.混凝土抗浮保护壳养护,同时施工其他基坑垫层;
f.停止降水,封降水井,将混凝土保护壳内防水卷材与其他部位防水卷材连接为整体;
g.混凝土抗浮保护壳独自承担水压,壳内进行正常筏板施工。
CN201410156683.XA 2014-04-18 2014-04-18 建筑物小面积深基坑抗浮止水施工方法 Active CN103898915B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410156683.XA CN103898915B (zh) 2014-04-18 2014-04-18 建筑物小面积深基坑抗浮止水施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410156683.XA CN103898915B (zh) 2014-04-18 2014-04-18 建筑物小面积深基坑抗浮止水施工方法

Publications (2)

Publication Number Publication Date
CN103898915A true CN103898915A (zh) 2014-07-02
CN103898915B CN103898915B (zh) 2016-02-10

Family

ID=50990468

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410156683.XA Active CN103898915B (zh) 2014-04-18 2014-04-18 建筑物小面积深基坑抗浮止水施工方法

Country Status (1)

Country Link
CN (1) CN103898915B (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107326918A (zh) * 2017-08-18 2017-11-07 云南省建设投资控股集团有限公司 一种隐藏型穿越筏板可封堵抗渗集水井及其施工工艺
CN108547315A (zh) * 2018-04-21 2018-09-18 天津中擎建筑工程有限公司 潮湿地带地下室施工方案
CN111705832A (zh) * 2020-06-24 2020-09-25 深圳市建工集团股份有限公司 一种地下室装配式承台及防水施工一体化施工方法
CN112554203A (zh) * 2020-12-03 2021-03-26 九冶建设有限公司 用于地下水丰富的淤泥流沙区的微型沉井预制胎模施工法
CN117230821A (zh) * 2023-11-02 2023-12-15 北京建工四建工程建设有限公司 一种高水位基坑工程坑中坑接力排水结构及其施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000336645A (ja) * 1999-05-26 2000-12-05 Ohbayashi Corp 水中掘削における土留め壁と底版の接合工法
CN101793032A (zh) * 2010-04-21 2010-08-04 邵辉 一种小场地深基坑施工方法
CN202627032U (zh) * 2012-05-30 2012-12-26 福建省泷澄建设集团有限公司 深基础底板浮力释放系统
CN103147464A (zh) * 2013-04-01 2013-06-12 四川省建筑科学研究院 一种地下室抗浮板的泄压结构及其施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000336645A (ja) * 1999-05-26 2000-12-05 Ohbayashi Corp 水中掘削における土留め壁と底版の接合工法
CN101793032A (zh) * 2010-04-21 2010-08-04 邵辉 一种小场地深基坑施工方法
CN202627032U (zh) * 2012-05-30 2012-12-26 福建省泷澄建设集团有限公司 深基础底板浮力释放系统
CN103147464A (zh) * 2013-04-01 2013-06-12 四川省建筑科学研究院 一种地下室抗浮板的泄压结构及其施工方法

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107326918A (zh) * 2017-08-18 2017-11-07 云南省建设投资控股集团有限公司 一种隐藏型穿越筏板可封堵抗渗集水井及其施工工艺
CN108547315A (zh) * 2018-04-21 2018-09-18 天津中擎建筑工程有限公司 潮湿地带地下室施工方案
CN111705832A (zh) * 2020-06-24 2020-09-25 深圳市建工集团股份有限公司 一种地下室装配式承台及防水施工一体化施工方法
CN111705832B (zh) * 2020-06-24 2021-07-06 深圳市建工集团股份有限公司 一种地下室装配式承台及防水施工一体化施工方法
CN112554203A (zh) * 2020-12-03 2021-03-26 九冶建设有限公司 用于地下水丰富的淤泥流沙区的微型沉井预制胎模施工法
CN117230821A (zh) * 2023-11-02 2023-12-15 北京建工四建工程建设有限公司 一种高水位基坑工程坑中坑接力排水结构及其施工方法

Also Published As

Publication number Publication date
CN103898915B (zh) 2016-02-10

Similar Documents

Publication Publication Date Title
CN105002913B (zh) 一种强透水地层深基坑封底止水结构及其施工方法
CN106638669B (zh) 一种盾构下穿既有地铁车站围护结构加固系统和方法
CN109371918B (zh) 具有永临结合多功能排水箱涵的大坝结构及其施工方法
CN103981898A (zh) 一种整体明挖节点逆作的地下工程施工方法
CN103898915B (zh) 建筑物小面积深基坑抗浮止水施工方法
CN103225306B (zh) 一种邻近水源基坑开挖过程中防止基坑渗漏的方法
CN103161172B (zh) 电梯井底降水施工方法
CN108166457A (zh) 深厚覆盖层坝基与砾质土心墙的防渗连接结构
CN205839779U (zh) 一种砂土地层基坑降水水位以下集水坑结构
CN112081125A (zh) 潜水砂卵石地层基坑封底结构及施工工艺
CN206448286U (zh) 一种用于降低灰场坝体浸润线的辐射井系统
CN105484277A (zh) 一种电梯基坑或集水坑内管井降水施工用构件及施工方法
CN203939036U (zh) 一种适用于河道的钢板桩围堰结构
CN205205844U (zh) 一种电梯基坑或集水坑内管井降水施工用构件
CN105421498B (zh) 一种基于立体帷幕‑井群体系的基坑防渗水及沉降控制方法
CN108104144A (zh) 基于降压减渗的强透水地层深基坑地下水控制方法及结构
CN215669620U (zh) 降水井的封堵结构
CN203768925U (zh) 一种基坑内降水井的封堵装置
CN105714771B (zh) 一种人工挖孔桩的施工方法
CN211312564U (zh) 基于降压减渗的强透水地层深基坑地下水控制结构
CN204690767U (zh) 一种用于深基坑的新型集水套管和给排水装置
CN207176628U (zh) 一种土石坝防渗止水结构
CN204825916U (zh) 一种强透水地层深基坑封底止水结构
CN204551507U (zh) 一种岩石地基小导管局部降水装置
CN213204183U (zh) 一种基坑内、外承压井结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant