CN103835524A - 受荷情况下楼面钢梁设计变更截面改小处理方法 - Google Patents

受荷情况下楼面钢梁设计变更截面改小处理方法 Download PDF

Info

Publication number
CN103835524A
CN103835524A CN201410082562.5A CN201410082562A CN103835524A CN 103835524 A CN103835524 A CN 103835524A CN 201410082562 A CN201410082562 A CN 201410082562A CN 103835524 A CN103835524 A CN 103835524A
Authority
CN
China
Prior art keywords
crossbeam
wing plate
change
web
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410082562.5A
Other languages
English (en)
Other versions
CN103835524B (zh
Inventor
赵永杰
刘和平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Jinhai Modern Construction Technology Co ltd
Original Assignee
HUNAN JINHAI STEEL STRUCTURE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN JINHAI STEEL STRUCTURE CO Ltd filed Critical HUNAN JINHAI STEEL STRUCTURE CO Ltd
Priority to CN201410082562.5A priority Critical patent/CN103835524B/zh
Publication of CN103835524A publication Critical patent/CN103835524A/zh
Application granted granted Critical
Publication of CN103835524B publication Critical patent/CN103835524B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明技术涉及受荷载情况下依照设计变更进行楼面钢梁截面改小施工处理技术。常规施工必须在钢梁下安装钢柱支撑后才能进行截面改小施工,因此往往存在下列问题:楼面荷载无法消除;位置较高时,钢柱支撑无法设置;钢柱支撑设置时,施工成本较大;钢柱支撑安装过程中,工人劳动强度大,存在安全隐患。本发明提供的方法,施工处理过程安全、经济,保证梁截面改小后的楼面钢梁达到使用可靠的设计要求,利用楼面钢梁自身受力的力学特点,在大梁设计变更位置开切口,逐段处理楼面钢梁腹板与下翼缘的安装联接,各分段的新安装下翼缘板与原有楼面钢梁腹板的焊接并逐步形成新梁整体,最后将多余的原楼面腹板、下翼缘板切除和防腐处理。

Description

受荷情况下楼面钢梁设计变更截面改小处理方法
技术领域: 
本发明技术涉及绿色环保建筑领域,具体指受荷载情况下依照设计变更进行楼面钢梁截面改小施工处理技术。
背景技术: 
 目前的许多高层、超高层房屋建筑和重型钢结构工业建筑都采用钢结构框架体系。施工过程中,常常是由于设计失误或业主要求等原因经常需要对一些已安装完毕的楼面钢大梁进行截面变更处理。对于一些截面需要改小的楼面钢梁在已承受各种荷载的情况下进行设计变更处理时,按照常规施工工艺必须在钢梁下安装钢柱支撑后才能进行截面改小变更施工,因此在施工过程中往往存在下列问题:
1:对于一些大梁下部有车辆通行的过道,钢柱支撑根本无法设置,按照常规施工工艺要求无法施工;
2:楼面荷载无法消除;
3:当要修改的大梁空间标高位置较高时,钢柱支撑无法设置;
4:钢柱支撑设置时,需要耗费部分管材、配置施工爬梯,需要配置油压千斤顶设备,甚至需要动用机械吊装设备,施工成本较大;
5:钢柱支撑安装过程中,工人劳动强度较大,存在较大的安全隐患,极易发生施工安全事故。
发明内容: 
为解决上述技术问题,本发明的目的在于提供一种受荷情况下楼面钢梁设计变更截面改小处理方法,使楼面钢梁截面改小施工处理过程安全、经济,保证梁截面改小后的楼面钢梁达到使用可靠的设计要求。
受荷情况下楼面钢梁设计变更截面改小处理时。本发明在楼面钢梁截面改小施工处理过程中不像常规施工处理方法那样设置钢管支撑,而是利用楼面钢梁自身受力的力学特点,按照施工验收规范要求,在保证楼面大梁原有截面受力不变的情况下,采取分步施工方法,逐段处理楼面钢梁腹板与下翼缘的安装联接,每段楼面钢梁腹板与下翼缘的安装联接各项尺寸校核无误后,随即进行各分段的新安装下翼缘板与原有楼面钢梁腹板的焊接并逐步形成新梁整体,最后将多余的原楼面腹板、下翼缘板切除和防腐处理,使楼面钢梁截面改小施工处理按设计要求顺利完成。 
为达到上述目的,本发明提供的方法是受荷情况下楼面钢梁设计变更截面改小处理方法:其特征在于,a:根据大梁承受荷载情况,进行大梁中部翼板变更位置剪力计算,确定大梁中部翼板变更位置;切口开孔后大梁腹板能承受剪力达到设计要求,弯矩由原大梁上下翼板承受不变; 
b:在大梁腹板上按设计变更安装新下翼板位置开设一道切口,切口宽度为新翼板厚度,切口长度大于或等于1/3大梁长度,用砂轮机打磨保留的腹板切口,为安装新下翼板作准备;
c:焊接大梁中部新下翼板,完成大梁中间部位截面改小变更施工,切割、拆除原大梁变更改小后多余的腹板和下翼板,此时大梁弯矩已由新安装翼板承受;
d:在大梁左侧设计变更位置再开切口,用砂轮机打磨保留的大梁左侧腹板切口,为安装新下翼板作准备;
e:焊接大梁左侧下部新下翼板,切割、拆除原大梁变更改小后多余的腹板和下翼板,完成大梁左侧下部截面改小变更施工;
f:在大梁右侧设计变更位置再开切口,用砂轮机打磨保留的大梁右侧腹板切口,为安装新下翼板作准备;
g:焊接大梁右侧下部新下翼板,切割、拆除原大梁变更改小后多余的腹板和下翼板,完成大梁右侧下部截面改小变更施工;
h:将各段翼板之间焊接,检测焊缝焊接质量,确保翼板对接焊接质量满足设计要求;
i:报请业主、设计、监理验收;
本发明与现有技术相比,在同等的施工条件下,可以避免采用人力安装钢管支撑、降低工人劳动强度、保证安全施工;可以保证大梁空间标高位置较高时钢柱支撑无法设置情况下楼面钢梁截面改小施工处理正常施工;施工过程中不要求消除楼面荷载,保证楼面上部工程正常进行;节约工程钢管支撑材料、机械设备,减少了施工工序,提前了施工进度,降低了工程施工成本。
附图说明: 
图1是原有楼面钢梁截面改小施工处理的安装连接施工过程示意图;
图2是本发明受荷情况下楼面钢梁设计变更截面改小处理方法施工过程示意图;
图3是本发明受荷情况下楼面钢梁设计变更截面改小处理方法施工过程横截面示意图。
具体实施方式: 
    参照附图1、附图2进一步描述,本发明受荷情况下楼面钢梁设计变更截面改小处理方法是a:根据大梁1承受荷载情况,进行大梁1中部新下翼板2变更位置剪力计算,确定大梁1中部新下翼板2变更位置;在腹板3上切口开孔后大梁1承受剪力能力满足设计规范要求;
b:按照设计变更要求,在腹板3设计变更安装新下翼2板位置中部开设一道切口,切口高度为新翼板厚度,切口长度大于或等于1/3大梁1长度。用砂轮机打磨保留的腹板3切口,为安装新下翼板2作准备;
c:焊接腹板3和新下翼板2,完成大梁1中间部位截面改小变更施工,切割、拆除原大梁变更改小后多余的腹板3和下翼板4,此时大梁弯矩已由新安装翼板2承受;
d:在大梁1左侧设计变更位置再开切口,用砂轮机打磨保留的大梁左侧腹板3切口,为安装新下翼板2作准备;
e:焊接大梁左侧下部腹板3新下翼板2,切割、拆除原大梁1变更改小后多余的腹板3和下翼板4,完成大梁1左侧下部截面改小变更施工;
f:在大梁1右侧设计变更位置再开切口,用砂轮机打磨保留的大梁右侧腹板3切口,为安装新下翼板2作准备;
g:焊接大梁右侧下部腹板3新下翼板2,切割、拆除原大梁变更改小后多余的腹板3和下翼板4,完成大梁右侧下部截面改小变更施工;
h:将各段新下翼板2之间焊接,检测焊缝焊接质量,确保新下翼板2对接焊接质量满足设计要求;
i:报请业主、设计、监理验收;
j:拆除施工脚手架,清理施工现场。
   本实用型楼面钢梁截面改小施工技术处理过程与原有楼面钢梁截面改小施工技术处理过程的技术方法不同。原有楼面钢梁截面改小施工处理是首先安装钢管支撑系统,工人劳动强度较大,施工危险较大,易发生施工安全事故;施工过程必须动用施工机械和施工设备﹙大吨位油压千斤顶﹚,钢管支撑必须按现场情况要求配置,施工成本较高;当要修改的大梁空间标高位置较高时,钢管支撑无法设置;钢管支撑设置后,下部楼层无法施工、下部通道车辆无法通行;楼面荷载必须消除,给楼面上部施工带来困难。采用新型楼面钢梁截面改小施工处理技术后,不需要安装钢管支撑系统,降低了工人劳动强度,减少施工危险性,避免易发生施工安全事故;施工过程不必再动用施工机械、施工设备﹙大吨位油压千斤顶﹚和钢管支撑,降低了施工机械和材料成本;避免了大梁空间标高位置较高时钢管支撑无法设置的困难;避免了钢管支撑设置后下部楼层无法施工、下部通道车辆无法通行的困难;避免了楼面荷载必须消除、给楼面上部施工带来的困难;减少了施工工序,降低了工程施工人工成本,确保了工程施工质量。 

Claims (1)

1.受荷情况下楼面钢梁设计变更截面改小处理方法:其特征在于采用如下步骤,a:根据大梁承受荷载情况,进行大梁中部翼板变更位置剪力计算,确定大梁中部翼板变更位置;切口开孔后大梁腹板能承受剪力达到设计要求,弯矩由原大梁上下翼板承受不变;
b:在大梁腹板上按设计变更安装新下翼板位置开设一道切口,切口宽度为新翼板厚度,切口长度大于或等于1/3大梁长度;用砂轮机打磨保留的腹板切口,为安装新下翼板作准备;
c:焊接大梁中部新下翼板,完成大梁中间部位截面改小变更施工,切割、拆除原大梁变更改小后多余的腹板和下翼板,此时大梁弯矩已由新安装翼板承受;
d:在大梁左侧设计变更位置再开切口,用砂轮机打磨保留的大梁左侧腹板切口,为安装新下翼板作准备;
e:焊接大梁左侧下部新下翼板,切割、拆除原大梁变更改小后多余的腹板和下翼板,完成大梁左侧下部截面改小变更施工;
f:在大梁右侧设计变更位置再开切口,用砂轮机打磨保留的大梁右侧腹板切口,为安装新下翼板作准备;
g:焊接大梁右侧下部新下翼板,切割、拆除原大梁变更改小后多余的腹板和下翼板,完成大梁右侧下部截面改小变更施工;
h:将各段翼板之间焊接,检测焊缝焊接质量,确保翼板对接焊接质量满足设计要求;
i:报请业主、设计、监理验收。
CN201410082562.5A 2014-03-09 2014-03-09 受荷情况下楼面钢梁设计变更截面改小处理方法 Active CN103835524B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410082562.5A CN103835524B (zh) 2014-03-09 2014-03-09 受荷情况下楼面钢梁设计变更截面改小处理方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410082562.5A CN103835524B (zh) 2014-03-09 2014-03-09 受荷情况下楼面钢梁设计变更截面改小处理方法

Publications (2)

Publication Number Publication Date
CN103835524A true CN103835524A (zh) 2014-06-04
CN103835524B CN103835524B (zh) 2017-01-25

Family

ID=50799384

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410082562.5A Active CN103835524B (zh) 2014-03-09 2014-03-09 受荷情况下楼面钢梁设计变更截面改小处理方法

Country Status (1)

Country Link
CN (1) CN103835524B (zh)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201133089Y (zh) * 2007-07-09 2008-10-15 李树林 屋面梁改为楼面梁的荷载转移装置
JP2009221755A (ja) * 2008-03-17 2009-10-01 Takenaka Komuten Co Ltd 建物
CN201778499U (zh) * 2010-04-08 2011-03-30 台州建筑安装工程公司 卸载钢筋混凝土柱负荷装置
CN102140849A (zh) * 2011-01-24 2011-08-03 中冶赛迪工程技术股份有限公司 托换屋面结构扩大钢结构厂房柱距的方法
JP2012207389A (ja) * 2011-03-29 2012-10-25 Fujita Corp 既存建物の耐震補強工法
CN103452328A (zh) * 2013-07-08 2013-12-18 中冶天工上海十三冶建设有限公司 用于钢筋混凝土构件的减柱强梁加固装置及方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201133089Y (zh) * 2007-07-09 2008-10-15 李树林 屋面梁改为楼面梁的荷载转移装置
JP2009221755A (ja) * 2008-03-17 2009-10-01 Takenaka Komuten Co Ltd 建物
CN201778499U (zh) * 2010-04-08 2011-03-30 台州建筑安装工程公司 卸载钢筋混凝土柱负荷装置
CN102140849A (zh) * 2011-01-24 2011-08-03 中冶赛迪工程技术股份有限公司 托换屋面结构扩大钢结构厂房柱距的方法
JP2012207389A (ja) * 2011-03-29 2012-10-25 Fujita Corp 既存建物の耐震補強工法
CN103452328A (zh) * 2013-07-08 2013-12-18 中冶天工上海十三冶建设有限公司 用于钢筋混凝土构件的减柱强梁加固装置及方法

Also Published As

Publication number Publication date
CN103835524B (zh) 2017-01-25

Similar Documents

Publication Publication Date Title
Marquez et al. Common root causes in recent failures of cranes
CN105019665A (zh) 基于全站仪的大跨度结构梁安装方法
CN103556823B (zh) 筒仓滑模操作平台作顶盖板模板支撑体系的施工方法
Bošnjak et al. Failure analysis and reconstruction design of the slewing platform mantle of the bucket wheel excavator O&K SchRs 630
CN103806660A (zh) 劲性混凝土结构梁-柱节点施工方法
Jovančić et al. Load-bearing steel structure diagnostics on bucket wheel excavator, for the purpose of failure prevention
CN105586833B (zh) 劲性骨架钢筋笼整体成型大型现浇薄壁高墩施工方法
Zrnic et al. Failure analysis of the tower crane counterjib
CN107558719A (zh) 用于高层框架钢结构可调节移动式操作平台及其施工方法
CN208561546U (zh) 一种置换穿心式千斤顶的工具锚装置
CN106368714A (zh) 一种用于隧道开挖施工的轮胎式自动升降组装台架
CN207191310U (zh) 一种用于船舶外板施工便携装置
CN103835524B (zh) 受荷情况下楼面钢梁设计变更截面改小处理方法
KR20110020286A (ko) 모노레일형 크레인거더의 단면구성방법
Nischeta et al. Damage of bridge lifting cranes and crane metal structures
Pelayo et al. Failure and repair analysis of a runway beam: Influence of the standard applied to lifetime prediction
CN104060832B (zh) 一种提高卸料平台安全性的方法及装置
CN204173804U (zh) 一种结构梁承载式的内爬塔吊安装及顶升结构
CN105986829A (zh) 一种砼衬砌钢模台车及其加工工艺
Bošnjak et al. Bucket chain excavator: Failure analysis and redesign of the counterweight boom supporting truss columns
Zolina Skewed crane movement as a cause of defect accumulation and damages of bearing frame structures of industrial building
CN102518317B (zh) 在线提升大跨度厂房屋架梁高度方法
CN106065689B (zh) 高层钢结构框架梁施工方法
CN205155340U (zh) 斜井压力钢管安装多层工作平台
CN219074786U (zh) 一种内置式钢管柱导向定位装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 411100 Jinhai Road, Jiuhua demonstration area, Xiangtan, Hunan 1

Patentee after: HUNAN JINHAI STEEL STRUCTURE CO.,LTD.

Address before: 410000 Jinhai Road, Jiuhua demonstration area, Xiangtan, Hunan 1

Patentee before: HUNAN JINHAI STEEL STRUCTURE Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221130

Address after: 416014 Ma'an Industrial Park, Hexi Town, Jishou City, Xiangxi Tujia and Miao Autonomous Prefecture, Hunan Province

Patentee after: Hunan Jinhai Modern Construction Technology Co.,Ltd.

Address before: 411100 Jinhai Road, Jiuhua demonstration area, Xiangtan, Hunan 1

Patentee before: HUNAN JINHAI STEEL STRUCTURE CO.,LTD.